Cashflow
Cashflow
00 36%
FOOTING 8,000.00 3%
COLOUMN STUMP 8,000.00 3%
GROUND BEAM 15,730.00 6%
GROUND SLAB 32,000.00 12%
APRON SLAB 6,400.00 2%
COLUMN 11,600.00 4%
ROOF BEAM 12,100.00 5%
ARCHITECTURE WORK 116,170.00 45%
ROOFING 27,435.00 11%
INTERNAL & EXTERNAL WALL 29,100.00 11%
INTERNAL & EXTERNAL FLOOR 17,300.00 7%
INTERNAL & EXTERNAL CEILING 19,480.00 7%
DOOR & WINDOW 19,855.00 8%
HANDRAILING 3,000.00 1%
MISCELLANEOUS WORK 10,000.00 4%
SANITARY APPLIANCE 4,000.00 2%
COUNTER TOP 6,000.00 2%
INTERNAL MECHANICAL & ELECTRICAL 40,000.00 15%
ELECTRICAL WORKS 15,000.00 6%
INTERNAL PLUMBING WORKS 10,000.00 4%
SEWERAGE WORKS 10,000.00 4%
PERIMETER DRAIN 5,000.00 2%
260,000.00 260,000.00 100% 100%