CM2 - W3 - PERT and Range Estimating
CM2 - W3 - PERT and Range Estimating
○ Optimistic (ta)
○ Pessimistic (tb)
PERT
○ tm: 7 days
○ tb: 12 days
○ te ?
te
Example 1
A D H
F Finish
Start
G
C I
Example 1
Activity tm ta tb te σ2
A 3 1 5 3 0.44
B 6 3 9 6 1.00
C 12 9 18 12.5 2.25
D 9 3 12 8.5 2.25
E 3 1 8 3.5 1.36
F 9 8 16 10 1.77
G 7 4 13 7.5 2.25
H 6 3 9 6 1.00
I 3 1 8 3.5 1.36
• ADH: 3+8.5+6 = 17.5 • BF: 6+10 = 16 What is the
• AEF: 3+3.5+10 = 16.5 • BGI: 6+7.5+3.5 = 17 critical path of
• AEGI:3+3.5+7.5+3.5 = 17.5 • CI: 12.5+3.5 = 16 the project?
A D H
3 8.5 6
E
3.5
F
Finish
Start 10
G
7.5
B
6
C I
12.5 3.5
• ADH: 3+8.5+6 = 17.5 • BF: 6+10 = 16 What is the
• AEF: 3+3.5+10 = 16.5 • BGI: 6+7.5+3.5 = 17 critical path of
• AEGI:3+3.5+7.5+3.5 = 17.5 • CI: 12.5+3.5 = 16 the project?
A D H
3 8.5 6
E
3.5
F
Finish
Start 10
G
7.5
B
6
C I
12.5 3.5
● For A-D-H:
○ Duration = 3 + 8.5 + 6 = 17.5
○ V1= 0.444 + 2.25 + 1.0 = 3.694
● For A-E-G-I:
○ Duration = 3+3.5+7.5+3.5= 17.5
○ V2 = 0.444 + 1.361 + 2.25 +1.361=5.416
A 2 4 7 4.17 ((7-2)/6)2
G 4 6 8 6.00 ((8-4)/6)2
F 4 7 12 7.33 ((12-4)/6)2
H 5 8 14 8.50 ((14-5)/6)2
σ = 2.27
Expected Duration Variance
Activity ta tm tb
A 2 4 7 4.17 ((7-2)/6)2
G 4 6 8 6.00 ((8-4)/6)2
F 4 7 12 7.33 ((12-4)/6)2
H 5 8 14 8.50 ((14-5)/6)2
σ = 2.27
1. Probability of completing Z Probability Probability Z
… … … … … … …
100 … … … … … …
… … … … … … …
100 … … … … … …