Retrofit Modernisation
Retrofit Modernisation
Mission
Extending our capabilities in manufacture, supply & services for the Power Plant needs in
Domestic and Overseas market. We target to be One of the leading Global players in
providing specialised Power solutions.
Quality Policy
We, Texron strongly believe in customer satisfaction at every stage through highest quality,
service and affordable pricing to customer, which is achieved by active participation from
every individual in the company. We consistently update the technological development
and take full responsibility for customer needs. We also believe in continual improvement
and quality is our way of growth.
We are the experts Steam Turbine repairs,
• Turbine repairs, steam path study and • Electrical & Automation solutions
efficiency restoration.
• Retrofit & Modernization of Steam
• Reverse engineering. Turbines, Hydro Turbines & Generators
• Spares manufacturing. • Total Electrical EPC – Concept to
• Engineering & consultancy services Commissioning.
Why TEXRON…?
• Voith
Products • Woodward
• ABB
Experience • MOOG
• CCC
Criteria Credentials
Being service provider, rich experience in all make and all
Experience type of turbines & R&M is our core area of Business and
executed many challenging projects
Hydraulic skid:
•New Hydraulic skid with Solenoid
valves in place of old skid.
•IH converter is mounted in the skid.
•Operation of ESV and servo motor
Speed Sensor: covers by the skid.
•Magnetic Pick up for Speed Sensing.
VALVES
•Speed sensing gear teeth wheel is
typically fitted in the front end of
Turbine rotor.
•Speed sensors are fitted on the turbine
front to focus the gear teeth. and Control Panel:
Hydraulic skid. •Control panel accommodates Digital
Governor.
DUPLEX FILTER
•Trip logics and protection wiring is
done in control panel.
•Interface wiring between Control panel
and Hydraulic skid. 11
Hydraulic Scheme for Retrofit on Siemens/BHEL
Turbine
TYPE - 1 TYPE - 2
Modification of Hydraulic Skid for 50 MW BHEL Turbine
BEFORE
AFTER
2
Supply and installation 4.7 MW WORTHINGTON TURBINE. CUSTOMER: ICS INDORAMA LTD - SENEGAL
Scope of Supply:
Governor panel with Voith DTc Electronic
Governor.
Valtek make Pneumatic actuator with complete
new spindle assembly in place of PG PL
mechanical Governor.
Vibration monitoring system for gear box.
Method of Execution:
Installation of Valtek pneumatic actuator in place
of old fulcrum drive.
Installation of Governor panel.
Interconnection between governor and Valtek
actuator.
BEFORE AFTER Interconnection between vibration monitoring
system and field sensors.
Retrofit with Voith DTc Governor, Direct acting Pneumatic Actuator & speed sensing wheel
Supply of Woodward make Over speed Protection system and speed sensors.
•The Redundant I/H converter block and 2 Out of 3 Logic Hydraulic trip block are India’s first
development products by Non-OEM.
•The complete design, development, manufacturing and supply has been achieved within 12
weeks time.
BEFORE
AFTER
Turbine Before – After Modification
BEFORE AFTER
5
Present low pressure actuators for Main steam stop valves (MSV) and control valves (CV) are removed.
Linear actuators for MSV and Rotary actuators for CV are introduced to operate in 135 bar.
BEFORE
AFTER
HIGH PRESSURE GOVERNING OIL SYSTM
BEFORE AFTER
Key Features:
• Fully Digital Control.
• Dual channel hot redundant.
• Fastest control in critical grid conditions.
• Historical Trends for fault Analysis.
• Operator Interface with HMI / SCP
• Modbus TCP/IP Protocol
6
Manufacturing and supply of Speed sensing wheel, Over speed trip hydraulic device and
mounting accessories.
Throttle valve with Turbine Control Panels with TG & Grid Load Sharing
Pneumatic Actuator Governor & Turbo-visory system Governing Hydraulic Skid Hydraulic Power Pack Panel
for Servo Motor
7
Turkey
Bahrain Bangladesh
TEXRON
Senegal Bangalore
Philippines
Ghana Srilanka
Malaysia
Uganda
Singapore
Kenya
Indonesia
Tanzania
Zambia
Uruguay
texronpower.com