Claim Lost of Productivity
Claim Lost of Productivity
Loss of Productivity
Ahmed Ibrahim PE
Planning Expert
Claims
Claims Management [email protected]
1- Introduction.
One of the most contentious areas in construction claims is the calculation or estimation of lost
productivity. Unlike direct costs, lost, productivity is often not tracked or cannot be discerned
separately and contemporaneously. As a result, both causation and entitlement concerning the
recovery of lost productivity are difficult to establish. Compounding this situation, there is no
uniform agreement within the construction industry as to a preferred methodology of
calculating lost productivity. There are, in fact, numerous ways to calculate lost productivity.
Many methods of calculation are open to challenge with respect to validity and applicability to
particular cases — thus making settlement of the issue on a particular project problematic. The
most common issues that we encounter in records, including those related to progress and that
have actually been produced partly or fully, are as follows:
1. Actual activity starts and finish dates and stated progress %’s not supported by
records.
2. Changes (e.g., to logic and durations) were made to programme when updating.
3. Inaccurate and overstated progress reporting.
4. Progress not recorded against an approved programme;
5. No contemporary records of labor productivity.
6. Missing information in progress reports (e.g., activity location)
7. A reluctance to produce actual cost records.
8. Over-reliance on letters rather than primary records.
9. Multi-topic correspondence.
10. Inconsistent and conflicting records.
11. Illegible documents.
12. Undated photographs, without location information (e.g., floor level).
13. Inadequate document management and control systems.
14. Incomplete or inaccurate document registers; and
15. Disputed record attributes e.g., not approved, not an “original”, not signed.
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.
The analysis has been established to compare the level of productivity achieved in areas or
periods of the works impacted by identified disruption events with productivity achieved on
identical or like activities in areas or periods of the works not impacted by those identified
disruption events.
1st Scenario, the contractor has executed 10000 EA brick walls on 19 working days with 1350
Man-hours.
The task /Activity has been executed on 19 working days. And the team worked without any
disruption and the predecessor’s activities finished on time and successors activities have
started on time without any delays.
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.
Actual Handcount
12
10
0
Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day- Day-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Handcount 5 7 8 9 9 10 10 11 11 9 8 8 7 5 4 4 4 3 3
(Anon., n.d.)
2nd Scenario, the contractor has executed 10000 EA brick walls on 24 working days with 1600
Man-hours.
The task /Activity has been executed on 24 working days. And due to the piece meal of design
and drawings suspension the crew efficiency has been disturbed.
Frequent design changes during the constructions had disrupted the workflow, lead to rework,
and extended the activity timeline.
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.
Actual Handcount
12
10
0
Da Da Da Da Da Da Da Da Da Da Da Da Da Da Da
Da Da Da Da Da Da Da Da Da
y- y- y- y- y- y- y- y- y- y- y- y- y- y- y-
y-1 y-2 y-3 y-4 y-5 y-6 y-7 y-8 y-9
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Disruption Period 5 7 8 9 9 10 9 6 6 9 3 8 8 7 4 4 5 8 3 3 3 3 3 3
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.
that is, for every 1.0 man-hour worked, 0.84 man-hour's value of work.
was produced, in the disruption period.
4-Conclusion
To conclude, this article discussed the cornerstones of the analysis of disruption claims, especially loss of
productivity. And disruption claims allow contractors to seek financial compensation for the additional
costs incurred due to unforeseen disruptions. This can include costs associated with extended project
durations, increased labor, additional materials, and equipment usage.
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.
And the article proved that comprehensive record-keeping is vital for substantiating claims and can be
beneficial for post-project evaluations, audits, and in the event of legal proceedings.
Anon., n.d. Estimating Lost Labor Productivity in Construction Claims. AACEI 25R-03 ed. s.l.:s.n.