0% found this document useful (0 votes)
11 views

Program Schedule & Micro Plan

Uploaded by

SKY Editz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

Program Schedule & Micro Plan

Uploaded by

SKY Editz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Revised Project Work Schedule

Jehovah Builders Pvt.Ltd.,

Project Name:Site Preparation work for delivery and installation of X- Ray based drive through container scanner at ChPT
Client :M/s Rapiscans Systems Pte Ltd.,
S.No Description of works Duration Start date Finish Date Remarks

1 Date of Receipt of LOA 1 Wednesday, August 5, 2020 Wednesday, August 5, 2020


2 Project Schedule 240 Wednesday, August 5, 2020 Friday, April 2, 2021
3 Site Bushes Cleaning 1 Wednesday, August 12, 2020 Thursday, August 13, 2020
4 Field Survey works 1 Friday, August 14, 2020 Saturday, August 15, 2020
5 Commencement of works 1 Sunday, August 16, 2020 Sunday, August 16, 2020
6 Operation and maintainance 199
building Sunday, August 16, 2020 Wednesday, March 3, 2021

Excavation

Pcc side shutering

Pcc

Reinforcement

Footing Shutering

Rcc
Plinth below short column
shutering & Rcc
Filling & Combaction
Plinth beam below pcc
Plinth beam Reinforcement
Plinth beam shutering
Plinth beam Rcc
Plinth beam Abow column 1st lift
Rcc
Plinth beam Abow column 2nd lift
Rcc
Roof beam and slab shutering
Roof beam and slab Rcc

Roof beam and slab Reinforcement

7 Sub Structure 75 Sunday, August 16, 2020 Friday, October 30, 2020
8 Super Structure 110 Sunday, September 6, 2020 Friday, December 25, 2020
9 Finishing works 150 Thursday, October 1, 2020 Sunday, February 28, 2021
Scanner area and roofing over
10 185 Saturday, August 29, 2020 Tuesday, March 2, 2021
scanner
11 Foundation works 80 Saturday, August 29, 2020 Tuesday, November 17, 2020
12 Super Structure 120 Saturday, October 10, 2020 Sunday, February 7, 2021
13 Roofing works 110 Saturday, December 12, 2020 Thursday, April 1, 2021
14 Compound wall 150 Sunday, September 27, 2020 Wednesday, February 24, 2021
External service-UG sump,DG and
15 173 Sunday, October 11, 2020 Friday, April 2, 2021
Septic tank

16 Road works 120 Sunday, October 11, 2020 Monday, February 8, 2021
17 Landscapping and development 90
works Sunday, October 25, 2020 Saturday, January 23, 2021
18 Electrical Works 150 Sunday, September 27, 2020 Wednesday, February 24, 2021
19 HVAC works 135 Sunday, October 18, 2020 Tuesday, March 2, 2021
20 Fire Fighting works 120 Sunday, November 8, 2020 Monday, March 8, 2021
21 Final Testing and commisioning 120
works Sunday, November 29, 2020 Monday, March 29, 2021
22 Final Site Handing over 4 Monday, March 29, 2021 Friday, April 2, 2021
Project Work Schedule
Jehovah Builders Pvt.Ltd.,

Project Name:Site Preparation work for delivery and installation of X- Ray based drive through container scanner at VOCPT
Client :M/s Rapiscans Systems Pte Ltd.,
S.No Description of works Duration Start date Finish Date Remarks

1 Date of Receipt of LOA 1 Wednesday, June 3, 2020 Wednesday, June 3, 2020


2 Project Schedule 240 Wednesday, June 3, 2020 Friday, January 29, 2021
3 Site Bushes Cleaning 1 Wednesday, June 10, 2020 Thursday, June 11, 2020
4 Field Survey works 1 Friday, June 12, 2020 Saturday, June 13, 2020
5 Commencement of works 1 Sunday, June 14, 2020 Sunday, June 14, 2020
6 Operation and maintainance 199
building Sunday, June 14, 2020 ###
7 Sub Structure 75 Sunday, June 14, 2020 Friday, August 28, 2020
8 Super Structure 110 Sunday, July 5, 2020 Friday, October 23, 2020
9 Finishing works 150 Thursday, July 30, 2020 Sunday, December 27, 2020
Scanner area and roofing over
10 185 Saturday, June 27, 2020 ###
scanner
11 Foundation works 80 Saturday, June 27, 2020 ###
12 Super Structure 120 Saturday, August 8, 2020 Sunday, December 6, 2020
13 Roofing works 110 Saturday, October 10, 2020 Thursday, January 28, 2021
14 Compound wall 150 Sunday, July 26, 2020 ###
External service-UG sump,DG
15 and Septic tank 173 Sunday, August 9, 2020 Friday, January 29, 2021

16 Road works 120 Sunday, August 9, 2020 Monday, December 7, 2020


17 Landscapping and development 90
works Sunday, August 23, 2020 ###
18 Electrical Works 150 Sunday, July 26, 2020 ###
19 HVAC works 135 Sunday, August 16, 2020 Tuesday, December 29, 2020
20 Fire Fighting works 120 Sunday, September 6, 2020 Monday, January 4, 2021
21 Final Testing and commisioning 120
works Sunday, September 27, 2020 Monday, January 25, 2021
22 Final Site Handing over 4 Monday, January 25, 2021 Friday, January 29, 2021