MST Cable Pulling, Termination and Testing (LV Power, ICT and Earthing Cables)
MST Cable Pulling, Termination and Testing (LV Power, ICT and Earthing Cables)
TABLE OF CONTENTS
1. SCOPE OF WORK
The method of statement covers basic requirements for Cable Pulling, Termination and
Testing (LV Power, ICT and Earthing Cables) for MAM 150 M UTILITY CORRIDOR AT
SOUTHERN
CLUSTER PROJECT, in accordance with a scope of work, Issued for Construction (IFC) Drawings,
PARSONS/
2. DEFINITION
COMPANY - NEOM
CONTRACTOR - Masad AL Mutery Group
ASTM - Job Safety Analysis
PMC - PARSONS
RFI - Request for Information
- Work Inspection request
WIR
- Health Safety and Environmental
HSE
- Quality Control Plan
QCP
- Inspection and Test Plan
ITP
- Safety Task Assignment
STA
- Personnel Protective Equipment
PPE - Quality Assurance/Quality Control
QA/QC - Quality Department
QD - Quality Control Plan
QCP
3. REFERENCES
Substations
Grounding
Lighting
Telecommunication: Building Cable Systems, Pathways and Spaces
ITP for Low voltage cables and wires
NESC - National Electrical Safety Code
NEC - National Electrical Code
ANSI - American National Standards Institute
NEMA - National Electrical Manufacturers Association
NFPA 13 - Standard for the Installation of Sprinkler Systems
NFPA 70 - National Electrical Code (NEC), 2011 Edition
NFPA 72 - National Fire Protection Association
ANSI/UL 10B - Fire Test for Door Assemblies
UL 268 - Smoke Detectors for Fire Alarm Signaling Systems
Vendor Manufacturer's Installation Instruction Manual
NEOM Project specifications/standards
NEOM/PARSONS IFC Drawings
Specific Note: All work shall be carried out in accordance with applicable ITP and associated checklists
as well as manufacture’s instruction either specified in this procedure or not.
4. RESPONSIBILITIES
The Project Manager has the overall responsibility t o attend the pre-construction meeting for any new
works related to the project and follow up the implementation of this Method Statement as follows.
- To ensure that all the preparation and application works are carried out according to the Contract
Specification.
- To ensure that the progressing of works is carried out according to the planned program and as per the
approved Method Statement.
- To ensure that all equipment and materials required for executing the work are available according to
the planned Construction Program.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
The Construction Manager is responsible to attend the pre-construction meeting and to verify and
implement this Method Statement at any subsequent revision of the project. In addition, He is
responsible for ensuring that all works performed timely, properly, accurately and completely and aside
from making sure, that corrective action are taken in case the work was not done correctly.
However, he ensures that all safety issues are promptly addressed and remedied and safety
requirements and stipulations are met and that all works are performed in accordance with well-
established practices, Method Statement and in compliance with the schedule.
The Construction Manager shall report to the Project Manager on the overall status of the site execution
works.
Electrical Superintendent shall study and review all necessary documents for the Installation and
provides necessary support in preventing unnecessary delays in Electrical, Instrument and Telecom
construction activities. This includes, technical scope of work, specifications, bill of quantities,
planned milestone dates and construction procedures. He shall monitor the availability of materials in
accordance with the scheduled construction activities.
He shall be directly reporting to the Electrical Construction Manager. He shall coordinate with other
disciplines to visualize possible conflicts in the obstruction and find appropriate solutions.
- Responsible for ensuring in the implementation of all activities related to this Method Statement
are being carried out as per project specification, drawings, material technical data sheets as well
as of the project safety requirement.
- Ensures that Site Engineer, Foreman and all operatives involved in the work will be briefed with
Method Statement and what will be expected of their work performance.
- Ensures that the Site Engineer and all supervisors perform their tasks properly and on time.
- Secures all work permits to execute the job and ensures that a copy of the permit will display in the
work area.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
- Supervise the execution of the work and ensure that it will do as per approved project
specifications, drawings, and work Method Statement.
- Ensures that all required equipment and materials to carry out all work activities are available and
properly distributed at site.
- Prepare and submit the daily report in coordination with the site foremen.
- To ensure that all field operatives including Subcontractor personnel directly involved with the
performance of the works will be briefed with this Method Statement and what will expected of their
works performance.
- Ensures that all corrective works is promptly performed following in-house inspection.
- Shall maintain the monitoring of the Bore holing Works until completion.
- The Site Engineer reports directly to Project Engineer or Superintendent.
4.5 FOREMAN
- Prepares STA’s and conduct on daily basis to ensure that each member of the crew is aware of their
tasks and recognize the hazards and to ensure that all control measures to arrest the hazards are
being implemented.
- To ensure that all members of the crew are familiar with the performance of the work they tasked to
perform and that they perform it properly and in a timely basis.
- He is responsible in the assignment of the qualified operatives to handle specific portable
equipment.
- The Foreman reports directly to the Site Engineer
The HSE Manager is responsible for overall responsibility of ensuring, through the Safety
Supervisors/Safety Officers supervising the work, that the works in the field are performed safely and
in compliance with all safety standards and procedures of PARSONS/NEOM .
The HSE Manager shall reports to the corporate HSE Manager and coordinates matters with
PARSONS/NEOM HSE Team along with the functional responsibility to the Project Manager.
- To ensure that all safety requirements necessary to start these activities provided by the
construction group as per project HSE Manual and specifications.
- Conduct Hazard Identification & Risk assessment prior to start of work.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
- To ensure appropriate work permit has been received prior to start any activities.
- Discuss STA, what is the importance of STA for every activity like for the potential hazard in the
workplace and how to eliminate the hazard.
- Conducts inspection with Field Supervisor to ensure that all safety requirements being maintained
up to the completion of these activities.
- To report any unsafe act/unsafe conditions on workplace to HSE Manager in order to take corrective
action.
- To implement & compliance to PARSONS/NEOM HSE policy at the construction site.
4.8 QC MANAGER
The QC Manager has the overall responsibility for ensuring that work activities in site are performed in
compliance with all applicable quality standards, stipulations and approved Quality Control Procedure
in addition that corrective actions are taken in cases where works are not performed correctly.
The QC Manager shall report to the corporate Quality Assurance Manager and coordinates matters with
PARSONS/NEOM Quality Team along with the functional responsibility to the Project Manager.
4.9 QC SUPERVISOR
The site Quality Control Supervisor reports to the site Quality Control Manager; he is responsible for
the coordination of the inspections and tests during construction and pre-commissioning phases and
communicates with subcontractors (a) supervisors/Inspectors and third-party agency. He has
sufficient authority, access to work areas and organizational freedom to identify quality problems,
initiate, recommend or provide solutions, and verify the implementation of solutions.
Main Responsibilities:
- Carry out all the tasks that involve the inspection and tests till the end of mechanical completion.
- Communicate with assigned inspector to ensure the findings are addressed correctly in the
inspection report. Verify the issuance of inspection and test reports in accordance with inspection
and test procedures.
- Review and approve the results of inspection and test performed by subcontractor/third-party
including NDT.
- Identifying activities requiring to prepare and submit two weeks lookahead inspection schedule for
site QC manager review.
- Review and validate contract and subcontractor test reports prior to submittal to COMPANY.
- Trace FRI when necessary to verify the inspection status.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
- Collect and ensure records for quality inspection activities, in agreement with procedure or
applicable operative instructions and maintain records.
- Initiate/issuance of Internal Non-Conformance Report once a nonconformity has been detected.
4.9 QC INSPECTOR
- The QC Inspector is responsible for the submission of the IN and coordinating on the relevant
inspection after verification of the completed work by the construction team, to ensure compliance
to standard and specification requirements.
- Reports to QC Supervisor and to Site Engineer if portion of the work has not been performed
correctly and ask the Site Engineer to take corrective action.
- Reports directly to the QC Supervisor.
- The QC Inspector shall conduct in-house inspections in coordination with the Project Engineer who
is to ensure that all corrective actions necessary from said inspections will be performed promptly
by the Site Engineer and/or Foreman.
- QC Inspectors to log in all observed non-conformances in the Daily Surveillance Report and shall
coordinate with the Construction team for implementation of timely corrective measures.
- To ensure all test inspections will be performed and all relevant inspection forms will be recorded
as per Project specifications and applicable ITP.
- The QC Inspector shall report directly to the Quality Control Manager
5. MANPOWER
• Electrical Forman
• Industrial electrician
• Instrument Fitter
• FO Cable Splicer
• Scaffolder
• Helper
• Manlift Operator
• Boom Truck Operator
• Forklift operator.
• Backhoe/Excavator Operator and riggers, flagman.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
• Measuring Tape
• Cable cutter
• Wire stripper
• Multi Tester
• Megger
• Heat gun or blow gun
• Marker pen
• Screwdriver Set, Spanner Key Set, LN Key Set
• Lorry crane, Excavator (Backhoe), Mobile crane
• Grinding Machine, Torque wrench, High Potential (Hipot) Test
• Manual Crimping Tools, Cable tie Tighting tools
• Hydraulic Crimping Machine
• Flat & Round Files
• Screw Drill Electrical
• Knife with blades.
• Fish Tape (Wire Puller)
• Cable Rollers or Cable drum stands.
• Wire and cables termination tool kit
• Control Cable termination and testing tool kit.
• A-type ladder
• Hand Gloves
• Eye protection
• Fire Extinguisher
• Data termination and testing tool kit (Insulation striper, RJ45 Crimping tool, RJ45
tester, cleaning accessories, T Cutter etc.)
• Labeling Kit
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
6.2 MATERIALS
• Storage and Handling of cable before and during installation is carried out according to
manufacturer’s recommendation.
• Prior for hauling and transferring of materials to laydown area, study and check possible route
to be taken and verify overhead clearances, turns radius and path are clear from any
obstructions. The use of equipment such as boom truck are necessary for proper hauling and
unloading of materials to its location.
• Ensure that all lifting gear are being checked and are in good condition prior for lifting and
unloading works to avoid possible damage to all the materials.
• All cable drums shall be properly stored and safe keep at lay down area. Cable drums must
be stored on their round side and must not lie on its flat side. It shall be stored in designated
areas in such a manner that it can be easily identified and/or removed.
7. SAFETY
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
7.1 All work shall be undertaken in accordance with the PARSONS/NEOM Project HSE Manual
and all individual activities will be set up in an orderly manner to ensure compliance with the
requirements.
7.2 Necessary work permits shall be obtained (by the Site Engineer) prior to start of any work
activity and work shall commence in accordance with the specific. Measures itemized in the
permit. A copy of the work permit shall be displayed at designated areas on site near the work
area to make available all relevant information on the permit to all operatives performing the
works.
7.3 All necessary Personal Protective Equipment (PPE) shall wear during work at all times (Where
required) shall wear shoes, safety helmet, safety vests, goggles and hand glove.
7.4 All operatives will receive a (STA) Safety Task Assignment prior to commencing the works. This
Method Statement will be briefed all Operatives carrying out the works.
7.5 Safety signage’s and barricades, traffic cones shall be provided whenever required during the
implementation of this activity.
7.6 The worksite shall be maintained in a clean and tidy condition for the duration of the works.
8.1 INTRODUCTION
8.1.1 Prior to starting any work covered by this Method Statement, a preconstruction or Toolbox
meeting between directly involved supervisory/management personnel including HSE &
Quality Control Department of the Contractor and sub-contractor together with the
Client Representative/s shall be scheduled.
8.2.1 Prior to starting any work covered by this Method Statement, a preconstruction or Toolbox
meeting between directly involved supervisory/management personnel including HSE &
Quality Control Department of the Contractor and sub-contractor together with the
Client Representative/s shall be scheduled.
8.2.2 Ensure that the material received follows the project specifications and approved MARs.
Delivered materials are to be received, inspected, and tested in accordance with ITP
approved by PMC/ESTD
8.2.3 Ensure that all required materials and accessories are delivered, inspected through WIR,
and approved by the NEOM and are readily available at the site to carry out the work.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
8.2.4 Prior to the commencement of work, areas, and access will be inspected to confirm that
site is ready to commence the work and coordinated with the related
disciplines/contractors.
8.2.5 All relevant documentation, approved shop drawings and material applicable to
particular section of works will be checked by Site Engineer prior to commencement of
work. Section of works will be checked by Site Engineer prior to commencement of work.
8.2.6 The Site Engineer/Site Supervisor will give necessary instructions to
tradesmen/electrician and provide necessary approved construction/shop drawings.
8.2.7 The Site Engineer/Site Foreman will check that proper tools and equipment are available
to carry out the work and are in compliance with JSA and contract specifications. All tools
and equipment shall be prepared and checked prior for cable pulling activities. Tools are to be
inspected and tagged to the site colour coding system and all defective tools and equipment
shall be returned immediately to Tool Room and/or Equipment Services to avoid inadvertent
use.
8.2.8 The Site Engineer will explain his team about HSE precautions to be observed.
8.2.9 The Site Engineer/Foreman ensures the cleanliness of area.
9.1.1 Special tools and testing shall bear valid calibration traceable to a national standard
indicating calibrating validity and periodically checked by third party laboratory testing
facility.
9.1.2 Check and prepare manpower, equipment, tools and other logistics for installation.
9.1.3 Ensure that working areas are ready for installation.
9.1.4 Review all references such as latest Issued For Construction drawings, Layout and
Technical Scope of Work, work permit requirements, and work procedures.
9.1.5 Secure necessary permits prior to start activity.
9.1.6 Confirm the installation of conduiting, cable tray has been completed and inspected
prior to pull wires and cable.
9.1.7 Ensure all materials, accessories and consumables shall be prepared and checked prior
to commencing with the works.
9.1.8 Ensure that all personnel are qualified for the work and are fully familiar with the tools
and equipment to be utilized.
9.1.9 Ensure technician must be qualified and approved as per schedule-Q.
9.1.10 CONTRACTOR shall obtain PMC/NEOM Approval of all job classifications (crafts) that
require qualification procedures and job clearance cards according to PMC/NEOM
requirements especially for MV cables termination and splicing works.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
9.1.11 Ensure that all relevant documents have been approved by contractor PMC/NEOM prior
to commencing installation, and that the latest revisions of IFC drawings [IFC drawings
shall be in line with mandatory standards requirements], specification, manufacturer’s
instruction/factory test reports, including approved procedures and disseminated to
concern personnel who carry out the work.
9.1.12 Ensure that all test equipment to be utilized is newly calibrated. Cable sealing shall be
done by proper cable gland or other applicable procedures as per requirement of
PMC/NEOM Standards.
9.1.13 Prior to installations and termination of cables and wires, verify the Electrical Equipment
(Panelboards, Transformers, Luminaires, wiring devices), Fire and Gas field instruments,
data outlets, Paging speakers, HVAC Field devices shall be suitable for the environment
where they are being installed. Panelboards, disconnect switches, Luminaires, outlets
and Fire Alarm/HVAC field devices installed outdoor shall be approved as weatherproof
and dust tight [IEC, NEMA, and UL may have differences in classifying and defining
weatherproof, rainproof, wet locations, etc. The intention of this requirement is to have
equipment suitable for the application.
10.1.1 Small Power & Lighting (Transformers, Panelboards, Disconnect Switches, Power
Receptacles).
10.1.2 Communication (Voice and Data; Paging Speakers; Access Control; CCTV)
10.1.3 Instrument Control Cables: Fire Alarm Cables
10.1.4 Instrument Control Cables: HVAC Control
10.2 METHODS & PROCEDURES FOR CABLING WORKS: CABLE PULLING ( LV & ICT)
10.2.7 Secure approved drawing for Electrical & ICT for reference during layout. It should be
approved for construction.
10.2.8 QC inspection and acceptance for the installed cable for all Electrical Equipment,
lighting fixtures, convenience outlets
10.2.9 All wires utilized shall be continuous from source to point of termination without any
through joint.
10.2.10 Cable shall be installed protected from mechanical damage and where possible, within
the web of existing steelwork.
10.2.11 Pull the cable on main cable tray and to its branches in safely manner avoiding possible
mechanical damages and stress to cable. Arrange the cable on tray and fasten properly
by using approved type cable ties.
10.2.12 low voltage, control, and instrument cable shall be segregated
respectively and categorized with respect cable schedule and protected as appropriate.
10.2.13 Wires or cables to be pulled inside conduits with gentle pull using approved lubricant
where required to avoid physical damages to the insulation or conductor itself.
10.2.14 Proper stands and rollers to be used for cable/wire pulling to avoid twisting of cables and
wires and to ensure smooth installation of cables and wires.
10.2.15 All wiring of multi point circuits shall be carried out in a looping loop -in system.
Connections other than those required for the connections of switches, fuses, socket
outlets, motor etc. shall not be allowed.
10.2.16 PVC Insulated wires shall not cross any luminaries or heat producing equipment.
10.2.17 Traffic control shall be in place while duct bank installation works and cable pulling
works along busy working areas.
10.3.1 Excavation of cable trench/duct banks shall comply with the latest issued approved for
construction drawings and specifications prior to cable pulling. The use of equipment
such as backhoe is necessary for this activity. Backfilling works for cable trench shall
commence after the all the cable pulling works are done.
10.3.2 All PVC & HDPE duct banks and building entries shall be identified according to
construction drawings. Temporary cable trench sectional marking shall be installed near
the cable trench for easy identification.
10.3.3 Underground cables shall be installed in Ducts/ High Density Polyethylene Pipes or
concrete encased PVC pipes in accordance with approved IFC/Shop drawings.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
10.3.4 Cable trench shall be inspected and to be free of any foreign materials and/or sharp
edges. Ensure that the cable trenches are of proper route, width, and depth conforming
to specifications and IFC/Shop drawings.
10.3.5 Upon acceptance of cable trench, sand bedding shall be placed. Sand bedding materials
to be used shall be free from any sharp stones, debris and contaminant material. The
sand bedding or soil in the cable trench and around the PVC Ducts shall be well water
compacted.
10.3.6 PVC / HDPE shall be used as conduit in the duct bank with a minimum distance between
them as per IFC/Shop drawings. The sizes of the PVC / HDPE shall be shown on the
approved IFC/Shop drawings. Duct banks shall also be inspected and to be free of any
foreign materials and/or sharp edges.
10.3.7 Upon completion and acceptance of installed PVC/HDPE duct banks, the cable trench
surface shall be covered with PVC warning tape (On top of sand bedding over PVC/HDPE
duct banks).
10.3.8 After installation of Warning Tape, proceed with final backfilling of cable trenches.
10.3.9 As part of cable pulling preparation, set cable drum jacks on leveled and stabled ground,
use dunnage or plywood if necessary.
10.3.10 To ensure that proper cable identification (Tagging) is provided at the lead end of the
cable before pulling and to the other end after cable laying matching the assigned cable
identification in the cable schedule.
10.3.11 Cables shall be carefully handled and pulled to avoid damage in insulation and over
tension during cable pulling. Sufficient clearance shall be provided from foreign
structures, such as water main, sewers and gas lines.
10.3.12 Pull underground cable manually and/or by machine with tension-meter (as appropriate)
in safely manner taking care of cable especially on MV voltage of big sizes. Sufficient
manpower shall be deployed in normal interval protecting the cable for possible
insulation damages and stress to cable. Cable will normally pull by hand, segregated by
voltage and duty into group to the dimensions detailed in the installation drawings. Laying
patterns shall be strictly adhered to since cable sizing and current ratings are based on
group rating factors applied especially to those patterns and relevant environmental
conditions.
10.3.13 Cable rollers, such as corner rollers and straight rollers shall be used wherever
necessary.
10.3.14 Before cutting the cable, both ends must be inspected to ensure sufficient length is left
for slack and termination allowance.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
10.4.1 Earthing cables shall be inspected for possible factory or handling damaged.
10.4.2 Install Earthing cable following the routing and plans in accordance with the IFC/
Shop drawing. Earthing cable shall be laid in direct buried in trench.
10.4.3 All installation works shall be in accordance with Earthing installation drawings. 10.4.4
Conduct Continuity and Insulation Resistance Test and Earthing Resistance Test for the
pulled earthing cable.
10.4.5 All inspection and testing of earthing cables shall conform for electrical inspection
and testing.
10.5 METHODS & PROCEDURES FOR CABLING WORKS: CABLE TERMINATION & TESTING (
LV and Lighting)
10.5.1 Material to be approved, inspected prior to using through material receiving inspection.
10.5.2 QC inspection and acceptance to be obtained for the installed Electrical Equipment,
lighting fixtures, convenience outlets, perforated trays and conduits prior to commence
cable termination works.
10.5.3 Ensure the cables are installed as per approved IFC/Shop drawings and NEC standards.
10.5.4 After completed installation, individual cable lengths shall be Continuity and Insulation
Resistance tested.
10.5.5 If the cable is not going to be terminated immediately after its installation, cable end shall be
sealed to avoid moisture and water-ingress. Provide temporary identification to each end for
easy reference during termination.
10.5.6 Minimum wires and cables extension to be maintained in termination or switch boxes in
accordance with NEC requirements.
10.5.7 All wires and cables to be tagged labeled in accordance with cable schedules and
according to dedicated circuits mentioned in panel schedules for termination. Labeling
the wires and conduit should be as per KSA standards and procedures using approved
method of labels.
10.5.8 Wires shall be drawn in a skillful and workmanship manner.
10.5.9 Glanding termination, splicing, cable tags, core marker and name plate installation as
per requirements for each discipline.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
10.5.13 QC inspection and acceptance for cable pulling above ground level passing main
tray
towards lighting panel board.
10.5.14 Cables and wires for power and lighting to be pulled according to color codes
mentioned
in lighting skeleton diagrams, panel schedules and NEOM standards or
applicable international standards.
10.5.15 Sizes of cables and wires to be installed carefully according to approved IFC drawings
and load ratings to be verified according to panel schedules.
10.5.16 Ensure the cables or wires length does not exceed the allowable length to control
the
load losses and voltage drops.
10.5.17 All wires utilized shall be continuous from source to point of termination.
10.5.18 Ensure the cables and wires are tested for Insulation resistance and recorded through
QC inspection as per requirements of IEC and NEC standards.
10.5.19 Ensure the cables and wires are secured at entries into panelboards/equipment using
appropriate cable terminal glanding or as per approved IFC drawings.
10.5.20 Ensure cables and wires meet the minimum extension requirements for
termination
inside the enclosures/Junction Boxes as per NEC standards.
10.5.21 Ensure the cables and wires are marked and labeled according to appliable standards
and terminated using appropriate terminal lugs for each size.
10.5.22 Ensure the cables and wires are labeled and marked as per approved IFC drawings and
NEC requirements.
10.5.23 Ensure the equipment tags are installed as per approved drawings and equipment tag
lists.
10.5.24 QC inspection and acceptance for cable and wire termination.
10.5.25 QC Inspection for final testing and acceptance. Internal inspection/ review by QC and
operation on a possible miss look of material requirements as per drawing and rectify
right away prior to WIR submittal within 24hrs.
10.6.1 Material to be approved, inspected prior to using through material receiving inspection.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
10.7 METHODS & PROCEDURES FOR CABLING WORKS: FIBRE OPTIC CABLES INSTALLATION,
TERMINATION AND TESTING
10.7.1 Material to be approved, inspected prior to using through material receiving inspection.
10.7.2 Pull cable with extra cautious to prevent the optical cable experiencing direct stress
following the cable pulling.
10.7.3 Cable must never be over-bent going through trays or conduits, between tray section, or
when making transitions between locations.
10.7.4 Cables should never be kinked or knotted.
10.7.5 Fibre Optic Cable termination works to be only carried out by authorized Fibre Optic cable
terminators.
10.7.6 Precautions should be taken to avoid cut fiber cables contact with eyes or skin or clothing
in terminating the cable.
10.7.7 Terminate the points of the fiber optic on the designated slot in the patch panel according
to approved for construction drawings.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
10.7.8 Use fusion type or any technique approved by client, for the termination or splicing of the
cable it should be compatible with the fiber optic cable.
10.7.9 For un-terminated connectors, install dust cap on it.
10.7.10 Prior to testing end connectors should be cleaned.
10.7.11 Conduct continuity test on the fiber optic cables by emitting a laser light on the fiber
cable and check if the other ends light.
10.7.12 Upon completion of termination of Fibre Optic cables, An OTDR test to be conducted to
verify the correctness of termination works.
10.8 METHODS & PROCEDURES FOR CABLING WORKS: CONTROL CABLES INSTALLATION,
TERMINATION AND TESTING (FIRE ALARM, HVAC CONTROL)
10.8.1 Material to be approved, inspected prior to using through material receiving inspection.
10.8.2 Ensure the IFC drawings are approved and NEOM stamped for all fire and gas alarm
system.
10.8.3 Ensure all IFC drawings to be approved for HVAC control system and meet the
requirements of HVAC Standards.
10.8.4 Ensure Fire Alarm and HVAC control system pathways to be completed and inspected in
accordance NEC/NFPA 72.
10.8.5 QC Inspection for all control cables ways, cables installation and testing to be done with
reference to Approved ITP.
10.8.6 Ensure the extension and looping of cables inside back boxes to meet minimum
requirements as per NEOM Standards.
10.8.7 Control cables to be pulled gently using cables rollers, cable lubricants to avoid
insulation damages and proper marked for identification with standard marking system.
10.8.8 IR testing of fire and gas, control cables to be carried out with reference to PMC/NEOM
Standards.
10.8.9 Control cable to be terminated and labeled as per approved IFC drawings, approved
vendor termination diagrams and applicable PMC/NEOM standards.
10.8.10 QC inspection and acceptance for cable termination with reference to approved ITP.
11.1.1 QC inspection for completed lightings, devices, and steel supports shall be requested,
and inspection/ test results shall be filed and recorded on appropriate approved forms.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
11.1.2 Pre-commissioning/ testing for panel board electrical components shall be performed in
accordance with the requirements. The result shall be recorded and reported to PMC QC.
11.1.3 Final Illumination and functional test shall be conducted, and all results shall be
recorded as per PMC/NEOM forms.
11.1.4 All inspection and testing activities for lighting shall be referred to the approved ITP
complying with all the requirements.
11.1.5 Inspection of electrical equipment and power outlets shall refer to the approved ITP. QC
Inspector shall witness and record the result and shall be submitted to PMC/NEOM.
11.1.6 Documentation of whole system after completion shall be completed as required, which
shall be submitted to PARSONS/NEOM then for review and approval of document.
11.1.7 After all the lighting fixtures, and devices are terminated, a functional test is then
performed to ensure that these are connected to the right panel board and circuit in
accordance with approved energization package.
11.1.8 Ensure that the orientation of the lighting fixtures is correctly adjusted to attain an
equality distributed level of desired illumination.
11.1.9 Perform the illumination test at any location to ascertain that the desired illumination
level is attained.
12. QUALITY CONTROL
12.1.1 Standards are complied with. All testing and Inspection shall be coordinated
with
PMC/MAM Inspectors.
12.1.2 PMC/ MAM QC Inspector shall be assigned to ensure the quality control and
assurance requirement of the project.
12.1.3 PMC/ MAM QC Inspector shall be responsible to conduct all required
inspection/
documentation and ensures that all applicable requirements, codes, and standards
are complied with.
12.1.4 PMC/MAM QC Inspector must utilize the applicable ITP/IC for every activity.
12.1.5 Contractor’s QC and PMC QC Inspectors shall carry out the necessary inspections
in
various stages of the Lighting system, power receptacles, switch gear and control
equipment, communication systems, fire and gas alarm system, HVAC control system,
cable laying, cable glanding /termination of electrical works. Inspections shall be based
on approved Inspection and Test Plan and discrepancies shall be within the accepted
allowable tolerances.
13. ENVIRONMENTAL , SAFETY AND HEALTH & RISK ASSESSMENT – SEE ATTACHED
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
Method Statement for Cable Pulling,coduit, Termination and Testing (LV Power, ICT and Earthing Cables)
Wet the ground before grading and clearing works to prevent excessive generation of dust.
The drop height of excavated materials onto the ground shall be minimized to limit dust emissions.
Spill kits shall have available, adequate and suitable contents, appropriate to the quantities, if the excavation
carried out by mechanical method
Stop Work and barricade the area if Contractor finds any Natural treasure during excavation so
immediately inform to your Contractor Environmental Manager and discovery shall be reported to the
Environmental department of PMC and NEOM
In case of eye contact, wash eyes with water from eye wash.
In case task resulted in waste, clean the task site and take waste to the right waste collection area.
Housekeeping shall be maintained throughout the task. Properly dispose of all waste; don’t dump on the
ground.
No activity shall be carried out unless there is valid PTW authorized by permit issuer. Dynamic risk
assessment/ toolbox talk shall be carried out prior to each activity
All the worker shall be inducted by safety and Neom ID’S shall be obtained.
Only competent persons shall carry out the activity tasks. Task technical & HSE instructions shall be
readily available to task performer (e.g. method statement risk assessment etc.)
Task performer shall ensure that all hand-tools & equipment which are required to carry out the activity
are in good condition and that he knows how to use them safely.
Safety shoes must be worn; dust mask and hand gloves shall be provided and must be used when required.
In case of chemical use then the PPE stated by Safety data sheet shall be provided and used.
Job performer shall be trained on how to carry out safe manual handling. In case of heavy load
mechanical aids shall be used.
Defective tool / equipment shall be immediately taken out of use.
Task performer shall be trained on how to use ladder safely.
Safe mean of access and egress shall be provided
All the electrical tool must be inspected by the competent person before the task and color code shall
be updated.
Daily housekeeping shall be done and empty container shall be removed
Welfare facilities shall be provided at site
Safety data sheet be communicated to all the workers before the task
Eye wash facilities shall be readily available at site.
ABC type fire extinguisher shall be available at site.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
Note “There is zero tolerance on site safety rules. Any violation of those rules may result in
intervention to the task until corrective action is taken place.”
• Do not attempt to help or rescue if not trained to do so, you may endanger yourself
as well as the injured person.
• Make the path accessible for the rescue vehicles, do not block at any time.
• Upon arrival of the Rescue Team, do not interrupt them or attempt to help if you
are not asked to do it.
A. When the monitoring personnel and site safety officer at the construction site find any
abnormality, they shall immediately report it to the on-site emergency rescue team, who
shall immediately order to stop the operation and organize the construction personnel to
evacuate to a safe place. The evacuation of personnel shall be directed by the team
members arranged by the team leader, and the specific commander shall arrange the
personnel to evacuate to a safe place quickly, and do a good job of on-site safety warning.
B. In case of collapse accident, the emergency rescue team shall be contacted on the
emergency numbers displayed on the site lactation. The rescue team shall be fully staffed,
and the site shall be protected in addition to reporting to the HSE department and HSE
safety manager will report to client (PARSONS & NEOM) immediately.
C. When the construction personnel are buried, pressed or trapped, the support shall be
observed first. If local reinforcement is required, personnel shall be immediately organized
for reinforcement, and then personnel can be organized for rescue on the premise of
confirming safety.
D. The IP shall be rescued by the male nurse with team member on-site
E. The Site nurse shall administer the first aid and determine if the patient needs to be
brought to the site first aid room or sent directly to the hospital
F. Male nurse will give the first aid to the IP
G. The IP shall be carried to the ambulance with a stretcher. The seriously injured shall be
immediately given oxygen inhalation and infusion, and then sent to the nearby hospital for
treatment.
H. After verifying that all personnel have been rescued, take photos or
videos of the location of the injured, prohibit irrelevant personnel from
entering the accident site, and wait for the accident investigation team to
investigate and handle.
TREATMENT
A. Conduct a primary survey upon reaching the victim.
B. Initiate C-spine precautions as soon as possible.
C. Conduct a secondary survey and correct any life-threatening conditions.
D. Consider removing the victim from danger prior to providing definitive care.
For other Medical related Emergency occurring on the job site, fellow employees shall inform a
supervisor or a safety representative to call the Project Site Nurse or if None is present, they would
contact the first aider or project Nurse themselves,
• Location of the incident
• Extent of injuries
• Description of symptoms
• Seriousness and nature of the emergency
The Site nurse upon arrival shall administer the first aid and determine if the patient needs to be
brought to the site first aid room or sent directly to the hospital.
Patient shall be then carefully laid on the stretcher as per the instruction and help of the Nurse and
brought to the ambulance; from there he shall be transported to the first aid room or the hospital.
On being informed, the HSE Manager will proceed to the incident location, appraise the situation and
in the event of need, will request assistance from the nearest medical facility: e.g., Tel: () giving details
of the emergency:
• Location;
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
in Case of Fire:
➢ Do attempt to fight the fire alone, unless it is small enough that can be extinguished by a portable
fire extinguisher, never approach any fire, where there is a risk for your own safety.
➢ To operate a portable fire extinguisher, you must:
➢ PULL... Pull the pin. This will also break the tamper seal.
➢ AIM... Aim low, pointing the extinguisher nozzle (or its horn or hose) at the base of the fire. ...
➢ SQUEEZE... Squeeze the handle to release the extinguishing agent.
➢ SWEEP... Sweep from side to side at the base of the fire until it appears to be out.
1 Equipment Notify First Aider, Project Nurse PM, CM, SM, PMC
overturn NEOM
2 Collision of Call the safety-first aider /foreman nearby. check if
equipment with the driver inside equipment/ vehicle, check if there
other vehicles is minor /major injury, and only remove the person
from equipment
3 Other Check the wellbeing of worker, wait for help,
document the accident
MAM will notify all Serious Incidents to the Project Management Consultant or Delivery Partner as
soon as possible by the quickest available means (normally by telephone). The Project
Management Consultant or Delivery Partner must then notify such events to the Employer as
soon as practicable and within 2 hours of occurrence.
Notification is designed to alert the Employer and it is recognized that only basic information may
be available immediately after an incident. The Project Management Consultant or Delivery
Partner is responsible for ensuring appropriate and factually correct information is provided to
the Employer.
All Serious Incidents must also be entered onto Enablon within 24 hours of occurrence. For
reference NEOM-NPR-STD-001 Appendix C provides further guidance on the key notification,
reporting and investigation steps following an incident.
evidence to complete the investigation, requirements for specialist testing, expert testimony, etc.,),
the Employer must be notified, and the investigation and report entered onto Enablon as soon as
possible.
All Contractors’ investigations must be reviewed and verified by the relevant Project
Management Consultant or Delivery Partner prior to submission to the Employer.
The final investigation report, whether generated by the Contractor or Project Management
Consultant or Delivery Partner, must be approved by a senior leader (e.g., Project Director) of
the Project Management Consultant or Delivery Partner.
Final investigation reports must be suitable and sufficient as well as proportionate to the
severity of the incident and the level of risk.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER
13.8.1 Rest area: - MAM shall provide designated rest areas that are sufficient to hold the
number of employees working in that area. Any rest areas should be adequately protected from
adjacent plant/equipment/roads etc. Rest shelters must be provided while workers are
undertaking site activities to protect them from adverse weather conditions (heat,
sun, wind, cold, etc.)
• The rest area shall be completely shaded from the sun, and allow fresh air to
circulate constantly; if indoors, ventilation or air-conditioning is to be provided.
• No construction materials, chemicals or flammables are to be stored within the rest
area.
• Where reasonably practicable, seating and tables are to be provided.
• Rest Areas are to be designated as “No Smoking
• Water coolers should be shaded where placed on-site out of direct sunlight wherever
possible
• Drinking water must be marked ‘Drinking Water’ in Arabic, English and the most
common languages used in the workplace.
13.8.3 First aid station: - for Employees during the installation of septic tank a First
Aid Room and qualified MOH male nurse and First Aid materials and supplies. A First Aid
Room shall be furnished and equipped as advised by a licensed nurse
A medical staff holding a current certificate issued by a registered nurse shall be on duty
in the station at all hours when work is in progress and he should be capable in dealing with
any emergency that arise within the project
Ambulance
- Driver must be a holder of a current Saudi Driving License with the specific restriction
code.
- He must be trained in first aid and able to understand and speak the English
language.
- He must be able to pass the practical driving test conducted by the Project Safety
Manager or his representative.
- The Ambulance driver must familiarize himself of the road access at the work site
and fabrication yards.
13.8.4 Toilet facilities: - MAM will provide portable toilets facilities during the
installation of temporary facilities and will make sure it should be sufficient in numbers with
adequate water supply with all be basic requirement as per NEOM safety standards
• MAM shall ensure an adequate supply of toilet paper, soap and a means of
hand at drying all times. Cleaning roster on the entire project site and lay down
area must be displayed outside of the toilet.
• Toilets should be well lit, ventilated and kept clean at all times. Contractor shall
introduce a cleaning and maintenance regime to ensure that good hygiene standards
are maintained. In the instance where portable toilets are hired for site, Contractor
shall ensure that cleaning and maintenance is provided by the Supplier as part of the
contract agreements.
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER
OXAGON, NEOM
NEOM City
Method Statement for E&I Cable Pulling,coduit, Termination
and Testing (LV Power, ICT and Earthing Cables)
IDFFFGULF CO-OPERATATION SYMBOLS
(MAM) 150 M UTILITY CORRIDOR AT
SOUTHERN CLUSTER
INCIDENT EMERGENCY
Chandra Dev
SAFETY OFFICER
0560466745
AYman
SITE NURSE
0538058472
RED CRESCENT
AMBULANCE 997
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 1 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 2 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 3 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 4 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 5 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 6 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 7 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 8 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 9 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 10 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 11 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 12 of 67
7 Material Storage and Handling Workers/ • All workers attended HSE induction and Responsible Person:
Operators/ Driver/ Construction manager /
3 P AR required training prior to work. 3 R A
Engineer/ Supervisor/
• Trip/slip and fall Supervisor/ • Short service employee should work under the Safety officer
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 13 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 14 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 15 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 16 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 17 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 18 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 19 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 20 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 21 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 22 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 23 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 24 of 67
11 Positioning of cable drum on Operatives/Staff • Consider the weight size and fitness and then Responsible Person:
cable jacks Construction manager/
assign them the work Engineer/ Supervisor/
• Manual handling
• Implement buddy system. Safety officer
• Slip and Trip/Fall hazard
• Use mechanical aid during lift as much as
• Sharp edges.
• Caught in between/Pinch possible
points • Do not put yourself in the line of fire.
• Ergonomics, Fatigue • Always be on alert.
• Unsecured cable jacks on 3 P AR • Ask for help on heavy load 3 R A
elevated area. • As much as Proper segregation of materials
• Rolling cable drums • Access shall not be obstructed. Keep all
materials in order
• Daily housekeeping of material shall be done
and material shall be removed and arranged
properly away from pedestrian walkway.
• Always use appropriate gloves when handling
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 25 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 26 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 27 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 28 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 29 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 30 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 31 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 32 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 33 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 34 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 35 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 36 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 37 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 38 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 39 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 40 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 41 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 42 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 43 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 44 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 45 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 46 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 47 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 48 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 49 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 50 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 51 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 52 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 53 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 54 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 55 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 56 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 57 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 58 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 59 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 60 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 61 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 62 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 63 of 67
24 Housekeeping Site Workers/ • Housekeeping shall be conducted prior to start Responsible Person: Site
• Trip, Slips & fall 3 P AR 3 R A Engineer/ Supervisor/
Supervisor/ the activity and after finished the job.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Rev.01
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 64 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 65 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 66 of 67
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form
Name of project
or activity:
150 M UTILITY CORRIDOR AT SOUTHERN CLUSTER NEOM code:
Component or
aspect of work:
Risk assessment for E&I cable pulling, termination and testing Sheet no. 67 of 67
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Naveed aftab
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI Safety manager
M = Possible – possible at some time UL N A A AR AR Engineer Real
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
Likelihood
H =Likely – likely to occur several times P A A AR AR UA ocm
5 to 15 man-days (LTI)
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
AC A AR UA UA UA
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
Incident resulting in complete
NEOM-NLFPRC-003 FRM 001 shutdown of operations
– Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
PROJECT TITLE
150 M UTILITY CORRIDOR AT SOUTHERN
CLUSTER PROJECT CONTRACT
OXAGON, NEOM CITY
Method Statement for E&I Cable Pulling, Termination
and Testing (LV Power, ICT and Earthing Cables)