CPM, CM & Consumption

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
117 views4 pages

CPM, CM & Consumption

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

CPM for BRL

Details Qty Remarks

Total Sewing Manpower 927 Sewing

Avg. Working Hour 10.00 Plan

Working Days 26 October

Total Available Minute (100%) 14461200 Minutes

Available Minute (45%) 6507540 Minutes

Factory Overhead Cost 35000000 Taka

5.38 Taka
CPM
0.06 $

CM Calculation (With CPM)


Average SMV 21.15
CPM 0.06 $
CM = Avg. SMV X CPM
CM 1.35 $
CM 113.75 Tk
Cost per minute of a sewing Line

Total Salary of Sewing Line for one day


CPM (Per Line) =
Total Minute available x Line Efficinecy %

Total Salary of Sewing Line for one day


=
Total No. of MP x Daily W.H. x 60 x Line Efficinecy %

Say, Total Salary of Sewing Line for one day (Tk.) 19231
Total No. of MP 48
Daily W.H. 10
Line Efficinecy % 45%

19231
CPM (Per Line) =
12960
= 1.48 Tk.

Total Salary of Sewing Line for one day


CPM (Per Line) =
Total Garments Produced x SMV

Say, Total Garments Produced : 1000


SMV : 16

19230.7692307692
CPM (Per Line) =
16000
= 1.20 Tk.
CM Calculation (BRL)

Factory Total Expenditure/ month x Total No. of Machine required to complete an Item
CM =
Total Machines x Total working day/ Month x Total Wokring Hrs/ Day x Targeted Production/ Hr

At BRL, Factory Total Expenditure/ month 25000000 Tk.


Total No. of M/C required to complete an Item 42
Total Machines 672
Total working day/ Month 26
Total Wokring Hrs/ Day 10
Targeted Production/ Hr 75 Pcs

1050000000
So, CM = Tk. (Pcs)
13104000
= 80.13 Tk. (Pcs)
= 0.95 $ (Pcs)
= 11.45 $ (Dozon)

2nd Easiest option of Calculating CM (Style wise):

CM= (SMV x Minute cost of the Labour)/ Line Efficinecy %

Say, SMV 25 Minute


Minute cost of the Labour 0.08 $
Line Efficinecy 50%

CM = 4.00 $
FABRIC CONSUMPTION

FABRIC CONSUMPTION (WOVEN) All LENGTH X WIDTH X NO OF PARTS X 12


+ WASTAGE % YARDS (PER DOZON)
Measurement in Inch= FABRIC WIDTH X 36 USE FOR
CALCULATING PART
WISE
FABRIC CONSUMPTION (KNIT) All LENGTH X WIDTH X NO. OF PARTS X GSM X 12 CONSUMPTION
+ WASTAGE % KG (PER DOZON)
measurement in cm = 10000000

FABRIC CONSUMPTION FOR BASIC T-SHIRT (BODY LENGTH + SLEEVE LENGTH + ALLOWANCE) X (1/2 CHEST WIDTH + ALLOWANCE) X 2 X GSM X 12
KG (PER DOZON)
(KNIT) All measurement in cm = 10000000 (LENGTH 100 X WIDTH 100 X WEIGHT 1000)

LADIES DOUBLE PKT WITH FLAP, RIVERY CLR WITH BOX-BTN FACING SHIRT

PARTS MEASUREMENT CM INCH NO. OF PARTS WOVEN KNIT


Length 50 19.69
COLLAR 2 1.14 0.22
Width 11 4.33
Length 16 6.30
FLAP 4 0.46 0.09
Width 7 2.76
BOX-BTN Length 62 24.41
2 1.73 0.33
FACING Width 13.5 5.31
Length 17 6.69
POCKET 2 0.56 0.11
Width 16 6.30
Length 56 22.05
YOKE 2 2.31 0.44
Width 20 7.87
Length 22 8.66
SLEEVE 2 2.00 0.38
Width 44 17.32
Length 57 22.44
BACK PART 1 3.36 0.64
Width 57 22.44
Length 63 24.80
FRONT PART 2 4.30 0.82
Width 33 12.99
15.86 3.04

Fabric Consumption (For Woven) 15.86 Yards


Fabric Consumption (For Knit) 3.04 Kg