1. General
i.
Keys Received?
ii.
Hallway Clearance?
iii.
Site photographs taken?
Page 1 of 8
Server & IDF Rooms Checklist
Page 2 of 8
Server & IDF Rooms Checklist
Page 3 of 8
Server & IDF Rooms Checklist
Page 4 of 8
Server & IDF Rooms Checklist
Plumbing System
i Any leakage - sighted?
waterproofing - functioning? Tested?
ii Results of flood test for at least 48 hours
presented?
iii Waterline – sighted? Functioning?
iv PACU drain line – sighted? Functioning?
Page 5 of 8
Server & IDF Rooms Checklist
Structured Cabling
i. IT Racks – in good condition?
ii. Patch panels – in good condition?
iii. Cable tie – in good condition?
Cables – in good condition? Harnessed?
iv.
Labelled?
Security System
i.
CCTV – installed? Functional?
ii. Access control devices – installed?
Functional?
iii.
NVR – installed and working?
iv. Access control panels – installed? No stains?
Labeled?