0% found this document useful (0 votes)
21 views

C Activate-2gshsjs

Uploaded by

tushar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

C Activate-2gshsjs

Uploaded by

tushar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 43

SAP Activate Project Manager

(C_ACTIVATE22)_v1.1
Question. 1
The hypercare period is part of which phase?

Deploy

Go-Live

Explore

Run

Question. 2
When does the Scrum Team receive formal confirmation
that the User Stories are completed to the satisfaction of
the Product Owner?

During the Sprint Review

During the User Acceptance Test

During the Sprint Retrospective

During the daily Scrum meeting

Answers A
Question. 3
Where can you find Data Migration templates?

SAP Cloud Appliance Library

SAP Roadmap Viewer

SAP S/4HANA Migration Cockpit

SAP Best Practices Explorer

Question. 4
Which of the following belong to the Application Design
and Configuration workstream for SAP S/4HANA Cloud
in the Explore phase? Note: There are 2 correct
answers to this question.

Configuration definition

Kick-off workshop

Integration prerequisites confirmation

Fit-to-standard workshop

Question. 5
What is the key characteristic of the Agile project
approach?
Frequent and detailed project scheduling

Iterative build with frequent inspections

Formal and detailed documentation

Frequent Quality Gates

Question. 6
What is the recommended integration bus in the
cloud?

SAP Best Practices Explorer

SAP Cloud Platform Integration

SAP API Business Hub

SAP Process Orchestration

Question. 7
Which Value Chains does SAP Solution Manager 7.2
deliver? Note: There are 3 correct answers to this
question.

Hire-to-Retire

Requirements-to-Deploy
Cash-to-Order

Request-to-Fulfill

Detect-to-Correct

Question. 8
Which estimation technique can be used in Agile
Delivery Approach to size the User Stories during Sprint
Planning?

Detailed bottom-up effort estimate that breaks each User


Story up into hours or shorter tasks

Detailed bottom-up effort estimate by the Scrum Master in


Story Points based on the User Story complexity

Product Owner's relative estimate of the effort that will be


needed to implement the User Story

Relative estimate in Ideal Person Days that reflects the best


estimate provided by the project team

Answers D

Question. 9
What criterion does the Product Owner use to sequence
the Product Backlog?
Business priority

Resource availability

Complexity

Relative effort

Question. 10
Which of the following are part of the 10 SAP Quality
Principles? Note: There are 2 correct answers to this
question.

Start scoping early.

Plan one phase at a time.

Use standard functionality optionally.

Achieve production readiness.

Question. 11
What tool would you use for managing project tasks
and Solution Documentation when implementing SAP
S/4HANA Cloud?

SAP Support Marketplace


SAP Roadmap Viewer

SAP Transformation Navigator

Implementation portal for SAP S/4HANA Cloud

Question. 12
What does the Side-by-Side Extensibility Option mean?

There are two SAP S/4HANA instances: one for standard


code, and another for custom developments.

Extensibility is based on the SAP Cloud Platform and


published APIs.

SAP S/4HANA extensions are context-aware and focused


on tight integration.

Reporting is transferred to BW/4HANA.

Question. 13
What does a Cutover involve?

Transporting new Product Increment in the Development


System
Switching productive business operations from one system
to another

Closing Quality Gate

Presenting completed User Story to Key Users

Question. 14
In which phase will the customer develop a preliminary
strategy for building a target Operations and Support
organizational model?

Discover phase

Explore phase

Run phase

Prepare phase

Question. 15
Where can you find the Integration Content? Note:
There are 3 correct answers to this question.

SAP Cloud Appliance Library


SAP API Business Hub

Cloud Integration Automation Service

SAP Solution Manager

SAP Best Practices Explorer

Question. 16
How would you describe the Realize phase in the
“New Implementation of SAP S/4HANA" transition
path?

Configure

Configure and adjust custom code

Configure and develop

Configuration copy

Question. 17
What is the term used for workshops, which are
intended to set value targets, validate SAP Standard
functionality against customer requirements, and
collect delta requirements in the “New Implementation
of SAP S/4HANA” transition path?
Backlog Grooming

Solution Validation

Design Thinking

Delta Design

Question. 18
What are the responsibilities of the Product Owner in
Release and Sprint Planning? Note: There are 2
correct answers to this question.

Prioritize backlog User Stories by business priority.

Analyze the functional and technical dependencies


between User Stories.

Define objectives for each Release.

Estimate the backlog User Stories.


Question. 19
Which role is responsible for defining the dataset
structure and its data usage in alignment with
requirements from all business functions?
Data Volume Management Consultant

Master Data Change Requester

System Administrator

Business Data Owner

Question. 20
What are some activities in the Requirements-to-deploy
scenario within SAP Solution Manager? Note: There are
2 correct answers to this question.
Walkthrough for Wave

SAP Model Company demo for every Wave

User Acceptance Test every Sprint

Demo for Sprint


Question. 21
What technique helps a Scrum Team to prioritize a
large, flat Backlog?
Retrospective
User Story Mapping
Planning Poker
Fit/Gap Analysis

Question. 22
What is the objective of a Sprint Retrospective
meeting?

Improve the Scrum process.

Provide formal feedback to the Project Manager.

Define the stakeholder management approach.

Review and prioritize the Backlog.

Question. 23
Ready-to-use Content in SAP Activate includes which
of the following? Note: There are 2 correct answers to
this question.
Business models from leading companies in each
industry sector

Courses delivered by SAP Education

Project Accelerators

SAP Best Practices

Question. 24
Which of the following scenarios are enabled for the
"Selective Data Transition" transition path with the
Aditya@9703658702
SAP Landscape Transformation tool? Note: There are
3 correct answers to this question.

Extraction of Business Units

System Consolidation

Consolidation through online data replication

Security Migration

System Upgrade
Question. 25
What is the primary purpose of the SAP Activate
Methodology?

To provide the sequence of actions in the project

To manage solution documentation

To enable access to the SAP Ecosystem

To provide end-to-end Application Lifecycle Management

Question. 26
What SAP Solution Manager capability in the Change
Control Management process is used to synchronize
changes between SAP ERP and SAP S/4HANA
maintenance tracks?
Business Process Change Analyzer

SAP Code Vulnerability Analyzer

Dual Landscape Synchronization (Retrofit)

SAP Code Inspector


Question. 27
Which of the following are levels in the structure of an
SAP Best Practices for SAP S/4HANA Solution
Package? Note: There are 2 correct answers to this
question.
Scope Items

Configuration Guides

Business Process Scenarios

Building Blocks

Question. 28
What are some important accelerators (guides,
templates) that could help establish the Test
Management Process in an SAP S/4HANA project? Note:
There are 2 correct answers to this question.
Data Migration Strategy
Test strategy

SAP Support Standards

SAP Transformation

Navigator Answers
Question. 29
What are some of the key characteristics of the
implementation approach in SAP Activate Methodology?
Note: There are 2 correct answers to this question.
Based on Ready-to-use Content

Cloud Ready

On premise only

Fixed scope

Question. 30
In which phase do you verify that the SAP Best Practices
content meets the customer's business needs, and then
capture gaps?

Realize

Deploy

Prepare

Explore
Question. 31
What is the best target deployment option of SAP
S/4HANA for the “System Conversion” transition
path?

SAP S/4HANA Cloud

SAP C/4HANA

SAP S/4HANA

Hybrid of SAP S/4HANA Cloud and SAP S/4HANA

Question. 32
Which of the following tools are specific to the Data
Management workstream? Note: There are 3 correct
answers to this question.
SAP Landscape Transformation

SAP Roadmap Viewer

SAP Data Services

SAP S/4HANA Migration Cockpit (for both SAP S/4HANA


Cloud and SAP S/4HANA editions)

SAP Solution Manager


Question. 33
What is SAP Activate?

A bundle of ASAP, SAP Launch, and Rapid Deployment


Solutions

Step-by-step instructions on how to move from SAP Best


Practices to your custom solution

A methodology for each of the deployment modes


(cloud, on premise, hybrid)

A Solution Adoption Framework

Question. 34
What tool can you use to collaborate with other SAP
Activate Methodology practitioners?
SAP Jam

SAP Solution Manager

SAP Implementation Assistant

SAP Roadmap Viewer


Question. 35
What accelerator can help you document the
Configuration Definition in the Explore phase?
Test Strategy

Change Request template

Data Definition

Backlog template

Question. 36
What tool provides sizing estimations for the
“System Conversion” transition path?
SAP Best Practices Explorer
SAP Readiness Check

Scope and Effort Analyzer

SAP Transformation Navigator


Question. 37
Via which media does SAP provide Ready-to-run
systems for SAP S/4HANA deployments? Note: There
are 2 correct answers to this question.
SAP App Center

SAP Cloud Appliance Library

Blu-ray disks

SAP Solution Builder tool

Question. 38
Why are Scaling Scrum techniques used to coordinate
large teams in complex projects?

To make test case execution as difficult as possible

To manage the flow of information between the project and


stakeholders

To staff as many people as possible on the project to


increase utilization

To ensure alignment in architecture, configuration, and


integration
Question. 39
Which artifacts in the Testing workstream are created
within the Realize phase for the “New Implementation of
SAP
S/4HANA Cloud” transition path? Note: There are 2
correct answers to this question.

Reporting Functional Specifications

Functional Specifications

User Acceptance Test - Plan

Functional Test Scenarios

Question. 40
In the "New Implementation of SAP S/4HANA" transition
path, which systems are part of the project system
landscape? Note: There are 2 correct answers to this
question.

QAS

DEV

P-system
Starter system

Question. 41
Which of the following are examples of Ready-to-run
SAP S/4HANA systems? Note: There are 2 correct
answers to this question.
Development system with activated SAP Best Practices

Fully Activated Appliance

SAP Mission Control Center

SAP Best Practices Explorer

Question. 42
What Sprint types are part of the SAP Activate
Methodology? Note: There are 3 correct answers to
this question.

Initial

Build

Daily

Firm-up
Foundational

Question. 43
What is the purpose of a Firm-up Sprint?

To run an end-to-end Integration Test

To revise the Release Plan and Sprint Plan

To perform a String Test

To demonstrate functionality from previous Sprints

Question. 44
You are defining the Testing Strategy for your project.
What would you include in a Scope of Integration
test?
The connectivity between database and application
servers The functionality of Modular Process
The functionality of End-to-End business processes
The network communication
Question. 45
Which new project roles are introduced with the SAP
Activate Methodology for the Agile delivery
approach, compared to Waterfall? Note: There are 2
correct answers to this question.
Integration Lead

Product Owner

Design Thinking Coach

Scrum Master

Question. 46
What is the basis for approving work results (signing
Act of Acceptance) on a Project Phase level?
Scrum of Scrums meeting decision

Definition of Done for User Story

Agreed and met Acceptance Criteria within Quality Gate

Definition of Ready for Sprint


Question. 47
Who determines the tasks that are required to complete
the committed Backlog Items in a Sprint?

Scrum Team

Product Owner

Project Manager

Scrum Master

Question. 48
What tool provides guidance on replacing custom code
developed for SAP ERP with SAP S/4HANA
functionality for the
“System Conversion” transition path?
Simplification Item Check (SI-Check)

SAP Code Inspector

Software Update Manager with Database Migration Option

Software Provisioning Manager


Question. 49
Which of the following is part of the Explore phase in
the “New Implementation of SAP S/4HANA Cloud”
transition path?

Simplification and Custom Code Impact Analysis

Solution Validation and Delta Design

Setup and Enablement

Fit-to-standard

Question. 50
Which end-to-end turn-key Application Lifecycle
Management (ALM) solution can support you in
managing requirements and software development for
large Agile projects?
Change Request Management

Solution Manager Test Suite

Requirement Management

Focused Build
Question. 51
How do you set up Scrum teams? Note: There are 2
correct answers to this question.

Based on End-to-End Processes like Order-to-Cash

As a cross-functional team covering multiple functions, like


configuration, data loads, and testing

By type of work, like configuration Scrum, documentation


Scrum, and testing Scrum.

Based on group size, but a minimum of 12 people

Question. 52
Which collaboration features can SAP Jam users
access in the SAP Methodologies Jam group? Note:
There are 2 correct answers to this question.
Ask questions

Update Key Deliverable wikis

Comment on Key Deliverables

Tweet questions
Answers A C

Question. 53
Which accelerators support the Fit-to-standard
workshop in the Explore phase? Note: There are 2
correct answers to this question.
Test Strategy

Backlog template

Business-Driven Configuration Questionnaire

Quality Gate Checklist

Question. 54
In which phase should you first run the SAP Readiness
Check for SAP S/4HANA in a "Selective Data
Transition" transition path, in a System Consolidation
scenario that includes conversion from SAP ERP?

Prepare

Realize

Discover

Explore
Question. 55
What is a Strategy Level 0 (L0) artifact?

Project result that is developed solely by the partner

Preliminary strategy developed by the customer to


approach the project in a specific workstream

Approach document that is developed by a united Project


Team (partner + customer)

Optional information that is NOT important for project


activities

Question. 56
Which tools offer support for the technical
implementation of SAP Fiori? Note: There are 3 correct
answers to this question.
SAP Fiori launchpad content manager

KPI Catalog

Industry Value Maps

Task lists for rapid activation


SAP Fiori apps reference library

Question. 57
What is Scrum of Scrums?

Integration meeting among the various Scrum teams

Alternative to regular Scrum process for smaller teams

Mechanism for gathering and validating requirements

Frequent inspection of code and configuration prior to


Quality Gates

Question. 58
According to the Definition of Done, which activity
must be completed for each Sprint?

The solution must be built and configured in the


development system (DEV).

Functionality must be tested in the Production System


(PROD).

End-user training must be delivered.


Functionality must be released to the business.

Question. 59
Which of the following are benefits of using Ready-
to-use Content? Note: There are 2 correct answers
to this question.
Exhaustive solution documentation

Predictable results

Minimized Total Cost of Ownership

Fast Time-to-Value

Question. 60
Which Scrum role is part of a Full Scrum Team in
the SAP Activate Methodology?
Application Consultant
Product Owner

Project Manager

System Administrator
Question. 61
In which phase should you create a Data Migration
Strategy (L0) during a Selective Data Transition?
Deploy

Realize

Explore

Discover

Question. 62
What Solution Operations Framework can customers
use to create a joint Business and IT organization?
Business Transformation Management Methodology
Customer Center of Expertise

SAP Leonardo

SAP Activate
Question. 63
What is the difference between the “System
Conversion” and the “New Implementation of SAP
S/4HANA” transition paths? Note: There are 2 correct
answers to this question.

SSCUIs are used in System Conversion for configuring SAP


S/4HANA through the Manage Your Solution app.

In the Realize phase, custom code is adjusted rather than


developed for System Conversion.

In the Realize phase, data is converted and NOT migrated


for System Conversion.

There are different upgrade cycles.

Question. 64
What information does the Project Team need before
they can correctly estimate the relative size of backlog
User Stories?

Available project resources

Overall project schedule

Definition of Done

Test Strategy
Question. 65
Which of the following best outlines the sequence of
testing within the Application Design and Configuration
workstream in the Realize phase?
Integration Test . User Acceptance Test . String test

String test. Integration Test. User Acceptance Test

String test. User Acceptance Test. Integration Test

Data Migration. String test. User Acceptance Test

Question. 66
Working in an Agile approach, what should your
planning look like at the beginning of the Realize phase?
User Stories are in Ready state for only the first 2 to 3

Sprints. Go-Live scope is fixed on the first of January the

following year. Project scope and planning are completed

and final.

Timelines of the Sprint may differ due to the workload.


Question. 67
What is the difference between the “New Implementation
of SAP S/4HANA Cloud” and the “New Implementation
of SAP
S/4HANA” transition paths? Note: There are 2 correct
answers to this question.

Different sets of workstreams are used for these transition


paths.

There are different roles in the Application Design and


Configuration workstream.

SAP S/4HANA uses the Implementation Guide (IMG) and


the In-App Extensibility Option for configuration and
development, and SAP S/4HANA Cloud uses SSCUIs and
the Side-by-Side Extensibility Option.

Upgrades of SAP S/4HANA Cloud are managed by SAP,


and upgrades of SAP S/4HANA are managed by the
customer.

Question. 68
Which activity helps the Project Team add User Stories
to the Product Backlog?

Assessing project risks

Preparing a project schedule


Planning the User Acceptance Test

Conducting the Solution Validation workshop

Question. 69
In which phase do you create “an ordered list of
everything that is known to be needed in the product”?

Prepare

Explore

Realize

Deploy

Question. 70
What does the Content element of SAP Activate
provide? Note: There are 3 correct answers to this
question.
Migration Content
Functional Specifications for WRICEF development
Business Processes Content
Integration Content

End-User guides

Question. 71
What capabilities does SAP API Business Hub provide
to help you select integration options for your project?
Note: There are 3 correct answers to this question.

Sandbox for testing APIs

Recommendations on using integration bus (SAP PO or


SAP CPI)

Pre-packaged integrations

Integration with IDE and Code Generation

Advice on selecting Scope Items in SAP Best Practices

Explorer

Question. 72
Which artifacts are part of the Solution Adoption
workstream? Note: There are 3 correct answers to this
question.

Project Business Case


Business Transformation Review (Point of View)

Project Plan

System GoLive Announcement (order)

Detailed Design – Business Process

Question. 73
In SAP Activate, what tool is used in the Agile Delivery
Approach during the Realize phase to make forecasts
based on actual data?
Burndown Chart

Project Plan

Product Increment

Release Plan

Question. 74
In which phase do you run the User Acceptance Test?

Final Preparation
Build and Test

Realize

Deploy

Question. 75
What is the purpose of the Scrum Board?

To visualize team progress

To manage the resource load

To document the results of the Integration Test

To show the functional breakdown of the solution

scope

Question. 76
What is the purpose of the Solution Validation activity
in the Explore phase? Note: There are 3 correct
answers to this question.

Verify technical installation.

Challenge changes to standard.

Log additional scope items.


Identify gaps.

Educate project participants.

Question. 77
Which artifacts are created within the Application Design
and Configuration workstream in the Explore phase of
the “New Implementation of SAP S/4HANA” transition
path? Note: There are 3 correct answers to this
question.

Organization Structure Specification

Roles and Authorizations Management Concept

Delta Requirements List – Register

Project Procedure – Mock-up Modeling

Detailed Design – Business Process

Question. 78
What are some of the key topics covered in the
Customer Team Enablement workstream? Note: There
are 3 correct answers to this question.
Project Sourcing Approach

Project Management

Technical Expertise

Planning Skills

Solution Expertise

Question. 79
What are the substreams in a Data Management
Workstream? Note: There are 3 correct answers to this
question.

Master Data Management

Data Migration

Project Management

Solution Adoption

Data Volume Management


Question. 80
Which SAP Solution Manager scenarios should you
implement while setting up the project infrastructure?
Note: There are 2 correct answers to this question.

Business Process Operations

Process Management

Project Management

Data Volume Management

None

You might also like