2 PFM 2
2 PFM 2
Planning An overview
As we have seen earlier the project comes from the national /
organizational plan (program).
There are:
Forecasting
Determination of objective
Determinations of means
Determination of resources
Implementation plan
Forecasting.
It is an intelligent estimation and prediction of the future
internal and external environment.
These forecasts is relate to aspects like,
Economic condition,
Technology,
Population structure and growth,
Social norms and value,
Political and legal conditions etc.
Forecast only provide data for planning, and do not
produce any plan.
Determination of objectives
Any plan starts with clearly defined objective
Some authors (Choudhury, 2005) presents the projects life cycle in to the life cycle curve
Inception (concept, definition, organizing etc) (12%)
Maturity ( implementation ) (85%)
Decay (clean up) (3%)
Level
Of effort inception decay (clean up)
maturity (implementation)
time
Explain what issues should be considered in each stage
Each stage follows the proceeding one and leads to the next.
These different phases are identified by different institutions
and authors.
Some of the phases as identified by different authors are:
The Baum cycle
The Baum Cycle (World Bank Procedures)
MACRO-LEVEL
National policies, strategies, sectoral, sub – sectoral or regional plans
General surveys,
Resource potential surveys,
Regional studies,
Master plan and
Statistical publications, which indicate directly or indirectly investment
opportunities.
Constraints on the development process due to shortage of essential
infrastructure facilities
Unusual events such as, Droughts, Floods, Earth – quakes, hostilities, etc
Identification...
Micro level
The identification of unsatisfied demand or needs
The need to remove shortages in
Essential materials,
Services or
Facilities that constrain development efforts;
The initiative of private or public enterprises in response
to incentives provided by the government;
Identification...
The necessity to complement or expand
investments previously undertaken.
Once a project has been carried out the actual progress with the
plans should be evaluated in order to judge whether the
decisions and actions taken were responsible and useful.