SAJCO - Quality - Objective
SAJCO - Quality - Objective
Project: VARIOUS
KPI Performance
Indicators Criteria Target Value
Description
QA01 Project Quality Index
Monthly Valuation ≥95%
(PQI)
QA02 Respect to the Audit
Audits performed vs. audits planned > 90%
plan established
QA03 Timely close out of
Audit report findings ∑ delay days / number of closed findings < 30 days
(average delay days)
QA04a Timely Site LBEs
LBEs closed within Agreed Closed Date as per ACD
closure
QA04b Timely Site NCRs
NCRs closed within Agreed Closed Date as per ACD
closure
QA04c Timely Site WSs
WSs closed within Agreed Closed Date as per ACD
closure
QA05
Participation to Quality
Participants / key positions > 80%
Training Workshops
Project: VARIOUS
KPI Performance
Indicators Criteria Target Value
Description
QA11 Efficient evaluation of
COMPANY provided ∑ delayed submission (days) / total
< 1 day
Project Quality Index submitted reports.
(PQI)
QC12a Concrete pouring: compliance with RFI > 95%
QC12b Effectiveness of Positive Crush tests > 98%
Concrete operations
QC12c (as per Schedule Q Consistent trends for Tests at 7-14-21-
> 98%
par. 7.4) 28 days
QC12d Finishing Repairs (surface) < 5%
QC13 Effectiveness of
Coatings
Defects (excluding touch up) < 2%
(as per Schedule Q,
Para. 7.4)
QC14 Effectiveness of Repeated test
Hydrostatic & Gravity (for piping systems exceeding 2” < 1%
Testing operations diameter)
(as per Schedule Q,
Para. 7.4) Valve Testing Rejection Rate: ≤2%
Project: VARIOUS
KPI Performance
Indicators Criteria Target Value
Description
QC20 100% - for SA NCR
(Major and
moderate) / WS
Prior to CA& PA
implementation
and closure
CONTRACTOR ensures Site Focus
CONTRACTOR Site Assessment (FA) prior to start new
25% - for SA LBE
Focus Assessment activities and at regular interval as a
(SV)
(FA) to Inspection Plan result of updated Risk Assessment to
each SATIPs/ITPs
20% - for CTR
INCR