Large Project Version11 Issued 072011
Large Project Version11 Issued 072011
Version 11
July 2011
Page1of65
Table of Contents
I.
II. Logging into the CII Website.................................................................................................. 3 III. Benchmarking System Access .............................................................................................. 3 IV. Instructions............................................................................................................................. 3
1. General Project Description ..................................................................................... 4 2. Engineering Deliverables ......................................................................................... 7 3. Contract Type ........................................................................................................... 8 4. Project Cost .............................................................................................................. 9 5. Project Schedule .................................................................................................... 13 6. Achieving Facility Capacity..................................................................................... 16 7. Project Outcomes ................................................................................................... 17 8. Workhours and Accident Data................................................................................ 18 9. Project Impact Factors ........................................................................................... 19 10. PDRI ....................................................................................................................... 20 11. Practices ................................................................................................................ 20 12. Engineering Productivity Metrics ............................................................................ 27 13. Construction Productivity Metrics ........................................................................... 43
Page2of65
I. Project Selection Criteria Applicable for both Owners and Contractors TIC > $5MM 14 months or longer in duration Managed by a dedicated project team Any industry group: buildings, heavy industrial, light industrial, infrastructure Completed within the past 2 years (with access to project team members)
II. Logging into the CII Website Log in to the CII website at http://construction-institute.org/Source/Security/MemberLogon.cfm If you do not know your login and/or password, you may change it by going to the log on page and click Reset My Password. If you have any questions about your access to the CII website, contact Hong Zhao at [email protected] or (512) 2320864. III. Benchmarking System Access Benchmarking Project Central (http://construction-institute.org/benchmarking) Training: access to Project Central is limited to trained Benchmarking Associates Includes questions to evaluate the value of CII Practices Project-level, confidential Key Report with scores and benchmark comparisons will be provided Includes measures for industry-specific and productivity metrics Industry-level report at the conclusion of study
IV. Instructions The first five sections of the survey are required. Sections one to three focus on general project information. Sections four and five require performance information. The remaining sections are recommended. If a question does not apply, indicate as much and follow the directions to skip to the next section. The online questionnaire has skip patterns programmed into the interface, thereby reducing the burden to the respondent and enhancing the validity of the responses. Text appearing in bold and red in the paper version prompts the respondent to skip sections that dont apply. Once finished with the questionnaire and the internal validation, submit it to CII. After submittal, CII will review the project data and validate it to ensure that the information is complete and correct. Thank you for benchmarking with CII.
Page3of65
1.1.1 Your Company Name: 1.1.2 Your Name: 1.1.3 Project Name: 1.1.4 Project Owner: 1.1.5 Primary Designer: 1.1.6 Primary Constructor: 1.1.7 Project Construction Location:
City:
, (State or Province):
, Country:
City:
, (State or Province):
, Country:
1.2
Project Description
Which of the following best describes industry group for this project? Heavy Industrial
Chemical Manufacturing Electrical (Generating) Environmental Metals Refining/Processing Mining Tailing Natural Gas Processing Oil/Gas Exploration/Production (well-site) Oil Refining Oil Sands Mining/Extraction Oil Sands SAGD Oil Sands Upgrading Cogeneration Pulp and Paper Other Heavy Industrial
Light Industrial
Automotive Manufacturing Consumer Products Manufacturing Foods Microelectronics Manufacturing Office Products Manufacturing Pharmaceutical Manufacturing Pharmaceutical Labs Clean Room (Hi-Tech) Other Light Industrial
Page4of65
Buildings
Communications Center Courthouse Dormitory/Hotel/Housing/Residential Embassy Low rise Office (3 floors) High rise Office (>3 floors) Hospital Laboratory Maintenance Facilities Movie Theatre Parking Garage Physical Fitness Center Prison Restaurant/Nightclub Retail Building School Warehouse Other Buildings
Infrastructure
Airport Electrical Distribution Flood Control Highway (including heavy haul road) Marine Facilities Navigation Rail Tunneling Water/Wastewater Telecom, Wide Area Network Pipeline Tank farms Gas Distribution Other Infrastructure
1.3
Project Nature
From the list below, please select the category that best describes the primary nature of this project. Please see the glossary for definitions. Grass Roots, Greenfield Brownfield (co-locate) Modernization, Renovation, Upgrade (changes to existing capacity) Addition, Expansion Other Project Nature
1.4
Project Priority
Please select the primary factor influencing the execution of this project. Assume safety is a given for all projects.
Cost Schedule Balanced
Page5of65
1.5
Business Driver
Quality Production Capacity Risk Operability Environmental Social Others
1.6
1.6.1
[Owner Only] What was the total installed cost for this project? $ [Contractor Only] What was the total project cost as billed or invoiced? $
1.6.2
The purpose of this question is to determine the extent to which the overall project cost and cost performance are driven by the purchase of major equipment. Please see the Equipment Reference Table provided below. Record the total purchase cost of major equipment for this project. Exclude costs for field services, bulk construction equipment (such as valves, bus ducts etc.) and off-the-shelf equipment. Project team costs and transportation costs are excluded. $ Not Applicable (no major equipment) Dont Know
Page6of65
Equipment Reference Table Examples of Major Equipment HVAC Systems Columns and Pressure Vessels Kinds of Equipment Covered
Prefabricated air supply houses Towers, columns, reactors, unfired pressure vessels, bulk storage spheres, and unfired kilns; includes internals such as trays and packing. Atmospheric storage tanks, bins, hoppers, and silos. Heat transfer equipment: tubular exchangers, condensers, evaporators, reboilers, coolers (including finfan coolers and cooling towers). Fired heaters, furnaces, boilers, kilns, and dryers, including associated equipment such as super-heaters, air preheaters, burners, stacks, flues, draft fans and drivers, etc. All types of liquid pumps and drivers. Mechanical vacuum pumps, ejectors, and other vacuum producing apparatus and integral auxiliary equipment. 600V and above Major electrical items (e.g., unit substations, transformers, switch gear, motor-control centers, batteries, battery chargers, turbines, diesel generators). Conveyers, cranes, hoists, chutes, feeders, scales and other weighing devices, packaging machines, and lift trucks. Integrated systems bought as a package (e.g., air dryers, air compressors, refrigeration systems, ion exchange systems, etc.). Agitators, crushers, pulverizers, blenders, separators, cyclones, filters, centrifuges, mixers, dryers, extruders, fermenters, reactors, pulp and paper, and other such machinery with their drivers.
Tanks Exchangers
Direct-fired Equipment
Pumps Vacuum Equipment Motors Electricity Generation and Transmission Materials-Handling Equipment
Package Units
1.7
[Heavy/Light Industrial project only] Construction performance (cost, schedule, quality) during project turnarounds, shutdowns, and outages may be impacted by schedule demands of the turnaround, shutdown or outage. These turnarounds may be scheduled or unscheduled. Please Page2of65
complete the blocks below to indicate the percentage of total construction work-hours completed during turnaround. 1) Percent construction during scheduled turnaround: 2) Percent construction during unscheduled turnaround: 3) Percent construction during non-turnaround: Note: the percentages should add up to 100 % Dont Know % % %
1.8
Please choose the project delivery method from those listed below that most closely characterizes the delivery method used for this project. If more than one delivery method was used, select the primary method. Delivery Method Design-Bid-Build Description Serial sequence of design and construction phases; Owner contracts separately with designer and constructor. Owner contracts with Design-Build (EPC) contractor. Owner contracts with designers and construction manager (CM). CM holds the contracts. Owner contracts separately with designer and multiple prime constructors.
Parallel Primes
[If not CM at Risk] Did you use a Construction Manager not at Risk in conjunction with the selected delivery system? Yes No
1.9
Work Scope
[Contractor Only] What was your company responsible on this project? (please check all that applied) FEP Detail Design/Engineering Procurement Construction Commissioning and Startup Page3of65
0%
10%
20%
30%
40%
50%
60%
70%
80%
90% 100%
Page4of65
Page5of65
Page6of65
2. Engineering Deliverables
Please provide information about this project's use of engineering standards and specifications. Process Industry Practices (PIP) is a consortium of process industry owners and engineering/ construction contractors who serve the industry. PIP publishes Practices" that reflect standards in many engineering disciplines.
The project was executed with internal A owner engineering standards and specifications. B The project was executed with contractor engineering standards and specifications.
The project was executed using industry C consortia engineering practices for standards and specifications. The project was executed using Process D Industry Practices (PIP) standards and specifications.
2.3. To what extent were the engineering deliverables complete and accurate (with minimal errors and omissions)?
Seldom Complete and Accurate 1 Dont Know Sometimes Complete and Accurate 4 Always Complete and Accurate 7
3. Contract Type
[Owner required section; Contractor please check the contract type for your work scope] Please indicate below the contract types that were used on this project. If you had multiple contractors for a particular function, please answer the questions below in terms of what was most common.
Page8of65
4. Project Cost
4.1. Budgeted and Actual Project Costs by Function
Please indicate the Budgeted (Baseline) Cost, Contingency, and Actual Project Costs in the table below.
1) If this project did not include a particular function, please select N/A for Not
Applicable.
2) If you know total project costs but have incomplete function information, you
may enter as much function information as you know and override the automatic totaling by manually filling in the total project cost. As long as you don't click back into a function field, your total will be accepted and recorded. Owner Instructions Budget amounts include contingency and correspond to funding approved at time of authorization. This is the original baseline budget, and should not be updated to include any changes since change data are collected in a later section. The total project budget amount should include all planned expenses (excluding the cost of land) from Front-end Planning through startup, including amounts estimated for in-house salaries, overhead, travel, etc. The total actual project cost should include all actual project costs (excluding the cost of land) from Front-end Planning through startup, including amounts expended for in-house salaries, overhead, travel, etc. Contractor Instructions: Only enter data for your scope of work Only enter cost data for your scope of work. Budget amounts should include contingency and correspond to the estimate at time of contract award. This is the original baseline budget, and should not be updated to include any changes since change data are collected in a later section. The total project budget amount should be the planned expenses of all functions performed by your company, including amounts for in-house salaries, overhead, travel, etc., but excluding the cost of land. The total actual project cost should be the actual project costs for functions performed by your company including amounts expended for in-house salaries, overhead, travel, etc., but excluding the cost of land.
Page9of65
Actual Cost
$___________
4.1.2. Phase Cost Baseline Budget (Including Contingency) $ NA Dont Know $ Detail Engineering $ Procurement NA Dont Know $ Construction NA Dont Know $ Startup / commissioning NA Dont Know $ NA Dont Know $ NA Dont Know $ NA Dont Know NA Dont Know $ NA Dont Know $ NA Dont Know $ NA Dont Know $ NA Dont Know Amount of Contingency in Budget $ NA Dont Know $ NA Dont Know
Project Function
Actual Cost
$ NA Dont Know
Page10of65
you can only provide total amounts, please indicate Dont Know in the preconstruction and construction through startup rows and indicate the total amounts in the totals row. As long as you dont click back into a detail information row, your total will be accepted and recorded. 3) Indicate whether the net impact was a (-) decrease or an (+) increase by indicating a negative number for a decrease and a positive number for an increase. If no change orders were granted during a phase, please enter zero. 4.2.1. Total project change cost: $ 4.2.2. Change cost by Time period Cost Increase (+) / Decrease (-) of Project Development Changes $ NA Dont Know $ NA Dont Know $ NA Dont Know Cost Increase (+) / Decrease (-) of Scope Changes $ NA Dont Know $ NA Dont Know $ NA Dont Know
Time period
Change Cost
PreConstruction
4.3.3. What was the primary source of rework on this project? Design Construction Suppliers Owner Dont Know
Page12of65
5. Project Schedule
Please indicate your project's Planned Baseline and Actual Project Schedule by function:
1) If this project did not include a particular function please select N/A. 2) If you have incomplete function information, you must enter project execution
start and stop dates. Please enter as much function information as possible. Contractor Instruction: please only enter schedule information for your scope of work, excluding FEP from execution schedule. Owner instruction: execution schedule start from the beginning of Detail Engineering and the end of Start-Up.
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
Detail Engineering
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
Procurement
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
Construction
NA Dont Know
NA Dont Know
NA Dont Know
NA Dont Know
Startup / Commissioning
NA
NA
NA
NA
Page13of65
Dont Know
Dont Know
Dont Know
Dont Know
5.3.2. What percentage of the total work hours for detail design was completed prior to start of the construction phase? % Dont Know
5.4.2. If yes, what was the total duration in weeks of any uncontrollable or unanticipated schedule disruption? weeks Dont Know
Page14of65
can only provide total amounts, please indicate Dont Know in the preconstruction and construction through startup rows and indicate the total amounts in the totals row. As long as you dont click back into a detail information row, your total will be accepted and recorded. 3) Indicate whether the net impact was a (-) decrease or an (+) increase by indicating a negative number for a decrease and a positive number for an increase. If no change orders were granted during a phase, please enter zero.
5.5.1. Total schedule impact of change: 5.5.2. Schedule impact of change by time period Schedule Increase (+) / Decrease (-) of Project Development Changes (weeks)
(weeks)
Time period
Page15of65
[If contractor did not perform start up activities, skip the rest of this section.]
6.2. [Heavy/Light Industrial project only] What percent of initial planned capacities
were achieved during Startup?
______% Dont Know
6.3. [Heavy/Light Industrial project only] To what extent were product quality
specifications achieved?
Not at All 1 Moderately 2 3 4 5 6 Fully Achieved 7 Dont Know NA
6.4. [Building project only] To what extent was the planned functionality of the
building achieved?
Not at All 1 Moderately 2 3 4 5 6 Fully Achieved 7 Dont Know NA
Page16of65
7. Project Outcomes
Using a scale from 1 to 7, where 1 means not at all successful and 7 means extremely successful please indicate the overall success of this project in terms of :
Not at All Successful 1 2 Meeting cost expectations Meeting schedule expectations Meeting safety expectations Meeting business objectives Meeting quality goals Moderately Successful 4 Extremely Successful 6 7
Using a 1 to 7 scale where 1 means not at all effective and 7 means extremely effective, please indicate how effective the following were on this project:
Not at All effective 1 2 Project teamwork Project team communications Your working relationship with the owner / primary contractor The key project team members understood the owners goals and objectives of this project Moderately effective 4 Extremely effective 6 7
Projects invariably differ in a variety of ways. Please indicate in the space below what you found to be particular challenges or difficulties on this project, compared to other comparable projects on which you have worked.
Page17of65
among this project's workers. If you do not track in accordance with these definitions, click Dont Know in the boxes below. 2) A consolidated project OSHA 300 log is the best source for the data. Note: for the CM tracking the safety data for the project, please report the safety statistics of the whole project, or skip this section.
8.1. Total site work hours 8.2. Total Number of first aids
Cases Dont Know
Dont Know
8.3. Total OSHA Number of Recordable Incident Cases (Injuries, Illnesses, Fatalities,
Transfers and Restrictions) Cases Dont Know
8.4. Total Number of OSHA DART Cases (Days Away, Restricted or Transferred)
Cases Dont Know
8.6. Please indicate the number of Workman Compensation Claims on this project.
Cases Dont Know
8.7. Please indicate the total dollar value of Workman Compensation Claims on this
project. Cases Dont Know
Page18of65
Page19of65
11. Practices
The following Practices sections include questions about practices implemented on this project. Please respond to every Practice. If a project did not implement a certain practice, indicate as such and skip to the next section.
11.2.2. How clearly was the project operations and maintenance philosophy communicated?
Not at All, Poorly Fair Very Well Dont Know
11.3. Partnering
Partnering is a commitment between two or more organizations for the purpose of achieving specific business objectives by maximizing the effectiveness of each participants resources. This requires changing traditional relationships to a shared culture without regard to organizational boundaries. The relationship is based on trust, dedication to common goals and an understanding of each others individual expectations and goals. We want to begin with some questions about your companys commitment to and experience with partnering. 11.3.1. Did you have a partnering agreement on this project with the owner/contractor? No Yes Dont Know
Page21of65
11.5.1. Did you consider alternative project delivery methods for this project? No Yes Dont Know 11.5.2. Did you consider alternative contract types for this project? No Yes Dont Know
11.6. Constructability
Constructability is the effective and timely integration of construction knowledge into the conceptual planning, design, construction and field operations of a project to achieve the overall project objectives in the best possible time and accuracy, at the most costeffective levels. 11.6.1. Was there a documented constructability plan for this project? No Yes Dont Know [Answer the next question, if yes to above.] 11.6.2. Was the constructability plan integrated into the project execution plan?
Not at All 1 2 3 Variable, Partial 4 5 6 Fully 7 Dont Know
Page22of65
[Skip the rest of this section if no risk assessment was conducted or dont know to above.] 11.7.2. Was the risk mitigation plan developed and implemented?
Not at All 1 2 3 Partially 4 5 6 Fully 7 Dont Know
[Skip this section if no or dont know to above.] 11.8.2. How clearly was the change management process specified in the project contract?
Not at all Clear 1 Moderate Clear 4 Very Clear 7 Dont Know
11.8.3. How well would you say key project personnel (both owners and contractors) understood the change management process?
Not at all Clear 1 Moderately Well 2 3 4 5 6 Very Well 7 Dont Know
Page23of65
11.9.2. Overall how many workers per full time safety professionals were typically (i.e., in terms of the average workforce) on site?
Over 201 151 to 200 71 to 150 21 to 70 1 to 20 Dont Know
11.10. Benchmarking
Benchmarking is a powerful technique that provides practical learning through comparing measurements or outcomes across industries, sectors, products or services. The essence of benchmarking is the process of identifying the highest standards of excellence for products, services or processes and then making the improvements necessary to reach those standards. 11.10.1. Was benchmarking results from past projects used to plan or execute this project? No Yes Dont Know
11.10.3.
Providing data for continuous improvement Establish a performance baseline Determine performance relative to peers Establish basis for continued project funding
11.10.4.
How long did it take to organize and input the data? Work Hours
11.11.1.
[If no, contractor should skip the rest of this section] 11.11.2. To what extent was a formal startup execution plan developed?
Not at All Developed 1 2 3 Partially Developed 4 5 Very Extensively Developed 6 7 Dont Know
None (1): No electronic tools or commonly used electronic tools, all processes completed manually Minimal (2): Checklists or simple tools are available to help complete the process Moderate (3): Electronic tools are available to help complete part of the work Extensive (4): Electronic tools complete most of the work after entering input data, with minimal amount of manual work after data are entered Complete (5): Entire process automatically completed after input data are entered.
Integration
None (1): No data communication or sharing with other electronic tools Minimal (2): Data (or information) produced from the work function are transferred manually because the data are rarely interoperable.
Page25of65
Moderate (3): Data (or information) produced from the work function are still manually transferred but some data are somewhat interoperable with other functions/stakeholders. Extensive (4): Data (or information) produced from the work function are mostly interoperable with other functions/stakeholders and do not require manual transfer. Complete (5): Data (or information) produced from the work function are seamlessly interoperable with other functions/stakeholders and no manual data transfer is required.
N/A or UNK
Project Management Front End Planning Detail Design Procurement Construction Startup/Commissioning
Page26of65
Page27of65
12.1.3. Please indicate the contractor engineering project managers level of experience with similar projects / process.
No Experience 0 2 or 3 projects 2 > 5 projects 3 4 NA/ UNK
12.1.4. What is the size of the engineering team in this project on the basis of 40 wk-hr /week? Maximum _________ FTE; Average _________ FTE;
12.1.5. What is the percentage turnover of engineering discipline / project leads assigned to the team in this project? __________ % 12.1.6. Please indicate the owner engineering project managers level of experience with similar projects / process.
Low No Experience 0 Medium 2 or 3 projects 2 High > 5 projects 3 4 NA/ UNK
Page28of65
12.1.7. Please indicate owner engineering teams level of experience with similar projects / process.
No Experience 0 2 or 3 projects 2 > 5 projects 3 4 NA/ UNK
12.1.8. What is the average percentage of overtime hours during detailed engineering phase excluding shutdown? (Overtime Hrs / Total Eng. Hrs)
<10% 10%~20% 20%~30% 30%~40% >40% NA/ UNK
12.1.9. Estimate the percentage detail engineering schedule delay because of information delay caused by suppliers: ________ % 12.1.10. Was the Front End Planning (FEP) design team the same as the detail engineering team? No Yes Dont Know [If yes, the FEP Design team was the same as the detailed engineering team, please skip next question.] 12.1.11. On average, the interfaces between prime design contractors were well managed and fully completed.
Strongly Disagree 0 Neutral 1 2 3 Strongly Agree 4 NA/ UNK
12.1.12. The schedule of detail engineering phase in this project is aggressive considering team size and project complexity.
Strongly Disagree 0 Neutral 1 2 3 Strongly Agree 4 NA/ UNK
12.1.13. Which type of organization is the most similar to the engineering team for this project? (Please see the definition below)
Functional Organization Project Organization Matrix Organization Task Organization NA/ UNK
Page29of65
Functional Organization
Staffs are recruited, trained, and assigned to support projects, but are permanently assigned to a functional manager.
Project Organization
Matrix Organization Project managers draw support from each function as required. Functional managers are responsible for recruitment, training and technical support.
Page30of65
12.2. Concrete
[Upstream Oil and Gas will not include this section)] Instructions Please complete the following tables indicating quantity and engineering work-hours for the categories appropriate to your project. If you cannot enter all data then enter totals only. Include rework in the work-hours only. If the project had no work hours or quantities for a category, check none. The quantity of concrete is that concrete that is required for the specified slab, foundation, or structure provided in the final Issued for Construction (IFC) drawings. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for a detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours. 12.2.1. Which design platform was used for this category in this project? Check all that apply. 2D 3D
IFC Quantity (cubic yards) Engineering Work-Hours (including rework) (hours)
Slabs
None
Foundations
None
Foundations (< 5CY) Foundations (>= 5CY) Total Foundations (CY) (Excluding piling)
None
Concrete Structures This includes concrete structures, columns, beams, cooling tower basins, trenches, formed elevated slabs/structures, retaining walls, and drainage structures.
Page31of65
None
Total Concrete The total concrete quantity and work hours may be greater than the sum of totals for slabs, foundations and concrete structures if the project included concrete not in these categories.
None
Piling
12.2.2. Concrete Design Reuse If the project design includes multiple similar components that allow reuse of design effort, estimate the percentage of the total quantity for concrete that did not require unique design. Example: The total concrete quantity for a project is 5,000 CY. The design includes three identical foundations of 1,000 CY each. There are no other identical components. The estimated design reuse for concrete is: 2000 CY 5000 CY = 40%
< 10%
>= 10%
> 20%
> 30%
> 40%
> 50%
> 60%
> 70%
> 80%
> 90%
The quantity of steel is that quantity of steel provided in the final Issued for Construction (IFC) drawings. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours. 12.3.1. Which design platform was used for this category in this project? Check all that apply.
2D Structural Steel Structural Steel This includes trusses, columns, girders, beams, struts, girts, purlins, vertical and horizontal bracing, bolts, and nuts. Pipe Racks & Utility Bridges This includes steel structures outside the physical boundaries of a major structure, which are used to support pipe, conduit, and/or cable tray. Combined Structural Steel and Pipe Racks & Utility Bridges* * Enter combined structural steel and pipe racks & utility bridges if you cannot separate the quantities above. Miscellaneous Steel This includes handrails, toeplate, grating, checker plate, stairs, ladders, cages, miscellaneous platforms, pre-mounted ladders and platforms, miscellaneous support steel including scab on supports, T and H type supports, trench covers, and Q decking. Total Steel This is the total of structural steel, pipe racks & utility bridges, and miscellaneous steel from above or the total of combined structural steel, pipe racks & utility bridges (if not separated) and miscellaneous steel. If you have quantities for steel not included in the breakouts above, include them in the totals here. 3D None IFC Quantity (tons) Engineering Work-Hours (including rework) (hours)
12.3.2. Structural Steel Design Reuse If the project design includes multiple similar components that allow reuse of design effort, estimate the percentage of the total quantity for structural steel that did not require unique design. Page33of65
Example: The total steel quantity for a project is 5,000 tons. The design includes three identical structural steel frames of 1,000 tons each. There are no other identical components. The estimated repeated quantity for steel is: 2000 Tons 5000 Tons = 40%
< 10%
>= 10%
> 20%
> 30%
> 40%
> 50%
> 60%
> 70%
> 80%
> 90%
12.4. Electrical
Instructions Please complete the following tables indicating quantity and engineering work-hours for the categories appropriate to your project. If you cannot enter all data then enter totals only. Include rework in the work-hours only. If the project had no work hours or quantities for a category, check none. 12.4.1. Total Direct Engineering Electrical Work-Hours for This Project _________ 12.4.2. Total Connected Horsepower of Motors _________ 12.4.3. Number of Motors _________ 12.4.4. Total KVA Load of Project _________
The quantity of electrical equipment, conduit, cable trays, wire, termination, and lighting fixtures are the quantity of each provided in the final Issued for Construction (IFC) drawings. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours.
12.4.5. Which design platform was used for this category in this project? Check all that apply.
2D 3D
Page34of65
Electrical Equipment Electrical Equipment 600V & Below Electrical Equipment Over 600V
None
Electrical equipment includes transformers, switchgear, UPS systems, MCCs, rectifiers, motors, etc. This also includes work-hours for single line, elementary diagrams and studies. (Generator data is collected in the power generation equipment section) Total Electrical Equipment Engineering Work-Hours (including rework) (hours)
IFC Quantity
This includes power plan, cable and conduit schedule and interconnects. Exposed / aboveground and underground Engineering Work-Hours (including rework) (hours)
This includes electrical and instrument cable trays, channels, supports, covers, etc. Engineering Work-Hours (including rework) (hours)
None Wire & Cable (w/o conduit or tray) Linear Feet Number of Terminations
IFC Quantity
This includes power, control and grounding cables. Engineering Work-Hours (including rework) (hours)
None Lighting
This includes fixtures, conduit, wiring, panels, and control devices. Quantity to be number of fixtures.
Page35of65
12.5. Piping
Instructions Please complete the following tables indicating quantity, percent hot and cold, and engineering work-hours for the categories appropriate to your project. Piping includes under ground pressure pipe. Exclude tubing. If you cannot enter all data then enter totals only. Include rework in the work-hours only. If the project had no workhours or quantities for a category, enter none. The quantity of piping is that piping specified in the final Issued for Construction (IFC) drawings. This quantity should not be cut lengths but should be measured center-to-center through valves and fittings as with the quantity for the construction metric. Most CADD dumps are cut lengths. The quantity should be adjusted to be the length measured as noted above. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours. Hot piping is that piping which has a design temperature greater than 250 degrees Fahrenheit. Cold piping is that piping which has a design temperature less than minus 20 degrees Fahrenheit. 12.5.1. Which design platform was used for this category in this project? Check all that apply.
2D Piping Small Bore (2-1/2 and Smaller) (linear feet) Large Bore (3 and Larger) (linear feet) Engineered Hangers and Supports (each) (Includes stress analysis) Number of pipe fittings* Total Piping (linear feet only)** * Elbows, flanges, reducers, branch connection fittings e.g. o-lets, saddles etc., Ys, Ts, caps, unions, couplings, etc. ** Total piping quantity is linear feet only. The total piping work-hours include those hours for small & large bore piping, engineered hangers and supports and fittings. 3D None IFC Quantity Percent Hot and Cold (%) Engineering Work-Hours (including rework) (hours)
Page36of65
12.6. Instrumentation
Instructions Please complete the following tables indicating quantity and engineering work-hours for the categories appropriate to your project. If you cannot enter all data then enter totals only. Include rework in the work-hours only. If the project had no workhours or quantities for a category, enter none. The quantity of instrumentation is that quantity provided in the final Issued for Construction (IFC) drawings. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours. 12.6.1. Which design platform was used for this category in this project? Check all that apply.
2D 3D
Engineering Work-Hours Instrumentation Loops (count) Tagged Devices (count) I/O (count) This includes all instrument and control design work-hours except DCS/PLC Configuration and Programming. I/O (count) includes the I/O that comes over digital communication interfaces from outside of the control system. For such interfaces, count the addressable points. For fieldbus interfaces, count only the devices. DCS/PLC Design included DCS/PLC Configuration and Programming None IFC Quantity (including rework) (hours)
Page37of65
12.7. Equipment
Instructions Please complete the following tables indicating quantity and engineering work-hours for the categories appropriate to your project. If you cannot enter all data then enter totals only. Include rework in the work-hours only. If the project had no workhours or quantities for a category, enter none. The Total Quantity of equipment is the quantity of tagged items provided in the final Issued for Construction (IFC) drawings with vendor designed skids being counted as a single item. The Individually Designed quantity is the quantity defined by unique data sheets. For example, pump P201a/b is one unique data sheet, but is a total of two items. These hours include only mechanical discipline hours. Refer to the section Instructions for Computation of Work-Hours and Rework-Hours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the work-hours. 12.7.1. Which design platform was used for this category in this project? Check all that apply.
2D None Pressure Vessels 3D Individually Designed (each) Total Quantity (each) Engineering Work-Hours (including rework) (hours)
This includes tray/packed towers, columns, reactors/regenerators, and miscellaneous other pressure vessels. Field fabricated towers, columns, reactors and regenerators should also be included. Individually Designed (each) Engineering Work-Hours (including rework) (hours)
This includes storage tanks, floating roof tanks, bins/hoppers/silos/cyclones, cryogenic & low temperature tanks and miscellaneous other atmospheric tanks. Individually Designed (each) Engineering Work-Hours (including rework) (hours)
None
This includes heat exchangers, fin fan coolers, evaporators, cooling towers and miscellaneous other heat transfer equipment.
Page38of65
Total (BTU/Hr)
This includes packaged boilers, field erected boilers, fired heaters, waste heat boilers, stand-alone stacks, and miscellaneous other boilers and fired heaters. Engineering Work-Hours (including rework) (hours)
None
Total (horsepower )
This includes compressors (centrifugal/reciprocating), blowers, screw rotary compressors, metering/in-line pumps, pumps (centrifugal/reciprocating), positive displacement pumps, agitators, mixers, blenders and other miscellaneous compressors, fans and pumps. Individually Designed (each) Engineering Work-Hours (including rework) (hours)
None
This includes conveyors (belt, chain, screen, rotor, etc.), cranes & hoists, scales, lifts, stackers, reclaimers, ship loaders, compactors, feeders and baggers, and miscellaneous other material handling equipment. Engineering WorkHours (including rework) (hours))
None
Total (kilo-watts)
This includes gas turbines, steam turbines, generators, and other miscellaneous power generation equipment.
Page39of65
None
Woodyard Equipment Pulp Mill Equipment Bleach Plant Equipment Stock Preparation Equipment Wet End Equipment (through the Presses) Dryer Sections Dry End Equipment including Roll Wrap/Converter Equipment Total Pulp & Paper Equipment This includes all paper machines and miscellaneous other pulp & paper equipment. Individually Designed (each) Engineering Work-Hours (including rework) (hours)
None
This includes specialty gas equipment, bulk chemical equipment, process equipment, particle extraction (bag houses, scrubbers, etc.), treatment systems (water treatment, etc.), incinerators, and flares/flare systems. Individually Designed (each) Engineering Work-Hours (including rework) (hours)
None
Page40of65
None
Skids & modules with multiple equipments are counted still as a single entry. * Total equipment count may include items not identified above. ** This is total mechanical discipline direct work-hours.
Withholding Federal income tax, Withholding and paying the employer social security and Medicare tax, Paying Federal unemployment tax (FUTA) Issuing Form W-2, Wage and Tax Statement, annually, Reporting wages on Form 941, Employers Quarterly Federal Tax Return
The term Off-Shore refers to the use of low-cost engineering centers throughout the world. (Source: International Revenue Service, IRS and Decline of the Engineering Class: Effects of Global Outsourcing of Engineering Services, Paul T. Bryant, P.E, Leadership and Management in Engineering, April 2006, pp.59-71)
Page41of65
Direct-Hire Disciplines Concrete Steel Piping Electrical Instr. Equipment Total None Contract Hrs Hrs Hrs Hrs Hrs Hrs Hrs Off-Shore Hrs Hrs Hrs Hrs Hrs Hrs Hrs Total Hrs Hrs Hrs Hrs Hrs Hrs Hrs Contract Hrs Hrs Hrs Hrs Hrs Hrs Hrs
Contract Off-Shore Hrs Hrs Hrs Hrs Hrs Hrs Hrs Total Hrs Hrs Hrs Hrs Hrs Hrs Hrs
Page42of65
Page43of65
13.1. Concrete
[Upstream Oil and Gas will not include this section] Instructions Please complete the following tables indicating installed neat quantity and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. Also, please record the total rework-hours with source information if available where requested at the end of the section. Include work-hours for the following selected activities: Loading material at the jobsite yard, hauling to, and unloading at the job work site; local layout, excavation and backfill, fabrication, installation, stripping and cleaning forms; field installation of reinforcing material; field installation of all embeds; all concrete placement, curing, finishing, rubbing, mud mats; and anchor bolt installation. Do not include work hours for: Piling, drilled piers, wellpoints and major de-watering, concrete fireproofing, batch plants, nonpermanent roads and facilities, third party testing, mass excavations, rock excavations, site survey, q-deck, sheet piles, earthwork shoring, cold pour preparation, grouting, precast tees, panels, decks, vaults, manholes, etc. Definitions The Installed Neat Quantity of concrete is that concrete that is required for the specified slab, foundation, or structure provided in the projects plans and specifications and does not include any quantity of concrete that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours.
Subcontracted (Yes or No) Installed Quantity (cubic yards) Actual Work-Hours (including rework) (hours)
None
Page44of65
Foundations < 5 cubic yards 5 20 cubic yards 21 50 cubic yards > 50 cubic yards Total Foundations
None
This includes concrete structures, columns, beams, cooling tower basins, trenches, formed elevated slabs/structures, retaining walls, and drainage structures. Actual Work-Hours (including rework) (hours)
The total concrete quantity and work hours may be greater than the sum of totals for slabs, foundations and concrete structures if the project included concrete not in these categories.
13.1.1. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
Page45of65
13.1.2. Concrete Repetitive Construction If the project includes multiple similar components that allow construction efficiencies (i.e. based on learning curve, formwork reuse, etc.), estimate the percentage of the total quantity for concrete that was repeated. Example: The total concrete quantity for a project is 5,000 CY. There are three identical foundations of 1,000 CY each installed on-site. There are no other identical components. The estimated repeated quantity for concrete is:
2,000 CY 5,000 CY
= 40%
< 10%
>= 10%
> 20%
> 30%
> 40%
> 50%
> 60%
> 70%
> 80%
> 90%
None
This includes trusses, columns, girders, beams, struts, girts, purlins, vertical and horizontal bracing, bolts, and nuts. Pipe Racks & Utility Bridges This includes steel structures outside the physical boundaries of a major structure, which is used to support pipe, conduit, and/or cable tray. Miscellaneous Steel This includes handrails, toeplate, grating, checker plate, stairs, ladders, cages, miscellaneous platforms, pre-mounted ladders and platforms, miscellaneous support steel including scab on supports, T and H type supports, trench covers, and Q decking. Total Structural Steel
13.2.1. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
13.2.2. Structural Steel Repetitive Construction If the project includes multiple similar components that allow construction efficiencies (i.e. based on learning curve, formwork reuse, etc.), estimate the percentage of the total quantity for structural steel that was repeated. Example: The total steel quantity for a project is 5,000 tons. There are three identical structural steel frames of 1,000 tons each installed on-site. There are no other identical components. The estimated repeated quantity for steel is: 2,000 Tons 5,000 Tons = 40% Page47of65
< 10%
>= 10%
> 20%
> 30%
> 40%
> 50%
> 60%
> 70%
> 80%
> 90%
13.3. Electrical
Instructions Please complete the following tables indicating installed quantity and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. Also, please record the total rework-hours with source information if available where requested at the end of the section. This includes work-hours for the following selected activities: Installation, testing, labeling, etc. Definitions The Installed Quantity of electrical equipment, devices, conduit and cable trays are the quantity of each provided in the projects plans and specifications and does not include any quantity that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours. 13.3.1. Total Direct Electrical Work-Hours for This Project _____________ 13.3.2. Total Connected Horsepower of Motors _____________ 13.3.3. Number of Motors _____________ 13.3.4. Total KVA Load of Project _____________
Electrical Equipment and Devices Panels and Small Devices This includes all labor for the installation of lighting and power panels, dry type transformers, control stations (pushbuttons, small local panels, etc.), welding receptacles and their supports. Count includes only actual electrical devices - not supports. Subcontracted Installed Quantity (Yes or No) (each) Actual Work-Hours (including rework) (hours)
None
Page48of65
Electrical Equipment 600V & Below Electrical Equipment Over 600V Total Electrical Equipment This includes all labor for the installation of transformers, switchgear, UPS systems, MCCs, DCS/PLC racks and panels, etc. Instructions for calculation of Weighted-Average Diameter of Conduit (Hyperlink) Weighted Conduit None Subcontracted (Yes or No) Average Diameter (inches) Exposed or Aboveground Conduit This includes all labor for installation of conduit, hangers, supports, fittings, flexible connections, marking, grounding jumpers, seals, boxes, etc. This excludes lighting conduit. Underground, Duct Bank or Embedded Conduit This includes all labor for installation of conduit, supports, grounding jumpers, etc. Does not include excavation, backfill, concrete, manholes, etc. Total Conduit Instructions for calculation of Weighted-Average Size of Cable Tray (Hyperlink) Weighted None Subcontracted Average Size (Yes or No) (width in inches) Actual Work Hours (including rework) (hours) Installed Quantity (lineal feet) Actual WorkHours (including rework) (hours)
Cable Tray This includes all labor for the installation of tray, channel, supports, covers, grounding jumpers, marking, etc. It does not include fire stop or cable tray for instrument wire and cable.
Page49of65
Wire and Cable Power and Control Cable - 600V & below
None
This includes all labor for the installation, termination, labeling, and testing of 600V and below power and control cable. It does not include heat-tracing cable. Power Cable 5 & 15KV This includes all labor for the installation, termination, labeling, and testing of medium voltage power cables. Total Wire and Cable Actual Work-Hours Installed Quantity (including rework) (hours)
None
This includes all labor for the installation of fixtures (including lamps and supports) and for the installation of conduit and wiring from the lighting panel to the fixtures. Includes any control equipment, switches, conduit, wiring and accessories installed on the load side of the lighting panel. Installation of lighting panels is included in Panels and Small Devices and power feeder wiring for the panel is included in Power and Control Cable - 600V. Grounding (lineal feet) This includes all the labor for the installation of cable, ground rods, connectors and all accessories for the installation of conduit and wiring from the lighting panel to the fixtures. Includes work hours for the installation of ground cables pulled into cable trays, duct banks, and installed exposed in electric or other rooms. The footage is based on the total footage of ground cable installed. Electrical Heat Tracing (lineal feet) This includes the labor for the installation of electric heat trace cable, power feeds to the cable, control accessories, end of line devices, connectors, tape or other strapping/support materials, and any other items needed to complete the heat trace system. Footage is based on the lineal footage of process and utility piping heat traced.
Page50of65
13.3.5. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
13.4. Piping
Instructions Please complete the following tables indicating the weighted-average diameter in inches, the installed quantity, percent shop fabricated, percent hot and cold, and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. Also, please record the total rework-hours with source information if available where requested at the end of the section. Include work-hours for the following selected activities: Erecting and installing piping, including welding, valves, in-line specials, flushing/hydro testing, tie-ins (excluding hot taps), material handling (from the laydown yard to the field), in-line devices, specialties, equipment operators, and hangers & supports. Do not include work-hours for: Non-destructive evaluation (NDE), steam tracing, stress relieving, underground piping, offloading pipe as it is received, commissioning, scaffolding and field fabrication of large bore. Definitions The Installed Quantity of piping is that piping specified in the projects plans and specifications and does not include any quantity of piping that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours. Page51of65
Instructions for calculation of Small Bore Weighted-Average Diameter (Hyperlink) Small Bore (2-1/2 and Smaller) - Field and Shop Fabricated and Field Run (Excludes Tubing)
Actual WeightedPercent Shop Installed Work-Hours Subcontracted Average Fabricated Quantity None (including rework) (Yes or No) Diameter (%) (lineal feet) (hours) (inches)
Small Bore Carbon Steel Stainless Steel Chrome Other Alloys Total Small Bore
In the following sections for large bore piping the following definitions apply for hot and cold piping. Hot piping is that piping which has a design temperature greater than 250 degrees Fahrenheit. Cold piping is that piping which has a design temperature less than minus 20 degrees Fahrenheit.
Instructions for calculation of ISBL and OSBL Large Bore Weighted-Average Diameter (Hyperlink)
Inside Battery Limits (ISBL) Large Bore (3 and Larger) (Excludes Tubing)
WeightedSubcontracted Average None (Yes or No) Diameter (inches) Average Installed Wall Quantity Thickness (lineal feet) (schedule) Actual WorkHours % Shop % Hot (including Fabricated and Cold rework) (%) (%) (hours)
Large Bore (ISBL) Carbon Steel Stainless Steel Chrome Other Alloys Total Large Bore (ISBL)
Page52of65
Outside Battery Limits (OSBL) Large Bore (3 and Larger) (Excludes Tubing)
WeightedSubcontracted Average None (Yes or No) Diameter (inches) Average Installed Wall Quantity Thickness (lineal feet) (schedule) Actual Work% Hot Hours % Shop and (including Fabricated Cold rework) (%) (%) (hours)
Large Bore (OSBL) Carbon Steel Stainless Steel Chrome Other Alloys Total Large Bore (OSBL)
13.4.1. Rework-Hours
Source of Rework-Hours for Piping Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
13.5. Instrumentation
Instructions Please complete the following tables indicating installed quantity and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. Also, please record
Page53of65
the total rework-hours with source information if available where requested at the end of the section. This includes work-hours for the following selected activities: Installation, calibration, testing, check out, and otherwise field certify the devices. A device is a physical device that has a tag number. This category includes process tubing, instrument air tubing, cable trays, conduits, instrument wire and cable, junction boxes, etc. Do not include work-hours for: DCS, software, installation of in-line devices, programming and configuration. Definitions The Installed Quantity of instrumentation is that quantity provided in the projects plans and specifications and does not include any quantity of instrumentation that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours.
Instrumentation Loops (count) Devices (Instruments, count) Unit of measure: Dual Each based on loop check quantity. Each based on field-installed devices. Instrumentation wire and cable (lineal feet) None Subcontracted Installed Quantity (Yes or No) Actual Work-Hours (including rework) (hours)
13.5.1. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
Page54of65
13.6. Equipment
Instructions Please complete the following tables indicating installed quantity and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. If equipment is preassembled on-skids Do not include in the equipment count. Also, please record the total rework-hours with source information if available where requested at the end of the section. Definitions The Installed Quantity of equipment is that quantity provided in the projects plans and specifications and does not include any quantity of equipment that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours.
Installed Quantity (each) Actual Work-Hours Total Weight (including rework) (tons) (hours)
Subcontracted None (Yes or No) Total Equipment Include all major equipment list below
None
This includes tray/packed towers, columns, reactors/regenerators, and miscellaneous other pressure vessels. Work-hours should include installation of trays and packing if installed in the field. Field fabricated towers, columns, reactors and regenerators are not to be included. Actual Work-Hours Total Subcontracted Installed (including rework) Capacity (Yes or No) Quantity (each) (hours) (tons)
None
This includes storage tanks, floating roof tanks, bins/hoppers/silos/cyclones, cryogenic & low temperature tanks and miscellaneous other atmospheric tanks. Include all shop built-up and fielderected tanks. Excluded are field fabricated and assembled tanks.
Page55of65
None
Actual Work-Hours Total Subcontracted Installed (including rework) Capacity (Yes or No) Quantity (each) (hours) (tons)
This includes storage tanks, floating roof tanks, bins/hoppers/silos/cyclones, cryogenic and low temperature tanks, and other miscellaneous atmospheric tanks. Actual Work-Hours Subcontracted Installed (including rework) (Yes or No) Quantity (each) (hours) Total Weight (tons)
None
This includes heat exchangers, fin fan coolers, evaporators, package cooling towers and miscellaneous other heat transfer equipment. Installed Quantity (each) Actual Work-Hours (including rework) (hours)
Subcontracted Boiler & Fired Heaters None (Yes or No) Boiler & Fired Heaters
Total (MBTU)
This includes packaged boilers, field erected boilers, fired heaters, waste heat boilers, stand-alone stacks, and miscellaneous other boilers and fired heaters. Installed Quantity (each) Actual Work-Hours Total (including rework) (horsepow (hours) er)
None
This includes compressors (centrifugal/reciprocating), blowers, screw rotary compressors, metering/in-line pumps, pumps (centrifugal/reciprocating), positive displacement pumps, agitators, mixers, blenders and other miscellaneous compressors, fans and pumps. Actual Work-Hours (including rework) (hours)
Subcontracted Material Handling None Equipment (w/drivers) (Yes or No) Material Handling Equipment (w/drivers)
This includes conveyors (belt, chain, screen, rotor, etc.), cranes & hoists, scales, lifts, stackers, reclaimers, ship loaders, compactors, feeders and baggers, and miscellaneous other material handling equipment.
Page56of65
None
This includes gas turbines, steam turbines, generators, and other miscellaneous power generation equipment. Actual Work-Hours (including rework) (hours)
Pulp & Paper Equipment Woodyard Equipment Pulp Mill Equipment Bleach Plant Equipment Stock Preparation Equipment Wet End Equipment (through the Presses) Dryer Sections Dry End Equipment including Roll Wrap/Converter Equipment Total Pulp & Paper Equipment
This includes all paper machines and miscellaneous other pulp & paper equipment. Actual WorkHours Subcontracted Installed Quantity None (including rework) (Yes or No) (each) (hours)
This includes specialty gas equipment, bulk chemical equipment, process equipment, particle extraction (bag houses, scrubbers, etc.), treatment systems (water treatment, etc.), incinerators, and flares/flare systems.
Page57of65
Actual WorkHours Subcontracted Installed Quantity None (including rework) (Yes or No) (each) (hours)
This includes on-site work hours for installation of modules (partial units) and complete skids units.
13.6.1. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
13.7. Insulation
Instructions Please complete the following tables indicating average thickness or diameter, installed quantity, and work-hours (including rework) for the categories appropriate to your project and indicate if the work performed for each category was subcontracted or not. If work performed for a category was both subcontracted and in-house, indicate the type that was more predominate. Also, please record the total rework-hours with source information if available where requested at the end of the section. Definitions The Installed Quantity of insulation is that quantity of insulation that is required for the equipment and piping provided in the projects plans and specifications and does not include any quantity of insulation that is used due to rework. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours.
Page58of65
13.7.1. Equipment This includes work-hours for the following selected activities: Installation of insulation, jacketing overall vessels, tanks, exchangers, etc.; installation of equipment blankets for pumps, exchangers, etc.; material handling.
Average Subcontracted Thickness None (Yes or No) (inches) Installed Quantity (square feet of insulated area) Actual Work-Hours (including rework) (hours)
Insulation Equipment
13.7.2. Piping This includes work-hours for the following selected activities: Installation of insulation and jacketing over pipe, valves and fittings; installation of valve insulation blankets and flange insulation.
Instructions for calculation of Weighted-Average Diameter of Piping with Insulation (Hyperlink) WeightedAverage Subcontracted Average Thickness Insulation None Diameter (Yes or No) (inches) (inches) Piping ELF Equivalent Linear Feet of insulation applied to piping. Multiple layers count only one time in linear footage. Installed Quantity (equivalent linear feet) Actual WorkHours (including rework) (hours)
13.7.3. Rework-Hours
Source of Rework-Hours for Concrete Design Vendor Owner Contractor Other: Total Rework-Hours (hours)
Page59of65
13.8. Scaffolding
Instructions Please complete the following table indicating work-hours for the scaffolding appropriate to your project and indicate if the work performed for the item was subcontracted or not. If work performed for the item was both subcontracted and in-house, indicate the type that was more predominant. Definitions Total scaffolding work-hours refers to the required work hours for scaffolding, collected to calculate the ratio in terms of scaffolding work-hours divided by total direct hours. Refer to the section Instructions for Computation of Actual Work-Hours and ReworkHours for an additional detailed listing of direct hours to be included and indirect hours that are to be excluded from the computation of the actual work-hours. This includes work-hours for the following selected activities: On-site transportation, installation and disassembly. Do not include work-hours for: Pre-fabrication of scaffold.
Source of Scaffold Materials? Free Issue to Contractor Rented Purchased & Included as part of Scaffold Cost
8/10/2011
60