W05 AnalyzingProcessFlowsDeterministic Part1
W05 AnalyzingProcessFlowsDeterministic Part1
PROCESS FLOWCHARTING
§ Purpose: To describe a process visually to find ways
of improving the current process.
OPIM 404 − Find repetitive operations
Business Process − Identify bottlenecks
− Describe directions, durations and distances of flows
Analysis & Design (people, material and information)
− Reduce waste à Any non-value adding operation
• Time in storage/queue
• Transportation time
Analyzing Process Flows – • Inspection time
1 3
4a 5b
Common Flowcharting Symbols (Figure 6.4) Two Flow-Process Chart Symbols (Cont’d)
§ Delay: A delay occurs when the immediate performance of the
next planned action does not take place. During the delay the
work pieces/papers/flow units may wait in buffers (i.e. queues
or waiting areas). Examples provided on next slide include
1. Material in truck or on floor at bench waiting to be
processed,
2. Employee waiting for the elevator, and
3. Papers waiting to be filed.
§ Storage: A storage occurs when an object is kept under
control in a storage area (such that its withdrawal may
require authorization). Examples provided on next slide
include
1. Bulk storage of raw material,
2. Finished products in a warehouse, and
3. Documents and records in storage vault.
5c 5e
5d 6
6b 6c
Asking What, When, Who, Where and Asking Flow, Time, Quantity, Quality,
How Questions Cost Questions
7b 7d
Asking What, When, Who, Where and Asking Flow, Time, Quantity, Quality,
How Questions Cost Questions
7e 9
Recall: Flow-Process Chart for Picking Unit Load, Load Batch, Capacity
Operations à
Material Flow § Unit Load à Sum of operation times of all activities
that utilize a specific resource (in minutes in OPIM 404)
§ Load Batching àSimultaneously process several
flow units
− Oven baking 10 loaves of bread à Load batch = 10
− The higher the load batch, the higher the capacity
§ Capacity of a single resource unit (i.e. Number of
units processed by a single resource unit per hour)
Realize various non-value = (60/Unit load) x Load batch
adding activities
(transportation, delays, § Capacity of a resource pool
storage and sometimes even
inspection) à 469 min out of = (60/Unit load) x Load batch x # of identical resources
526 min
8 10
Managing Process Flows – Pizza USA 3 Reducing the Flow Time (Throughput Time)
§ What is the flow rate of the process? § Perform activities in parallel
− Flow rate = Min{Demand, Supply, Process Capacity}
§ Change the sequence of activities
− Flow rate = Min{Demand, Supply, 10 orders/hr}
− Assuming Demand and Supply > 15 orders/hr à § Reduce interruptions
Maximum flow rate of this process is 10 orders/hr § Identify and make max use of bottlenecks
§ What is the bottleneck in this process?
§ Plan and coordinate process activities better
− Process can not produce more than bottleneck
− Resource with smallest capacity à Bottleneck à Oven
− If we buy another oven, what would be new capacity of
the process & what would be the new bottleneck?
Capacity of oven = (60/24) x 4 x 2 = 20 orders/hr
Capacity of process = Min{20, 12, 20} = 12 orders/hr
New bottleneck à Chef à Relocate some of chef’s jobs
16
Tevhide Altekin
15 17
output and leaves the process. − No waiting between activities. Assuming, all activities are
in series, simply the summation of all activity times
§ Flow time includes all Activity Minutes Resource
− Processing times à “Considers” work contents of all Take the order 1 Assistant
conducted activities Make the crust 3 Chef
− Waiting times Prepare & add ingredients 2 Chef
Bake the pizza 24 Oven
§ Min. Theoretical Flow Time (assume no Cut pizza & put in a box 1 Assistant
waiting)= 5 + 3 = 8 min Take payment 1 Assistant
Min Theoretical Flow Time 32 min
5 min 3 min − Will adding one more oven change min. theo. flow time?
§ Min. Theo. Flow Time = • NO
Resources
hour. Flow rate of the process is 75 units per hour. 2
Then 3 Blocked
Time
19 21
Managing Process Flows – Pizza USA 5 Gantt Chart Example Th. Min. Flow Time = 5+2 = 7 min
Capacity of Op1 = (60/5)x1x1 =
§ Considering the original process with 1 Chef, 1 = 12 units/hr
A B Capacity of Op2 = (60/2)x1x1=
Assistant and 1 Oven, what is the utilization of each
= 30 units/hr
resource? 5 min 2 min Capacity of Pr. = Min{12, 30}
Operator 1 Operator 2 = 12 units/hr
− Flow rate of process = 10 orders/hr
Assume load batches of activity A and B are both 1 Flow Rate of Process =
− Capacity of oven = 10 orders/hr Min{Supply, Demand, Pr. Capacity}
Assume we have 1 Operator 1 and 1 Operator 2
= 12 units/hr
− Capacity of chef = 12 orders/hr Assume both demand and supply are 15 units/hr Cycle Time = 1/Flow Rate
− Capacity of assistant = 20 orders/hr 5 10 15 20 Cycle Time = 1/12 = 0.0833 hr
= 0.0833x60 = 5 min
Resources
Op 2 B B B B
− Utilization of Assistant = 10/20 = 50% à Idle half of time 7 12 17 22
22-1
22-3
24
Takt Time
§ An indication of how fast processes must be in order to meet
demand in allotted time
§ Amount of time available / Units demanded
§ Suppose you had to produce 600 units in 80 hours to meet
the demand requirements of a product. What is the takt
time?
In 80 hours we have 4,800 minutes (60 minutes/hr x 80 hrs)
Takt time = 4,800 min/600 units
= 8 min btw consecutive units