SOP For Flanges
SOP For Flanges
2. Scope
This Standard Operating Procedure (SOP) focuses on the way to perform a Basic
Verification Service. This service consists of comparison of the customer
requirements specifications with the material offered at the time of Verification.
3.Verification Procedure:
The Verification service involves checking material offered. All the documents
viz. P.O., QAP, Datasheet, Drawings, approved by customer is referred at the time
of verification.
Following are the checks carried out during verification:
3.1 Visual Verification: Visual Verification is carried out with reference to the
P.O. requirements. In this case the Model number (Order Code), Tag number (if
applicable). Validation is also made with reference to the customer/consultant
approved datasheet specification.
3.3 Local material will be inward at warehouse only after clearance from Quality
team after Quality check
Threaded Flanges: -
Threaded flanges are also known as screwed flanges and it is having a thread
inside the flange bore which fits on the pipe with matching male thread on the pipe
this type of joint connection is speedy and simple but not suitable for high pressure
and temperature applications. Threaded flanges are mostly used in utility services
such as air and water.
FLANGES MATERIAL: -
Flanges are manufacture from
1) Carbon Steel
2) Low Steel
3) Stainless Steel
4) Combination & Exotic Material (Stub)
5) List of material used to manufacture flanges is covered in ASME B16.5 &
B16.47
6) ASME B16.5 pipe flanges &Flanges fiting NPS ½’’ to 24’’
7) ASME B 16.47 Large diameter steel flange NPS 26’’ to 60’’
MARKING: -
Following shall be marked on flange body
(1) Manufacturing logo
(2) ASTM material code
(3) Material grade
(4) Service rating (pressure-temp class)
(5) Size
(6) Thickness
(7) Heat no
(8) Special marking if any QT (quenched & tempered) or W(Repair by
Welding)