Saudi Aramco Typical Inspection Plan
Saudi Aramco Typical Inspection Plan
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY
TASK / ACTIVITY ASSIGNMENTS REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD
Subcon Contractor SA
1.0 DOCUMENT REVIEW
Soil Improvement/ Fill Compaction Works (DC / RDC) Method Method
1.1 Method Statement Statement Statement
RH RH
RECEIVING
2.0
INSPECTION
Dynamic Compaction / Rapid Dynamic Compaction
2.1 Materials Receiving Inspection
ASCIC-A-1002 ASCIC-A-1002 H I W
3.0 INSTALLATION
Soil Improvement/ Fill Compaction Dynamic
3.1 Compaction (DC) Rapid Dynamic Compaction (RDC) ASCIC-A-1013 ASCIC-A-1013 H I W
Pre-Installation (Survey)
Dynamic Compaction / Rapid Dynamic Compaction
3.2 Work Inspection
ASCIC-A-1016 ASCIC-A-1016 H I W
4.0 PRE-COMMISSIONING
4.1 Not Applicable
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Insp ection Personnel. After this period Saudi Aramco Inspection may adjust the levels of Saudi Aramco
1
participation based upon the Contractor's performance
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization represe ntative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco
LEGEND
H Hold Point for QC Inspection / Test R Review of Documents
W Witness Inspection / Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Dynamic Compaction, Rapid Dynamic Compaction
ASCIC-A-1001 CIVIL-
Material Sampling, Testing and Review of Test Reports
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
TREVITIP-A-000-01
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
RH RH
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Laboratory Testing
Tests are performed in accordance to applicable Standards in the Schedule "Q" Section
A2
presence of Contractor and Saudi Aramco Representatives. 1.4
B Fill Materials
Fill materials shall consist of gravel or sand and should achieve the
following specifications:
B1 - Sandy material with up to 15% fine contents (passing sieve #200) SAES-114 Section 6
- Clay content less than 1%
- Maximum particle size: 200 mm
Fill materials shall be non-plastic and free from organic matter and Method Statement
B2
deleterious substances, physically stable in water. Section 5.2
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-114 -- Excavation and Backfill
2- Schedule Q
Page 1 of 1
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Dynamic Compaction, Rapid Dynamic Compaction
ASCIC-A-1002 CIVIL-
Materials Receiving Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
TREVITIP-A-000-01
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W I
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Fill Materials
Delivered fill materials shall be non-plastic and free from organic Method Statement
A2
matter and deleterious substances, physically stable in water. Section 5.2
REMARKS:
REFERENCE DOCUMENTS:
Page 1 of 1
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Soil Improvement/ Fill Compaction Dynamic Compaction
ASCIC-A-
(DC) Rapid Dynamic Compaction (RDC) Pre-Installation CIVIL-
1013
(Survey)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
TREVITIP-A-000-01
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W I
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Major Plant facilities will be referenced to a local plant grid which in SAES-A-100
A2
turn is tied into the UTM coordinate system. Sec. 4.3
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-100 - Survey Coordinates, Datum's and Data Formats
2- Soil Improvement / Fill Compaction Works method statement
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Date:
Page 1 of 1
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Dynamic Compaction, Rapid Dynamic Compaction Work
ASCIC-A-1016 CIVIL-
Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
TREVITIP-A-000-01
SAUDI ARAMCO INSPECTION LEVEL
W
CONTRACTOR INSPECTION LEVEL
I
Y
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Working Levels (W.L.) have been established before any fill SAES-A-100/
A2
compaction Works are commenced. IFC Drawings
Method
Pounder type, weight, height and number of drops for phase 1 (first
B1 Statement,
pass) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 1 (first pass)
B2 Statement,
shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 1
B3 Statement,
(second pass if needed) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 1 (second
B4 Statement,
pass if needed) shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 2 (first
C1 Statement,
pass) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 2 (first pass)
C2 Statement,
shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 2
C3 Statement,
(second pass if needed) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 2 (second
C4 Statement,
pass if needed) shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 1 (first
D1 Statement,
pass) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 1 (first pass)
D2 Statement,
shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 1
D3 Statement,
(second pass if needed) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 1 (second
D4 Statement,
pass if needed) shall be done as per Method Statement.
Section 5.6
Page 1 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Dynamic Compaction, Rapid Dynamic Compaction Work
ASCIC-A-1016 CIVIL-
Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Method
Pounder type, weight, height and number of drops for phase 2 (first
E1 Statement,
pass) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 2 (first pass)
E2 Statement,
shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 2
E3 Statement,
(second pass if needed) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 2 (second
E4 Statement,
pass if needed) shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 3 (first
F1 Statement,
pass) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 3 (first pass)
F2 Statement,
shall be done as per Method Statement.
Section 5.6
Method
Pounder type, weight, height and number of drops for phase 3
F3 Statement,
(second pass if needed) shall be as per Method Statement.
Section 5.6
Method
Filling of materials on craters after pounding for phase 3 (second
F4 Statement,
pass if needed) shall be done as per Method Statement.
Section 5.6
G Levelling
Pounder type, weight, height and number of drops for levellin/ironing Method
G1 for phase 1, phase 2 and phase 3 (If needed) locations shall be as Statement,
per Method Statement. Section 5.6
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-100 - Survey Coordinates, Datum's and Data Formats
2- Approved Method Statement for soil improvement fill compaction works
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Date:
Page 2 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 0 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Verification of Soil Improvement / Fill Compaction Works ASCIC-A-1015 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
TREVITIP-A-000-01
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General
Attachment IV to
A3 All equipments/gauges shall have valid Calibration Certificates.
Schedule Q 961
SABP-Q-014
The location and depth of cone penetration soundings shall be as
B1 Method Statement,
specified in the Method of Statement (Each 1,000 sq.m).
Section 6.2
For all cone penetration calibration, testing and data reporting, ASTM
B3 ASTM D-5778
D5778 shall be followed.
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-100 - Survey Coordinates, Datum's and Data Formats
2- Approved Method Statement for soil improvement/ fill compaction works
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Date:
Page 1 of 1