SSR 2024-25-Datas-17.08.2024
SSR 2024-25-Datas-17.08.2024
Constituency
:: Munugodu
Sub-Division
:: Choutuppal
District
:: Yadadri-Bhongir
Intra Village system for providing drinking water supply to Lachammagudem X Road
Habitation of Lachammagudem Gram Panchayath in Narayanpur Mandal of Munugodu
Constituency in Yadadri-Bhongir District
A. Introduction
Intra Village system for providing drinking water supply to Lachammagudem X Road Habitation of
Lachammagudem Gram Panchayath in Narayanpur Mandal of Munugodu Constituency in Yadadri-
Bhongir District
The Tapping point for the OHSR which supply water to newly proposed OHSR is being taken on 250-
6 Kg/Cm2 mm dia HDPE pipeline of node Hillfoot on Lachammagudem Side to Lachammagudem Jn
Of Lachammagudem ELBR under AKBR Segment.
1 Construction of 20KL OHSR with 12 Mts Staging with raft foundation using M30 Concrete.
2 Supply, Delivery & Laying, Jointing and Testing of HDPE pipes of PE-100 grade.
3 Cutting of CC Road Surface and Restoration of CC Road using Cement Concrete of (1:4:8) proportion.
4 Providing of 15mm dia Household connections using all fixtures etc., including earthwork
excavation, laying, lowering, jointing and testing.
5 Construction of CC Pedestals using Cement Concrete of (1:4:8) proportion.
6 Amount towards 18% GST, 1% Labor Cess, 0.5% QC Charges & 0.1% NAC charges.
The Estimate is prepared for the work “Intra Village system for providing drinking water supply to
Lachammagudem X Road Habitation of Lachammagudem Gram Panchayath in Narayanpur Mandal
of Munugode Constituency in Yadadri-Bhongir District" with an E/c of Rs: 54.50 Lakhs as per the
SSR 2024-25, Steel, Cement are adopted from PHED Monthly rates July 2024 and the same is
submitting for kind approval.
2 Day School
UPS 0
PS 0
ZPHS 0
Anganwadi 0
0
3 Boarding schools 0
KPVGB 0
SWR 0
Model Schools 0
0
4 Hospital 0
5 Hostels 0
6 GP Offices 0
7 Restaurants 0
9 Industries 0
Total 80
10 Prospective demand calculations
Population to be served as per 2024 80
Present Population : Growth in 0 Years 80 X (1+ 0.02)0 80
Procpective population (15 years) upto 2039 80 X (1+ 0.02)15 108
LPCD Proposed 100
Prospective Demand @ 100 LPCD 108 X 100 10800 Litres
Demand for Day Schools 0X 45 0 Litres
Demand for Gp Offices 0X 45 0 Litres
Demand for Boarding schools 0X 135 0 Litres
Demand for Hospital 0X 340 0 Litres
Demand for Hostels 0X 135 0 Litres
Demand for Hotels 70 X 180 12600 Litres
Demand for Industries 0X 30 0 Litres
Total 23400 Litres
11 Existing Facilities
Capacity of existing OHSR dilapidated 0 0 0
Capacity of existing OHSR 0 0 0
12 Service reservoir calculations 23400
No of Filling proposed 2
Capacity required ( Prospective demand 11700 Ltrs
with one / Two filling )
Capacity of Existing OHSR 0 Ltrs
Net capacity of OHSR required 11700 Ltrs
Hence provide 20000 Litres capacity OHSR
3 LS 4,267.00
Provision for NAC @ 0.10 %
4 LS 21,334.00
Provision for QC @ 0.50 %
5 LS 42,669.00
Provision for labour cess @ 1%
6 LS 780,323.00
Provision for GST @18%
7 LS 50,000.00
Provision of Price variation of cement, Steel
8 LS 70305.00
LS for unforeseen
Construction of 20,000.00 Lts capacity OHSR with 12.00 Mts staging at Lachammagudem X Road
Construction of VRCC OHSR as per departmental drawings and specifications, with 12 Mts staging height and with raft footings. And with
cement rate of Rs.5100 / MT and steel rate @ Rs 51000 /MT inclusive of three coats of food grade epoxy paint to inner surface of the
reservoir including roof dome for a finished work including 2 coats of weather proof emulsion painting for external surfaces over one coat
of primer of approved make, lettering, all required fixtures, pipes, bends, valves etc., for pipe connections but excluding cost of pipes,
bends and valves as per departmental designs and drawings. Fixtures includes: a) RCC or Aluminium ladder inside 0.60 m wide. b) spiral
staircase on the outside shall be provided upto 200KL ELSR. Above 200KL ELSR Capacity dog legged staircase shall be provided with
staircase flight width of 1.0mts and landing width of 1.20m. S.S railing to stair case upto 1.2m height. c) Lightning arrestor, including
conductor and earthing etc with relevant IS codes.d) RCC ventilators with copper or stainless Steel fly proofmesh e) D.I Manholes frame
and cover 0.60x0.60 m as per IS specifications (light duty) - 2 Nos. f) Water level indicator of good quality with ebonite/ copper float
approved pattern - 1 No. g) The ladder shall be with Aluminium and Verticals with HDPE of 10kg/Sqcm shall be provided for single column
OHSRs only. h) The increase in staging shall be at 1.0mt interval. i)The railing provided to the gallery and stair case shall be with stainless
Steel of grade 304 for a height of 1.20m. j)The dog legged staircase shall be enclosed with brick/CRS wall on three sides and front side
with PVC door of standard make up to 1st brace level from ground level to prevent unauthorized entry. k) D.I swan neck ventilators shall
be provided in top dome and slab-4Nos minimum. l) The above rates are exclusive of all inlet, outlet connections, valves and bolts & nuts
but including labour charges for hoisting, jointing with rubber insertion, nuts and bolts. All valves near inlet, outlet and for scour of ELSRs
shall be D.I valves, as per SOR 2024-25 Specification of OHSR including 13.615% Contractor profit
Total: 1,408,083.00
2 Outlet connections
D/F pipes - 2m. Long 80 6 5268.78 Each 31,613.00
D/F pipes - 1.0m. Long 80 1 3355.74 Each 3,356.00
D/F pipes - 0.6m. Long 80 1 3353.39 Each 3,353.00
Bell mouths 80 1 1123.58 Each 1,124.00
Duck foot bends 80 1 2238.99 Each 2,239.00
3 Scour connections
D/F pipes - 2m. Long 80 6 5268.78 Each 31,613.00
D/F pipes - 1.0m. Long 80 3 3355.74 Each 10,067.00
D/F pipes - 0.6m. Long 80 2 3353.39 Each 6,707.00
Duck foot bends 80 2 2238.99 Each 4,478.00
Semicircular bend 80 1 3200.43 Each 3,200.00
4 Overflow connections
D/F pipes - 2m. Long 80 7 5268.78 Each 36,881.00
D/F pipes - 1.0m. Long 80 1 3355.74 Each 3,356.00
D/F pipes - 0.6m. Long 80 1 3353.39 Each 3,353.00
Bell mouths 80 1 1123.58 Each 1,124.00
Duck foot bends 80 1 2238.99 Each 2,239.00
5 Sluice Valves
Sluice valve for Outlet 80 1 9897.00 Each 9,897.00
Sluice valve for Scour 80 1 9897.00 Each 9,897.00
Sluice valve for Inlet 80 1 9897.00 Each 9,897.00
Sub Total 221,347.00
Add contractor Profit @ 13.615% 30,136.00
Total 251,483.00
Supply and Delivery of HDPE pipes as per IS:4984-2016 with its amendments and
revisions thereof, including earth work excavtion for pipe line trench in all soils upto
SDR except Rock requiring blasting, lowering, laying and jointing of pipe lines true to
1 alignment and gradient, and refilling trenches with excavated earth (other than rocky
soil and boulders) with watering, tamping and removeing surplus earth from site of
work and filling pipe line with water and testing etc., complete including cost pipes and
its specials on HDPE pipeline
Supply and Delivery of HDPE pipes as per IS:8329-2000 with its amendments,including
earth work excavtion for pipe line trench in all soils upto SDR except Rock requiring
blasting, lowering, laying and jointing of pipe lines true to alignment and gradient, and
refilling trenches with excavated earth (other than rocky soil and boulders) with
watering, tamping and removeing surplus earth from site of work and filling pipe line
with water and testing etc., complete including cost pipes and its specials on HDPE
pipeline
Supply, delivery, laying and Jointing of and DI D/F Kinetic DI Air Valve as per
IS:14845 Heavy Duty with isolating valve bevel gear operated as per IS 14846 on pipe
line including supply of Air valve, CI Specials to suit the pressure class of pipe and
4
construction of RCC valve chambers as per requirement with RCC slab and RCC
manhole cover with locking arrangements etc.complete for finished item of work but
excluding CED.
a. 50mm dia air valve on 90mm pipline 1 - - - 1 No.s 70598.06 No.s 70,598.00
Providing 15mm dia House Service Connection as per standard specification
including the cost of the materials like PP Clamp Saddle comply with AS/NZS 4793 or
relevant international standards Mechanical tapping saddles for water works purposes
and designed for use with PVC/PE pipe as per IS 4985/ IS 4984 respectively. These
saddles should be contoured to fit around the pipe. PP Saddles shall be blue with
moulded SS female threaded outlets. Seal shall be thermoplastic elastomer rubber
5 suitable for drinking water and SS nut-bolt washer. Maximum working pressure rating of
10 bar, Compression Fittings ( FTA & FTO) Elbows, MDPE pipe PN-12.5, S&F of 15 mm
brass body CP finish bib tap, S& F 15 mm Nominal Bore GI pipe Medium Grade , S&F of
tamper proof house hold non return cum flow control valve , including lowering, laying
and jointing including earth work excavation and refilling the pipe line trench after
laying the pipe line etc complete as directed by departmental officer for finished item
of work ( As per SSR 2024-25 )
Cutting of CC road surface including water bound macadam /wet mix macadam etc.,
6
and stacking of excavated materials excluding all Taxes.
Cutting of BT road surface including water bound macadam /wet mix macadam etc.,
7
and stacking of excavated materials excluding all Taxes.
Earthwork excavation in all soils upto SDR using 2/3rd manual and 1/3rd Machinery MA 0%
Rate Analysis : Rate Add: LI 13% Total Sand for bedding/en Rate Earth work classification : Rate/m3
1 E/W Rate -using machine 108.88 - 108.88 Cost of sand for filling - 1 Sand or Loose soils wet sand(8b)
2 Diff. of 20a & 20b (of 8,9,12,13) 0.00 0.00 Conveyance charges 10KM Lead 2 Loamy clayey soils like BC and OG soils (9b)
included
3 Cost of refilling 0.00 Seignorage charges 40/1.13615 3 Slushy Soils (10b)
in e/w
4 Cost of sand filling 0.00 - 0.00 Filling charges - 4 Clayey Soils(11b)
E/W rate - manual
5 209.30 209.30 Deduct stacking stacking 5 Hard gravelly soils (12b)
(as per Std. data)
Add: MA on filling charges 6 Mixture of gravel and SDR (13b)
E/w rate for 1/3 machinery &
rd
175.83 /cum Total: 0.00 Total: 209.30
2/3rd manual
a) Material Componenet
Pipe dia in mm 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
Pipe cost 6kg/cm2 90.00 123.00 179.00 256.00 329.00 421.00 547.00 703.00 857.00 1156.00 1411.00 1781.00 2241.00
Add CP @13.615% 12.25 16.75 24.37 34.85 44.79 57.32 74.47 95.71 116.68 157.39 192.11 242.48 305.11
Total 102.25 139.75 203.37 290.85 373.79 478.32 621.47 798.71 973.68 1313.39 1603.11 2023.48 2546.11
Pipe dia in mm 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
1 Earth work 123.08 123.08 123.08 123.08 123.08 123.08 209.53 209.53 209.53 257.15 257.15 257.15 257.15
2 Extra allowance at 75% 73.26 73.26 73.26 73.26 73.26 73.26 92.09 92.09 92.09 113.02 113.02 113.02 113.02
3 Refilling charges
Lowering, Laying,
4 10.21 12.15 14.58 17.82 20.25 22.26 25.44 28.62 31.80 35.78 39.75 44.52 50.09
Jointing
Cost of & HF testing
specials
5 (1.20%) with same 1.08 1.48 2.15 3.07 3.95 5.05 6.56 8.44 10.28 13.87 16.93 21.37 26.89
pressure gauge
207.63 209.97 213.07 217.23 220.54 223.65 333.62 338.68 343.70 419.82 426.85 436.06 447.15
Add CF 13.615% 28.27 28.59 29.01 29.58 30.03 20.48 32.88 33.57 34.26 41.77 42.73 43.98 45.49
Sub Total 235.90 238.56 242.08 246.81 250.57 244.13 366.50 372.25 377.96 461.59 469.58 480.04 492.64
Total Cost per Rmt 338.15 378.31 445.45 537.66 624.36 722.45 987.97 1170.96 1351.64 1774.98 2072.69 2503.52 3038.75
HDPE pipes -6 Kg/cm2 - material, E/w, L/J & testing cost for Rmt
a) Material Componenet
Pipe dia in mm 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
Pipe cost 6kg/cm2 106.00 148.00 212.00 355.00 414.00 517.00 680.00 852.00 1062.00 1360.00 1680.00 2098.00 2650.00
Add CP @13.615% 14.43 20.15 28.86 48.33 56.37 70.39 92.58 116.00 144.59 185.16 228.73 285.64 360.80
Total 120.43 168.15 240.86 403.33 470.37 587.39 772.58 968.00 1206.59 1545.16 1908.73 2383.64 3010.80
Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
###
1 Earth work 123.08 123.08 123.08 123.08 123.08 123.08 154.73 154.73 154.73 189.90 189.90 189.90 189.90###
2 Extra allowance 73.26 73.26 73.26 73.26 73.26 73.26 92.09 92.09 92.09 113.02 113.02 113.02 113.02###
3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ###
Laying, Jointing & H F
4 45.00 49.00 58.00 71.00 84.00 90.00 97.00 106.00 115.00 129.00 136.00 149.00 232.00###
Testing
Cost of specials
5 (0.50%) with same 0.53 0.74 1.06 1.78 2.07 2.59 3.40 4.26 5.31 6.80 8.40 10.49 13.25###
pressure gauge
Sub Total 241.87 246.08 255.40 269.12 282.41 288.93 347.22 357.08 367.13 438.72 447.32 462.41 548.17###
Add CF 13.615% 32.93 33.50 34.77 36.64 38.45 39.34 34.74 36.08 37.45 44.34 45.51 47.57 59.25###
Sub Total 274.80 279.58 290.17 305.76 320.86 328.27 381.96 393.16 404.58 483.06 492.83 509.98 607.42###
Total Cost per Rmt 395.23 447.73 531.03 709.09 791.23 915.66 1154.54 1361.16 1611.17 2028.22 2401.56 2893.62 3618.22
###
DI Specials
2.0m length
1 2 3 4 5 6 7 8 9 10 11
2 100 2 5292 0.43 550.00 473.00 5765.00 36.80 5782.66 Rc Rate. since
80mm not in
3 150 2 7651 0.56 550.00 616.00 8267.00 55.40 8293.59 SSR
1 2 3 4 5 6 7 8 9 10 11
1 2 3 4 5 6 7 8 9 10 11
Dia Wt. in
Sno. Rate Transportation Amount Revised cost
(mm) Kg/ Pc
1 2 3 4 5 6 7
Bell Mouth
Dia Wt. in
Sno. Rate Transportation Amount Revised cost
(mm) Kg/ Pc
1 2 3 4 5 6 7
Dia Wt. in
Sno. Rate Transportation Amount Revised cost
(mm) Kg/ Pc
1 2 3 4 5 6 7
Providing 15mm dia House Hold Connection as per standard specification including the cost of the materials like PP Clamp Saddle confirming to prEN
12201-3, Manufactured from virgin resin of PE-80/PE-100 with Flow control valve,Compression FTA,MDPE PE 80 Blue Pipe and Supplying and Fixing
of GI Pipe including lowering, laying and jointing including earth work excavation and refilling the pipe line trench after laying the pipe line and including
Supply, delivery and fixing of 15 mm dia brass body bib tap etc., including GI verticals complete for finished item of work.
MATERIAL COMPONENT
PP Clamp Saddle shall comply with AS/NZS 4793 or relevant international standards-Mechanical tapping saddles for water works
purposes and designed for use with PVC/PE pipe as per IS 4985/ IS 4984 respectively. These saddles should be contoured to fit
1
around the pipe. PP Saddles shall be blue with moulded SS female threaded outlets. Seal shall be thermoplastic elastomer rubber
suitable for drinking water and SS nut-bolt-washer. Maximum working pressure rating of 10 bar. (Exclusive of GST) (Saddles)
Supply and Fixing of Compression Fittings shall comply with ISO 17885 – 2015, PN-16 rating and manufactured from virgin resin
of PE-80 having blue colour. Raw material must be WRAS Approved as per BS 6920 for effect on water quality intended for human
consumption. Compression fittings should have moulded-in SS 304 threaded insert outlet with thread dimension conforming to IS
3
554/ISO 7. The cost shall include testing of all materials, labour, inspection charges, transportation up to site, transit insurance,
loading, unloading, stacking, providing and fixing etc. Complete as specified and directed by the Departmental Engineers, but
excluding all taxes.
Manufacture, Supply, Delivery, E/w of trench size 0.3x0.6x6.0 and L/J/Tof MDPE pipe conforming to ISO 4427 Part-2 (or any
equivalent Bureau of Indian Standards code) of PE-80 grade material along with all fittings, including cost of materials,
4
manufacturing, loading, unloading, stacking, transit insurance, transportation to any where in Telangana but excluding GST.
(MDPE) including CP
S& F 15 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI fittings including the cost of
5
pipe & its fittings &labour charges complete (GI pipe)
S&F of 15 mm brass body CP finish bib tap of not lessthan 300 grams weight screw type (full turn) withinternal / external threaded
6
connection conforming to IS 8931 (Bib Tap)
CIVIL COMPONENT
1 Skilled Fitter Cl-I for 26 Connections/Day 1/26 1/26 Job 735.00 Day 28.27
2 Semi Skilled Fitter Cl-II for 26 Connections/Day 1/26 1/26 Job 615.00 Day 23.65
2) Rate inclusive of three coates of food grade epoxy paint to inner surface of the reservoir including roof dome.
3) The above rates be adopted for estimate purposes for construction of ELSR for a finished work including 2 coats of wheather proof emulsion painting for external surfaces, lettering, all
required fixtures, pipes, bends, valves etc., for pipe connections but excluding cost of pipes,bends and valves as per departmental designs and drawings.
4) Fixtures include :
e) D.I Manholes frame and cover 0.60x0.60 m as per IS specifications (light duty) - 2 Nos.
f) Water level indicator of good quality with ebonite/ copper float approved pattern - 1 No.
g) The ladder shall be with Aluminium and Verticals with HDPE of 10kg/Sqcm shall be provided for single column OHSRs only.
j) The railing provided to the gallery and staircase shall be with stainless steel of grade 304 for a height of 1mts
k)The railing provided to the gallery and stair case shall be with stainless steel of grade 304 for a height of 1.20mts.
l)The dog legged staircase shall be enclosed with brick/CRS wall on three sides and front side with PVC door of standard maker up to 1st brace level from ground level to prevent
unauthorized entry.
m) D.I swan neck ventilators shall be provided in top dome and slab.
n) The above rates are exclusive of all inlet, outlet connection and valves. All valves near inlet, out let and for scour of ELSRs shall be D.I valves.
53.37 48.18 42.98 36.80 30.62 29.73 28.85 27.95 27.07 23.67 22.22 21.51 21.26 20.77 20.28 89.77
50.90 45.95 40.99 35.10 29.20 28.36 27.52 26.66 25.82 22.58 21.19 20.52 20.28 19.81 19.34 85.62
50.90 45.95 40.99 35.10 29.20 28.36 27.52 26.66 25.82 22.58 21.19 20.52 20.28 19.81 19.34 85.62
57.83 52.21 46.57 39.88 33.18 32.22 31.27 30.29 29.34 25.65 24.08 23.31 23.04 22.51 21.97 97.28
BLD-CSTN
659
DATA FOR C.C & B.T ROAD SURFACE CUTTING - SSR 2024-25
Pg 436-520
MISSION BHAGIRATHA DEPARTMENT
DATA SHEET
Datas-SSR -2024-25
Contract 13.615%
CC Pedastals
0.90 cum 20mm HBG graded metal 1658.64 cum 1492.78
0.45 cum Sand for concrete 1786.75 cum 804.04
400 Kgs Cement 5100.00 Kgs 2040.00
0.133 day 1st Class Mason 645 day 85.79
0.267 day 2nd Class Mason 615 day 164.21
3.6 day Mazdoor (Both Men and Women) 575 day 2070.00
1 hour Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capa 529.70 hour 529.70
1.2 kl Water (including for curing) 81.00 kl 97.20
1 Add for Centering Charges 2033.00 2033.00
Sub-Total 9316.71
Contractor's Profit 13.615% 1268.47
10585.18
Cement concrete(1:1.5:3) prop 1 0.30 0.30 0.30 0.027 10,585.18 cum 286.00
using 20mm gauge HG metal
including cost and
2 conveyance of all materials
and labour charges ,seign.
charges etc.complete.
Total 304.00
8 Cost of MS flanges 2nos for main pipe (480 of 520) 236.00 296.00 322.00
9 Cost of MS flanges 2nos for stem pipe (480 of 520) 184.00 184.00 184.00
Jointing materials such as bolts nuts and rubber vouchers
10 672.40 672.40 672.40
including material cost for main line - 4nos
50mm DI pipe 50mm DI pipe 50mm DI pipe 50mm DI pipe 50mm DI pipe 50mm DI pipe
6 Cost of D/F Vertical Stem Pipe 3m long double 4,192.55 3m long double 4,192.55 3m long 4,192.55 3m long double 4,192.55 3m long double 4,192.55 3m long double 4,192.55
flanged flanged double flanged flanged flanged flanged
7 Cost of HDPE Tail pieces 2 nos 286.00 516.00 518.00 724.00 1,026.00 1,320.00
8 Cost of MS flanges 2nos for main pipe (480 of 520) 334.00 458.00 498.00 654.00 924.00 1,192.00
9 Cost of MS flanges 2nos for stem pipe (480 of 520) 184.00 184.00 184.00 184.00 184.00 184.00
Jointing materials such as bolts nuts and rubber vouchers
10 1,059.36 1,104.60 1,610.84 1,610.84 1,774.84 1,774.84
including material cost for main line - 4nos
0.8 X 0.8 X 0.4 M 0.8 X 0.8 X 0.4 M 0.8 X 0.8 X 0.5 M 0.8 X 0.8 X 0.5 M 0.8 X 0.8 X 0.5 M 0.8 X 0.8 X 0.5 M
14 RCC (1:1.5:3) Footing + Stem Column 11,989.00 11,989.00 12,435.00 12,435.00 12,435.00 12,435.00
0.3 X 0.3 X 3 M 0.3 X 0.3 X 3 M 0.3 X 0.3 X 3 M 0.3 X 0.3 X 3 M 0.3 X 0.3 X 3 M 0.3 X 0.3 X 3 M
15 Add: contractors profit 13.615% 7,242.21 7,415.35 7,915.61 7,964.90 8,065.11 8,795.04
Total 72,424.09 73,868.92 78,489.54 78,900.82 79,737.03 85,828.20
110mm 125mm 140mm 160mm 180mm 200mm
3 Transportation charges(5%) 471.30 471.30 471.30 621.70 621.70 978.85 978.85 978.85
4 Cost of 0.6m DI D/F pipes 2nos 3,422.70 3,422.70 3,422.70 4,024.00 4,024.00 6,033.42 6,033.42 6,033.42
5 Cost of HDPE Tial pieces 2 nos 132.00 160.00 206.00 286.00 516.00 518.00 724.00 1,026.00
6 Cost of MS flanges 2nos 236.00 296.00 322.00 334.00 458.00 498.00 654.00 924.00
8 Lowering of valve and keeping in postion 124.14 124.14 124.14 164.85 158.74 279.40 279.40 279.40
9 Add: contractors profit 13.615% 2,661.02 2,673.01 2,682.81 3,467.45 3,516.63 5,271.12 5,320.41 5,398.28
Grand total 22,205.82 22,305.80 22,387.60 28,935.35 29,345.74 43,986.65 44,397.94 45,047.81
S. No Description Unit Quantity Rate Rs. Amount Rs. Remarks
Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of labour cost. Assessment for dewatering shall be made as per site conditions.
2. The cost of shoring and shuttering, where needed, may be added on cost of excavation for open foundation.
3. The excavated earth if found suitable, can be used partly for backfilling in trenches & partly for road work. Hence cost of disposal has not been added except for
marshy soil. This note is common to all cases of item 11.1 excluding 11.1 V
(B) Mechanical Means
i Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate day -
Pg. No 14 Labour
Mazdoor (Unskilled) day 8.32 575.00 4784.00 Rates SoR 2024-
25
b) Machinery
Pgno.17
(slno.52)Hire
Hydraulic Excavator 1 cum bucket capacity hour 6.00 3557.70 21346.20 Charges of
Machinery SoR
2024-25
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d 26130.20
Rate per cum = (a+b+c+d)/240 108.88
HOUSE SERVICE CONNECTIONS DATA for Pipe Line with Flow control Valve
Part B
Part B
Part B
Cost of Synthetic 6mm thick rubber sheet Cost of MS nut bolts including vauchers -
Labour charges for 12kg/sqm - PHSSR 31 PHSSR 31
Total Cost of
Sl Description of DI Joint including Total for Each
Jointing
no. Fixture jointing materials as joint
Metrials
PHSSR 24-25 Rate per Weight
Size Wieght Kgs Amount No of bolts Rate Rs. Amount Rs.
Kg Kgs
1 2 3 4 5 6 7 8 9 10 11 12 14
Jointing DI D/F
DI PIPE LINE pipes Per Joint Size considered from TG standard PH data upto 750mm dias (above 750mm - from SSR directly)
1 1000mm dia D/F 8728.00 1.215x1.215 10.500 111.00 1165.50 51.80 51.80 93.00 4817.40 5982.90 14710.90
Joint
2 900mm dia D/F Joint 7539.00 1.115x1.115 9.450 111.00 1048.95 40.60 40.60 93.00 3775.80 4824.75 12363.75
3 800mm dia D/F Joint 6353.00 1.015x1.015 8.400 111.00 932.40 27.36 27.36 93.00 2544.48 3476.88 9829.88
4 750mm dia D/F Joint 3670.48 0.965x0.965 7.843 111.00 870.57 26.04 93.00 2421.72 3292.29 6962.77
5 700mm dia D/F Joint 3410.54 0.915x0.915 6.891 111.00 764.90 24.48 93.00 2276.64 3041.54 6452.08
6 600mm dia D/F Joint 2685.34 0.815x0.815 5.171 111.00 573.98 19.20 93.00 1785.60 2359.58 5044.92
7 500mm dia D/F Joint 1953.23 0.670x0.670m 3.819 111.00 423.91 13.40 93.00 1246.20 1670.11 3623.34
8 450mm dia D/F Joint 1656.93 0.615x0.615m 2.266 111.00 251.53 12.30 93.00 1143.90 1395.43 3052.36
9 400mm dia D/F Joint 1449.38 0.565x0.565m 2.764 111.00 306.80 9.84 93.00 915.12 1221.92 2671.30
10 350mm dia D/F Joint 953.95 0.505mx0.505 2.126 111.00 235.99 16nosx0.39 Kg 5.44 93.00 505.92 741.91 1695.86
11 300mm dia D/F Joint 660.79 0.45mx0.45m 1.028 111.00 114.11 12nosX0.39Kg 3.96 93.00 368.28 482.39 1143.18
0.00
11 250mm dia D/F Joint 620.12 0.40mX.040m 0.85 111.00 94.35 12nosX0.39Kg 3.96 93.00 368.28 462.63 1082.75
12 200mm dia D/F Joint 443.71 0.35mX0.365m 0.62 111.00 68.38 8nosX0.39Kg 2.52 93.00 234.36 302.74 746.45
13 150mm dia D/F Joint 402.71 0.30mX0.30m 0.43 111.00 47.73 8nosX0.39Kg 2.40 93.00 223.20 270.93 673.64
14 125mm dia D/F Joint 276.15 0.26mX0.26m 0.31 111.00 34.85 8nosX0.297Kg 1.36 93.00 126.48 161.33 437.48
0.00
15 100mm dia D/F Joint 264.84 0.23mX0.23m 0.25 111.00 28.19 8nosX0.297Kg 1.36 93.00 126.48 154.67 419.51
16 80mm dia D/F Joint 168.10 0.21mX0.21m 0.21 111.00 23.59 4nosX0.297Kg 0.68 93.00 63.24 86.83 254.93
17 50mm dia D/F Joint 168.10 0.20mX0.20m 0.15 111.00 16.65 4nosX0.297Kg 0.43 93.00 39.53 56.18 224.28
18 40mm dia D/F Joint 168.10 0.13mX0.13m 0.13 111.00 14.43 4nosX0.21Kg 0.34 93.00 31.62 46.05 214.15
65000.00 MS tees 8mm thick weight withwastage fabrication cost lowering MS tee Reducers
65 300x80 41.21 43.28 38 4457.33 151.46
103 350x100 48.12 50.53 5204.13 176.84 DI Double Flange reducers for Sluice valves
400x100 54.04 56.74 5844.24 198.59 Dia Weight
450x100 59.96 62.95 6484.35 220.34 700x600 241
500x150 68.34 71.76 7391.18 251.16 750x600 260
600x150 80.18 84.19 8671.41 294.66 800x600 288
700x150 92.02 96.62 9951.64 338.16 900x600 348
800x150 105.83 111.12 11445.24 388.92 1000x600 420
900x150 117.66 123.55 12725.47 432.42 1000x700 425
1000x150 129.50 135.98 14005.69 475.92
1100x150 141.34 148.41 15285.92 519.42
1200x200 153.67 161.35 16619.49 564.74
1300x200 165.51 173.78 17899.72 608.24
1400x200 175 177.35 186.21 19179.95 651.75
1500x200 187.5 189.18 198.64 20460.18 695.25
1600x250 200 201.02 211.07 21740.4 738.75
1700x300 213.84 224.54 23127.32 785.88
1800x300 225.68 236.97 24407.55 829.38
1900x300 237.52 249.40 25687.77 872.89
2000x300 249.36 261.83 26968 916.39
34450.325
11077.1045
HDPE Fittings conforming to IS 4984 45527.4295 600mm dia
50 86
63 109 56604.534 700mm dia
75 131
90 170
110 236
125 424
140 428
160 597
180 847
200 1089
225 1248
250 1463
280 1635
315 1886
355 3940
400 5251
450 8738
500 9725
Lowering
Lowering tee
Amount lowering DI tee DI A/F TEES TAKEN FROM WEIGHTS DI per kg 3.5 from PH data
1365 45.5 80x80x80 21.00 128.00 2688.00 73.5
1575 52.5 100x100x80 25.00 128.00 3200.00 87.50
1575 52.5 100x100x100 26.00 128.00 3328.00 91
1890 63 125x125x80 32.00 128.00 4096.00 112
2100 70 125x125x100 34.00 128.00 4352.00 119
2310 77 125x125x125 36.00 128.00 4608.00 126
1785 59.5 150x150x80 41.00 128.00 5248.00 143.5
3675 122.5 150x150x100 42.00 128.00 5376.00 147
3780 126 150x150x125 45.00 128.00 5760.00 157.5
7035 234.5 150x150x150 47.00 128.00 6016.00 164.5
8820 294 200x200x80 62.00 128.00 7936.00 217
25623 766.5 200x200x100 63.00 128.00 8064.00 220.5
25857 773.5 200x200x125 66.00 128.00 8448.00 231
27846 833 200x200x150 68.00 128.00 8704.00 238
33813 1011.5 200x200x200 74.00 128.00 9472.00 259
42237 1263.5 250x250x80 89.00 128.00 11392.00 311.5
250x250x100 90.00 128.00 11520.00 315
250x250x125 93.00 128.00 11904.00 325.5
250x250x150 96.00 128.00 12288.00 336
250x250x200 102.00 128.00 13056.00 357
250x250x250 109.00 128.00 13952.00 381.5
300x300x80 122.00 128.00 15616.00 427
300x300x100 124.00 128.00 15872.00 434
300x300x125 126.00 128.00 16128.00 441
300x300x150 129.00 128.00 16512.00 451.5
300x300x200 136.00 128.00 17408.00 476
300x300x250 143.00 128.00 18304.00 500.5
300x300x300 151.00 128.00 19328.00 528.5
350x350x200 169.00 128.00 21632.00 591.5
350x350x250 173.00 128.00 22144.00 605.5
350x350x300 188.00 128.00 24064.00 658
350x350x350 195.00 128.00 24960.00 682.5
400x400x200 211.00 128.00 27008.00 738.5
400x400x250 215.00 128.00 27520.00 752.5
400x400x300 232.00 128.00 29696.00 812
400x400x350 239.00 128.00 30592.00 836.5
400x400x400 246.00 128.00 31488.00 861
450x450x250 260.00 128.00 33280.00 910
450x450x300 277.00 128.00 35456.00 969.5
450x450x350 284.00 128.00 36352.00 994
450x450x400 290.00 128.00 37120.00 1015
450x450x450 296.00 128.00 37888.00 1036
500x500x250 315.00 140.00 44100.00 1102.5
500x500x300 334.00 140.00 46760.00 1169
500x500x350 342.00 140.00 47880.00 1197
500x500x400 349.00 140.00 48860.00 1221.5
500x500x450 356.00 140.00 49840.00 1246
500x500x500 363.00 140.00 50820.00 1270.5
600x600x300 466.00 140.00 65240.00 1631
600x600x350 475.00 140.00 66500.00 1662.5
600x600x400 485.00 140.00 67900.00 1697.5
600x600x450 492.00 140.00 68880.00 1722
600x600x500 499.00 140.00 69860.00 1746.5
600x600x600 516.00 140.00 72240.00 1806
80x80x40 18.13 128.00 2320.64 63.46
80x80x50 19.13 128.00 2448.64 66.96
100x100x40 22.05 128.00 2822.40 77.18
1590 100x100x50 23.05 128.00 2950.40 80.68
125x125x50 29.56 128.00 3783.68 103.46
150x150x50 38.00 128.00 4864.00 133.00
200x200x50 57.80 128.00 7398.40 202.30
350x350x100 161.08 128.00 20618.24 563.78
400x400x100 202.75 128.00 25952.00 709.63
450x450x100 249.76 128.00 31969.28 874.16
500x500x150 308.94 128.00 39544.32 1081.29
600x600x150 440.59 140.00 61682.60 1542.06
700x700x150 608.40 140.00 85176.00 2129.40
400mm
400mm
20935.643
94128
-125449.071
-135889.428
r Sluice valves
Rate Amount
117 28197
117 30420
117 33696
117 40716
117 49140
117 49725
Index-code S. No Description
1 2
day -
day 3.64 575.00 2093.00 ssr 24-25 Pg.43
209.30
equired, up to 5 per cent of labour cost. Assessment for
eded, may be added on cost of excavation for open
d partly for backfilling in trenches & partly for road work.
or marshy soil. This note is common to all cases of item
day -
day 8.32 575.00 4784.00 ###
1 2 3 4 5.00 6
Sub Analysis
PHE-LCIF- 2 A Sub Analysis : (Basic Data)
2A
OBSERVED DATA FOR TESTING OF 450
MM DIA PSC MAIN : Pumping main to
Hydralic field test pressure including
transportation of Water with minimum
lead of 500 M
(a) Labour charges for laying, jointing & testing rm 6.300 1.62 10.21
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 10.21
ii 75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing rm 7.500 1.62 12.15
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 12.15
iii 90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing rm 9.000 1.62 14.58
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 14.58
iv 110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing rm 11.000 1.62 17.82
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 17.82
v 125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing rm 12.500 1.62 20.25
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 20.25
vi 140 mm dia pipe
Weight of 1m length = (2.144+3.116+4.905)/3 =3.388 kgs
(a) Labour charges for laying, jointing & testing rm 14.000 1.62 22.68
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 22.68
vii 160 mm dia pipe
Weight of 1m length = (2.799+4.012+6.414)/3 =4.408 kgs
(a) Labour charges for laying, jointing & testing rm 16.000 1.62 25.92
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 25.92
viii 180 mm dia pipe
Weight of 1m length = (3.581+5.134+8.092)/3 =5.602 kgs
(a) Labour charges for laying, jointing & testing rm 18.000 1.62 29.16
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 29.16
ix 200 mm dia pipe
Weight of 1m length = (4.331+6.351+10.001)/3 =6.894 kgs
(a) Labour charges for laying, jointing & testing rm 20.000 1.62 32.40
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 32.40
x 225 mm dia pipe
Weight of 1m length = (5.511+7.975+12.675)/3 =8.72 kgs
(a) Labour charges for laying, jointing & testing rm 22.500 1.62 36.45
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 36.45
xi 250 mm dia pipe
Weight of 1m length = (6.674+9.886+15.666)/3 =10.742
kgs
(a) Labour charges for laying, jointing & testing rm 25.000 1.62 40.50
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 40.50
xii 280 mm dia pipe
Weight of 1m length = (8.453+12.404+19.616)/3 =13.491
kgs
(a) Labour charges for laying, jointing & testing rm 28.000 1.62 45.36
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 45.36
xiii 315 mm dia pipe
Weight of 1m length = (10.682+15.723+24.732)/3 =17.046
kgs
(a) Labour charges for laying, jointing & testing rm 31.500 1.62 51.03
(b) Overheads & Contractors Profit 0.00
Rate per metre a+b 51.03
13 Sub Analysis :
Labour charges for laying in position
PHE-CISP- S&S or flanged C.I. specials such as
14(sub_anal tees, bends, collars tapers and caps
ysis)
etc
Unit each
i 40 mm dia
(a) Labour
Lowering charges for air valve kgs 27.000 3.50 94.50
Boring main & threding etc
Plumber 2nd class day 0.140 400.00 56.00
Man mazdoor day 0.140 350.00 49.00
Overheads & Contractors Profit 0.00
Rate per each valve 199.50
ii 25 mm dia
(a) Labour
Lowering charges for air valve kgs 20.000 3.50 70.00
Boring main & threding etc
Plumber 2nd class day 0.110 400.00 44.00
Man mazdoor day 0.110 350.00 38.50
Overheads & Contractors Profit 0.00
Rate per each valve 152.50
Less for shaft 22/7 x 4 x 0.452 x 1.1= 0.175cum = 0.919 cum 0.920
cum
Cement Concrete 1:2:4 (plain)
0.90 x 0.90 x 0.15 = 0.122 cum
Less for shaft 22/7x4 x 0.452 x 0.15= 0.024cum = 0.098 cum 0.100
cum
(c) Total (a+b)
(d) Add for water charges @ 1% on Labour & Testing 1%
Charges on Labour Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 1 No = e+f
Well Sinking
28 Well sinking in sandy and other loose
soils under water either by manual
labour, divers or dredgers weighting
the top of staining to assist sinking
etc., including dewatering and other
incidental charges such as hire
PHE-WSNP- charges for mechanical equipment
28
etc., complete upto 4.0 m dia (For non
perennial rivers)
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 13 MT 2121.00
Rate per MT 163.15
ii RCC Pipes and Collars (load per truck =7.205 T)
Taking Output = 14.41 MT
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 14.41 MT 2121.00
Rate per MT 147.19
iii AC Pipes and Collars (load per truck = 5.40 T)
Taking Output = 10.8 MT
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 10.8 MT 2121.00
Rate per MT 196.39
iv Stone ware pipes (load per truck = 5.40 T)
Taking Output = 10.8 MT
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 10.8 MT 2121.00
Rate per MT 196.39
35 Loading or unloading materials such as C.I / D.I. Pipes,
PHE-LUMS- stone ware pipes, R.C.C. pipes, A.C. Pressure pipes and
35 specials from 300 mm to 600 mm dia upto 4 mts in length
including stacking.
i C.I. / D.I. Pipes (load per truck = 5.5 T)
Taking Output = 11 MT
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 11 MT 2121.00
Rate per MT 192.82
ii RCC Pipes and Collars (load per truck =5.75 T)
Taking Output = 11.5 MT
a) Labour
Man Mazdoor day 6.000 350.00 2100.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 21.00
Overheads & Contractors Profit 0.00
Cost for 11.5 MT 2121.00
Rate per MT 184.43
iii AC Pipes
Taking Output = 1MT
a) Labour
Man Mazdoor day 0.700 350.00 245.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.45
Overheads & Contractors Profit 0.00
Cost for MT 247.45
iv Stone ware pipes
Taking Output = 1MT
a) Labour
Man Mazdoor day 0.700 350.00 245.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.45
Overheads & Contractors Profit 0.00
Cost for MT 247.45
36 Loading or unloading materials such as CI / DI Pipes, A.C.
PHE-LUGS-
pressure pipes less than 300 mm dia above 4.00 M in
36
length including stacking
i C.I. / D.I. Pipes (load per truck = 8.46 T)
Taking Output = 1 MT
a) Labour
Man Mazdoor day 0.710 350.00 248.50
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.49
Overheads & Contractors Profit 0.00
Cost for 1 MT 250.99
ii AC Pipes (load per truck = 3.78 T)
Taking Output = 1MT
a) Labour
Man Mazdoor day 0.790 350.00 276.50
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.77
Overheads & Contractors Profit 0.00
Cost for MT 279.27
37 Loading or Unloading materials such as C.I / D.I. Pipes,
PHE-LUBS- A.C. Pressure pipes from 300 to 600mm dia above 4.00
37 m including stacking
i
AC Pipes (load per truck = 4.3 T)
Taking Output = 1 MT
a) Labour
Man Mazdoor day 0.714 350.00 249.90
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.50
Overheads & Contractors Profit 0.00
Cost for 1 MT 252.40
ii C.I. Pipes (load per truck = 3.85 T)
Taking Output = 1MT
a) Labour
Man Mazdoor day 0.780 350.00 273.00
Add sundries at 1% towards Nylon rope, Tyres etc 1% 2.73
Overheads & Contractors Profit 0.00
Cost for MT 275.73
38 Centering and scaffolding charges for R.C.C. members
PHE-CSRC- including all materials and labour charges for forming and
38 dismantling
A For R.C.C. Elevated Service Reservoir of Staging upto
40 Ft. below G.W.L.
i Side wall straight surfaces:
Details cost for 15 M long and 1 M height wall
Surface area = 2 x 15 x 1 = 30 Sqm
a) Materials
i) Planks 33 mm thick
2 x 15 x 1 = 30.00 sqm
Add 5% wastage = 1.5
=31.50 sqm
31.50 x 0.038 = 1.197 Cum cum 1.197
ii) Batters – 75 x 50 mm
2 x 13 x 0.075 x 0.05 = 0.095 cum cum 0.095
iii) Ballies – 125 dia for strutting
ver 13 x 1.5 = 19.5
13 x 4.5 = 58.5
= 78.00
5% for wastage = 3.9
= 81.90
81.90 x π x 0.1252 / 4 =1.005 Cum cum 1.005
Assuming that timber shall become unserviceable after
being used for 5 times
Cost for 5 times
Rate per 1 time
b) Labour
Labour charges for assembling, erection, dismantling and
cleaning
Carpenter 2nd class day 7.500
Man Mazdoor day 6.000 350.00 2100.00
Sundries for nails etc
Overheads & Contractors Profit
c) Cost for 30 Sqm
Rate per sqm =c/30
ii Side walls curved surfaces
Considering 4 M internal dia and 1 Meter depth. Consider
30 mm thick.
Surface area:
Outside – π x 4.40 x 1.00 = 13.83 Sqm
Inside area = π x 4 x 1 = 12.57 Sqm
= 26.40 Sqm
a) Materials
i) Planks 33 mm
26.40 x 0.038 = 1.003 cum
Extra & Wastage @ 20% = 0.201 cum
= 1.204 Cum cum 1.204
ii) Hattens – 75 x 38 mm
Inside – 2 x 25 x 0.50 x 0.075 x 0.075 = 0.1406
Outside – 2 x 28 x 0.50 x 0.075 x 0.175 = 0.1575
= 0.2981
= 278.46
kgs
a) Labour
Labour for hoisting inn position:
Mason 2nd class day 1.000 400.00 400.00
Man Mazdoor day 2.750 350.00 962.50
Total 1362.50
(b) Overheads & Contractors Profit 0.00
c) Cost for 278.46 Sqm 2725.00
Rate per sqm =c/278.46 9.79
Cost for 50 Kg
PHE-LCVS- 40 Labour charges for fixing ventilating shafts in
40 sewerage scheme complete with all accessories
Unit – Each
a) Labour
Mason 1st class day 0.150 515.00 77.25
Mason 2nd class day 0.350 400.00 140.00
Plumber 2nd Class day 0.600 400.00 240.00
Man Mazdoor day 2.000 350.00 700.00
Overheads & Contractors Profit 0.00
Rate 1157.25
)
Remarks
TESTING
PVC PIPES
Pg 13 -520 SSR 2024-25
64.80
355mm 35.5 1.62 57.51
incl.transportation
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
SSR Rate
NOT
UPDATE
D
AIR VALVES
WELL SINKING NON PERENIAL
WELL SINKING PERENIAL
100mm
Dia of Valve 80mm dia 150mm dia 150mm dia 200mm dia 300mm dia 500mm dia
dia
SL
>125- >180- >225- >350- >400- >600-
No. 63-125mm
Discription of Item/ Dia of valve 180mm 225mm dia 350mm dia 400mm dia 600mm dia 1000mm
dia line
dia line line line line line dia line
0.90x0.75x 1.35m 0.90x0.90x 0.90x0.90x 1.90m 0.90x0.90x 1.90m 0.90x0.90x 1.90m 1.05x1.20x 1.20x1.20x
Size of Chamber 1.90m 2.00m 2.10m
1 DI D/F Gate valves ( soft Seated ) valves conforming to IS 3896-oart 2- 9426 12434.00 19577.00 19577.00 32532.00 68098.00 395083.00
1985 wedge fully rubber lined with EPDM food grade quality and the
valve should be of vacuum tight and 100% leak proof with face to face
dimensions. All the valves should be with Electrostatic powder caoting
both insisde and outside pockets body passages.Drilled as per IS: 1538
Cost of Dismantling Joint (up to 300 mm dia CI and above 300 mm dia 5559.00 7294.00 9379.00 10289.00 14591.00 17369.00 27791.00
MS
2 Transportation chargers (5% of basic cost) 749.25 986.40 1447.80 1493.30 2356.15 4273.35 21143.70
3 Cost of DI Duck foot bend 1920.00 2176.00 3456.00 3456.00 4864.00 8448.00 20224.00
4 Cost of 0.6m DI D/F pipes 3nos 5114.88 6013.44 9016.32 9016.32 12272.64 21534.72 40773.12
5 Cost of DI Semicircular bend 1792.00 2304.00 4096.00 4096.00 6272.00 14848.00 41600.00
6 Jointing materials such as bolts nuts and rubber vouchers - 7 Jobs 607.79 1082.72 1896.51 1896.51 2119.15 3376.72 11690.76
7 Jointing materials such as bolts nuts and rubber washers for valve 0.00 0.00 0.00 0.00 0.00 0.00 0.00
fixing - 2Jobs
8 Labour charges for lowering DI pipes & Bends (5 jobs) 215.90 273.10 446.10 446.10 641.85 1121.85 2425.40
9 Sluice valve lowering and fixing charges 124.14 164.85 279.40 279.40 460.95 932.61 2931.25
10 Cost of RCC valve chamber 29354.00 32703.00 53153.00 53153.00 32703.00 53153.00 49721.00
11 Add: contractors profit 13.6150% 3473.05 4455.99 6752.24 6882.33 10362.34 19061.31 76742.61
Grand total
58336.01 69887.49 109499.37 110584.96 119175.08 212216.55 690125.85
Assistant Executive Engineer Deputy Executive Engineer Executive Engineer Superintending Engineer
MB Grid sd Jadcherla MB Grid sd Jadcherla MB Grid Div Mahabubnagar MB circle - Mahabubnagar
Sub Estimate for House hold connection
#REF!
a SADDLES
63 mm dia 0 No 0
1X0
75mm dia 35 No 155.0 5425
1X35
90mm dia 15 No 177.0 2655
1X15
110mm dia 10 No 213.0 2130
1X10
b FTO 60 No 108.0 6480
1X60
c FTA 60 No 108.0 6480
1X60
d FCV 60 No 265 15900
1X60
e MDPE 360 Mts 30.32 10915.2
1X360
f GI Fittings 60 No 267.60 16056
1X60
g Bib Cocks 60 No 271 16260
1X60
10069
Total(Part-A) 92370.2
Total(Part-B) 38199.00
Total(Part-A + B) 130569.20