Microsoft Word
Microsoft Word
LECTURE NOTES
ON
CONSTRUCTION MANAGEMENT
Compiled by
Mrs. Nivedita Panda
(Lecturer in Department of Civil Engineering, KIIT Polytechnic BBSR)
CONTENTS
No. Name
06. 47-76
07. 77-98
08. 99-118
09. 119-148
10. 149-168
CHAPTER-1
INTRODUCTION
Construction Management
KIIT POLYCTECHNIC
Owner:
The owner may be an individuals or group of individuals, private or public sector company.
The owner is the ultimate authority over the project. All the power of decision making regarding
managerial financial and administrative aspects is invested in him. He is responsible for the fund
and other resource of the project.
Engineer:
It includes the empowered construction engineers who are socially responsible for the
project management, store control inspection and quality assurance, construction supervision, cost
control and such similar assets. It also includes architect, structural engineer, quantity surveyor,
mechanical and electrical engineer, specialists such as structural constant, safety and maintenance
planner, soil investigator.
➢ Architects-The duty of architects is to assess the owner’s functional requirements and prepare plans
and specification for the purpose.
➢ Structural engineer-The structural engineer is to prepare structural design as for requisite loads
through technical design and to prepare working drawing which is handed over to construction
engineer.
➢ Mechanical Engineer-He is responsible for mechanical services associate with the project during
and after construction.
➢ Electrical Engineer-He is concerned with the preparation of working drawing for electrical power
and distribution system during and after construction.
➢ Quantity Surveyor-His duty is to,
• Estimate the cost of work.
• Prepare bill of quantities and tender document.
• Asses the extra cost due to special features.
• Prepare the cash flow statement during construction.
• Prepare the final accounts on completion of the project.
➢ Specialist-They have to perform specialized work entrusted to them. such as soil investigator collect
information regarding soil for the proper design of foundation.
Construction Management
KIIT POLYCTECHNIC
Contractor:
➢ The contractor may be an individual undertaking small contracts or a large construction company
undertaking turn –key projects.
➢ Contractor whether small or big needs the services of qualified engineers. Some of the engineers
employed by the contractor deal with office work such as designing, tendering, scheduling etc. and
others known as site engineers are concerned with the actual execution of work such as surveying,
leveling, construction & billing.
➢ He has to collect rates of materials and labour to determine the time rate.
➢ It is duty and liability of a contractor to follow the labour act.
➢ It is duty of contractor to safeguard his own men and material.
➢ He should finally handover the completed work to the owner and get the final payment, adjusting
the running bill accounts.
Construction Management
KIIT POLYCTECHNIC
CHAPTER-2
CONSTRUCTIONAL PLANNING
2.1 IMPORTANTS OF CONSTRUCTIONAL PLANNING:
The need for better construction practice, systematized planning and programming of works
and effective management in the industry is therefore the demand of the day.
Constructional planning is the first step of the construction management. The construction
planning of a civil engineering project must consider the wide range of aspect involved, site
investigation, market survey, bidding of the works, post tender negotiation and agreement
planning for the works monitoring and controlling the progress of work during the execution up
to the completion of the work, even its maintenance during the stipulated period.
For effective planning, it is necessary to break down the total project into subsections and
activities. Each activity or job may further be sub-divided into smaller jobs for planning at
various levels.
The functional elements of project and their inter-relationship are determined by a technique
known as work breakdown structure. Such a technique establishes the hierarchical order in a
system by breaking the project into recognizable systems, subsystems, and discrete activities. For
example, construction of a compound wall may be broken down as shown in figure,
Construction Management
KIIT POLYCTECHNIC
COMPOUND WALL
Construction Management
KIIT POLYCTECHNIC
2.3
CONSTRUCTION PLANNING STAGES:
For efficient implementation of project activities, planning is essential at various stages.
Planning for construction may be done in the following two stages. Planning for construction may
be done in the following two stages:
• Pre-tender Stage
• Post tender
Stage Pre-Tender Stage:
Pre-tender planning is broad based and is carried out by the contractor. It is the stage in
which a contractor has the best opportunity of planning his likely method of construction for the
future contract and prepares a realistic programme for carrying out the work. This stage enables
the contractor to make a proper bid and prepare him for completing the work in the stipulated
time. During this stage, the contractor’s main aim is to see whether the contract under
consideration is profitable or not. Before a contract is undertaken, the contractor is required to
visit the site of construction work. Pre –tender planning includes the following steps:
➢ Examining drawings and specifications to identify various items of work.
➢ Carrying out site investigation and market survey to assess the availability and rates of
materials, manpower, machinery and other facilities.
➢ Identifying alternative methods of executing the work for selecting the most suitable4 and
economical method.
➢ Estimating the quantities of different items of work and the time required for their completion.
➢ Preparing the tentative construction schedule with reference to the stipulated time of
completion.
➢ Deciding the overheads and margin of profit and finalizing the tender price for completing the
work within the stipulated time.
Post-tender stage:
Post-tender stage is also called Contract stage or construction stage. This stage
commences with the acceptance of the tender and extends till completion of the contract. After
the pre-tender stage, the contractor has to undertake detailed planning to organize various
activities of construction work so that the project may be completed within the scheduled time.
Post-tender planning is used in chalking out specific details for execution of the project.
Inadequate planning at this stage inevitably results in delays leading to heavier expenditure than
originally estimated.
Post-tender stage planning involves the following steps:
Construction Management
KIIT POLYCTECHNIC
➢ Establishing a good communication system between members of the construction team for the
smooth running of project work.
➢ Evaluating alternative construction methods identified during the pre-tender stage in order to
select the most economical and efficient method.
➢ Studying inter-relationships of various items of work and finalization of proper sequence of
operations.
➢ Calculating the phased requirement of construction materials such as cement, aggregate, bricks,
steel etc.
➢ Determining the phased requirement of plant and machinery including repair and maintenance
facilities.
➢ Preparing details of manpower requirement including labour, supervisors and managerial staff
for various stages of the work.
Good communication between various members of the construction team is essential to complete
the project within scheduled time. Proper co-ordination between members of the construction
team voids the possibility of delays at various stages of the work. Various alternatives have to be
considered in derail to ensure proper utilization of project resources, leading to the greatest
economy in cost. Construction programme is depicted in the form of charts which can be readily
understood by workers, supervisors and construction managers. The programme provides
information regarding the date and time of starting and completing different items and activities
of work including working drawings, staff recruitment, supply orders, delivery of materials etc.
Scheduling is the process of fitting the work plan to a time frame indicating the start and
completion each activity. It also shows sequential relationships among various activities.
The construction schedule is a tool that a contractor uses to manage time and execute
activities in a proper sequence. To prepare a construction schedule, the project is divided into
different activities or operations. The sequence of operations can be decided after knowing their
inter-relationship as per the construction method adopted.
The conventional method of scheduling used in the construction industry is the bar chart.
It is also known as Gantt Chart after Henry Gantt. Who developed this technique around 1900. A
bar chart consists of two co-ordinate axes, one showing the time and the other showing jobs or
activities to be performed. Each job is depicted in the form of a horizontal line or bar and the
length of a bar indicates duration of the job or activity. In a project, some jobs are taken up
concurrently and some are required to be completed before other can begin. Thus, in a bar chart,
some of the bars run parallel to each other and some run serially with one bar beginning after the
other bar ends. The level of detail of the activities and the unit of time is determined by the
intended use of the bar chart.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
For any given work, the resources required are materials, manpower, machinery and money.
These resources have to be utilized in a planned and efficient manner in order to derive the
maximum benefit. Further, there may be many uncertainties in the availability of resources. The
right type of labour or equipment may not e available at the required time due to labour unrest or
breakdown of machinery. Thus, to execute the construction work in an efficient manner and
without wastage of any of the inputs, schedules for various project resources need to be prepared.
Construction Management
KIIT POLYCTECHNIC
prepared either month wise or week wise depending on the extent of the project and storage
space.
Let us consider a typical material schedule prepared week wise for the construction of a
temporary shed(8m x 20m).
Week s
Material Unit
5 1 2 3 4
➢ It provides the site in charge with ample warning of his future labour requirements.
➢ By noting the actual work force regularly on the chart, a direct measure of labour
expenditure on site can be obtained.
➢ If a manpower shortage is likely in a particular section of the project, it enables such type
of labour force to be sought from elsewhere before a delay occurs.
➢ It helps in efficient and optimum deployment of the labour force in various sections of the
project.
Nameofwork…………………………………………………………………Preparedby……………………
……………………
……………Date……………………………………………………………………….
Construction Management
KIIT POLYCTECHNIC
Manpower Weeks
1 2 3 4
Fore man 1 1 1
1 1
Carpenter - - - 1 1 Welder - - 3 2 1
Mason 1 1 2 2 1
Mixer operator - - - -
- Labourers 3 3 10
6 3 - - -
- -
-
2.5.3 Preparation of
Equipment (Machinery) Schedule
An equipment schedule is prepared for all plant/equipment required to be deployed on the project.
From this schedule, delays in the work that may occur either due to nonavailability or breakdown
of equipment can be averted.
Name of work ............................................................. Prepared
by……………………………………………………
Date……………………………………………………………………….
Weeks
Equipment 1 2 3 4 5
Concrete mixer - - 1 - -
Vibrator - - 1 - -
Welding set - - 1 1 1
Truck - - 1 1 1
- - - - - -
Such a schedule enables the efficient and optimal utilization of plant and
equipment on a project. Using this schedule, timely arrangements can be made for renting or
deploying particular equipment at a particular time.
2.5.3 Preparation of Finance Schedule
Finance schedules are essential both for the pre-tender and construction stages. A finance
schedule shows the amount of cash required at different stages of the construction project. It
enables long-term financial planning for the entire project to be carried out in an efficient manner.
It also considers cash inflow from the running bills and indicates finances required for the
Construction Management
KIIT POLYCTECHNIC
successful completion of the project. The finance schedule for the construction of a temporary
shed.
➢ Interdependencies of activities
A construction project consists of a large number of activities. The bar chart does not
show clearly the interdependencies among the various activities. This is a major
deficiency. The mere fact that two or more activities are scheduled to start at the same
time, does not make them interdependent or completely independent.
Consider a construction project involving excavating foundation, fixing shuttering and concreting
in which the time consumed by each activity is as under:
Excavating foundation 20 weeks Fixing shuttering 14 weeks
Concreting 16 weeks
If the activities are taken up in a series, the total time taken for completion of
project will be 50 weeks. As we can easily see, fixing of shuttering may start after the completion
of say half of foundation excavation. Similarly, concreting may start say 5 weeks
after fixing of shuttering. The bar chart of these activities is shown in figure 3.5. As per the bar
chart, fixing of shuttering still has 4 weeks of work after excavation is over. If, however,
excavation is delayed by 1 or 2 weeks due to unexpected difficulties, its effect on fixing of
shuttering is not clear from the bar chart.
Construction Management
KIIT POLYCTECHNIC
➢ Project Progress
A conventional bar chart cannot be used as an efficient control device because it does
not show the progress of work. A knowledge of the quantum of work completed or
progress achieved is essential in any project. A conventional bar chart can be made more
useful by modifying it as shown in figure 3.6. In the modified bar chart, the progress of
work can be depicted by colouring/hatching blank bars. For example, on reviewing the
progress after 16 weeks of the project, excavation work is observed to be 2 weeks behind
schedule as shown in figure 3.6.
➢ Quantities of items of work
The bar chart depicts the time schedule for various activities but it does not indicate the
quantities of work. The bar chart may be improved by showing quantities of work
against individual items.
➢ Critical Activities
Another limitation of the bar chart is that it does not indicate critical activities
requiring careful attention of the construction team. Knowledge of critical activities is
essential for rescheduling or accelerating the project completion.
Defination of terms:
(a) Activity: An activity is the performance of a specific task, operation, job or function
which consumes times and resources and has a definite beginning and end. An activity is
graphically represented by an arrow drawn from left to the right. The length, shape and
orientation of arrow have no significance. For example excavate foundation, lay brick work,
backfill trench, fix shuttering etc are all activities.
Construction Management
KIIT POLYCTECHNIC
Fix
shuttering
4(days)
(Representation of Activity)
(b) Event: Event (also called NODE) represents instant in time when certain activity has been
started or completed. In other words an event describes start or completion of task. It is
represented by a number enclosed in a circle. The beginning of an activity is marked by a tail
event or preceding event and the end by a head event or succeeding event. While drawing
network, it is assumed that, time flows from left to right.
Pour concrete
1 2
(Representation of Event)
(C) Network: A network is a diagrammatic representation of a work plan showing the
activities, step-by-step, leading to the established goal. It depicts the inter dependence between
the various activities, i.e. which activities can be done together and which activities must precede
or succeed others.
Construction Management
KIIT POLYCTECHNIC
Network techniques are effective tools for planning and scheduling and controlling
construction jobs. Network techniques provide a rational approach to the planning and
construction work. The allocation of such techniques inevitable when there is a constrain or
resources and need for higher productivity. The two commonly used network technique are
CPM and PERT.
CPM and PERT network are very powerful tools and facilitate the work management in the
various phases of the project by the following ways:
Planning Phases: Planning is the process of choosing a particular method and order of work to be
adopted for a project from all the various ways and sequences in which it could be done. The
sequence of steps required to achieve the optimum result is the proper plan for the works and is
shown schematically on the network diagram. Furthermore, it permits the ready evaluation and
comparison of alternative works and helps in choosing the best plan based on minimum cost and
minimum time.
Organizing Phase: It helps in awarding the contract to the best and efficient contractor because
the network of the project furnished by the contractor along with the tender is the mirror image
of the resource capacity of the contractor and the methodology of the project.
Scheduling Phase: Scheduling is the determination of timing of the operations comprising the
project which helps in the preparation of various calendars, such as; from the starting date to the
finishing date, the delivery time of the materials used in the project is clearly mentioned on
material calendar.
Controlling and Monitoring Phase: Network facilitates in controlling the execution of the
project activities to ensure timely completion of the project through periodical reviewing and
applying corrective measures.
Evaluating Phase: After the completion of the project, the planned and actual tie and cost are
compared, the reasons for deviation are analyzed and specific difficulties while execution are
highlighted. These reports are made available to the executive for use in future projects.
Construction Management
KIIT POLYCTECHNIC
CPM PER
T
(a) CPM is activity oriented. (a) PERT is event oriented
(b) Single time estimates are used for the (b) The time estimates for activities are
various probabilistic. The
activities i.e. the time estimates are following three type of time estimates
determi- used for
nistic. are
each activity:
(i) Optimistic time
(ii) Pessimistic time
(c) CPM is used for repetitive types of (iii) Likely time
projects
i.e. projects (c) PERT is used for pioneering type of
where the time estimates for various
activities prior project which are the first of their one kind
are either known or can be determined
accurately.
(d) CRM places emphasis upon optimizing alloca- (d) PERT lays emphasis on
reducing project completion
tion of resources and minimizing overall time without cost constraint. project cost.
NETWORK ANALYSIS:
(a) Earliest start time (EST): The earliest start time is the earliest possible time at which an
activity can start.
(b) Earliest finish time (EFT): The earliest finish time is the earliest possible time at which
an activity can finish.
(c) Latest start time (LST): The latest start time is the latest possible time by which an
activity can start without any delay of project time forecast on the basis of earliest occurrence
time to the final event.
(d) Latest finish time (LFT): The latest finish time is the latest possible time that an activity
can finish without any delay in completion of the project.
Construction Management
KIIT POLYCTECHNIC
FLOATS: Float indicates the range within which the start and finish time of an activity may vary
without affecting the completion time of the project.
(a) Total float (TF) of an activity is the excess of the maximum available time over the
activity time.
(b) Free float (FF) of an activity is the excess of available time over the activity time when
all jobs start as clearly as possible. The term “free” indicates that the use of this float does not
affect the succeeding activities.
(c) Independent float (IF) of an activity is the excess of minimum available time over activity
time. In some cases the absorption of this float neither predecessor nor successor activity that’s
why, it is called independent.
Exp. 1. Find the critical path and project duration of the given CPM project. Also calculate EST, EFT,
LST, LFT and TF, FF, IF in a tabular form.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
CHAPTER-3
3.0 MATERIALS AND STORES MANAGEMENT
Definition
The International Federation of Purchasing and Materials Management accept the definition of materials
management given below.
According to it, materials management is a total concept having its definite organization to plan
and control all types of materials, its supply , and its flow from raw stage to finished stage so as
to deliver the product to customer as per his requirements in time. This involves materials
planning , purchasing , receiving, storing, inventory control, scheduling, production, physical
distribution and marketing. It also controls the materials handling and its traffic. The materials
manager has to manage all these functions with proper authority and responsibility in the material
management department.
Scientific classification of various items of stores is essential for a good system of store keeping.
Materials in stores are classified either on the basis of their nature or on their basis of their use.
The former method of classification is most commonly used. For example the material may be
classified as construction materials, consumable stores, spare parts, abrasives, lubricating oils ,
etc. After dividing all items of stores into various classifications, the next step is to codify
alphabetically or numerically each item of stores by giving it a distinctive stores code number.
Decimal system of codification is more commonly used. Under this method of codification, the
whole numbers are used to indicate the main group and decimals to indicate primary, secondary
and other groups. For example materials may be classified as follows.
Section body -2 i.e., sub-code consists of the next two or three digits depending upon the
requirement.
Construction Management
KIIT POLYCTECHNIC
Section body -3 i.e., details of the sizes, quality etc. Last one or two digits depending upon the requirement
Following are the advantages of a system of classification and codification.
Construction Management
KIIT POLYCTECHNIC
(iv) Secrecy of descriptions can be maintained because a distinctive store code number ( amd not
description of the item of stores) is used.
(v) The biggest advantage of codification is the distinctive code given to each item of
stores and avoidance of duplication due to multiple names which results in a reduction of
items of stores carried.
(vi) It facilitates the identification of various items of stores resulting into prompt issue
of stores. This is particularly useful in those cases where the same material is known
by more than on name.
TYPES OF STORES
1 . FUNCTIONAL – depending on the use to which material is put –chemicals, tool, raw
materials stores etc.
2 . PHYSICAL – depending upon its size and location- central stores, decentralises store and
central stores with sub-stores. These are discussed below;
(A) Centralised Stores: - The usual practice in most of the concerns is to have a central store. In case of
such a store, materials are received by and issued from one stores department. All materials are kept
at one central store. The advantages and disadvantages of this type stores are as follows;
Advantages :-
1. Better control can be exercised over stores because all stores are housed in one department.
Construction Management
KIIT POLYCTECHNIC
5. Economy in cost. Examples are reduced clerical costs and economy in records are stationery
6. Economy in staff and concentration of experts in one depertment will lead to development of
high technical skill.
7. Less botheration in inventory checks as the stores are located in one place.
Disadvantages :-
1. This system of stores increases transportation costs because one central store may not
be near to the every department of the factory.
2. Delay and inconvenience may be caused to departments ( situated at a distance from the
central store) in drawing materials from the central stores.
3. Greater risks of loss in case of fire because all items of stores are kept at one place.
Under this type of stores , independent stores are situated in various departments.
Handling of stores is undertaken by the shopkeeper of each department. This department
requiring stores can draw from them their respective stores situated in their departments.
The disadvantage of centralised stores can be eliminated if there are decentralised stores.
Such type of stores set up to meet the requirements of materials of each production
department are not popular because of the heavy expenditure involved.
Construction Management
KIIT POLYCTECHNIC
In large factories, departments are situated at a distance from the central stores; so in order
to keep the transportation cost of handling charges to minimum, sub-stores ( in addition to
the central stores near the receiving department) should be situated near the production
department.
For each item of materials, a quantity is determined and this should be kept in stock in
substore at the beginning of any period. At the end of a period, the shopkeeper of each
substore will requisition from the central store the quantity of the material continued to
bring the stock upto the predetermined quantity. In short, this type of store operates in a
similar way to a petty cash system ; so this system of stores is also known as the imprest
system of store control.
The purchase officer does not initiate any action for the purchase of items on his own accord.
With the help of purchase requisitions, the purchase officer comes to know the types of materials
or items needed in the organization.
(iv) from production department to purchase the plant and machinery or any other equipment.
Construction Management
KIIT POLYCTECHNIC
The purchase requisition is generally prepared in triplicate. The original copy is sent to
the purchasing department, the duplicate is kept by the storekeeper or the department which
initiates the requisitions and the triplicate is sent to the authorising executive.
The purchase requisition initiated by the storekeeper for regular items of materials is
called regular purchase requisition and the purchase requisition and purchase requisition
prepared by the department head for special materials is known as special or occasional
purchase requisition. Regular purchase requisition are prepared when the item of materials
reach at the ordering levels, i.e. the level at which the order for fresh supply should be
placed. This is done so that there may be no shortage of materials and production may not be
held up for want of materials. The specimen form of a purchase requisition is given below.
It is clear from the specimen of the purchase requisition that it provides the following three
basic informations which assist in the work of purchase department
b. When is to be purchased?
The purchase department is to make timely purchases to avoid the situation of rush orders
to the extent possible because it costs more to make purchases by rush orders. The
purchase department should be in constant touch with the suppliers, the market trends and
sociopolitical conditions so that timely steps may be taken to procedure the items.
Anticipating advance needs will determine the kind of order.
Construction Management
KIIT POLYCTECHNIC
Purchase Officer
Purchase Budget
I. Quantity and quality of each material needed according to the production target.
II. Capital items, tools and general supplies required during the budget period.
III. The present stock position and materials expected to arrive, already covered by purchase orders.
IV. The dates on which purchase items are required.
Construction Management
KIIT POLYCTECHNIC
X. Storage capacity.
There are two aspects of store accounting i.e., value of the materials stored and quantity of the materials
stored. Stores accounting is necessary is regard to value due to the following reasons:
As regards quantity of materials, it is necessary to ensure, that all the materials received have
been accounted for. Similarly all receipts and issues have been entered in stock ledger or
register and have been accounted for.
The following are main purposes for which stock records are necessary:
(i) They indicate the amount of any material in stock at any time without any physical
checking.
(ii) They help to tally the stock as shown by stores accounts. All receipts and issues and
issues entered in stock records are subsequently posted in value to stores accounts.
Construction Management
KIIT POLYCTECHNIC
(iii) They help in determining, the ordering quantity in order to maintain the stocks at the
required level.
(iv) They help in comparing the quantities of all items in the stores ascertained by physical
checking with that of quantity balances as per stores records.
(v) They help the stores staff in locating the goods in the store house.
(vi) They serve the purpose of a price list, as unit prices given in stores can be used for
pricing all stores documents which are ultimately posted to the records.
STORES RECORDS
The following are the most important records used in the stores :
(i) BINCARD :- the card is generally kept in the bin along with particular item. To hold the
bincard, usually there is a metal holder attached to the bin. These cards are very simple
and give details regarding code number, the unit of issues, the quantity of the received
and issued and the balance remaining in the bin.
(ii) STOCK CARD: - stock cards are kept together at one place in the stores office. This
office should be within the stores building and not far away from the other offices of the
company. This is necessary to keep the proximity between the stores documents and the
stores themselves. Stores cards can be of three types i.e., (i)showing only quantities ,
(ii)shoeing quantities, and unit price , and (iii)showing quantity , unit price , value of
each transaction and the value of balance in stock, (iv)is the best as it gives all details but
it requires greater effort and expertise to maintain. Entry of every receipt and issue of
store must be done in time and not postponed to the next day.
(iii) STORES TRANSFER NOTE :- this form is used for transfer of materials from one
store to another store.
(iv) MATERIAL RETURN NOTE :-this form is used for return of items of surplus material
from production or engineering department to the stores department.
(v) GOODS INWARD OR RECEIPTS NOTE:- this form is used for recording receipts
Construction Management
KIIT POLYCTECHNIC
(vi) MATERIAL REJECTION NOTE:- this note is issued by the inspection department and
gives various reasons or rejecting an item of store.
(vii) SCRAP NOTE :- This note is used for sending the scrap to the stores.
(viii) MATERIAL REQUISION FORM :- this form is used for indenting or requisition of
materials from the stores.
(ix) GATE PASS :- in order to prevent pilferage , it is necessary that a gate is issued for
taking any item out of the stores and must be presented at the gate. Usually material
requisition form or material transfer note can be used as a gate pass.
(xi) STOCK VALUATION FORM:- this form is usually used for valuation of stocks in hand
at the end of the year so that it’s value may be included in the annual accounts.
(xii) TEMPORARY LOAN VOUCHER :- this voucher is used for issuing tools to the
workers which are to be returned to the stores at the end of the day.
(xiii) PERMANENT LOAN VOUCHER :- this voucher is used for issuing tools required for
daily use or for a long period by an employee or section.
BIN CARD
A bin card makes a record of the receipt and issue of material and is kept for each item of
stores carried. Quantity of stores received is entered in the receipt column of the bin card
and the quantity of stores issued is recorded in the store column of the bin card and a balance
of the quantity of the stores is taken after every receipt or maintained by the storekeeper and
the store keeper is answerable for any difference between the physical stock and the balance
shown in the bin card. These cards are used not only for recording receipts and issues of
stores but also assist the storekeeper to control the stock. For each items of
Construction Management
KIIT POLYCTECHNIC
stores, minimum quantity, maximum quantity and ordering quantity are stated requisition for
the purchase of material in time.
A bin card is also known as bin tag or stock card and usually bung up or placed in shelf,
rack, bin where the materials has been kept. Bin cards can also be in the form of loose sheets
which can be maintained in the ledger kept in the stores.
STORES LEDGER
This ledger is kept in the costing department and is identical with the bin card except the
receipts, issues and balances are shown along with their money values. This contains a
account for every items of stores and makes a record of receipts, issues and balances, both in
quantity and value. Thus, this ledger provides the information for the pricing of materials
issued and the money value at any time of each item of stores.
Construction Management
KIIT POLYCTECHNIC
Bin
Card
vs. Stores Ledger –
The difference between a bin card and the stores ledger can be summarised as follows:
3. Normally posted just before the 3. Always posted after the transaction
transaction takes place. transaction takes place.
Construction Management
KIIT POLYCTECHNIC
In every enterprise it is possible that the balance of stock shown by stock cards may differ
from the actual balance of stock ascertained by physical verification. It may be due to the
following reasons:
Avoidable causes
(i) Clerical mistakes i.e., wrong posting non-posting of entries, wrong casting etc. Such errors can be
corrected and actual balance can agree with book balance by making the required correction in
cards or stores ledger :
Unavoidable causes:
(iii) Actual balance may be more due to break down of fire, riots etc.
(iv) Material may be lost due to breaking of bulk material into smaller parts for issue. For example,
some iron is lost due to breaking up big iron rods into smaller parts.
Physical stock taking is very important for a concern as it serves the following
purposes:
(ii) It supports the value of stock shown in the balance sheet by physical
Construction Management
KIIT POLYCTECHNIC
verification.
(iii) It helps to disclose the possibility of fraud, theft or loss.
(iv) It helps to reveal the weakness in the system for the custody and control of
stock.
In short the difficulty and effectiveness of store keeping methods, controls and
procedures can be revealed by the size and number of surpluses and
efficiencies by stock taking.
Construction Management
KIIT POLYCTECHNIC
CHAPTER-4
4.0 Factors influencing selection ,design and layout of temporary facilities and services at
construction site
Every site, whether large or small, requires temporary services which are designed and provided
by the contractor. On a small site, the temporary services co nsi s t of a c c e s s roads, water supply,
electric supply, sewer connections etc. On a large construction site, temporary services include a
number of facilities such as telephone connection, batching plant, tube wells, service roads, repair and
construction yards, material storage yards, canteen and medical facilities etc. There is no specific or
fixed pattern for the type of temporary services required at a site. These services depend on the following
factors:
Various temporary services required at the site are briefly described below:-
(a) Water Supply
Water supply is essential for all construction sites. For large construction sites, tube wells may be
bored which could be later used on a permanent basis. Water supply is required for industrial and drinking
purposes. Industrial water supply is required for rock drilling, pile driving, feed water for boiler plant and
transporting materials by pipe lines etc. Drinking water supply is required for the work areas, offices,
canteen etc. To obtain water supply connections, the contractor or project manager has to apply to the
public Health Engineering Department stating the purpose and quantity of water required.
Construction Management
KIIT POLYCTECHNIC
Such types of yards are essential for repair and maintenance of equipment and machinery and as a
working area for bar benders, carpenters, welders etc. These yards are set up on the construction site for
smooth and unobstructed construction activity.
(d) Material Stores
Such stores are usually constructed with brick walls and G.l. Sheet roofing. G.I. sheets are preferred
for roofing purposes because of their high re- usability. The stores are used for the storage of cement,
electrical materials, hardware, paints, tools, spare parts, stationery etc. Sometimes A.C. sheets are also
used for roofing purposes.
The materials at the site should be stored in such a manner so as to prevent deterioration or
mixing of foreign matter. So following are the points of prime importance to be considered for storing
and stacking of materials.
Construction Management
KIIT POLYCTECHNIC
(i) Materials stored at the site should be protected from the atmospheric agencies such as rain, sun, wind and
moisture.
(ii) Materials susceptible to fire should be stored so as to prevent fire hazards. Petroleum products
and explosives should be stored according to the existing rules and regulations.
(iii) Materials like precast beams, slabs and pieces of timber, which are likely to be affected by the
subsidence of soil or support, shall be stored by adopting suitable measures against this risk.
(iv) For the storage of materials which are easily and immediately affected by the contact of
moisture, special precautions are to be taken. For example cement bags are should be stacked on
raised platform, with adequate water proof cover , having not more than 12 bags in a stack and at
least 30 cm clearance from any wall.
Brick and tiles should be stacked on a level ground limiting the height of stacks to 1.5m and
one metre.
Fine and coarse aggregate shall be stacked on a hard surface in regular stacks of size 2m ×
2m ×5 m and in such a way so as to prevent the admixture of vegetable and other foreign
materials.
(v) Materials constantly in use shall be relatively nearer to the place of use, but not too close. Similar
materials should be stacked close by.
(vi) Heavy units should be stacked near the hoist and the ramp.
(vii) Perishable materials which normally deteriorate during storage shall be kept constantly moving,
by replacing old materials with fresh stocks. Freshly arrived materials shall never be placed over
materials which had arrived earlier.
(viii) Fire extinguishers and fire buckets should be provided wherever necessary for safety.
The following basic factors should be taken in respect of receipt, storage and issue of stores :
1. There should be only one in-gate and one out-gate for entry and exit of stores unless the stores
themselves are classified into separate groups and are handled by separate sections such as iron,
steel , timber, brick, cement and aggregates and miscellaneous section in which case each group may
have its own entry and exit gates and connected security arrangements .
2. Entry of all consignments is recorded at the in-gate.
3. No stores/consignments are taken out unless authorised by a supporting out pass/gate pass slip.
4. That total storage accommodation should be divided into the following three sections. a. Receipt
Depot
b. Holding Depot
c. Issue Depot
The following factors should taken into consideration so that the stores are protected from the
weathering action of elements such as wind, rain and sun and that the sequence of arrangement should
provide first in first out principle so that stores do not deteriorate due to long storage.
Construction Management
KIIT POLYCTECHNIC
(i) Inflammable material (POL, explosives) should be stored separately and storage license for such
commodity should be obtained and bylaw/storage regulation prescribed from time to time
should be adhered to.
(ii) Stores more frequently require to be issued should be stored relatively near to the exit end.
(iii) Storage yard for timber and similar other materials should have adequate anti-fire measures such
as fire extinguishers, sand bucket etc.
(iv) Coarse and fine aggregates should be stacked in bin and underground pits respectively.
(v) Materials like cement, lime should be protected from contact of moisture.
(vi) Cement bags should be stacked clear off the ground by providing donnge of stone slabs, steel
girders or timber beams / ballies. They should be stacked at least 30 cm away from the wall and
the height should be restricted to 12 bags.
4.3-(I)Location of Equipment
With the ever- increasing cost of labour , it becomes necessary to use more and more
mechanical equipment in association with the available man power for construction work. Only
by very careful consideration the right type of equipment is chosen for any particular project.
Correctly chosen and well operated plant will enable a construction project to be completed
quickly and economically.
At the same time no contractor or owner can own all type of equipment needed for the
job, due to limited resources and also due to the reason that some of equipments may remain
idle, when they are not in use. Thus the owner or the contractor will purchase some of the
equipments and others he will hire or he will give further contract for such items which will
involve the use of equipments to such an organizations taking such works.
1. For the owned equipments suitable sheds may be provided near the entrance so that it can be
guarded without any additional chowkidar.
2. It should be near to the construction site.
3. It should be near to the materials.
4. For the hired equipments, suitable place may be left vacant where it can be accommodated as per the
equipment schedule
5. For the repair of equipment provision may be made in the shed itself.
6. The project equipment should be provided permanent shed for static equipment and temporary
garages for mobile equipment.
7. All equipments received in the project should have initial inspection carried out. In the case of new
equipment this inspection is carried out jointly by the project workshop and the representative of the
firm from which it is obtained. The equipment should be taken complete with history sheet, log
book, maintenance manual and operation manual. A trial demonstration should invariably be insisted
upon.
8. Adequate provision for fast moving parts as spares should be made along with the procurement.
Construction Management
KIIT POLYCTECHNIC
10. Responsibility for workshop cover and regular inspection should be fixed.
This is another task for the supervisory staff to organize the labour properly so that the
maximum output may be taken from them. The supervisor may divide the labour into groups
with a proper leader who can easily control and pass instructions to them clearly.
Suppose one and ten labourers are put for laying foundation concrete. The division of the
labourers will be:
(i) Say three labourers are put for bringing the aggregates.
(ii) Two labourers will be deputed for bringing cement.
(iii) Two for mixing the ingredients for the first batch.
(iv) Two for the tamping purposes.
(v) One for bringing water.
After the material is put on the platform for mixing, these three labourers can be
put on some other work if another batch is not to be prepared. Similarly after mixing ,
one labourer out of two and one who is bringing water is now free, can be put for
carrying the mixed concrete to the site.
From this it is clear that it is the duty of supervisor to organise the labour in such
a way so that there should be no wastage and work should be done efficiently.
However, the following points may be kept in mind, while organising labour at site.
(i) The supply of labour should be uninterrupted when needed.
(ii) Un-necessary rehandling of material should be avoided.
(iii) The material required during the day should be taken once for all from the go-down as it will avoid
frequent movement of labour.
(iv) Labour should not remain idle for want of material.
(v) It is economical to have some permanent labour.
(vi) Increase and decrease of labour should be suitably done.
(vii) Drinking water should be made available at site to avoid wastage of useful time of labourers.
(viii) The progress of the labourer should be recorded and compared in order to complete the job at the right
time.
The organisation of labour for a project involves the following:
1.recruitment of labour
This is particularly important in the case of departmentally run projects. If local labour is
available, it saves considerable amount of expense and administrative arrangements. In projects in
Construction Management
KIIT POLYCTECHNIC
remote areas or in the forward areas where local labour is not possible, labour recruiting zones have be
established and a special training cell in the project to take care of the labour from the recruiting zone
to the work site has to be established.
When labour is an imported one, the transit cell makes the transit arrangement whereas the
administrative cell makes arrangement for their living, eating and medical treatment. Sometimes all
such facilities consisting of transport , accommodation , messing and clothing are provided free as part
of agreement with the workers and entire expenditure is debited to the project.
Labour is primarily classified into skilled and unskilled. Whereas the unskilled labour can be
deployed directly on the job under supervision of technical supervisory personnel, the workers
required to do specialised/skilled jobs such as carpenters, masons and other trades-men have to be
trade tested at the time of recruitment. In case skilled trademen are not available semi-skilled are
initially recruited on a lower grade, given training and then deployed on job on higher grade after
qualifying in the trade test.
4. While deploying workmen on production jobs the following points should be considered :
(a) Work should be divided into a number of teams doing similar work.
(b) Production of such teams is regularly assessed and reasons for short fall if any investigated.
(c) Work incentive for higher production is provided. A small incentive helps increase output
considerably.
(d) Grievance/ complaints of workers are heard from time to time by having open meetings
where every individual can bring out his points. (e) Proper welfare activities are provided.
Chapter-5.0
Construction Organisation
Line and Staff Organisation:
Line organisation aims at having direct responsibility for attaining the objectives of the enterprise while staff organisation
refers to those elements of the organisation that help the line to work more effectively in attaining the primary objectives of
an enterprise. Line functions cover production, sales and sometimes finance whereas staff functions cover purchase,
accounts, personnel, plant maintenance and quality control. Line organisation establishes a direct relationship of authority
and responsibility between the superior and subordinates.
When the size of organisation expands for large and complex projects, the key men are to be assisted by specialists in
different fields. Staff people in an organisation are experts who do not have line authority but whose function is largely
Construction Management
KIIT POLYCTECHNIC
advisory. The activities such as research, design, planning, scheduling & recording of performance are executed by staff.
Line people maintain discipline and stability in an organisation.
The structure of line and staff organisation is illustrated below for better understanding of line and staff relationship.
Chief Engineer
Staff Function€Surveyor of Works Architect Vigilance Administration Wing Design Wing Accounts BranchStaff function
Line Function
7- Principle of specialisation- Activities of the organisation should be grouped as per the functions and
assigned to individuals in accordance with their specialisation.
8- Communication- Transmitting information and instructions within the organisation and to out side
persons connected with the organisation is essential to achieve the goals.
9- Flexibility and stability- Flexibility specifies the capacity to adjust work assignment, personnel and
facilities to temporary changes in the volume of work. Stability, on the other hand, refers to the
capacity to withstand the losses of key personnel without serious loss to the effectiveness of the
organisation.
10- Effective Delegation: Effective Delegation gives a change to sub-ordinates to think and develop any
task which they can decide themselves and perform efficiently and effectively.
11- Continuity- The organisation structure should be dynamic so as to maintain a link between the past
and the future.
5.3 Leadership
Leadership is the process of influencing the activities of an individual or a group towards
the achievement of goal in a given situation. Since all the successful manages must have
leadership quality, it thus becomes absolutely necessary to know about leadership.
Styles of Leadership- Styles are the ways in which the leader influences the followers and the various
styles in this respect are:
1- Autocratic or Authoritarian Leadership- The leader concentrates all the authority and all the
decision making powers in himself. There is no participation by his subordinates. He is the
sole unifying force in the organisation.
2- Democratic or Consultative or participative Leadership- The leader takes decision after
consulting his followers with their active participation in decision making process. He works
through the people instead of working over the people. He develops a team spirit among the
followers.
3- Free-rein or Laissez faire Leadership- This is described as “No leader at all” because the
leader delegates the authority for decision making in to the hands of the subordinates
completely.
4- Bureaucratic Leadership- It is characterised by high degree of reliance on rules, regulations
and procedures. The process of administration, thus, is reduced a series of routine actions.
5- Manipulative Leadership- It is based upon the belief that employees should be manipulated by
the leader so that the goal of the leader may be attained. It exploits the aspirations of the
employees.
6- Expert Leadership- Such leadership exhibits the knowledge, skill and ability of the leader
irrespective of his age, gender, physical and other related attributes. The subordinates are
treated as fellow employees with the mix of skills and their needs in a situation.
Role of a Leader
1. To help in defining the mission of the group.
2. To create a congenial working environment committed to attainment of goals.
3. To act as an interpreter of the message and behaviour of other groups and individual who may have some
influence on the group.
4. To Co-ordinate the activities of group members towards the achievement of organisational goal .
5. To provide the needed resources for the group.
6. To plan, organise the work, delegate authority and control position activities.
7. To quickly adjust to changing condition in environment.
8. To have foresight and to foresee new trends and opportunities.
9. To understand individuals and recognise their problems, motivate them to work together.
10. To make decisions without the influence of personal and emotional interests.
Construction Management
KIIT POLYCTECHNIC
5.5 : MOTIVATION:
Motivation refers to the way on which urges, drives, desires, aspirations, and strivings or needs
direct, control or explain the behaviour of human beings” Classification of Motives:
1- Power Motive: The ability to induce or influence behaviour is power. People with a high
power need have a great concern for exercising influence and control. Such people generally
seek positions of leadership and they are forceful, outspoken and hard headed and demanding
in nature.
2- Affiliation Motive: People like to interact and be with others in situations where they feel they
belong to and are accepted since they are social animals. Affiliation motive plays a very
complex but vital role in human behaviour. People with high need for affiliation usually
derive pleasure from being loved and tend to avoid the pain of being rejected. They maintain
pleasant social relationship, enjoy a sense of intimacy and understanding and enjoy consoling
and helping others in trouble.
3- Achievement Motive: Some people have an intense motive to achieve. It is based on the n-
Ach hypothesis developed by David McClelland. He has identified four basic characteristics
of high achievers
(i) Moderate Risk: Moderate Risk situation is within one’s reach as against high risk situation
which may not fulfil one’s mission.
(ii) Immediate feedback: Immediate and precise feedback information is necessary to evaluate
the progress of work towards achieving goal.
(iii) Accomplishment: Accomplishment of task intrinsically satisfying not necessarily
associated with material rewards is the motive behind the people with affiliation motive.
Different approaches to Motivation:
1- Carrot and Stick approach: The carrot and stick approach of motivation comes from the old
story that the best way to make a donkey move is to put a carrot out in front of him or jab him
with stick from behind. The carrot is the reward for moving and stick is the punishment for
not moving. In motivating people for desirable behaviour, some rewards such as money,
promotion and other financial and non-financial factors and some sticks i.e. punishments are
used to push the people for desired behaviour or to refrain from undesired behaviour.
2- Contingency approach: Since individuals differ, it is not possible to motivate them by a single
method. Depending on the situation, the contingency approach is made to motivate people.
This approach suggests that in motivating people, all the contextual variables must be
specified and their inter relationship should be established. What would be the best
motivational strategy, depends on the factors like individual personality, organisational
climate and type of incentives available.
3- Theory ‘X’ Approach:
Construction Management
KIIT POLYCTECHNIC
6- Group Decision making- Decision making is a process whereby a final but best choice is made
among alternatives available. Group decision is made through consensus mood or through
majority vote.
CHARACTERISTICS OF GROUP BEHEAVIOUR:
I. Two or more persons
II. Collective identity
III. Interaction
IV. Common purpose
MOB PSYCHOLOGY
Mob psychology is the study of men at works in groups and relationship between groups. It
studies human behaviour in groups to obtain information that can be applied to resolve
industrial/organisational problems. It aims at resorting the mental health of upset and confused groups.
HANDLING OF GRIVANCES
A grievance is defined as any feeling of discontent or dissatisfaction, expressed or not and
whether valid or not, arising out of anything connected with the working place that an employee
thinks, believes or even feels is unfair, unjust or inequitable.
STEPS INVOLVED IN GRIGANCE HANDLING PROCEDURE:
1- An aggrieved employee presents his grievances in writing to his foreman or supervisor and to union
representative who is also a full time employee of the organisation.
2- The grievance is looked into by the middle management and, if not settled, is forwarded to the top
management and to union officials.
3- Top management or top union official discuss the grievance and, if fail to settle the issue, the next
step is to submit the same to an impartial arbitrator for a final decision.
4- Failure to settle the issue timely may result in strikes, picketing, gherao or lock out.
A good grievance handling procedure should be i) simple, easy to understand and operate ii) settle
grievances of the lower level iii) depending upon the nature of grievance, refer it to the
appropriate authority.
LABOUR WELFARE: Labour Welfare may be categorised into three classes, such as:
(1) Economic (a) Group insurance (b) Retirement and Pension Plans (c) Health and Accident Services (d)
Credit Unions (e) Paid holidays (f) Profit sharing
2. Recreational (a) Sports (b) Social get- together (c) Special interest groups such as athletic programmes,
dramatics, flying and particular hobbies.
(3) Facilitative (a) Housing (b) Transport (c) Educational facilities and Library services (d)
Medical Services (e) Canteens, Cafeteria and Lunch Wagons (f) Company cheap stores (g)
Discount on purchase of company products (h) Rest rooms and Locker rooms (g) Legal and
Financial counselling.
Inter Personal Conflict: Conflict between two or more people is called inter personal conflict.
Individual differences create inter personal conflict. Wide differences are noticed between people
in terms of personalities, perceptions, values and attitudes.
Inter group conflict:When conflict occurs between groups or teams, it is known as inter group
conflict. Such conflict arises when one group sets out to undermine others, gain power and
improve its image. Such group conflict of negative consequences like aggression, hostile and
prejudice towards the other groups.
Resolving conflicts:
Several techniques have been envisaged for resolving conflict. The styles to resolve conflicts are:
(1) Avoiding (2) Accommodating (3) Competing (4) Compromising (5) Collaborating
(1) Avoiding is a deliberated decision to side step a conflictful issue, postponed addressing it till later or
withdraw from a conflicting situation. When parties are very much angry and need time to cool
down, it may be the best to use avoidance.
(2) Accommodating: In this style one party is willing to self-sacrifice in the interest of other party.
(3) Competing: This style tries to meet one’s goals at the other party’s expense.
(4) Compromising: Each party tries to give up something to reach a solution to the conflict. Give and
take policy dominates the behaviour of conflicting parties.
(5) Collaborating: It involves attempts to satisfy the needs of both the parties.
TEAM BUILDING
A team is a group whose members have complementary skills and are committed to a
common purpose or set of performance goals for which they hold themselves mutually
accountable. Team building involves certain stages to proceed from beginning to its building
1. Problem Sensing & Identification with a view how to solve the problem and improve team
effectiveness.
2. Examining perceptual differences: Efforts are made to reduce for remove individual differences in
realising the problems through specially designed communication and training sessions.
3. Feedback: The feedback given to members may include their feelings, approach, and way, staying
with the topic and going off on tangents. Feedback provides the members opportunity to evaluate,
introspect, understand and know themselves.
4. Developing Argumentative skills: The basic objective of this stage-cum-process is to increase the
ability among people as to how they should interact with others and engage in constructive
behaviour.
5. Follow up Action:-The total team is convened to review what has been learnt and to identify what
the next steps should be. Follow-up action also helps in overcoming the drawback involved at the
initial stages of team building.
*************
Construction Management
KIIT POLYCTECHNIC
CHAPTER 6:
Construction Labour and Labour Management:
Labour management in building construction means controlling the manpower problems, improving
labour productivity and reducing time and cost overrun of projects. To improve the labour performance, there
will be needed a good labour management practice.
6.1 Preparing labor schedule: In any construction project, it is necessary to estimate the required labour,
required for completion of the project. This can be done with the help of construction schedules. Separate
schedules are prepared for labour, material and equipment. These schedules help in procurement of labour,
material and equipment at proper time and their efficient usage and storage. Labour Schedule (MLS) shows the
construction project standard specification of the quality of manpower required for the execution of project.
Labour schedule, helps in providing future labour requirements and efficient and optimum deployment of labour
force where ever necessary.
6.2 Conventionally, productivity in many industries including construction has been evaluated as the ratio of
input versus output i.e. the quantity of the input delivered by a certain resource against the quantity of the value
created by that resource. Quantitatively, there are many ways to define productivity including physical metrics
such as the quantity of concrete poured in an hour by a single unit of labor.
The two key metrics of labor productivity include:
• Effectiveness – how much work a unit of labor can accomplish in a certain construction process.
• Efficiency – the quantity of work completed by a unit of labor in a given period of time.
More than labor effectiveness, labor efficiency is used in the construction industry to calculate overall output with
respect to the resources spent. Efficiency is generally used to measure and monitor performance.
To overcome the barriers and challenges in improving labor productivity in the construction industry, below steps
can be adopted:
• Providing adequate and timely training to laborers
Construction Management
KIIT POLYCTECHNIC
The following points highlight the top three methods of wage payments. The methods are: 1. Time Rate System 2.
Piece Rate System Method # 1. Time Rate System:
Under this method of wage payment, the workers are paid the wages on the basis of time. In this system of wage
payment, the workers are paid the wages on the basis of time as, per hour, per day, per week, per fortnight or per
month etc. This system does not consider the production of the employees during this time.
The amount of wages under this system is calculated as under:
Wages = Time spent by the worker × Rate of wages according to time.
Suitability of Time Rate System:
This system of Wage Payment is particularly suitable in the following circumstances:
1. When it is not possible to measure the production in terms of units or in any other terms.
2. When the work is of high standard.
4. When the production is of the nature that it requires efficiency more than the speed.
Construction Management
KIIT POLYCTECHNIC
This system encourages labour unions. Sometimes, these labour unions misuse their powers.
4. Misuse of Time by Workers:
Under this system of wage payment, the workers do not make proper Utilisation by their time.
5. Fall in the Quantity of Production:
Construction Management
KIIT POLYCTECHNIC
Under this system of wage payment, the quantity of production decreases because the workers do not
get any incentive for increasing the production.
The amount of wages to be paid to a worker under this system is calculated as under:
Wages = Units of production × Rate per unit.
Construction Management
KIIT POLYCTECHNIC
9. Mobility of Workers:
This system of wage payment increases the mobility of workers because they can change their
enterprise easily.
Construction Management
KIIT POLYCTECHNIC
11. Justified:
This system of wage payment justified also because the workers are paid the wages according to the
work performed by them.
12. Helpful in Maintaining Industrial Peace:
This system brings industrial peace also because it satisfies both the workers and the employer.
Construction Management
KIIT POLYCTECHNIC
7. Uncertainty of Wages:
As the amount of wages depends upon the quantity of production, the actual amount of wages to be paid
is always uncertain. The workers also cannot estimate their remuneration in advance.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
iii. Employees very often ask for compensation whenever production flow is disrupted due to the
fault of management. iv. Unless greater vigilance is exercised there is a danger of workers disregarding
safety regulations. v. Unless a maximum ceiling on incentive earning is fixed some workers tend to
overwork and undermine their health.
vi. Jealousies may arise among workers because some are able to earn more than others. In the case
of group systems, the fast workers may be dissatisfied with the efforts of the slower members of the
group; where heavy work is involved older workers in particular are likely to be criticised for being too
slow.
One likely effect of this is the splitting up of trade unions.
vii. The introduction of a system by results increases the amount and cost of clerical work since it
involves considerably more bookkeeping. This is particularly true when the production is subdivided
into many processes.
Worker motivation can be based on below 5 main categories and related sub categories:
Construction Management
KIIT POLYCTECHNIC
EQUIPMENT MANAGEMENT
INTRODUCTION
Construction Management
KIIT POLYCTECHNIC
Good project management in construction must vigorously pursue the efficient utilization of
labor, material and equipment.
The use of new equipment and innovative methods has made possible wholesale changes in
construction technologies in recent decades. The selection of the appropriate type and size of
construction equipment often affects the required amount of time and effort and thus the job-site
productivity of a project.
It is therefore important for site managers and construction planners to be familiar with the
characteristics of the major types of equipment most commonly used in construction.
An civil engineering project needs a variety of equipment and it is imperative for engineer or
contractor to know what type of equipment and what number of the equipment and for how many
days (with exact dates) for each will be needed for the purpose. So that he may arrange them
timely by hiring/purchasing or by any other means and the work may not be delayed because of
nonavailability of equipment. So an equipment schedule is to be prepared to ensure the efficiency
in stipulated time.
EQUIPMENT SCHEDULE
This schedule indicates the number of equipments of various types to be used during different
periods. Such an arrangement ensures efficient use of equipments. It also contains information
such as ownership of equipment, rent to be paid for hired equipment, condition of working etc.
Construction Management
KIIT POLYCTECHNIC
➢ Economic Considerations
➢ Company-Specific
➢ Site-Specific
➢ Equipment-Specific
➢ Manufacturer-Specific
➢ Labor Consideration
Economic Considerations
The economic considerations such as owning costs, operating labour costs and operating
fuel costs of equipment are most important in selection of equipment.
Besides, the resale value, the replacement costs of existing equipment, and the salvage value
associated with the equipment are also important.
Company-Specific
The selection of equipment by a company may be governed by its policy on 'owning' or 'renting’.
While emphasis on 'owning' may result in purchase of equipment keeping in mind the
future requirement of projects, the emphasis on 'renting' may lead to putting too much focus on
short-term benefits.
Site-Specific
Construction Management
KIIT POLYCTECHNIC
Site conditions-both ground conditions as well as climatic conditions-may affect the equipment-
selection decision.
For example, the soil and profile of a site may dictate whether to go for a crawler-
mounted equipment or a wheel-mounted equipment. If there is a power line at or in the vicinity of
site, one may go for a fixed-base kind of equipment rather than a mobile kind of equipment.
Equipment-Specific
Construction equipments come with high price tags. While it may be tempting to
go for the equipment with low initial price, it is preferable to opt for standard equipments.
Such equipments are manufactured in large numbers by the manufacturers, and their spare
parts are easily available, which would ensure minimum downtime. Besides, they can also fetch
good salvage money at the time of their disposal.
The owner/client in a certain project may have certain preferences that are not in line with
the construction company's preferred policies as far as equipment procurement is concerned.
The schedule, quality and safety requirements demanded of a particular project may in some
cases force the company to yield to the demands of the client.
Manufacturer-Specific
A construction company may prefer to buy equipment from the same manufacturer again
and again, and that too from a specific dealer. This may be to bring in uniformity in the
equipment fleet possessed by the company or because the company is familiar with the working
style of the manufacturer and the dealer.
Labor Consideration
Shortage of manpower in some situations may lead to a decision in favour of
procuring equipment that is highly automated. Further, the selection of equipment may be governed by
the availability or non-availability of trained manpower.
Construction Management
KIIT POLYCTECHNIC
➢ Ownership cost
➢ Operating cost
1. OWNERSHIP COST
This should expressed as an hourly cost and used for estimating and for charging equipment cost
to projects, it does not include job overhead or profit. Therefore if the equipment is to be rented
to others, profit should include to obtain an hourly rental rate. Ownership costs are “fixed” costs.
Almost all of these costs are annual in nature and include:
➢ Initial Cost
➢ Depreciation
➢ Investment Cost
➢ Insurance Tax and Storage Cost
INITIAL COST
On an average, initial cost makes up about 25% of the total cost invested during
the equipment’s useful life. This cost is incurred for getting equipment into contractor’s yard, or
construction site, and having the equipment ready for operation. Many kinds of ownership and
operating costs are calculated using initial cost as a basis, and normally this cost can be
calculated accurately. Initial cost consists of the following items:
• Price at Factory + extra equipment + sales tax
• Cost of shipping
• Cost of assembly and erection
DEPRECIATION
The decline in market value of a piece of equipment due to age, wear, deterioration and obsolescence.
Depreciation can result from:
However, there is always some uncertainty about the exact length of the useful life of the asset
and about the precise amount of salvage value ( i.e. the demand for equipment after its useful
period), which will be realized when the asset is disposed.
INVESTMENT COST
Investment or interest cost represents the annual cost (converted into an hourly cost) of
Construction Management
KIIT POLYCTECHNIC
capital invested in a machine. If borrowed funds are utilized for purchasing a piece of equipment,
the investment cost is simply the interest charged on these funds. If it is purchased with company assets,
an interest rate that is equal to the rate of return on company investment should be charged.
INSURANCE TAX AND STORAGE
COSTS
• Insurance cost represents the cost incurred due to fire, theft, accident and liability insurance for the
equipment.
• Tax cost represents the cost of property tax and licenses for the equipment.
• Storage cost includes the cost of rent and maintenance for equipment storage yards, the wages of
guards and employees involved in moving equipment in and out of storage, and associated direct
overhead.
2. OPERATING COST
Operating costs are also called “variable” cost. Because they depend on several factors
such as the number of operating hours, the types of equipment used, and the location and
working condition of the operation.
➢ Maintenance & Repair cost
➢ Tire cost
➢ Consumable cost (Ex- fuel/energy consumption, lubricating oil)
➢ Mobilization & Demobilization cost
➢ Equipment Operator cost
➢ Special Items cost
Inspection and testing , including cleaning is required in order to keep work equipment in
good working order and to ensure that it remains safe. If inspection and testing is not carried
out properly, two types of risk can be created:
• The performance of the equipment, including any safety features, may deteriorate to
the where the users are put at risk;
• The persons carrying out the inspection, testing and maintenance may be put at risk
Construction Management
KIIT POLYCTECHNIC
It is essential that an appropriate ‘competent person’, conducts the inspection and/or testing of
equipment. But there remains a responsibility on all personnel to identify defective or potentially
defective equipment, whenever this may come to their attention and to take appropriate action.
Equipment failing to meet the requirements of a specific inspection and/or test shall be dealt with
immediately either by rectifying the fault or reporting it as appropriate. Consideration shall be
given as to whether the equipment may remain in service.
It is essential that all inspections and/or tests together with any maintenance activities or repairs
of equipment be recorded. As a minimum, such records shall include the following:
➢ information on the type and model of equipment;
➢ any identification mark or number that it has;
➢ its normal location;
➢ the date that the inspection was carried out;
➢ who carried out the inspection;
➢ any faults found as a result of the inspection;
➢ any action taken regarding such faults;
➢ to whom, and by whom, these faults have been reported;
➢ the date when repairs or other necessary action were carried out
The inspection and/or test frequency/schedule identified for each particular item of equipment
shall be regarded as a minimum requirement and should be increased for equipment that is used
extensively or where an item of equipment may have been used beyond its recommended
working limits or for a purpose for which it was not intended. When determining the frequency of
inspection and/or test, consideration should also be given to the following:
• Intensity of use – frequency and maximum working limits;
• Operating environment, for example, marine, outdoors;
• Legislative requirements;
• Manufacturers guidance;
• Variety of operations – is the equipment performing the same task all the time or does this change?
• Risk to health and safety from malfunction or failure.
JOB LAYOUT FOR DIFFERENT CONSTRUCTION SITES EGO DAM SITE, MULTISTORIED BUILDINGS,
BRIDGE CONSTRUCTION SITE ETC.
The controlling contractor must consider many factors when laying out a site to
support construction operations
Construction Management
KIIT POLYCTECHNIC
Fig.1 shows the layout of the project under consideration. The entry is one-way and the notations on the
figure indicate the following:
1 : Watchman room or cabin
2 : Offices for contractors, engineers, etc.
3 : Store for plumping items, wood, electric fittings, etc.
4 : Store for cement
5 And 12 : Space for surplus earth
6 : Store for less costly miscellaneous items
7 And 14 : Space for coarse aggregate
8 And 15 : Space for sand
9 And 16 : Space for bricks
10 : Space for centring material
11 : Space for construction material
13 : Space for steel
Construction Management
KIIT POLYCTECHNIC
Ans.
•User safety
Performances to be carried out for maintainance and repair of equipment
➢ Tools and materials required for maintenance and repair are identified and obtained and used
according to manufacturer specifications. .
Supervisory processes and checks and measures are implemented to ensure work is completed
within time available.
Lubrication is applied to moving parts according to manufacturer specifications.
STUDY MATERIAL
8.1 Meaning
Quality may be defined as fitness for purpose as lowest cost. Quality means degree of
perfection. It can be determined by some characteristics such as design, size, materials,
chemical composition, machine functioning, work man ship finishing and other
properties.
Quality control is concerned with making things right rather than discovering and
rejecting those made wrong. Quality control is techniques of management for achieving
required standard of products.
Construction Management
KIIT POLYCTECHNIC
Advantages:-
Def.
Quality is the essence of a construction work. The main objectives of the inspection and
quality control is to achieve sound construction work which results in a structure of good
strength and good life at a reasonable rate.
Major items of control:-
Major items of construction should be controlled like materials, equipment and construction work.
• Materials
All the materials should be inspected and tested a per standard specifications laid
own. The samples of materials should be selected at random and checked.
• Equipment
The equipment purchase should confirm to the specifications and laid standards, as per terms
and conditions given in supply order.
• Construction work
Different standards and specifications are followed in different types of works. The
inspection checking and testing of construction work is carried out at suitable
intervals during course of construction.
2. Quality assurance
Construction Management
KIIT POLYCTECHNIC
STUDY MATERIAL
9.1
Progress of any work may be defined as an achievement at regular intervals of time when compose with
the estimated work. Progress reports are prepared at regular intervals to have better control of progress.
Purpose
• It gives information to the planner as to whether the work is being one as per schedule
• It gives assurance to the owner as to whether he is getting back for what he is spending.
• It permits collective action to bring the work on schedule if the same is behind schedule.
• It forms the basis of making payments.
Programme:
It is a comprehensive plan designed to implement the policies and accomplish the objectives. It is a
combination of goals, policies, task assignments, resource flows, etc. It is a concrete well defined scheme
designed to accomplish a specific objective. In business programmes are used in various areas,
e.g. developing a new product, training programme, advertising programme, expansion programme, etc.
Features of a programme:
• It is a single use but comprehensive plan.
• It is based on the objectives and policies of the organisation
• It is an action plan indicating the activities to be performed and time for activities to be performed and time for
each activity.
• It is designed to ensure smooth and efficient functioning of the organisation.
A programme serves as a useful guide in day to day operations. It is action based and result
oriented.
C Job dairy: it is most important documents. It records attendance record, progress of work one, record
of payments made, receipt an issue of materials to the work, inspection report, office
correspondence record etc. It helps in solving disputes with contractors and can be produced as
evidence in the court of law.
Construction Management
KIIT POLYCTECHNIC
C Register of instructions: The site engineer records his observations regarding quality and progress of
work in this register. This is the channel of communication between the engineer and the
contractor at the site of work.
C Progress reports: The engineer prepares the progress report, progress charts at regular intervals to
keep the owner and home office fully informed. The reports can be submitted daily, weekly,
fortnightly and sometimes monthly.
C Construction reports: The daily reports regarding progress of construction material used are to be
entered in prescribed forms regularly. The construction reposts are intended to recorded time,
quality and quantity of work and general conditions to ensure satisfactory progress on work as per
laid specifications.
C Abstract of quantities and cost: The materials issued to the work are also recorded in this register.
These are further posted on registers and indicate the up to date progress of work.
Work study is the study of human. Work in all aspects in order to improve productivity. Work
study is a systematic an analytical study of work process and work methods with the objective of
increasing efficiency and reducing costs.
Work study is a vital tool of improving productivity and cost effectiveness. Work study makes
improvements in the areas of:
• Work environment
• Plant layout
• Material handling
• Employee safety
• Equipment utilisation
Construction Management
KIIT POLYCTECHNIC
WORK STUDY
1. METHOD ANALYSIS
2. WORK MEASUREMENT
1. Method analysis/method study: It is to find out better ways of doing work. It leads to standardization of
methods and procedures. It is also known as work improvement.
2. Work measurement: it refers to the study of work content of a job so as to lay down fair days. It is
closely related to method analysis.
Method/motion study: the analysis during the execution of the project would invariably slow slackness
or comparatively less output in certain fields
C Method adopted for the job C
Quality of finished products
C Specifications of materials
• Proper accounts of the material purchased, and consumed on the work as per
material schedule is kept.
• Proper record of labour employed, payment made to them and progress of work
one b them are recorded and compared with the
labour schedule and corrective action taken.
• The deployment of equipment as per equipment schedule must be checked.
• Progress of construction should be compare with construction schedule and in
case the work behind schedule the causes must be investigated.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
Tools and equipment should be kept organized and put away after use. At the end of each day, check that there are no tools
or materials left on the platform—clutter could lead to trip and fall injuries, or they may pose a hazard for those working
on lower levels.
9. Mind the Weather
When working at height, you want to make sure the working conditions are safe. Working during harsh weather conditions
or other environmental hazards can increase the risk of serious injury. For instance, high winds could risk injury to those
working on the scaffold. If a storm has brought down a power line, that could also create a scaffolding hazard.
10. Be Fully Licensed
Being fully licensed—and working with licensed contractors—helps prevent injuries since everyone working on the site
is aware of the potential hazards and the best ways to avoid them. The process of becoming licensed often involves
education and training, which helps your team work safely.
11. Climb Responsibly
Those who scale your scaffolding should exercise proper safety techniques when doing so. One tip is to make sure
employees always have at least three points of contact with the structure at all times, meaning either one hand and two
feet or two hands and one foot.
In addition, some parts of the scaffold, such as cross braces, shouldn’t be used for climbing—they’re not usually designed
to support sheer weight on their own.
Overall safety culture can be described as a set of beliefs, norms attitudes and social technical practices
that are concerned with minimizing the exposure of individuals, within and beyond an organization, to
conditions considered dangerous or injurious.
Safety is looked into from the cultural point of view as shared characteristics of a group dynamic relating
to a system (e.g., group, community, race, nation, religion) which include beliefs, values, attitudes,
opinions and motivations. Organizations with good safety cultures have employees with positive patterns
of attitudes towards safety practice. These organizations have mechanisms in place to gather safety-
related information, measure safety performance and bring people together to learn how to work more
safely. Employees’ perceptions of safety culture as follows:
• management attitudes towards safety;
• perceived level of risk;
• effects of work pace;
• management actions towards safety;
Construction Management
KIIT POLYCTECHNIC
• status of safety adviser and safety committee; • importance of health and safety training; • social status of
safety and promotion.
and losses caused through an accident in course of and arising out of the employment subject to
specific expectations as mentioned in the act.
The objective of the Workmen's Compensation Act
The Workmen’s Compensation Act, 1923 was majorly formed to provide compensation to the
workmen at the time of an accident.
The act mentions that it is the duty and responsibility of the employer to include the welfare of
the workers when an injury is the result of the employment in the same way the employer has
reserved the right of making profits. The main aim of this act is to ensure that the workmen
have sustainable life even after encountering an employment-related injury.
The Liability of the Employer for Compensation
To make the employer pay the workers compensation at the time of injury or death suffered by
the employee or workman should be a consequence of some accident in course of or out of
his/her employment depends on the following four conditions.
Construction Management
KIIT POLYCTECHNIC
permit may contain conditions about the hours of work, fixation of wages, and other necessary facilities
to the contract labours.
Construction Management
KIIT POLYCTECHNIC
• Canteen to the labours (if the employed workmen are 100 or more and the work is performed for six
months or more).
• Issues employment card to the labours.
• Restrooms for the workers working at night and where the work is performed for three months or more.
• Required number of separate urinals for men and women.
• Drinking water, washing, first aid, crèche, etc. for the labours.
• Maintains the various registers and records, notices, etc.
Violations To the Contract Labour Act
Any person who violates any part of any clause of the act will be punished with custody for more than
three months or with a fine of Rs 1,000 or maybe both, depending on the severity of the violations. If
a person breaks any rules under the act for which no additional fine is provided, then he or she shall be
sentenced to three months imprisonment or a fine of one thousand rupees or both.
Construction Management
KIIT POLYCTECHNIC
The Indian sub-continent, like many other regions in the world, is vulnerable to a number of natural
hazards such as earthquakes, landslides, tsunamis, floods, cyclones, storm surges and thunderstorms.
High vulnerability of its physical and socio-economic profile characterize the disaster scenario of the
subcontinent which has been, traditionally, facing different types of natural calamities that often turn into
disasters, causing high loss of life and property. India has witnessed several disasters leaving a trail of
destruction and irreparable loss of lives.
BMTPC has prepared the third edition of the Vulnerability Atlas of India which includes hazard maps of
earthquakes, wind, cyclones, floods, landslides, thunderstorms and vulnerability risk tables based on
available latest data in order to help in enhancing preparedness of Governments and various other
agencies in mitigating natural disasters. The Atlas is a useful tool not only for public but also for urban
managers and National and State Authorities dealing with disaster mitigation and management.
Natural Hazards are elements of circumstances in the Natural environment that have the potential to cause
harm to people or property or both. These may be swift or permanent aspects of the respective
environmental settings like currents in the oceans, steep slope and unstable structural features in the
Himalayas or extreme climatic conditions in deserts or glaciated areas.
Natural disaster is an undesirable occurrence resulting from forces that are largely outside human control,
strikes quickly with little or no warning, which causes or threatens serious disruption of life and property
including death and injury to a large number of people, and requires therefore, mobilisation of efforts in
excess of that which are normally provided by statutory emergency services”.
India has been vulnerable, in varying degrees, to a large number of natural, as well as, human-made
disasters on account of its unique geo-climatic and socioeconomic conditions. It is highly vulnerable to
Construction Management
KIIT POLYCTECHNIC
floods, droughts, cyclones, earthquakes, landslides, avalanches and forest fires. Out of 36 states and
union territories in the country, 27 of them are disaster prone.
India is one of the ten most disaster-prone countries of the world. The country is prone to disasters due to
a number of factors; both natural and human induced, including adverse Geo- climatic conditions,
topographic features, environmental degradation, population growth, urbanization, industrialization, non-
scientific development practices, etc.
• Disaster risk reduction: The concept and practice of reducing disaster risks through systematic
efforts, to analyse and manage the causal factors of disasters, including through reduced exposure
to hazards, lessened vulnerability of people and property, wise management of land and the
environment, and improved preparedness for adverse events.
• Early warning system: The set of capacities needed to generate and disseminate timely and
meaningful warning information to enable individuals, communities and organizations threatened
by a hazard to prepare and to act appropriately and in sufficient time to reduce the possibility of
harm or loss. Emergency management: The organization and management of resources and
responsibilities for addressing all aspects of emergencies, in particular preparedness, response and
initial recovery steps.
• Emergency services: The set of specialized agencies that have specific responsibilities and
objectives in serving and protecting people and property in emergency situations.
• Environmental degradation: The reduction of the capacity of the environment to meet social and
ecological objectives and needs.
• Environmental impact assessment: Process by which the environmental consequences of a
proposed project or programme are evaluated, undertaken as an integral part of planning and
decision-making processes with a view to limiting or reducing the adverse impacts of the project
or programme.
• Forecast: Definite statement or statistical estimate of the likely occurrence of a future event or
conditions for a specific area.
• Hazard: A dangerous phenomenon, substance, human activity or condition that may cause loss of
life, injury or other health impacts, property damage, loss of livelihoods and services, social and
economic disruption, or environmental damage.
• Mitigation: The lessening or limitation of the adverse impacts of hazards and related disasters.
• Natural hazard: Natural process or phenomenon that may cause loss of life, injury or other health
impacts, property damage, loss of livelihoods and services, social and economic disruption, or
environmental damage.
• Preparedness: The knowledge and capacities developed by governments, professional response
and recovery organizations, communities and individuals to effectively anticipate, respond to and
recover from, the impacts of likely, imminent or current hazard events or conditions.
• Prevention: The outright avoidance of adverse impacts of hazards and related disasters.
• Public awareness: The extent of common knowledge about disaster risks, the factors that lead to
disasters and the actions that can be taken individually and collectively to reduce exposure and
vulnerability to hazards.
• Recovery: The restoration, and improvement where appropriate, of facilities, livelihoods and
living conditions of disaster-affected communities, including efforts to reduce disaster risk factors.
• Response: The provision of emergency services and public assistance during or immediately after
a disaster in order to save lives, reduce health impacts, ensure public safety and meet the basic
subsistence needs of the people affected.
• Retrofitting: Reinforcement or upgrading of existing structures to become more resistant and
resilient to the damaging effects of hazards.
• Risk: The combination of the probability of an event and its negative consequences. Sustainable
development: Development that meets the needs of the present without compromising the
ability of future generations to meet their own needs.
Construction Management
KIIT POLYCTECHNIC
• Vulnerability: The characteristics and circumstances of a community, system or asset that make it
susceptible to the damaging effects of a hazard.
Magnitude is a measure of earthquake size and remains unchanged with distance from the earthquake.
Intensity describes the degree of shaking caused by an earthquake at a given place and decreases with distance
from the earthquake epicentre. Magnitude measurement requires instrumental monitoring for its calculation,
however, assigning an intensity requires a sample of the felt responses of the population.
This is then graded according to the EMS intensity scale.
A seismic zone is used to describe an area where earthquakes tend to focus; for example, the New
Madrid Seismic Zone in the Central United States. A seismic hazard zone describes an area with a
particular level of hazard due to earthquakes.
Seismic hazard is the hazard associated with potential earthquakes in a particular area, and a seismic
hazard map shows the relative hazards in different areas. The maps are made by considering what we
currently know about: Past faults and earthquakes.
Construction Management
KIIT POLYCTECHNIC
The tendency of the roof structure to remain at its original position is called inertia. The inertia forces
can cause shearing of the structure which can concentrate stresses on the weak walls or joints in the
structure resulting in failure or perhaps total collapse. Finally, more mass means higher inertia force that
is why lighter buildings sustain the earthquake shaking better.
Construction Management
KIIT POLYCTECHNIC
Fig. 2: Development of Great Inertia Forces in the Six Storey of Imperial County Services Building
These internal forces are termed stiffness forces. The stiffness forces would be higher as the size of
columns gets higher. The stiffness force in a column is the column stiffness times the relative
displacement between its ends.
Construction Management
KIIT POLYCTECHNIC
However, horizontal shaking along X and Y directions is critical for the performance of the structure
since it generates inertia forces and lateral displacement and hence adequate load transfer path shall be
provided to prevent its detrimental influences on the structure.
Proper inertia force transfer path can be created through adequate design of floor slab, walls or columns,
and connections between these structural elements. It is worth mentioning that the walls and columns are
critical structural members in transferring the inertial forces. It is demonstrated that, masonry walls and
thin reinforce concrete columns would create weak points in the inertia force transfer path.
Construction Management
KIIT POLYCTECHNIC
• Structural simplicity
• Uniformity, redundancy and symmetry
• Bi-directional resistance and stiffness
• Torsional resistance and stiffness
• Adequacy of diaphragms at each storey level
• Adequate foundations
Construction Management
KIIT POLYCTECHNIC
Structural simplicity pertains to the provision of obvious, simple and straightforward load path to transfer
seismic forces from different part of the structure to its foundation. Not only does the load path need to be
clear and simple but also its components must have sufficient stiffness, ductility and strength.
This requirement should be examined by a structural designer who commonly designs the load path. One of
the significant advantages of direct load path is that it would contribute in the decrease of doubts and
uncertainty in the evaluation of strength, ductility and dynamic behavior. In contrary, complicated load path
is likely to cause stress concentration and toughen the estimation of strength, ductility and dynamic response
of structures. It should be bore in mind that, acceptable structures with complex load path can be designed.
Construction Management
KIIT POLYCTECHNIC
Fig.5: Desirable Symmetrical Shape Plan for Building in Seismic Prone Areas
Construction Management
KIIT POLYCTECHNIC
Fig.7: Provision of Seismic Joints for Decrease or Eliminate Torsional Motion due to
Earthquakes
Construction Management
KIIT POLYCTECHNIC
Lateral torsional deformation, which might stress various structural members in an un-uniform manner, could
occur during earthquakes. The factor that leads to lateral torsional motion is the eccentricity between center
of mass and stiffness. So, this problem need to be tackled at the design stage.
Fig.9: Center of Mass and Center of Stiffness in a Structure Subjected to Earthquakes and Suffered
Displacements
The eccentricity could be decreased at design stage but it may not be completely eliminated because of
number of factors which are out of designer control. For example, non-uniform mass distribution and uneven
stiffness deterioration of structural elements during earthquakes. Finally, this problem can be dealt with by
arranging stiff and resistant members close to the periphery of the structure.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
Fig.11: Connection of individual footing with tie beams or structural slabs to prevent possible relative
movement during earthquakes
Wind / Cyclone hazard and vulnerability, wind speed and pressures, wind hazard
and cyclone occurrence maps, storm surveys and cyclone resistant measures.
11.3 Wind / Cyclone hazard and vulnerability, wind speed and pressures, wind hazard and cyclone occurrence maps,
storm surveys and cyclone resistant measures.
Indian sub-continent is the worst affected region of the world, having a coast line of 7516 kms. (5400
kms along the mainland, 132 kms in Lakshadweep and 1900 kms in Andaman and Nicobar Islands) is
exposed to nearly 10% of the world’s Tropical Cyclones. There are 13 coastal states/UTs encompassing
84 coastal districts which are affected by Saffir-Simpson Hurricane Scale Source: NWS, NOAA
cyclones (Fig. 1). Four States (Andhra Pradesh, Odisha, Tamil Nadu and West Bengal) and one UT
(Pondicherry) on the East Coast and One State (Gujarat) on the West Coast are more vulnerable to
cyclone disasters. 40% of the total population lives within 100 km of coastline. Analysed data for the
period 1980-2000 shows that on an average, annually 370 million people are exposed to cyclones in
India.
Atmospheric pressure and wind speed change across the diameter of a hurricane. To
demonstrate, the diagram below shows a rough profile of wind speed (blue) and surface
pressure (red) across a hurricane. Between 100 and 200 kilometers from the eye, the winds
are fast enough to qualify as tropical storm force. The atmospheric pressure here will still be
Construction Management
KIIT POLYCTECHNIC
relatively high compared to the storm's center at about 990 to 1010 millibars. However, the
pressure gradually falls and the wind speed rises upon getting closer to the eye wall. It is only
over the last 50 to 100 kilometers that the large changes in pressure and wind speed occur.
Construction Management
KIIT POLYCTECHNIC
Storm survey:
A survey team's mission is to gather data in order to reconstruct a tornado's life cycle, including where it
occurred, when and where it initially touched down and lifted (path length), its width, and its magnitude.
• Choose the location carefully to avoid the full force of the wind or flood
• Use building layout with a simple regular shape, to avoid concentration of pressure.
• Build the roof at an angle of 30° to 45° to prevent it being lifted off by the wind.
• Avoid wide roof overhangs; separate the veranda structure from the house.
• Make sure the foundations, walls, and roof structure are all firmly fixed together.
Construction Management
KIIT POLYCTECHNIC
• Reinforce the bracing in the structure; strengthen walls and joints/ junctions to increase stiffness.
• Make sure the roof covering is firmly attached to the roof structure to prevent it from lifting.
• If doors & shutters cannot be shut, make sure there are opposing openings to reduce pressure build up.
• Plant trees around the house as wind breaks and reduce flow of water, but not too close.
11.4 Flood hazard and vulnerability, Flood hazard and Flood prone areas of the country, General
protection of habitants and flood resistant construction
Five factors that determine flood vulnerability include the nature of soil, dwelling type, employment
status, education and rainfall. All these factors were ranked according to their importance by using a
fivepoint ranking scale, from most important to second, third, fourth and least important. The nature of
the soil was ranked as the most important factor, followed by dwelling types. Respondents’ rankings
were influenced by the collapsed and cracking of their houses that occurred during the flood event.
Construction Management
KIIT POLYCTECHNIC
Though the north-Indian plains prone to flood more, the "India flood prone areas" can be broadly categorized in three divisions:
• Ganga Basin: The Ganga Basin gets flooded mostly in the northern part by its northern tributaries. The badly
affected states of the Ganga basin are West Bengal, Bihar and Uttar Pradesh. Besides the Ganga, rivers like
Sarada, Rapti, Gandak and Ghagra causes flood in eastern part of Uttar Pradesh. The Yamuna is famous for
flooding Haryana and Delhi. Bihar experiences massive dangerous flood every year. River Burhi, Bagmati,
Gandak, Kamla along with many small rivers contribute to that. In West Bengal, rivers like Mahananda,
Bhagirathi, Damodar, Ajay etc. causes floods because of tidal effects and insufficient river channels.
• Brahmaputra and Barak Basins: The river banks of Brahmaputra and Barak gets flooded due to the Surplus
water found in the Brahmaputra basin and the Barak basin. These rivers along with their tributaries flood the
northeastern states like West Bengal, Assam and Sikkim. Jaldakha, Teesta and Torsa in northern West Bengal
and rivers in Manipur often overflow their banks.
• Central India and Deccan Rivers Basin: In Orissa, spilling over of river banks by Mahanadi, Baitarni and
Brahmani causes havoc. The deltaic area formed by these three rivers is thickly populated. Even some small
rivers of Kerala and mud stream from the nearby hills add on to the destruction. Southern and central India
observes floods caused by Narmada, Godavari, Tapi, Krishna and Mahanadi due to heavy rainfall. Cyclonic
storms in the deltaic regions of Godavari, Mahanadi and Krishna even floods the coastal regions of Andhra
Pradesh, Orissa and Tamil Nadu occasionally.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
Sewer backflow valves prevent flooded sewage systems from backing up into a home. In certain flood-prone areas, this
issue is common, and can cause damage that is both difficult to repair and hazardous to occupants’ health. Generally,
gate valves are preferred over flap valves because they provide a better seal against flood pressure.
Grade the Lawn Away from the House
One final method that architects can use to mitigate damage from flooding is to grade the lawn away from the house. If
the lawn tilts toward the house, rainwater will pool around the home. Conversely, tilting it outward directs rainwater
away. To this end, the lawn should use a heavy soil that contains clay content and sand, allowing the surface runoff to
empty into a more appropriate place such as a street gutter.
Earthquakes and volcanic eruptions that cause the sea-floor to move abruptly resulting in sudden
displacement of ocean water in the form of high vertical waves are called tsunamis (harbour waves) or
seismic sea waves. Normally, the seismic waves cause only one instantaneous vertical wave; but, after
the initial disturbance, a series of afterwaves are created in the water that oscillate between high crest
and low trough in order to restore the water level.
Construction Management
KIIT POLYCTECHNIC
Construction Management
KIIT POLYCTECHNIC
Other ways to prepare for and mitigate the potential impacts of a tsunami emphasize thoughtful land-use
planning and building design in tsunami hazard zones and include the following:
Improving evacuation routes
Building tsunami evacuation structures
Limiting new development in tsunami hazard zones
Designing, siting, and building structures to minimize tsunami damage
Adopting building codes that address tsunamis
Protecting and strengthening existing structures and infrastructure that if damaged would negatively affect
response and recovery
Moving important community assets and vulnerable populations out of tsunami hazard zones Planning for post-
tsunami recovery
Construction Management
KIIT POLYCTECHNIC
11.6 Housing vulnerability risk tables and usage of vulnerability atlas of India, Inclusion of
vulnerability atlas in Tender documents.
Vulnerability Atlas of India, brought out by BMTPC, is collation of the existing hazard scenario for the entire country
and presents the digitized State/UT-wise Hazard Maps with respect to Earthquakes, Winds & Floods for district-wise
identification of vulnerable areas. The latest edition contains additional digitized maps for Thunderstorms, Cyclones and
Landslides.
The Atlas also presents the district-wise Housing Vulnerability Risk Tables based on wall types and roof types as per 2011
Census Housing data. The Atlas is a useful tool not only for public but also for urban managers, State & National
Authorities dealing with disaster mitigation and management.
The Vulnerability Atlas created by Building Materials and technology Promotion Council (BMTPC) was updated in
2019. It was released by the Hon. Prime Minister on 2nd March, 2019 at New Delhi. This atlas gives the latest
information regarding vulnerability of housing stock to earthquakes, cyclones; floods, landslides and thunderstorms. The
State Governments have the basic mandate for management of disasters and the executive actions are taken at the
district levels with the District Collector playing the pivotal role. This Atlas provides some ready information, though at
macro-level, for use of the authorities involved in the tasks of disaster mitigation, preparedness and preventive actions.
A glance at the hazard maps will bring to the notice of the district authorities, the location and percent areas of the
districts most susceptible to hazard occurrence, the probable maximum hazard intensities, the type of housing and its
vulnerability and risk to the hazards. Knowing the extent of the problem of future disasters, the district authorities can
formulate development plans for (a) preventive actions like hazard resistant construction, retrofitting and
upgrading/retrofitting of existing buildings, (b) mitigating the intensity and extent of the disasters, (c) early warning
system installation and drills for its use, (d) instituting a hierarchical structure for preparedness down to the village level,
(e) training of manpower in various tasks in the emergency (f) implementation of land zoning regulations in flood plains
and coastal areas, and building bylaws with disaster resistant features in various towns and cities, etc. (g) supporting
land use zoning and urban planning (h) integration of DRR with development and (i) supporting in locating industries
and other development projects. Similarly, various Ministries can use this atlas to make all the structures under their
jurisdiction disaster resilient, infrastructure constructed and maintained by them hazard resistant and people/economic
activities less susceptible. It is urged by the Hon. Prime Minister that all the construction and building related tenders
may utilise this vulnerability atlas as a guiding factor, to arrive at the cost which will include Disaster Resilience.
Construction Management