CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027
EWF-HI.3 Construction of 23 Housing Units 566 01-Oct-24 22-Jul-26 22-Jul-26, EWF-HI.3 Construction of 23 Housing Units
EWF-HI.3.1 Demolition Work 104 01-Oct-24 29-Jan-25 29-Jan-25, EWF-HI.3.1 Demolition Work
A2470 Demolition of Housing Units 100 01-Oct-24* 25-Jan-25 Demolition of Housing Units
A2480 Disposal & Site Clearance 80 28-Oct-24* 28-Jan-25 Disposal & Site Clearance
A3680 Survey, Layout and Marking 81 28-Oct-24* 29-Jan-25 Survey, Layout and Marking
EWF-HI.3.5 Construction Work 23 Housing Units 543 28-Oct-24 22-Jul-26 22-Jul-26, EWF-HI.3.5 Construction Work 23 Housing U
EWF-HI.3.5.2 Sub Structure Work 167 28-Oct-24 10-May-25 10-May-25, EWF-HI.3.5.2 Sub Structure Work
A1780 Demarcation 85 28-Oct-24* 03-Feb-25 Demarcation
A1790 Excavation 90 28-Oct-24* 09-Feb-25 Excavation
A1800 Levelling and Compaction of Earth 90 30-Oct-24* 11-Feb-25 Levelling and Compaction of Earth
A1810 PCC Work 90 02-Nov-24* 13-Feb-25 PCC Work
A1820 Settingout for Footings 90 05-Nov-24* 17-Feb-25 Settingout for Footings
A1830 Steel Work for Footing 90 09-Nov-24* 20-Feb-25 Steel Work for Footing
A1840 Shuttering Work for Footing 90 13-Nov-24* 25-Feb-25 Shuttering Work for Footing
A2490 Concreting Work & Curing for Footing 90 16-Nov-24* 27-Feb-25 Concreting Work & Curing for Footing
A2500 Deshuttering - Footing Work 92 20-Nov-24* 06-Mar-25 Deshuttering - Footing Work
A2510 Steel Work for Short Columns 88 26-Nov-24* 09-Mar-25 Steel Work for Short Columns
A2520 Shuttering Work for Short Columns 85 05-Dec-24* 13-Mar-25 Shuttering Work for Short Columns
A2530 Concreting Work curing for Short Columns 88 05-Dec-24* 17-Mar-25 Concreting Work curing for Short Columns
A2540 Deshuttering for Short Columns 90 05-Dec-24* 19-Mar-25 Deshuttering for Short Columns
A2550 Solid Block Work 95 05-Dec-24* 25-Mar-25 Solid Block Work
A3700 Steel Work for Plinth Beam 90 11-Dec-24* 26-Mar-25 Steel Work for Plinth Beam
A3860 Shuttering Work for Plinth Beam 90 21-Dec-24* 03-Apr-25 Shuttering Work for Plinth Beam
A3900 Concreting work & Curing for Plinth Beam 80 04-Jan-25* 06-Apr-25 Concreting work & Curing for Plinth Beam
A3910 Deshuttering for Plinth Beam 76 15-Jan-25* 13-Apr-25 Deshuttering for Plinth Beam
A3920 Bitumen Paint Work 77 18-Jan-25* 16-Apr-25 Bitumen Paint Work
A3930 Backfilling Work 77 21-Jan-25* 20-Apr-25 Backfilling Work
A4050 Earth Compaction and MEP Sleeves Work 78 26-Jan-25* 26-Apr-25 Earth Compaction and MEP Sleeves Work
A4060 Anti-Termite Treatment 79 27-Jan-25* 29-Apr-25 Anti-Termite Treatment
A4070 Polythene Sheet 79 28-Jan-25* 29-Apr-25 Polythene Sheet
A4270 BRC Mesh Work 80 30-Jan-25* 03-May-25 BRC Mesh Work
A4280 Concreting Work 81 05-Feb-25* 10-May-25 Concreting Work
EWF-HI.3.5.1 Super Structure Work 437 24-Feb-25 18-Jul-26 18-Jul-26, EWF-HI.3.5.1 Super Structure Work
EWF-HI.3.5.1.3 Civil Work 261 24-Feb-25 24-Dec-25 24-Dec-25, EWF-HI.3.5.1.3 Civil Work
A2560 Settingout for Columns 120 24-Feb-25* 13-Jul-25 Settingout for Columns
A2570 Steel Work for Columns 124 24-Feb-25* 17-Jul-25 Steel Work for Columns
A2580 Shuttering Work for Columns 127 24-Feb-25* 21-Jul-25 Shuttering Work for Columns
A2590 Concreting Work for Columns 118 11-Mar-25* 27-Jul-25 Concreting Work for Columns
A2600 Deshuttering and Curing Work for Columns 120 11-Mar-25* 29-Jul-25 Deshuttering and Curing Work for Columns
A2610 Shuttering Work for GF Slab and Beams 122 11-Mar-25* 31-Jul-25 Shuttering Work for GF Slab and Beams
A2620 Steel Work GF Slab and Beams 120 11-Mar-25* 29-Jul-25 Steel Work GF Slab and Beams
A2630 Concreting Work GF Slab and Beams 123 13-Mar-25* 03-Aug-25 Concreting Work GF Slab and Beams
A2640 Curing Work GF Slab and Beams 124 16-Mar-25* 06-Aug-25 Curing Work GF Slab and Beams
A2650 Settingout for Staircase Tower Columns 120 23-Mar-25* 09-Aug-25 Settingout for Staircase Tower Columns
A2660 Steel Work For FF Columns 118 30-Mar-25* 13-Aug-25 Steel Work For FF Columns
A2670 Shuttering Work FF Columns 120 07-Apr-25* 24-Aug-25 Shuttering Work FF Columns
A2680 Concreting Work FF Columns 122 12-Apr-25* 31-Aug-25 Concreting Work FF Columns
A2690 Shuttering Work for FF Beams and Slab 124 16-Apr-25* 07-Sep-25 Shuttering Work for FF Beams and Slab
A2700 Steel Work for FF Beams and Slab 124 22-Apr-25* 14-Sep-25 Steel Work for FF Beams and Slab
A2710 Concreting Work for FF Beams and Slab 120 27-Apr-25* 14-Sep-25 Concreting Work for FF Beams and Slab
A2720 Deshuttering Work for FF Beam and Slab 120 27-Apr-25* 14-Sep-25 Deshuttering Work for FF Beam and Slab
A2721 Ramps and Planters Work 160 24-Feb-25* 28-Aug-25 Ramps and Planters Work
A2722 Block Work GF 115 04-May-25* 14-Sep-25 Block Work GF
A2723 Block Work FF 70 11-Sep-25* 01-Dec-25 Block Work FF
A2730 Parapet Wall Work 100 27-Apr-25* 21-Aug-25 Parapet Wall Work
A2731 GRC Mesh Work 90 27-Aug-25* 09-Dec-25 GRC Mesh Work
A2740 Screed in Slope on Roof Slabs 70 07-May-25* 28-Jul-25 Screed in Slope on Roof Slabs
A2750 Bitumenous Primer Coat 50 10-Jun-25* 06-Aug-25 Bitumenous Primer Coat
A2760 Reinforced Water Proofing Memberane Work 50 06-Jul-25* 02-Sep-25 Reinforced Water Proofing Memberane Work
A4290 Thermal Insulation Work 45 24-Jul-25* 14-Sep-25 Thermal Insulation Work
A4300 Sand Fillings 50 14-Aug-25* 11-Oct-25 Sand Fillings
A4310 Sand Cement Mortor Work 52 01-Sep-25* 30-Oct-25 Sand Cement Mortor Work
A4320 Roof Tiles Work 55 10-Sep-25* 12-Nov-25 Roof Tiles Work
A4330 Skirting Work 60 16-Oct-25* 24-Dec-25 Skirting Work
A6020 Combo System Option for Activity A2750-A4290 83 10-Jun-25* 14-Sep-25 Combo System Option for Activity A2750-A4290
EWF-HI.3.5.1.2 Finishes Work 177 23-Aug-25 17-Mar-26 17-Mar-26, EWF-HI.3.5.1.2 Finishes Work
A2930 Internal Plaster Work 120 23-Aug-25* 08-Jan-26 Internal Plaster Work
A2940 External Plaster Work 120 23-Aug-25* 08-Jan-26 External Plaster Work
A2950 Internal Floor Tiles For Rooms 110 09-Sep-25* 15-Jan-26 Internal Floor Tiles For Rooms
A2960 AntiSlip tile Work in Wet Areas 108 16-Sep-25* 19-Jan-26 AntiSlip tile Work in Wet Areas
A2961 Skirting and Wall tiles Work 108 21-Sep-25* 25-Jan-26 Skirting and Wall tiles Work
A2970 Staircase Steps & Enterance Tiling Work 109 01-Oct-25* 04-Feb-26 Staircase Steps & Enterance Tiling Work
A2980 Ceramic Tile Work 112 02-Oct-25* 09-Feb-26 Ceramic Tile Work
A2990 Internal Paint Work 112 06-Oct-25* 12-Feb-26 Internal Paint Work
A3000 External Paint Work 113 11-Oct-25* 18-Feb-26 logistic External Paint Work
constraint
A3010 Internal External Cladding Work 115 20-Oct-25* 02-Mar-26 Internal External Cladding Work
because of the
A3020 Internal External Decorative Work 111 30-Oct-25* 08-Mar-26 weather Internal External Decorative Work
A3030 Supply fabricate and installation of Kitchen Stage & Stage Korean Top 90 25-Nov-25* 10-Mar-26 Supply fabricate and installation of Kitchen Stage & Stage Korean Top
A3040 Gas Cylinder Stage 80 14-Dec-25* 17-Mar-26 Gas Cylinder Stage
EWF-HI.3.5.1.4 Sanitaryware, Fittings and Installations 344 20-Mar-25 25-Apr-26 25-Apr-26, EWF-HI.3.5.1.4 Sanitaryware, Fittings and Installations
A3200 UPVC pipes including all joints & accessories and brackets 133 20-Mar-25* 21-Aug-25 UPVC pipes including all joints & accessories and brackets
A3210 Sanitary Fittings and Valves Work 191 17-Apr-25* 25-Nov-25 Sanitary Fittings and Valves Work
A3220 Sanitaryware Installations 130 25-Nov-25* 25-Apr-26 Sanitaryware Installations
EWF-HI.3.5.1.1 Doors and Windows Work 145 11-Nov-25 28-Apr-26 28-Apr-26, EWF-HI.3.5.1.1 Doors and Windows Work
A2770 Wooden Doors Work 122 11-Nov-25* 01-Apr-26 Wooden Doors Work
A2780 UPVC Doors Work 122 17-Nov-25* 08-Apr-26 UPVC Doors Work
A2790 Windows & Ventilators Work 120 25-Nov-25* 13-Apr-26 Windows & Ventilators Work
A2800 WPC Work 116 09-Dec-25* 22-Apr-26 WPC Work
A2810 Ironmongry Work 70 07-Feb-26* 28-Apr-26 Ironmongry Work
EWF-HI.3.5.1.5 Water Supply & Drainage 263 07-Jul-25 09-May-26 09-May-26, EWF-HI.3.5.1.5 Water Supply & Drainage
A3440 Cold and Hot water pipes with insulation 68 07-Jul-25* 23-Sep-25 Cold and Hot water pipes with insulation
A3450 Cold and Hot water Valves 73 13-Sep-25* 07-Dec-25 Cold and Hot water Valves
A3460 Water Tank & Heater Installation 49 02-Nov-25* 29-Dec-25 Water Tank & Heater Installation
A3470 Booster Pump Installation 49 17-Nov-25* 13-Jan-26 Booster Pump Installation
A3480 Booster Pump Installation 49 13-Jan-26* 11-Mar-26 Booster Pump Installation
A3490 Rain Water UPVC Pipes & Drainage Work 50 13-Jan-26* 12-Mar-26 Rain Water UPVC Pipes & Drainage Work
A3500 Gas Line Work 49 12-Mar-26* 09-May-26 Gas Line Work
EWF-HI.3.5.1.6 Fire Fighting Installations 87 02-Nov-25 11-Feb-26 11-Feb-26, EWF-HI.3.5.1.6 Fire Fighting Installations
A3510 Supply and Installation of Complete fire fighting System as per civil defence Approval 58 02-Nov-25 08-Jan-26 Supply and Installation of Complete fire fighting System as per civil defence Approv
A3520 Fire hose reel With All Accessories 51 30-Nov-25* 28-Jan-26 Fire hose reel With All Accessories
A3530 fire blanket, Carbon dioxide fire extinguisher 51 07-Dec-25* 04-Feb-26 fire blanket, Carbon dioxide fire extinguisher
A3540 Automatic Multi detector point 51 14-Dec-25* 11-Feb-26 Automatic Multi detector point
EWF-HI.3.5.1.7 Air Conditioning & Mechanical Installations 61 14-Feb-26 25-Apr-26 25-Apr-26, EWF-HI.3.5.1.7 Air Conditioning & Mechanical Installatio
A3560 Installation of Wall Mounted ACs with DX units 61 14-Feb-26 25-Apr-26 Installation of Wall Mounted ACs with DX units
EWF-HI.3.5.1.8 Electrical Work 204 19-Nov-25 14-Jul-26 14-Jul-26, EWF-HI.3.5.1.8 Electrical Work
A3590 Cable Work 50 19-Nov-25* 15-Jan-26 Cable Work
A3600 Distribution Boards Work 55 19-Nov-25* 21-Jan-26 Distribution Boards Work
A3610 Earthing Work 60 17-Dec-25* 24-Feb-26 Earthing Work
A3620 Small Power Accessories and cable and Conduits Installation 80 23-Dec-25* 26-Mar-26 Small Power Accessories and cable and Conduits Installation
A3630 Lighting Accessories and cable and conduits installation 85 28-Dec-25* 05-Apr-26 Lighting Accessories and cable and conduits installation
A3640 Lighting Fixture 82 04-Feb-26* 10-May-26 Lighting Fixture
A3650 Ceiling fan 90 25-Feb-26* 09-Jun-26 Ceiling fan
A3660 Chandelier 75 25-Mar-26* 21-Jun-26 Chandelier
A3670 Wall mounted exhaust fan 80 12-Apr-26* 14-Jul-26 Wall mounted exhaust fan
EWF-HI.3.5.1.9 TV, Data and CCTV System 141 04-Feb-26 18-Jul-26 18-Jul-26, EWF-HI.3.5.1.9 TV, Data and CCTV System
A3710 Cable and conduit to TV point in concealed installation from satellite 50 04-Feb-26* 02-Apr-26 Cable and conduit to TV point in concealed installation from satellite
A3720 Flush mounted TV Satellite outlet 50 21-Feb-26* 20-Apr-26 Flush mounted TV Satellite outlet
A3730 Co axial cable in concealed conduit from dish antenna to satellite switcher 70 08-Mar-26* 27-May-26 Co axial cable in concealed conduit from dish antenna to satellit
A3740 TV System Installation 65 15-Apr-26* 29-Jun-26 TV System Installation
A3750 Data System Installation 60 02-May-26* 11-Jul-26 Data System Installation
A3760 CCTV System Installation 54 17-May-26* 18-Jul-26 CCTV System Installation
EWF-HI.3.5.10 External Works 245 11-Oct-25 22-Jul-26 22-Jul-26, EWF-HI.3.5.10 External Works
A4340 Site Prepartion 90 11-Oct-25 22-Jan-26 Site Prepartion
A4350 Demarcation for compound wall and septic tank 80 28-Oct-25* 28-Jan-26 Demarcation for compound wall and septic tank
A4360 Excavation compound wall and septic tank 90 09-Nov-25* 22-Feb-26 Excavation compound wall and septic tank
A4370 Foundation Work for compound wall and septic tank 120 23-Nov-25* 11-Apr-26 Foundation Work for compound wall and septic tank
A4380 Coloumns Work compound wall and septic tank 120 08-Dec-25* 26-Apr-26 Coloumns Work compound wall and septic tank
A4390 Block Work compound wall and septic tank 136 24-Dec-25* 01-Jun-26 Block Work compound wall and septic tank
A4391 Covering Slab for Septic tank 120 24-Jan-26* 11-Jun-26 Covering Slab for Septic tank
A4392 Electro-Mechanical Works in compound area and Inatallations 125 24-Jan-26* 17-Jun-26 Electro-Mechanical Works in compound area and Inatallation
A4400 Car Entrance and Wicket Gate 126 28-Jan-26* 23-Jun-26 Car Entrance and Wicket Gate
A4410 Curb Stone Work 90 23-Mar-26* 05-Jul-26 Curb Stone Work
A4420 External Interlock Work 94 01-Apr-26* 19-Jul-26 External Interlock Work
A4430 Design & Build Solar Panel Canopy 245 11-Oct-25 22-Jul-26 Design & Build Solar Panel Canopy
EWF-HI.2 Maintenance of Existing 1-12/29 Housing Units 222 30-Sep-24 16-Jun-25 16-Jun-25, EWF-HI.2 Maintenance of Existing 1-12/29 Housing Units
A1110 Maintain Exiting Aluminium Windows 69 19-Nov-24* 06-Feb-25 Maintain Exiting Aluminium Windows
EWF-HI.2.1.7 Sanitary Wares & Installations 167 03-Dec-24 16-Jun-25 16-Jun-25, EWF-HI.2.1.7 Sanitary Wares & Installations
A1200 Remove all sanitary that were fixed 35 18-Dec-24* 28-Jan-25 Remove all sanitary that were fixed
A1210 Supply and install Vent cowl 30 28-Jan-25* 04-Mar-25 Supply and install Vent cowl
A1220 Floor Drain trap 35 27-Feb-25* 08-Apr-25 Floor Drain trap
A1230 Gully Trap 10 03-Dec-24 15-Dec-24 Gully Trap
A2210 Semi pedestal wash basin 10 28-Jan-25* 09-Feb-25 Semi pedestal wash basin
A2220 Stainless Steel Sink 10 09-Feb-25* 20-Feb-25 Stainless Steel Sink
A2230 European Water Closet 10 20-Feb-25* 04-Mar-25 European Water Closet
A2240 shower tray 12 04-Mar-25* 18-Mar-25 shower tray
A2250 Ablution Faucet 15 18-Mar-25* 05-Apr-25 Ablution Faucet
A2260 shower Mixer 12 05-Apr-25* 19-Apr-25 shower Mixer
A2270 Wash Basin Mixer 13 19-Apr-25* 04-May-25 Wash Basin Mixer
A2280 Sink Mixer 12 04-May-25* 18-May-25 Sink Mixer
A2290 Toilet tissue holder 12 18-May-25* 01-Jun-25 Toilet tissue holder
A2300 Towel rail 12 01-Jun-25* 15-Jun-25 Towel rail
A2310 Mirror 13 01-Jun-25* 16-Jun-25 Mirror
EWF-HI.2.1.8 Water Supply & Rain Water Installations 107 21-Jan-25 25-May-25 25-May-25, EWF-HI.2.1.8 Water Supply & Rain Water Installations
A1160 Pressure Test and Replace defects/Polypropylene random copolymer pipe 30 21-Jan-25* 24-Feb-25 Pressure Test and Replace defects/Polypropylene random copolymer pipe
A1170 Cold and Hot water Valves 35 03-Feb-25* 15-Mar-25 Cold and Hot water Valves
A1180 Remove of all Equipment and Accessories that were fixed 30 18-Feb-25* 24-Mar-25 Remove of all Equipment and Accessories that were fixed
A1190 Water Tank Including Connection and Accessories 35 27-Feb-25* 09-Apr-25 Water Tank Including Connection and Accessories
A2390 Water Heater Connection and Accessories 35 06-Mar-25* 16-Apr-25 Water Heater Connection and Accessories
A2400 Rain Water UPVC Pipeswith outlet 45 19-Mar-25* 11-May-25 Rain Water UPVC Pipeswith outlet
A2410 Tap and Ablution Faucet 31 20-Apr-25* 25-May-25 Tap and Ablution Faucet
EWF-HI.2.1.9 Electrical Installations 116 09-Jan-25 24-May-25 24-May-25, EWF-HI.2.1.9 Electrical Installations
A1120 Checking to Identify any issue in Existing Power Distribution System 5 11-Jan-25 16-Jan-25 Checking to Identify any issue in Existing Power Distribution System
A1130 Installtion of Solar system 116 09-Jan-25* 24-May-25 Installtion of Solar system
A1140 Replace the existing with new weatherproof IP 65 Main 15 16-Jan-25 03-Feb-25 Replace the existing with new weatherproof IP 65 Main
A1150 Small Power Accessories removing 10 03-Feb-25 15-Feb-25 Small Power Accessories removing
A2330 Small Power Accessories Installation 12 15-Feb-25 01-Mar-25 Small Power Accessories Installation
A2340 Small Power Lighting Fixture removing 12 01-Mar-25 15-Mar-25 Small Power Lighting Fixture removing
A2350 Small Power Lighting Fixture Installations 12 15-Mar-25 29-Mar-25 Small Power Lighting Fixture Installations
A2360 Ceiling Fan Installation with All Accessories 12 29-Mar-25 12-Apr-25 Ceiling Fan Installation with All Accessories
A2370 Earthing Installations 12 12-Apr-25 26-Apr-25 Earthing Installations
A2380 TV Points and Dish Installations 12 26-Apr-25 10-May-25 TV Points and Dish Installations
EWF-HI.2.1.10 Air Conditioning Work 56 06-Jan-25 11-Mar-25 11-Mar-25, EWF-HI.2.1.10 Air Conditioning Work
A1280 Remove all Equipments and Accessories Fixed Indoor/Outdoor 38 06-Jan-25* 18-Feb-25 Remove all Equipments and Accessories Fixed Indoor/Outdoor
A1290 Replace Wall mounted Split AC with DX unit 28 22-Jan-25* 23-Feb-25 Replace Wall mounted Split AC with DX unit
A1300 Install Wall mounted Split AC with DX unit In Kitchen With Connections 25 30-Jan-25* 27-Feb-25 Install Wall mounted Split AC with DX unit In Kitchen With Connections
A1310 Install Wall mounted Split AC with DX unit in Salah & Majles 22 09-Feb-25* 05-Mar-25 Install Wall mounted Split AC with DX unit in Salah & Majles
A2320 Replace the Existing Ventilation Fans 20 17-Feb-25* 11-Mar-25 Replace the Existing Ventilation Fans
EWF-HI.2.1.1 Partial Handing Over of 1-12/29 Units 60 17-Feb-25 27-Apr-25 27-Apr-25, EWF-HI.2.1.1 Partial Handing Over of 1-12/29 Units
A4440 Handingover of Drawings 20 17-Feb-25* 11-Mar-25 Handingover of Drawings
A4450 Handing Over of Material Approvals 15 12-Mar-25* 30-Mar-25 Handing Over of Material Approvals
A4460 Handing over of Waranty Guarantee Documents 10 30-Mar-25* 10-Apr-25 Handing over of Waranty Guarantee Documents
A4470 Handing Over of Inspection, Testing and Comissioning Reports 8 10-Apr-25* 20-Apr-25 Handing Over of Inspection, Testing and Comissioning Reports
A4480 Handingover of Keys 6 20-Apr-25* 27-Apr-25 Handingover of Keys
A4490 Progress Report Compliance with Invesntory and Sanglist 14 10-Apr-25* 26-Apr-25 Progress Report Compliance with Invesntory and Sanglist
EWF-HI.5 Maintenance of Existing 13-20/29 Housing Units 206 28-Apr-25 23-Dec-25 23-Dec-25, EWF-HI.5 Maintenance of Existing 13-20/29 Housing Units
A4650 Remove all sanitary that were fixed 28 11-Aug-25* 13-Sep-25 Remove all sanitary that were fixed
A4660 Supply and install Vent cowl 21 13-Sep-25* 07-Oct-25 Supply and install Vent cowl
A4670 Floor Drain trap 23 30-Jul-25* 26-Aug-25 Floor Drain trap
A4680 Gully Trap 8 21-Aug-25 31-Aug-25 Gully Trap
A5070 Semi pedestal wash basin 8 13-Sep-25* 22-Sep-25 Semi pedestal wash basin
A5080 Stainless Steel Sink 7 22-Sep-25* 30-Sep-25 Stainless Steel Sink
A5090 European Water Closet 8 30-Sep-25* 09-Oct-25 European Water Closet
A5100 shower tray 7 09-Oct-25* 18-Oct-25 shower tray
A5110 Ablution Faucet 9 18-Oct-25* 28-Oct-25 Ablution Faucet
A5120 shower Mixer 9 28-Oct-25* 08-Nov-25 shower Mixer
A5130 Wash Basin Mixer 9 08-Nov-25* 18-Nov-25 Wash Basin Mixer
A5140 Sink Mixer 9 18-Nov-25* 29-Nov-25 Sink Mixer
A5150 Toilet tissue holder 8 29-Nov-25* 08-Dec-25 Toilet tissue holder
A5160 Towel rail 7 08-Dec-25* 16-Dec-25 Towel rail
A5170 Mirror 8 08-Dec-25* 17-Dec-25 Mirror
EWF-HI.5.1.8 Water Supply & Rain Water Installations 56 31-Aug-25 04-Nov-25 04-Nov-25, EWF-HI.5.1.8 Water Supply & Rain Water Installations
A4610 Pressure Test and Replace defects/Polypropylene random copolymer pipe 30 31-Aug-25* 05-Oct-25 Pressure Test and Replace defects/Polypropylene random copolymer pipe
A4620 Cold and Hot water Valves 35 03-Sep-25* 14-Oct-25 Cold and Hot water Valves
A4630 Remove of all Equipment and Accessories that were fixed 30 14-Sep-25* 19-Oct-25 Remove of all Equipment and Accessories that were fixed
A4640 Water Tank Including Connection and Accessories 35 10-Sep-25* 21-Oct-25 Water Tank Including Connection and Accessories
A5250 Water Heater Connection and Accessories 35 17-Sep-25* 28-Oct-25 Water Heater Connection and Accessories
A5260 Rain Water UPVC Pipeswith outlet 45 10-Sep-25* 02-Nov-25 Rain Water UPVC Pipeswith outlet
A5270 Tap and Ablution Faucet 31 29-Sep-25* 04-Nov-25 Tap and Ablution Faucet
EWF-HI.5.1.9 Electrical Installations 116 05-Aug-25 17-Dec-25 17-Dec-25, EWF-HI.5.1.9 Electrical Installations
A4570 Checking to Identify any issue in Existing Power Distribution System 5 03-Sep-25* 09-Sep-25 Checking to Identify any issue in Existing Power Distribution System
A4580 Installtion of Solar system 90 05-Aug-25* 17-Nov-25 Installtion of Solar system
A4590 Replace the existing with new weatherproof IP 65 Main 15 09-Sep-25 27-Sep-25 Replace the existing with new weatherproof IP 65 Main
A4600 Small Power Accessories removing 10 27-Sep-25 08-Oct-25 Small Power Accessories removing
A5190 Small Power Accessories Installation 10 08-Oct-25 20-Oct-25 Small Power Accessories Installation
A5200 Small Power Lighting Fixture removing 11 20-Oct-25 02-Nov-25 Small Power Lighting Fixture removing
A5210 Small Power Lighting Fixture Installations 9 02-Nov-25 12-Nov-25 Small Power Lighting Fixture Installations
A5220 Ceiling Fan Installation with All Accessories 11 12-Nov-25 25-Nov-25 Ceiling Fan Installation with All Accessories
A5230 Earthing Installations 10 25-Nov-25 07-Dec-25 Earthing Installations
A5240 TV Points and Dish Installations 9 07-Dec-25 17-Dec-25 TV Points and Dish Installations
EWF-HI.5.1.10 Air Conditioning Work 68 27-Aug-25 15-Nov-25 15-Nov-25, EWF-HI.5.1.10 Air Conditioning Work
A4690 Remove all Equipments and Accessories Fixed Indoor/Outdoor 32 27-Aug-25* 04-Oct-25 Remove all Equipments and Accessories Fixed Indoor/Outdoor
A4700 Replace Wall mounted Split AC with DX unit 23 14-Sep-25* 09-Oct-25 Replace Wall mounted Split AC with DX unit
A4710 Install Wall mounted Split AC with DX unit In Kitchen With Connections 19 28-Sep-25* 19-Oct-25 Install Wall mounted Split AC with DX unit In Kitchen With Connections
A4720 Install Wall mounted Split AC with DX unit in Salah & Majles 18 15-Oct-25* 04-Nov-25 Install Wall mounted Split AC with DX unit in Salah & Majles
A5180 Replace the Existing Ventilation Fans 17 26-Oct-25* 15-Nov-25 Replace the Existing Ventilation Fans
EWF-HI.5.1.1 Partial Handing Over of 13-20/29 Units 67 07-Oct-25 23-Dec-25 23-Dec-25, EWF-HI.5.1.1 Partial Handing Over of 13-20/29 Units
A5290 Handingover of Drawings 20 07-Oct-25* 29-Oct-25 Handingover of Drawings
A5300 Handing Over of Material Approvals 15 08-Nov-25* 24-Nov-25 Handing Over of Material Approvals
A5310 Handing over of Waranty Guarantee Documents 10 25-Nov-25* 06-Dec-25 Handing over of Waranty Guarantee Documents
A5320 Handing Over of Inspection, Testing and Comissioning Reports 8 07-Dec-25* 15-Dec-25 Handing Over of Inspection, Testing and Comissioning Reports
A5330 Handingover of Keys 7 16-Dec-25* 23-Dec-25 Handingover of Keys
A5340 Progress Report Compliance with Invesntory and Sanglist 14 07-Dec-25* 22-Dec-25 Progress Report Compliance with Invesntory and Sanglist
EWF-HI.8 Maintenance of Existing 21-29/29 Housing Units 180 24-Dec-25 21-Jul-26 21-Jul-26, EWF-HI.8 Maintenance of Existing 21-29/29
EWF-HI.4 Storm Water and Drainage Work 494 21-Jan-25 19-Aug-26 19-Aug-26, EWF-HI.4 Storm Water and Drainage W
EWF-HI.4.4 Storm Water and Drainage Work (Re-Constructed Units) 424 21-Jan-25 31-May-26 31-May-26, EWF-HI.4.4 Storm Water and Drainage Work (Re-C
EWF-HI.4.4.1 Line 1 281 21-Jan-25 14-Dec-25 14-Dec-25, EWF-HI.4.4.1 Line 1
A3980 Survey and Marking for Line 1 85 21-Jan-25* 30-Apr-25 Survey and Marking for Line 1
A3990 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1 80 30-Apr-25 02-Aug-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1
A4000 Crosschecking of Levels 120 25-Feb-25* 15-Jul-25 Crosschecking of Levels
A4010 Bedding for Pipes with approved Material 90 22-Apr-25* 04-Aug-25 Bedding for Pipes with approved Material
A4030 Laying of Pipes and Welding 45 18-Jun-25* 10-Aug-25 Laying of Pipes and Welding
A4190 Testing 30 09-Jul-25* 12-Aug-25 Testing
A4200 Concreting Work for Pipes and till Transition Slab 60 03-Aug-25* 11-Oct-25 Concreting Work for Pipes and till Transition Slab
A4210 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 24-Aug-25* 25-Nov-25 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin
A6200 Pre-Cast Concrete Cover Slab Work 20 02-Nov-25 25-Nov-25 Pre-Cast Concrete Cover Slab Work
A6210 Backfilling & Compaction 40 12-Oct-25* 26-Nov-25 Backfilling & Compaction
A6220 Block Work With Ring for Opening and Grating 35 01-Nov-25* 11-Dec-25 Block Work With Ring for Opening and Grating
A6230 Connections with Existing Network 15 27-Nov-25* 14-Dec-25 Connections with Existing Network
EWF-HI.4.4.2 Line 1-1 259 30-Apr-25 26-Feb-26 26-Feb-26, EWF-HI.4.4.2 Line 1-1
A6240 Survey and Marking for Line 1-1 85 30-Apr-25* 07-Aug-25 Survey and Marking for Line 1-1
A6250 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1 80 07-Aug-25 09-Nov-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1
A6260 Crosschecking of Levels 120 15-Jul-25* 02-Dec-25 Crosschecking of Levels
A6270 Bedding for Pipes with approved Material 90 05-Aug-25* 17-Nov-25 Bedding for Pipes with approved Material
A6280 Laying of Pipes and Welding 45 10-Aug-25* 01-Oct-25 Laying of Pipes and Welding
A6290 Testing 30 13-Aug-25* 16-Sep-25 Testing
A6300 Concreting Work for Pipes and till Transition Slab 60 12-Oct-25* 20-Dec-25 Concreting Work for Pipes and till Transition Slab
A6310 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 25-Nov-25* 26-Feb-26 Chamber Including Reinforcement and Concreting with Connection from Cat
A6320 Pre-Cast Concrete Cover Slab Work 20 03-Feb-26 26-Feb-26 Pre-Cast Concrete Cover Slab Work
A6330 Backfilling & Compaction 40 27-Nov-25* 12-Jan-26 Backfilling & Compaction
A6340 Block Work With Ring for Opening and Grating 35 11-Dec-25* 21-Jan-26 Block Work With Ring for Opening and Grating
A6350 Connections with Existing Network 15 12-Jan-26* 28-Jan-26 Connections with Existing Network
EWF-HI.4.4.3 Line 1-1-6 254 07-Aug-25 31-May-26 31-May-26, EWF-HI.4.4.3 Line 1-1-6
A6360 Survey and Marking for Line 1-1-6 85 07-Aug-25* 15-Nov-25 Survey and Marking for Line 1-1-6
A6370 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6 80 15-Nov-25 16-Feb-26 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6
A6380 Crosschecking of Levels 120 02-Dec-25* 21-Apr-26 Crosschecking of Levels
A6390 Bedding for Pipes with approved Material 90 02-Dec-25* 17-Mar-26 Bedding for Pipes with approved Material
A6400 Laying of Pipes and Welding 45 15-Nov-25* 06-Jan-26 Laying of Pipes and Welding
A6410 Testing 30 15-Nov-25* 20-Dec-25 Testing
A6420 Concreting Work for Pipes and till Transition Slab 60 21-Dec-25* 28-Feb-26 Concreting Work for Pipes and till Transition Slab
A6430 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 26-Feb-26* 31-May-26 Chamber Including Reinforcement and Concreting with Connect
A6440 Pre-Cast Concrete Cover Slab Work 20 07-May-26 31-May-26 Pre-Cast Concrete Cover Slab Work
A6450 Backfilling & Compaction 40 26-Feb-26* 14-Apr-26 Backfilling & Compaction
A6460 Block Work With Ring for Opening and Grating 35 08-Mar-26* 16-Apr-26 Block Work With Ring for Opening and Grating
A6470 Connections with Existing Network 15 09-Apr-26* 26-Apr-26 Connections with Existing Network
EWF-HI.4.1 Storm Water and Drainage Work (Maintenance Units) 441 08-Feb-25 06-Jul-26 06-Jul-26, EWF-HI.4.1 Storm Water and Drainage Work (M
EWF-HI.4.1.1 Line 2 266 08-Feb-25 14-Dec-25 14-Dec-25, EWF-HI.4.1.1 Line 2
A6480 Survey and Marking for Line 1 85 08-Feb-25* 17-May-25 Survey and Marking for Line 1
A6490 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1 80 18-May-25 18-Aug-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1
A6500 Crosschecking of Levels 120 08-Mar-25* 24-Jul-25 Crosschecking of Levels
A6510 Bedding for Pipes with approved Material 90 22-Apr-25* 04-Aug-25 Bedding for Pipes with approved Material
A6520 Laying of Pipes and Welding 45 18-Jun-25* 10-Aug-25 Laying of Pipes and Welding
A6530 Testing 30 09-Jul-25* 12-Aug-25 Testing
A6540 Concreting Work for Pipes and till Transition Slab 60 03-Aug-25* 11-Oct-25 Concreting Work for Pipes and till Transition Slab
A6550 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 24-Aug-25* 25-Nov-25 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin
A6560 Pre-Cast Concrete Cover Slab Work 20 02-Nov-25 25-Nov-25 Pre-Cast Concrete Cover Slab Work
A6570 Backfilling & Compaction 40 12-Oct-25* 26-Nov-25 Backfilling & Compaction
A6580 Block Work With Ring for Opening and Grating 35 01-Nov-25* 11-Dec-25 Block Work With Ring for Opening and Grating
A6590 Connections with Existing Network 15 27-Nov-25* 14-Dec-25 Connections with Existing Network
EWF-HI.4.1.2 Line 2-4 245 18-May-25 26-Feb-26 26-Feb-26, EWF-HI.4.1.2 Line 2-4
A6600 Survey and Marking for Line 1-1 85 18-May-25* 24-Aug-25 Survey and Marking for Line 1-1
A6610 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1 80 25-Aug-25 25-Nov-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1
A6620 Crosschecking of Levels 120 26-Jul-25* 11-Dec-25 Crosschecking of Levels
A6630 Bedding for Pipes with approved Material 90 05-Aug-25* 17-Nov-25 Bedding for Pipes with approved Material
A6640 Laying of Pipes and Welding 45 25-Aug-25* 15-Oct-25 Laying of Pipes and Welding
A6650 Testing 30 25-Aug-25* 28-Sep-25 Testing
A6660 Concreting Work for Pipes and till Transition Slab 60 12-Oct-25* 20-Dec-25 Concreting Work for Pipes and till Transition Slab
A6670 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 25-Nov-25* 26-Feb-26 Chamber Including Reinforcement and Concreting with Connection from Cat
A6680 Pre-Cast Concrete Cover Slab Work 20 03-Feb-26 26-Feb-26 Pre-Cast Concrete Cover Slab Work
A6690 Backfilling & Compaction 40 27-Nov-25* 12-Jan-26 Backfilling & Compaction
A6700 Block Work With Ring for Opening and Grating 35 11-Dec-25* 21-Jan-26 Block Work With Ring for Opening and Grating
A6710 Connections with Existing Network 15 12-Jan-26* 28-Jan-26 Connections with Existing Network
EWF-HI.4.1.3 Line 2-4-3 & 2-4-5 256 11-Sep-25 06-Jul-26 06-Jul-26, EWF-HI.4.1.3 Line 2-4-3 & 2-4-5
A6720 Survey and Marking for Line 1-1-6 85 11-Sep-25* 20-Dec-25 Survey and Marking for Line 1-1-6
A6730 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6 80 20-Dec-25 23-Mar-26 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6
A6740 Crosschecking of Levels 120 13-Dec-25* 30-Apr-26 Crosschecking of Levels
A6750 Bedding for Pipes with approved Material 90 17-Jan-26* 30-Apr-26 Bedding for Pipes with approved Material
A6760 Laying of Pipes and Welding 45 10-Mar-26* 02-May-26 Laying of Pipes and Welding
A6770 Testing 30 05-Apr-26* 09-May-26 Testing
A6780 Concreting Work for Pipes and till Transition Slab 60 05-Apr-26* 13-Jun-26 Concreting Work for Pipes and till Transition Slab
A6790 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 05-Apr-26* 06-Jul-26 Chamber Including Reinforcement and Concreting with Con
A6800 Pre-Cast Concrete Cover Slab Work 20 14-Jun-26 06-Jul-26 Pre-Cast Concrete Cover Slab Work
A6810 Backfilling & Compaction 40 13-Apr-26* 30-May-26 Backfilling & Compaction
A6820 Block Work With Ring for Opening and Grating 35 22-Apr-26* 01-Jun-26 Block Work With Ring for Opening and Grating
A6830 Connections with Existing Network 15 20-May-26* 07-Jun-26 Connections with Existing Network
EWF-HI.4.2 Protection Work 377 07-Jun-25 19-Aug-26 19-Aug-26, EWF-HI.4.2 Protection Work
EWF-HI.4.2.2 Establishment of Dyke 1 Near Existing Dyke 117 20-Dec-25 04-May-26 04-May-26, EWF-HI.4.2.2 Establishment of Dyke 1 Near Existing D
A6840 Survey and Existing levels of the location 20 20-Dec-25 12-Jan-26 Survey and Existing levels of the location
A6850 Filling Material to Establish Dyke 1 in layers 90 20-Dec-25 04-Apr-26 Filling Material to Establish Dyke 1 in layers
A6860 Compaction of material in layers and slopes 80 06-Jan-26* 09-Apr-26 Compaction of material in layers and slopes
A6870 Final Inspection of the Dype 1 80 01-Feb-26* 04-May-26 Final Inspection of the Dype 1
EWF-HI.4.2.3 Establishement of Dyke 2 151 29-Jan-26 23-Jul-26 23-Jul-26, EWF-HI.4.2.3 Establishement of Dyke 2
A6890 Survey and Existing levels of the location 15 29-Jan-26* 15-Feb-26 Survey and Existing levels of the location
A6900 filling the material as per approved/excavated material 80 04-Apr-26 06-Jul-26 filling the material as per approved/excavated material
A6910 Compaction of material in layers and slopes 70 27-Apr-26* 16-Jul-26 Compaction of material in layers and slopes
A6920 Filling the material up to the proposed level 65 05-May-26* 20-Jul-26 Filling the material up to the proposed level
A6930 Final Inspection of the Dyke 2 2 20-Jul-26 22-Jul-26 Final Inspection of the Dyke 2
A6980 Handing Over with Related Dcoments 1 22-Jul-26 23-Jul-26 Handing Over with Related Dcoments
EWF-HI.4.2.4 Rehaping of Proposed Wadi 139 16-Feb-26 27-Jul-26 27-Jul-26, EWF-HI.4.2.4 Rehaping of Proposed Wadi
A6940 Survey to take initial levels 25 16-Feb-26 16-Mar-26 Survey to take initial levels
A6950 Proposed levels to maintain the flow 15 16-Feb-26* 04-Mar-26 Proposed levels to maintain the flow
A6960 Cutting and Filling Work 80 04-Apr-26 06-Jul-26 Cutting and Filling Work
A6970 Dressing of the Sides and Compaction 75 30-Apr-26* 26-Jul-26 Dressing of the Sides and Compaction
A6990 Handing Over with Related Dcoments 1 27-Jul-26 27-Jul-26 Handing Over with Related Dcoments
EWF-HI.4.2.1 Concrete Work/Box Curvert 326 07-Jun-25 22-Jun-26 22-Jun-26, EWF-HI.4.2.1 Concrete Work/Box Curvert
A4080 Box culvert N2 Size 2x1.5m concrete class Blinding C15 200 07-Jun-25* 26-Jan-26 Box culvert N2 Size 2x1.5m concrete class Blinding C15
A4090 Concrete Class 35 in box culverts wing walls apron slab 166 06-Sep-25* 17-Mar-26 Concrete Class 35 in box culverts wing walls apron slab
A4100 Concrete Class 35 in box culverts Retaining walls 150 25-Oct-25* 16-Apr-26 Concrete Class 35 in box culverts Retaining walls
A4110 Reinforcement as per HDS 2017 104 18-Jan-26* 18-May-26 Reinforcement as per HDS 2017
A4120 High tensile steel bar factory epoxy coated reinforcement 50 25-Apr-26* 22-Jun-26 High tensile steel bar factory epoxy coated reinforcement
EWF-HI.4.2.5 Bitumen/Asphalt Work 161 26-Jan-26 01-Aug-26 01-Aug-26, EWF-HI.4.2.5 Bitumen/Asphalt Work
A3940 2 Coats of Bitumen Paint for concrete structure 35 26-Jan-26 08-Mar-26 2 Coats of Bitumen Paint for concrete structure
A3950 4mm Geotextile Memberane for concrete structure 25 09-Feb-26* 10-Mar-26 4mm Geotextile Memberane for concrete structure
A3960 Subgrade Sub Base work 45 15-Mar-26* 05-May-26 Subgrade Sub Base work
A3970 Bituminous Prime Coat Application rate 1.5 KgSq.m 40 06-May-26 21-Jun-26 Bituminous Prime Coat Application rate 1.5 KgSq.m
A4040 Bituminous Wearing Course Class B 35 22-Jun-26 01-Aug-26 Bituminous Wearing Course Class B
EWF-HI.4.2.6 Slope Protection & Stabilization Work 120 02-Apr-26 19-Aug-26 19-Aug-26, EWF-HI.4.2.6 Slope Protection & Stabili
A7000 Levelling and Compaction of the slopes 40 02-Apr-26* 18-May-26 Levelling and Compaction of the slopes
A7010 Mortard Riprap work including filter memberance 50 19-May-26 15-Jul-26 Mortard Riprap work including filter memberance
A7020 finishing work and cleaning 30 16-Jul-26 19-Aug-26 finishing work and cleaning
A4220 Demobilization of Machinery & Equipment 15 02-Aug-26* 18-Aug-26 Demobilization of Machinery & Equipment
A4230 Engineering Facility 15 19-Aug-26 05-Sep-26 Engineering Facility
A4240 Successive/Completion Certificate 12 06-Sep-26 19-Sep-26 Successive/Completion Certificate
A4260 Project Signout Document 5 14-Sep-26 19-Sep-26 Project Signout Document
EWF-HI.6 Project Handing Over 98 09-Jun-26 30-Sep-26 30-Sep-26, EWF-HI.6 Project Handing Over