0% found this document useful (0 votes)
10 views

Construction Program Revision V 30 June 2024

Uploaded by

planner.ahar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

Construction Program Revision V 30 June 2024

Uploaded by

planner.ahar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT.

2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

30-Sep-26, EWF-HI Construction, Completion a


EWF-HI Construction, Completion and Maintenance of (20 NOS) Housing729 03-Jun-24
Units 30-Sep-26
and Miantenance work for the Exis
EWF-HI.1 Preliminaries & Mobilization 103 03-Jun-24
120 30-Sep-24 30-Sep-24, EWF-HI.1 Preliminaries & Mobilization

MO1000 Construction Program (Revision 3) 14 03-Jun-24* 18-Jun-24 Construction Program (Revision 3)


MO1010 Material Approval Schedule (Revised) 30 06-Jun-24* 10-Jul-24 Material Approval Schedule (Revised)
MO1030 Construction Methodology (Submitted) 20 20-Jun-24* 13-Jul-24 Construction Methodology (Submitted)
MO1040 Vendors Approval List (Revised) 35 12-Jun-24* 22-Jul-24 Vendors Approval List (Revised)
MO1050 Sub Contractors Approval List (Revised) 35 12-Jun-24* 22-Jul-24 Sub Contractors Approval List (Revised)
MO1060 Machinery List (Revised) 40 06-Jul-24* 20-Aug-24 Machinery List (Revised)
MO1070 Manpower List (Revised) 69 23-Jun-24* 10-Sep-24 Manpower List (Revised)
MO1110 Layout of Engineering Facilities 81 20-Jun-24* 22-Sep-24 Layout of Engineering Facilities
MO1120 Approval of the Project Sign Board (Approved & Installed) 80 26-Jun-24* 26-Sep-24 Approval of the Project Sign Board (Approved & Installed)
MO1130 Site Handover 3 26-Sep-24* 30-Sep-24 Site Handover
MO1160 Movement of the Machinery and Equipments to site 67 06-Jul-24* 21-Sep-24 Movement of the Machinery and Equipments to site
MO1170 Installation management of labour facilities at site 21 07-Sep-24* 30-Sep-24 Installation management of labour facilities at site

EWF-HI.3 Construction of 23 Housing Units 566 01-Oct-24 22-Jul-26 22-Jul-26, EWF-HI.3 Construction of 23 Housing Units

EWF-HI.3.1 Demolition Work 104 01-Oct-24 29-Jan-25 29-Jan-25, EWF-HI.3.1 Demolition Work
A2470 Demolition of Housing Units 100 01-Oct-24* 25-Jan-25 Demolition of Housing Units
A2480 Disposal & Site Clearance 80 28-Oct-24* 28-Jan-25 Disposal & Site Clearance
A3680 Survey, Layout and Marking 81 28-Oct-24* 29-Jan-25 Survey, Layout and Marking
EWF-HI.3.5 Construction Work 23 Housing Units 543 28-Oct-24 22-Jul-26 22-Jul-26, EWF-HI.3.5 Construction Work 23 Housing U
EWF-HI.3.5.2 Sub Structure Work 167 28-Oct-24 10-May-25 10-May-25, EWF-HI.3.5.2 Sub Structure Work
A1780 Demarcation 85 28-Oct-24* 03-Feb-25 Demarcation
A1790 Excavation 90 28-Oct-24* 09-Feb-25 Excavation
A1800 Levelling and Compaction of Earth 90 30-Oct-24* 11-Feb-25 Levelling and Compaction of Earth
A1810 PCC Work 90 02-Nov-24* 13-Feb-25 PCC Work
A1820 Settingout for Footings 90 05-Nov-24* 17-Feb-25 Settingout for Footings
A1830 Steel Work for Footing 90 09-Nov-24* 20-Feb-25 Steel Work for Footing
A1840 Shuttering Work for Footing 90 13-Nov-24* 25-Feb-25 Shuttering Work for Footing
A2490 Concreting Work & Curing for Footing 90 16-Nov-24* 27-Feb-25 Concreting Work & Curing for Footing
A2500 Deshuttering - Footing Work 92 20-Nov-24* 06-Mar-25 Deshuttering - Footing Work
A2510 Steel Work for Short Columns 88 26-Nov-24* 09-Mar-25 Steel Work for Short Columns
A2520 Shuttering Work for Short Columns 85 05-Dec-24* 13-Mar-25 Shuttering Work for Short Columns
A2530 Concreting Work curing for Short Columns 88 05-Dec-24* 17-Mar-25 Concreting Work curing for Short Columns
A2540 Deshuttering for Short Columns 90 05-Dec-24* 19-Mar-25 Deshuttering for Short Columns
A2550 Solid Block Work 95 05-Dec-24* 25-Mar-25 Solid Block Work
A3700 Steel Work for Plinth Beam 90 11-Dec-24* 26-Mar-25 Steel Work for Plinth Beam
A3860 Shuttering Work for Plinth Beam 90 21-Dec-24* 03-Apr-25 Shuttering Work for Plinth Beam
A3900 Concreting work & Curing for Plinth Beam 80 04-Jan-25* 06-Apr-25 Concreting work & Curing for Plinth Beam
A3910 Deshuttering for Plinth Beam 76 15-Jan-25* 13-Apr-25 Deshuttering for Plinth Beam
A3920 Bitumen Paint Work 77 18-Jan-25* 16-Apr-25 Bitumen Paint Work
A3930 Backfilling Work 77 21-Jan-25* 20-Apr-25 Backfilling Work
A4050 Earth Compaction and MEP Sleeves Work 78 26-Jan-25* 26-Apr-25 Earth Compaction and MEP Sleeves Work
A4060 Anti-Termite Treatment 79 27-Jan-25* 29-Apr-25 Anti-Termite Treatment
A4070 Polythene Sheet 79 28-Jan-25* 29-Apr-25 Polythene Sheet
A4270 BRC Mesh Work 80 30-Jan-25* 03-May-25 BRC Mesh Work
A4280 Concreting Work 81 05-Feb-25* 10-May-25 Concreting Work
EWF-HI.3.5.1 Super Structure Work 437 24-Feb-25 18-Jul-26 18-Jul-26, EWF-HI.3.5.1 Super Structure Work
EWF-HI.3.5.1.3 Civil Work 261 24-Feb-25 24-Dec-25 24-Dec-25, EWF-HI.3.5.1.3 Civil Work
A2560 Settingout for Columns 120 24-Feb-25* 13-Jul-25 Settingout for Columns
A2570 Steel Work for Columns 124 24-Feb-25* 17-Jul-25 Steel Work for Columns
A2580 Shuttering Work for Columns 127 24-Feb-25* 21-Jul-25 Shuttering Work for Columns
A2590 Concreting Work for Columns 118 11-Mar-25* 27-Jul-25 Concreting Work for Columns
A2600 Deshuttering and Curing Work for Columns 120 11-Mar-25* 29-Jul-25 Deshuttering and Curing Work for Columns
A2610 Shuttering Work for GF Slab and Beams 122 11-Mar-25* 31-Jul-25 Shuttering Work for GF Slab and Beams
A2620 Steel Work GF Slab and Beams 120 11-Mar-25* 29-Jul-25 Steel Work GF Slab and Beams
A2630 Concreting Work GF Slab and Beams 123 13-Mar-25* 03-Aug-25 Concreting Work GF Slab and Beams
A2640 Curing Work GF Slab and Beams 124 16-Mar-25* 06-Aug-25 Curing Work GF Slab and Beams
A2650 Settingout for Staircase Tower Columns 120 23-Mar-25* 09-Aug-25 Settingout for Staircase Tower Columns
A2660 Steel Work For FF Columns 118 30-Mar-25* 13-Aug-25 Steel Work For FF Columns
A2670 Shuttering Work FF Columns 120 07-Apr-25* 24-Aug-25 Shuttering Work FF Columns
A2680 Concreting Work FF Columns 122 12-Apr-25* 31-Aug-25 Concreting Work FF Columns
A2690 Shuttering Work for FF Beams and Slab 124 16-Apr-25* 07-Sep-25 Shuttering Work for FF Beams and Slab
A2700 Steel Work for FF Beams and Slab 124 22-Apr-25* 14-Sep-25 Steel Work for FF Beams and Slab
A2710 Concreting Work for FF Beams and Slab 120 27-Apr-25* 14-Sep-25 Concreting Work for FF Beams and Slab
A2720 Deshuttering Work for FF Beam and Slab 120 27-Apr-25* 14-Sep-25 Deshuttering Work for FF Beam and Slab
A2721 Ramps and Planters Work 160 24-Feb-25* 28-Aug-25 Ramps and Planters Work
A2722 Block Work GF 115 04-May-25* 14-Sep-25 Block Work GF
A2723 Block Work FF 70 11-Sep-25* 01-Dec-25 Block Work FF
A2730 Parapet Wall Work 100 27-Apr-25* 21-Aug-25 Parapet Wall Work
A2731 GRC Mesh Work 90 27-Aug-25* 09-Dec-25 GRC Mesh Work
A2740 Screed in Slope on Roof Slabs 70 07-May-25* 28-Jul-25 Screed in Slope on Roof Slabs
A2750 Bitumenous Primer Coat 50 10-Jun-25* 06-Aug-25 Bitumenous Primer Coat
A2760 Reinforced Water Proofing Memberane Work 50 06-Jul-25* 02-Sep-25 Reinforced Water Proofing Memberane Work
A4290 Thermal Insulation Work 45 24-Jul-25* 14-Sep-25 Thermal Insulation Work
A4300 Sand Fillings 50 14-Aug-25* 11-Oct-25 Sand Fillings
A4310 Sand Cement Mortor Work 52 01-Sep-25* 30-Oct-25 Sand Cement Mortor Work
A4320 Roof Tiles Work 55 10-Sep-25* 12-Nov-25 Roof Tiles Work
A4330 Skirting Work 60 16-Oct-25* 24-Dec-25 Skirting Work
A6020 Combo System Option for Activity A2750-A4290 83 10-Jun-25* 14-Sep-25 Combo System Option for Activity A2750-A4290
EWF-HI.3.5.1.2 Finishes Work 177 23-Aug-25 17-Mar-26 17-Mar-26, EWF-HI.3.5.1.2 Finishes Work
A2930 Internal Plaster Work 120 23-Aug-25* 08-Jan-26 Internal Plaster Work
A2940 External Plaster Work 120 23-Aug-25* 08-Jan-26 External Plaster Work
A2950 Internal Floor Tiles For Rooms 110 09-Sep-25* 15-Jan-26 Internal Floor Tiles For Rooms
A2960 AntiSlip tile Work in Wet Areas 108 16-Sep-25* 19-Jan-26 AntiSlip tile Work in Wet Areas
A2961 Skirting and Wall tiles Work 108 21-Sep-25* 25-Jan-26 Skirting and Wall tiles Work
A2970 Staircase Steps & Enterance Tiling Work 109 01-Oct-25* 04-Feb-26 Staircase Steps & Enterance Tiling Work
A2980 Ceramic Tile Work 112 02-Oct-25* 09-Feb-26 Ceramic Tile Work
A2990 Internal Paint Work 112 06-Oct-25* 12-Feb-26 Internal Paint Work
A3000 External Paint Work 113 11-Oct-25* 18-Feb-26 logistic External Paint Work
constraint
A3010 Internal External Cladding Work 115 20-Oct-25* 02-Mar-26 Internal External Cladding Work
because of the
A3020 Internal External Decorative Work 111 30-Oct-25* 08-Mar-26 weather Internal External Decorative Work
A3030 Supply fabricate and installation of Kitchen Stage & Stage Korean Top 90 25-Nov-25* 10-Mar-26 Supply fabricate and installation of Kitchen Stage & Stage Korean Top
A3040 Gas Cylinder Stage 80 14-Dec-25* 17-Mar-26 Gas Cylinder Stage
EWF-HI.3.5.1.4 Sanitaryware, Fittings and Installations 344 20-Mar-25 25-Apr-26 25-Apr-26, EWF-HI.3.5.1.4 Sanitaryware, Fittings and Installations
A3200 UPVC pipes including all joints & accessories and brackets 133 20-Mar-25* 21-Aug-25 UPVC pipes including all joints & accessories and brackets
A3210 Sanitary Fittings and Valves Work 191 17-Apr-25* 25-Nov-25 Sanitary Fittings and Valves Work
A3220 Sanitaryware Installations 130 25-Nov-25* 25-Apr-26 Sanitaryware Installations

Actual Level of Effort Remaining Work Page 1 of 6 Eng. Muhammad Ahmed


Actual Work Critical Remaining Work [email protected]
PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT. 2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

EWF-HI.3.5.1.1 Doors and Windows Work 145 11-Nov-25 28-Apr-26 28-Apr-26, EWF-HI.3.5.1.1 Doors and Windows Work
A2770 Wooden Doors Work 122 11-Nov-25* 01-Apr-26 Wooden Doors Work
A2780 UPVC Doors Work 122 17-Nov-25* 08-Apr-26 UPVC Doors Work
A2790 Windows & Ventilators Work 120 25-Nov-25* 13-Apr-26 Windows & Ventilators Work
A2800 WPC Work 116 09-Dec-25* 22-Apr-26 WPC Work
A2810 Ironmongry Work 70 07-Feb-26* 28-Apr-26 Ironmongry Work
EWF-HI.3.5.1.5 Water Supply & Drainage 263 07-Jul-25 09-May-26 09-May-26, EWF-HI.3.5.1.5 Water Supply & Drainage
A3440 Cold and Hot water pipes with insulation 68 07-Jul-25* 23-Sep-25 Cold and Hot water pipes with insulation
A3450 Cold and Hot water Valves 73 13-Sep-25* 07-Dec-25 Cold and Hot water Valves
A3460 Water Tank & Heater Installation 49 02-Nov-25* 29-Dec-25 Water Tank & Heater Installation
A3470 Booster Pump Installation 49 17-Nov-25* 13-Jan-26 Booster Pump Installation
A3480 Booster Pump Installation 49 13-Jan-26* 11-Mar-26 Booster Pump Installation
A3490 Rain Water UPVC Pipes & Drainage Work 50 13-Jan-26* 12-Mar-26 Rain Water UPVC Pipes & Drainage Work
A3500 Gas Line Work 49 12-Mar-26* 09-May-26 Gas Line Work
EWF-HI.3.5.1.6 Fire Fighting Installations 87 02-Nov-25 11-Feb-26 11-Feb-26, EWF-HI.3.5.1.6 Fire Fighting Installations
A3510 Supply and Installation of Complete fire fighting System as per civil defence Approval 58 02-Nov-25 08-Jan-26 Supply and Installation of Complete fire fighting System as per civil defence Approv
A3520 Fire hose reel With All Accessories 51 30-Nov-25* 28-Jan-26 Fire hose reel With All Accessories
A3530 fire blanket, Carbon dioxide fire extinguisher 51 07-Dec-25* 04-Feb-26 fire blanket, Carbon dioxide fire extinguisher
A3540 Automatic Multi detector point 51 14-Dec-25* 11-Feb-26 Automatic Multi detector point
EWF-HI.3.5.1.7 Air Conditioning & Mechanical Installations 61 14-Feb-26 25-Apr-26 25-Apr-26, EWF-HI.3.5.1.7 Air Conditioning & Mechanical Installatio
A3560 Installation of Wall Mounted ACs with DX units 61 14-Feb-26 25-Apr-26 Installation of Wall Mounted ACs with DX units
EWF-HI.3.5.1.8 Electrical Work 204 19-Nov-25 14-Jul-26 14-Jul-26, EWF-HI.3.5.1.8 Electrical Work
A3590 Cable Work 50 19-Nov-25* 15-Jan-26 Cable Work
A3600 Distribution Boards Work 55 19-Nov-25* 21-Jan-26 Distribution Boards Work
A3610 Earthing Work 60 17-Dec-25* 24-Feb-26 Earthing Work
A3620 Small Power Accessories and cable and Conduits Installation 80 23-Dec-25* 26-Mar-26 Small Power Accessories and cable and Conduits Installation
A3630 Lighting Accessories and cable and conduits installation 85 28-Dec-25* 05-Apr-26 Lighting Accessories and cable and conduits installation
A3640 Lighting Fixture 82 04-Feb-26* 10-May-26 Lighting Fixture
A3650 Ceiling fan 90 25-Feb-26* 09-Jun-26 Ceiling fan
A3660 Chandelier 75 25-Mar-26* 21-Jun-26 Chandelier
A3670 Wall mounted exhaust fan 80 12-Apr-26* 14-Jul-26 Wall mounted exhaust fan
EWF-HI.3.5.1.9 TV, Data and CCTV System 141 04-Feb-26 18-Jul-26 18-Jul-26, EWF-HI.3.5.1.9 TV, Data and CCTV System
A3710 Cable and conduit to TV point in concealed installation from satellite 50 04-Feb-26* 02-Apr-26 Cable and conduit to TV point in concealed installation from satellite
A3720 Flush mounted TV Satellite outlet 50 21-Feb-26* 20-Apr-26 Flush mounted TV Satellite outlet
A3730 Co axial cable in concealed conduit from dish antenna to satellite switcher 70 08-Mar-26* 27-May-26 Co axial cable in concealed conduit from dish antenna to satellit
A3740 TV System Installation 65 15-Apr-26* 29-Jun-26 TV System Installation
A3750 Data System Installation 60 02-May-26* 11-Jul-26 Data System Installation
A3760 CCTV System Installation 54 17-May-26* 18-Jul-26 CCTV System Installation
EWF-HI.3.5.10 External Works 245 11-Oct-25 22-Jul-26 22-Jul-26, EWF-HI.3.5.10 External Works
A4340 Site Prepartion 90 11-Oct-25 22-Jan-26 Site Prepartion
A4350 Demarcation for compound wall and septic tank 80 28-Oct-25* 28-Jan-26 Demarcation for compound wall and septic tank
A4360 Excavation compound wall and septic tank 90 09-Nov-25* 22-Feb-26 Excavation compound wall and septic tank
A4370 Foundation Work for compound wall and septic tank 120 23-Nov-25* 11-Apr-26 Foundation Work for compound wall and septic tank
A4380 Coloumns Work compound wall and septic tank 120 08-Dec-25* 26-Apr-26 Coloumns Work compound wall and septic tank
A4390 Block Work compound wall and septic tank 136 24-Dec-25* 01-Jun-26 Block Work compound wall and septic tank
A4391 Covering Slab for Septic tank 120 24-Jan-26* 11-Jun-26 Covering Slab for Septic tank
A4392 Electro-Mechanical Works in compound area and Inatallations 125 24-Jan-26* 17-Jun-26 Electro-Mechanical Works in compound area and Inatallation
A4400 Car Entrance and Wicket Gate 126 28-Jan-26* 23-Jun-26 Car Entrance and Wicket Gate
A4410 Curb Stone Work 90 23-Mar-26* 05-Jul-26 Curb Stone Work
A4420 External Interlock Work 94 01-Apr-26* 19-Jul-26 External Interlock Work
A4430 Design & Build Solar Panel Canopy 245 11-Oct-25 22-Jul-26 Design & Build Solar Panel Canopy

EWF-HI.2 Maintenance of Existing 1-12/29 Housing Units 222 30-Sep-24 16-Jun-25 16-Jun-25, EWF-HI.2 Maintenance of Existing 1-12/29 Housing Units

EWF-HI.2.6 External Works 98 30-Sep-24 21-Jan-25 21-Jan-25, EWF-HI.2.6 External Works


A1850 Site Clearance 5 30-Sep-24* 06-Oct-24 Site Clearance
A1870 Demolish and Rebuild Gate Columns 35 30-Sep-24* 10-Nov-24 Demolish and Rebuild Gate Columns
A1880 Demolish and Rebuild Damaged Boundry Wall 38 30-Sep-24* 13-Nov-24 Demolish and Rebuild Damaged Boundry Wall
A1890 Repair and Maintain Damaged Manholes 25 30-Sep-24* 29-Oct-24 Repair and Maintain Damaged Manholes
A1900 Repair and Maintain Gate Damaged 25 10-Nov-24* 09-Dec-24 Repair and Maintain Gate Damaged
A1910 Repair and Maintenance of Holding Tank and Soakpits 28 02-Oct-24* 03-Nov-24 Repair and Maintenance of Holding Tank and Soakpits
A1920 Repainting Maintenance, Cleaning and Disposal Work 18 21-Oct-24* 11-Nov-24 Repainting Maintenance, Cleaning and Disposal Work
A1930 Boundry Wall, Repairing Maintenane Work 28 13-Nov-24* 16-Dec-24 Boundry Wall, Repairing Maintenane Work
A1940 Removing Existing Paint and Cleaning 35 13-Nov-24* 24-Dec-24 Removing Existing Paint and Cleaning
A1950 Water Proofing and Bitument Painting 32 20-Nov-24* 28-Dec-24 Water Proofing and Bitument Painting
A1960 Repainting With Weather Sheild 28 08-Dec-24* 08-Jan-25 Repainting With Weather Sheild
A1970 GI Gates with Columns 25 18-Dec-24* 15-Jan-25 GI Gates with Columns
A1980 Pea Gravel Arround the House and Inside Boundry Wall 18 26-Dec-24* 15-Jan-25 Pea Gravel Arround the House and Inside Boundry Wall
A1990 Gas Cylinder Room 32 16-Dec-24* 21-Jan-25 Gas Cylinder Room
EWF-HI.2.1 Super Structure Works -Demolition and Rebuilt 222 30-Sep-24 16-Jun-25 16-Jun-25, EWF-HI.2.1 Super Structure Works -Demolition and Rebuilt
EWF-HI.2.1.6 Civil Work 199 30-Sep-24 19-May-25 19-May-25, EWF-HI.2.1.6 Civil Work
A2010 Demolition of Staircase Slabs 35 30-Sep-24* 10-Nov-24 Demolition of Staircase Slabs
A2020 ReConstruction of Staircase slab With Finishes 40 30-Sep-24* 16-Nov-24 ReConstruction of Staircase slab With Finishes
A2030 Removal of Roof tiles to make it ready for new Waterproofing 30 12-Oct-24* 16-Nov-24 Removal of Roof tiles to make it ready for new Waterproofing
A2040 Screed in Slope 12 12-Oct-24* 26-Oct-24 Screed in Slope
A2050 Apply Bitumen Sheet 20 12-Oct-24* 04-Nov-24 Apply Bitumen Sheet
A2060 High Density Extruded Polystrene Foam Board 50mm 26 12-Oct-24* 11-Nov-24 High Density Extruded Polystrene Foam Board 50mm
A2070 Rain water Outlets and Gorgyles 12 28-Oct-24* 11-Nov-24 Rain water Outlets and Gorgyles
A2080 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed 35 28-Oct-24* 08-Dec-24 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed
A2090 Skirting tile and skirting groove tiles work 20 x 100 Terrazo 32 05-Nov-24* 11-Dec-24 Skirting tile and skirting groove tiles work 20 x 100 Terrazo
A2100 Replace Existing Entrance Flooring with Marble Tiles & Skirting 22 05-Nov-24* 30-Nov-24 Replace Existing Entrance Flooring with Marble Tiles & Skirting
A2110 Replace Flooring with Porcelain in Salah and Majles+Skirting 38 05-Nov-24* 18-Dec-24 Replace Flooring with Porcelain in Salah and Majles+Skirting
A2120 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets 27 13-Nov-24* 15-Dec-24 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets
A2130 Replace Stairs Landing and steps with Marble+Skirting 35 23-Nov-24* 02-Jan-25 Replace Stairs Landing and steps with Marble+Skirting
A2140 Internal Walls - Removal of Existing Paint and repaint 35 07-Dec-24* 16-Jan-25 Internal Walls - Removal of Existing Paint and repaint
A2150 External Walls - Removal of Existing Paint and repaint 30 16-Dec-24* 19-Jan-25 External Walls - Removal of Existing Paint and repaint
A2160 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles 22 09-Jan-25* 04-Feb-25 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles
A2170 Replace the Ceiling Finishes 32 27-Jan-25* 05-Mar-25 Replace the Ceiling Finishes
A2180 External Wall Finishes Natural Stone 28 12-Feb-25* 17-Mar-25 External Wall Finishes Natural Stone
A2190 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles 35 09-Apr-25* 19-May-25 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles
A2200 Replace Kitchen Hood Range Cabinet above and below Cabinet. 23 09-Apr-25* 05-May-25 Replace Kitchen Hood Range Cabinet above and below Cabinet.
EWF-HI.2.1.5 Metal Works 96 30-Sep-24 19-Jan-25 19-Jan-25, EWF-HI.2.1.5 Metal Works
A1080 Removal of Old Handrails 15 30-Sep-24* 17-Oct-24 Removal of Old Handrails
A1090 Installation of Handrails 30 16-Nov-24 21-Dec-24 Installation of Handrails
A1100 Galvanized steel cat Ladder 20 28-Dec-24* 19-Jan-25 Galvanized steel cat Ladder
EWF-HI.2.1.4 Door & Windows 112 30-Sep-24 06-Feb-25 06-Feb-25, EWF-HI.2.1.4 Door & Windows
A1040 Remove All Doors 25 18-Dec-24* 16-Jan-25 Remove All Doors
A1050 Maintain Old door Frames 50 30-Sep-24* 27-Nov-24 Maintain Old door Frames
A1060 Install New Wooden Doors (Replacement) with Accessories 32 18-Dec-24* 25-Jan-25 Install New Wooden Doors (Replacement) with Accessories
A1070 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessories 22 22-Dec-24* 15-Jan-25 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessories

Actual Level of Effort Remaining Work Page 2 of 6 Eng. Muhammad Ahmed


Actual Work Critical Remaining Work [email protected]
PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT. 2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

A1110 Maintain Exiting Aluminium Windows 69 19-Nov-24* 06-Feb-25 Maintain Exiting Aluminium Windows
EWF-HI.2.1.7 Sanitary Wares & Installations 167 03-Dec-24 16-Jun-25 16-Jun-25, EWF-HI.2.1.7 Sanitary Wares & Installations
A1200 Remove all sanitary that were fixed 35 18-Dec-24* 28-Jan-25 Remove all sanitary that were fixed
A1210 Supply and install Vent cowl 30 28-Jan-25* 04-Mar-25 Supply and install Vent cowl
A1220 Floor Drain trap 35 27-Feb-25* 08-Apr-25 Floor Drain trap
A1230 Gully Trap 10 03-Dec-24 15-Dec-24 Gully Trap
A2210 Semi pedestal wash basin 10 28-Jan-25* 09-Feb-25 Semi pedestal wash basin
A2220 Stainless Steel Sink 10 09-Feb-25* 20-Feb-25 Stainless Steel Sink
A2230 European Water Closet 10 20-Feb-25* 04-Mar-25 European Water Closet
A2240 shower tray 12 04-Mar-25* 18-Mar-25 shower tray
A2250 Ablution Faucet 15 18-Mar-25* 05-Apr-25 Ablution Faucet
A2260 shower Mixer 12 05-Apr-25* 19-Apr-25 shower Mixer
A2270 Wash Basin Mixer 13 19-Apr-25* 04-May-25 Wash Basin Mixer
A2280 Sink Mixer 12 04-May-25* 18-May-25 Sink Mixer
A2290 Toilet tissue holder 12 18-May-25* 01-Jun-25 Toilet tissue holder
A2300 Towel rail 12 01-Jun-25* 15-Jun-25 Towel rail
A2310 Mirror 13 01-Jun-25* 16-Jun-25 Mirror
EWF-HI.2.1.8 Water Supply & Rain Water Installations 107 21-Jan-25 25-May-25 25-May-25, EWF-HI.2.1.8 Water Supply & Rain Water Installations
A1160 Pressure Test and Replace defects/Polypropylene random copolymer pipe 30 21-Jan-25* 24-Feb-25 Pressure Test and Replace defects/Polypropylene random copolymer pipe
A1170 Cold and Hot water Valves 35 03-Feb-25* 15-Mar-25 Cold and Hot water Valves
A1180 Remove of all Equipment and Accessories that were fixed 30 18-Feb-25* 24-Mar-25 Remove of all Equipment and Accessories that were fixed
A1190 Water Tank Including Connection and Accessories 35 27-Feb-25* 09-Apr-25 Water Tank Including Connection and Accessories
A2390 Water Heater Connection and Accessories 35 06-Mar-25* 16-Apr-25 Water Heater Connection and Accessories
A2400 Rain Water UPVC Pipeswith outlet 45 19-Mar-25* 11-May-25 Rain Water UPVC Pipeswith outlet
A2410 Tap and Ablution Faucet 31 20-Apr-25* 25-May-25 Tap and Ablution Faucet
EWF-HI.2.1.9 Electrical Installations 116 09-Jan-25 24-May-25 24-May-25, EWF-HI.2.1.9 Electrical Installations
A1120 Checking to Identify any issue in Existing Power Distribution System 5 11-Jan-25 16-Jan-25 Checking to Identify any issue in Existing Power Distribution System
A1130 Installtion of Solar system 116 09-Jan-25* 24-May-25 Installtion of Solar system
A1140 Replace the existing with new weatherproof IP 65 Main 15 16-Jan-25 03-Feb-25 Replace the existing with new weatherproof IP 65 Main
A1150 Small Power Accessories removing 10 03-Feb-25 15-Feb-25 Small Power Accessories removing
A2330 Small Power Accessories Installation 12 15-Feb-25 01-Mar-25 Small Power Accessories Installation
A2340 Small Power Lighting Fixture removing 12 01-Mar-25 15-Mar-25 Small Power Lighting Fixture removing
A2350 Small Power Lighting Fixture Installations 12 15-Mar-25 29-Mar-25 Small Power Lighting Fixture Installations
A2360 Ceiling Fan Installation with All Accessories 12 29-Mar-25 12-Apr-25 Ceiling Fan Installation with All Accessories
A2370 Earthing Installations 12 12-Apr-25 26-Apr-25 Earthing Installations
A2380 TV Points and Dish Installations 12 26-Apr-25 10-May-25 TV Points and Dish Installations
EWF-HI.2.1.10 Air Conditioning Work 56 06-Jan-25 11-Mar-25 11-Mar-25, EWF-HI.2.1.10 Air Conditioning Work
A1280 Remove all Equipments and Accessories Fixed Indoor/Outdoor 38 06-Jan-25* 18-Feb-25 Remove all Equipments and Accessories Fixed Indoor/Outdoor
A1290 Replace Wall mounted Split AC with DX unit 28 22-Jan-25* 23-Feb-25 Replace Wall mounted Split AC with DX unit
A1300 Install Wall mounted Split AC with DX unit In Kitchen With Connections 25 30-Jan-25* 27-Feb-25 Install Wall mounted Split AC with DX unit In Kitchen With Connections
A1310 Install Wall mounted Split AC with DX unit in Salah & Majles 22 09-Feb-25* 05-Mar-25 Install Wall mounted Split AC with DX unit in Salah & Majles
A2320 Replace the Existing Ventilation Fans 20 17-Feb-25* 11-Mar-25 Replace the Existing Ventilation Fans
EWF-HI.2.1.1 Partial Handing Over of 1-12/29 Units 60 17-Feb-25 27-Apr-25 27-Apr-25, EWF-HI.2.1.1 Partial Handing Over of 1-12/29 Units
A4440 Handingover of Drawings 20 17-Feb-25* 11-Mar-25 Handingover of Drawings
A4450 Handing Over of Material Approvals 15 12-Mar-25* 30-Mar-25 Handing Over of Material Approvals
A4460 Handing over of Waranty Guarantee Documents 10 30-Mar-25* 10-Apr-25 Handing over of Waranty Guarantee Documents
A4470 Handing Over of Inspection, Testing and Comissioning Reports 8 10-Apr-25* 20-Apr-25 Handing Over of Inspection, Testing and Comissioning Reports
A4480 Handingover of Keys 6 20-Apr-25* 27-Apr-25 Handingover of Keys
A4490 Progress Report Compliance with Invesntory and Sanglist 14 10-Apr-25* 26-Apr-25 Progress Report Compliance with Invesntory and Sanglist

EWF-HI.5 Maintenance of Existing 13-20/29 Housing Units 206 28-Apr-25 23-Dec-25 23-Dec-25, EWF-HI.5 Maintenance of Existing 13-20/29 Housing Units

EWF-HI.5.6 External Works 80 28-Apr-25 29-Jul-25 29-Jul-25, EWF-HI.5.6 External Works


A4730 Site Clearance 5 28-Apr-25* 03-May-25 Site Clearance
A4740 Demolish and Rebuild Gate Columns 31 03-May-25* 08-Jun-25 Demolish and Rebuild Gate Columns
A4750 Demolish and Rebuild Damaged Boundry Wall 33 06-May-25* 12-Jun-25 Demolish and Rebuild Damaged Boundry Wall
A4760 Repair and Maintain Damaged Manholes 21 26-May-25* 19-Jun-25 Repair and Maintain Damaged Manholes
A4770 Repair and Maintain Gate Damaged 22 08-Jun-25* 03-Jul-25 Repair and Maintain Gate Damaged
A4780 Repair and Maintenance of Holding Tank and Soakpits 25 19-Jun-25* 19-Jul-25 Repair and Maintenance of Holding Tank and Soakpits
A4790 Repainting Maintenance, Cleaning and Disposal Work 15 01-Jul-25* 19-Jul-25 Repainting Maintenance, Cleaning and Disposal Work
A4800 Boundry Wall, Repairing Maintenane Work 24 23-Jun-25* 20-Jul-25 Boundry Wall, Repairing Maintenane Work
A4810 Removing Existing Paint and Cleaning 30 25-Jun-25* 29-Jul-25 Removing Existing Paint and Cleaning
A4820 Water Proofing and Bitument Painting 23 23-Jun-25* 19-Jul-25 Water Proofing and Bitument Painting
A4830 Repainting With Weather Sheild 25 26-Jun-25* 24-Jul-25 Repainting With Weather Sheild
A4840 GI Gates with Columns 22 30-Jun-25* 24-Jul-25 GI Gates with Columns
A4850 Pea Gravel Arround the House and Inside Boundry Wall 16 09-Jul-25* 28-Jul-25 Pea Gravel Arround the House and Inside Boundry Wall
A4860 Gas Cylinder Room 27 26-Jun-25* 28-Jul-25 Gas Cylinder Room
EWF-HI.5.1 Super Structure Works -Demolition and Rebuilt 206 28-Apr-25 23-Dec-25 23-Dec-25, EWF-HI.5.1 Super Structure Works -Demolition and Rebuilt
EWF-HI.5.1.6 Civil Work 157 28-Apr-25 27-Oct-25 27-Oct-25, EWF-HI.5.1.6 Civil Work
A4870 Demolition of Staircase Slabs 35 28-Apr-25* 07-Jun-25 Demolition of Staircase Slabs
A4880 ReConstruction of Staircase slab With Finishes 40 01-May-25* 16-Jun-25 ReConstruction of Staircase slab With Finishes
A4890 Removal of Roof tiles to make it ready for new Waterproofing 30 15-May-25* 18-Jun-25 Removal of Roof tiles to make it ready for new Waterproofing
A4900 Screed in Slope 12 07-Jun-25* 19-Jun-25 Screed in Slope
A4910 Apply Bitumen Sheet 20 07-Jun-25* 29-Jun-25 Apply Bitumen Sheet
A4920 High Density Extruded Polystrene Foam Board 50mm 26 07-Jun-25* 06-Jul-25 High Density Extruded Polystrene Foam Board 50mm
A4930 Rain water Outlets and Gorgyles 12 23-Jun-25* 06-Jul-25 Rain water Outlets and Gorgyles
A4940 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed 35 23-Jun-25* 02-Aug-25 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed
A4950 Skirting tile and skirting groove tiles work 20 x 100 Terrazo 32 29-Jun-25* 04-Aug-25 Skirting tile and skirting groove tiles work 20 x 100 Terrazo
A4960 Replace Existing Entrance Flooring with Marble Tiles & Skirting 22 29-Jun-25* 23-Jul-25 Replace Existing Entrance Flooring with Marble Tiles & Skirting
A4970 Replace Flooring with Porcelain in Salah and Majles+Skirting 38 13-Jul-25* 25-Aug-25 Replace Flooring with Porcelain in Salah and Majles+Skirting
A4980 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets 27 30-Jul-25* 31-Aug-25 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets
A4990 Replace Stairs Landing and steps with Marble+Skirting 35 30-Jul-25* 09-Sep-25 Replace Stairs Landing and steps with Marble+Skirting
A5000 Internal Walls - Removal of Existing Paint and repaint 35 30-Jul-25* 09-Sep-25 Internal Walls - Removal of Existing Paint and repaint
A5010 External Walls - Removal of Existing Paint and repaint 30 30-Jul-25* 03-Sep-25 External Walls - Removal of Existing Paint and repaint
A5020 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles 22 09-Sep-25* 05-Oct-25 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles
A5030 Replace the Ceiling Finishes 32 09-Sep-25* 16-Oct-25 Replace the Ceiling Finishes
A5040 External Wall Finishes Natural Stone 28 30-Jul-25* 01-Sep-25 External Wall Finishes Natural Stone
A5050 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles 35 09-Sep-25* 20-Oct-25 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles
A5060 Replace Kitchen Hood Range Cabinet above and below Cabinet. 23 30-Sep-25* 27-Oct-25 Replace Kitchen Hood Range Cabinet above and below Cabinet.
EWF-HI.5.1.5 Metal Works 111 28-Apr-25 03-Sep-25 03-Sep-25, EWF-HI.5.1.5 Metal Works
A4540 Removal of Old Handrails 13 28-Apr-25* 12-May-25 Removal of Old Handrails
A4550 Installation of Handrails 25 17-Jun-25 15-Jul-25 Installation of Handrails
A4560 Galvanized steel cat Ladder 17 14-Aug-25* 03-Sep-25 Galvanized steel cat Ladder
EWF-HI.5.1.4 Door & Windows 87 12-Jun-25 21-Sep-25 21-Sep-25, EWF-HI.5.1.4 Door & Windows
A4500 Remove All Doors 25 11-Aug-25* 09-Sep-25 Remove All Doors
A4510 Maintain Old door Frames 50 12-Jun-25* 09-Aug-25 Maintain Old door Frames
A4520 Install New Wooden Doors (Replacement) with Accessories 32 11-Aug-25* 17-Sep-25 Install New Wooden Doors (Replacement) with Accessories
A4530 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessories 22 11-Aug-25* 06-Sep-25 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessories
A5280 Maintain Exiting Aluminium Windows 69 03-Jul-25* 21-Sep-25 Maintain Exiting Aluminium Windows
EWF-HI.5.1.7 Sanitary Wares & Installations 120 30-Jul-25 17-Dec-25 17-Dec-25, EWF-HI.5.1.7 Sanitary Wares & Installations

Actual Level of Effort Remaining Work Page 3 of 6 Eng. Muhammad Ahmed


Actual Work Critical Remaining Work [email protected]
PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT. 2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

A4650 Remove all sanitary that were fixed 28 11-Aug-25* 13-Sep-25 Remove all sanitary that were fixed
A4660 Supply and install Vent cowl 21 13-Sep-25* 07-Oct-25 Supply and install Vent cowl
A4670 Floor Drain trap 23 30-Jul-25* 26-Aug-25 Floor Drain trap
A4680 Gully Trap 8 21-Aug-25 31-Aug-25 Gully Trap
A5070 Semi pedestal wash basin 8 13-Sep-25* 22-Sep-25 Semi pedestal wash basin
A5080 Stainless Steel Sink 7 22-Sep-25* 30-Sep-25 Stainless Steel Sink
A5090 European Water Closet 8 30-Sep-25* 09-Oct-25 European Water Closet
A5100 shower tray 7 09-Oct-25* 18-Oct-25 shower tray
A5110 Ablution Faucet 9 18-Oct-25* 28-Oct-25 Ablution Faucet
A5120 shower Mixer 9 28-Oct-25* 08-Nov-25 shower Mixer
A5130 Wash Basin Mixer 9 08-Nov-25* 18-Nov-25 Wash Basin Mixer
A5140 Sink Mixer 9 18-Nov-25* 29-Nov-25 Sink Mixer
A5150 Toilet tissue holder 8 29-Nov-25* 08-Dec-25 Toilet tissue holder
A5160 Towel rail 7 08-Dec-25* 16-Dec-25 Towel rail
A5170 Mirror 8 08-Dec-25* 17-Dec-25 Mirror
EWF-HI.5.1.8 Water Supply & Rain Water Installations 56 31-Aug-25 04-Nov-25 04-Nov-25, EWF-HI.5.1.8 Water Supply & Rain Water Installations
A4610 Pressure Test and Replace defects/Polypropylene random copolymer pipe 30 31-Aug-25* 05-Oct-25 Pressure Test and Replace defects/Polypropylene random copolymer pipe
A4620 Cold and Hot water Valves 35 03-Sep-25* 14-Oct-25 Cold and Hot water Valves
A4630 Remove of all Equipment and Accessories that were fixed 30 14-Sep-25* 19-Oct-25 Remove of all Equipment and Accessories that were fixed
A4640 Water Tank Including Connection and Accessories 35 10-Sep-25* 21-Oct-25 Water Tank Including Connection and Accessories
A5250 Water Heater Connection and Accessories 35 17-Sep-25* 28-Oct-25 Water Heater Connection and Accessories
A5260 Rain Water UPVC Pipeswith outlet 45 10-Sep-25* 02-Nov-25 Rain Water UPVC Pipeswith outlet
A5270 Tap and Ablution Faucet 31 29-Sep-25* 04-Nov-25 Tap and Ablution Faucet
EWF-HI.5.1.9 Electrical Installations 116 05-Aug-25 17-Dec-25 17-Dec-25, EWF-HI.5.1.9 Electrical Installations
A4570 Checking to Identify any issue in Existing Power Distribution System 5 03-Sep-25* 09-Sep-25 Checking to Identify any issue in Existing Power Distribution System
A4580 Installtion of Solar system 90 05-Aug-25* 17-Nov-25 Installtion of Solar system
A4590 Replace the existing with new weatherproof IP 65 Main 15 09-Sep-25 27-Sep-25 Replace the existing with new weatherproof IP 65 Main
A4600 Small Power Accessories removing 10 27-Sep-25 08-Oct-25 Small Power Accessories removing
A5190 Small Power Accessories Installation 10 08-Oct-25 20-Oct-25 Small Power Accessories Installation
A5200 Small Power Lighting Fixture removing 11 20-Oct-25 02-Nov-25 Small Power Lighting Fixture removing
A5210 Small Power Lighting Fixture Installations 9 02-Nov-25 12-Nov-25 Small Power Lighting Fixture Installations
A5220 Ceiling Fan Installation with All Accessories 11 12-Nov-25 25-Nov-25 Ceiling Fan Installation with All Accessories
A5230 Earthing Installations 10 25-Nov-25 07-Dec-25 Earthing Installations
A5240 TV Points and Dish Installations 9 07-Dec-25 17-Dec-25 TV Points and Dish Installations
EWF-HI.5.1.10 Air Conditioning Work 68 27-Aug-25 15-Nov-25 15-Nov-25, EWF-HI.5.1.10 Air Conditioning Work
A4690 Remove all Equipments and Accessories Fixed Indoor/Outdoor 32 27-Aug-25* 04-Oct-25 Remove all Equipments and Accessories Fixed Indoor/Outdoor
A4700 Replace Wall mounted Split AC with DX unit 23 14-Sep-25* 09-Oct-25 Replace Wall mounted Split AC with DX unit
A4710 Install Wall mounted Split AC with DX unit In Kitchen With Connections 19 28-Sep-25* 19-Oct-25 Install Wall mounted Split AC with DX unit In Kitchen With Connections
A4720 Install Wall mounted Split AC with DX unit in Salah & Majles 18 15-Oct-25* 04-Nov-25 Install Wall mounted Split AC with DX unit in Salah & Majles
A5180 Replace the Existing Ventilation Fans 17 26-Oct-25* 15-Nov-25 Replace the Existing Ventilation Fans
EWF-HI.5.1.1 Partial Handing Over of 13-20/29 Units 67 07-Oct-25 23-Dec-25 23-Dec-25, EWF-HI.5.1.1 Partial Handing Over of 13-20/29 Units
A5290 Handingover of Drawings 20 07-Oct-25* 29-Oct-25 Handingover of Drawings
A5300 Handing Over of Material Approvals 15 08-Nov-25* 24-Nov-25 Handing Over of Material Approvals
A5310 Handing over of Waranty Guarantee Documents 10 25-Nov-25* 06-Dec-25 Handing over of Waranty Guarantee Documents
A5320 Handing Over of Inspection, Testing and Comissioning Reports 8 07-Dec-25* 15-Dec-25 Handing Over of Inspection, Testing and Comissioning Reports
A5330 Handingover of Keys 7 16-Dec-25* 23-Dec-25 Handingover of Keys
A5340 Progress Report Compliance with Invesntory and Sanglist 14 07-Dec-25* 22-Dec-25 Progress Report Compliance with Invesntory and Sanglist

EWF-HI.8 Maintenance of Existing 21-29/29 Housing Units 180 24-Dec-25 21-Jul-26 21-Jul-26, EWF-HI.8 Maintenance of Existing 21-29/29

EWF-HI.8.6 External Works 76 24-Dec-25 22-Mar-26 22-Mar-26, EWF-HI.8.6 External Works


A5580 Site Clearance 4 24-Dec-25* 28-Dec-25 Site Clearance
A5590 Demolish and Rebuild Gate Columns 29 29-Dec-25* 31-Jan-26 Demolish and Rebuild Gate Columns
A5600 Demolish and Rebuild Damaged Boundry Wall 31 01-Jan-26* 05-Feb-26 Demolish and Rebuild Damaged Boundry Wall
A5610 Repair and Maintain Damaged Manholes 20 12-Jan-26* 03-Feb-26 Repair and Maintain Damaged Manholes
A5620 Repair and Maintain Gate Damaged 20 01-Feb-26* 23-Feb-26 Repair and Maintain Gate Damaged
A5630 Repair and Maintenance of Holding Tank and Soakpits 22 25-Jan-26* 19-Feb-26 Repair and Maintenance of Holding Tank and Soakpits
A5640 Repainting Maintenance, Cleaning and Disposal Work 13 04-Feb-26* 19-Feb-26 Repainting Maintenance, Cleaning and Disposal Work
A5650 Boundry Wall, Repairing Maintenane Work 22 07-Feb-26* 03-Mar-26 Boundry Wall, Repairing Maintenane Work
A5660 Removing Existing Paint and Cleaning 27 12-Feb-26* 15-Mar-26 Removing Existing Paint and Cleaning
A5670 Water Proofing and Bitument Painting 21 21-Feb-26* 17-Mar-26 Water Proofing and Bitument Painting
A5680 Repainting With Weather Sheild 23 24-Feb-26* 22-Mar-26 Repainting With Weather Sheild
A5690 GI Gates with Columns 30 14-Feb-26* 19-Mar-26 GI Gates with Columns
A5700 Pea Gravel Arround the House and Inside Boundry Wall 15 24-Feb-26* 14-Mar-26 Pea Gravel Arround the House and Inside Boundry Wall
A5710 Gas Cylinder Room 24 21-Feb-26* 21-Mar-26 Gas Cylinder Room
EWF-HI.8.1 Super Structure Works -Demolition and Rebuilt 172 03-Jan-26 21-Jul-26 21-Jul-26, EWF-HI.8.1 Super Structure Works -Demolitio
EWF-HI.8.1.6 Civil Work 104 03-Jan-26 03-May-26 03-May-26, EWF-HI.8.1.6 Civil Work
A5720 Demolition of Staircase Slabs 32 03-Jan-26* 08-Feb-26 Demolition of Staircase Slabs
A5730 ReConstruction of Staircase slab With Finishes 35 08-Jan-26* 17-Feb-26 ReConstruction of Staircase slab With Finishes
A5740 Removal of Roof tiles to make it ready for new Waterproofing 34 10-Jan-26* 17-Feb-26 Removal of Roof tiles to make it ready for new Waterproofing
A5750 Screed in Slope 31 17-Jan-26* 21-Feb-26 Screed in Slope
A5760 Apply Bitumen Sheet 18 04-Feb-26* 24-Feb-26 Apply Bitumen Sheet
A5770 High Density Extruded Polystrene Foam Board 50mm 24 04-Feb-26* 03-Mar-26 High Density Extruded Polystrene Foam Board 50mm
A5780 Rain water Outlets and Gorgyles 11 19-Feb-26* 03-Mar-26 Rain water Outlets and Gorgyles
A5790 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed 31 19-Feb-26* 26-Mar-26 Roofing tiles 300 x 300 x 25 mm terrazzo With Cement Bed
A5800 Skirting tile and skirting groove tiles work 20 x 100 Terrazo 30 23-Feb-26* 29-Mar-26 Skirting tile and skirting groove tiles work 20 x 100 Terrazo
A5810 Replace Existing Entrance Flooring with Marble Tiles & Skirting 20 25-Feb-26* 19-Mar-26 Replace Existing Entrance Flooring with Marble Tiles & Skirting
A5820 Replace Flooring with Porcelain in Salah and Majles+Skirting 34 26-Feb-26* 06-Apr-26 Replace Flooring with Porcelain in Salah and Majles+Skirting
A5830 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets 24 01-Mar-26* 28-Mar-26 Replace Flooring with Antislip Ceramic tiles Kitchen & Toilets
A5840 Replace Stairs Landing and steps with Marble+Skirting 30 05-Mar-26* 08-Apr-26 Replace Stairs Landing and steps with Marble+Skirting
A5850 Internal Walls - Removal of Existing Paint and repaint 31 09-Mar-26* 13-Apr-26 Internal Walls - Removal of Existing Paint and repaint
A5860 External Walls - Removal of Existing Paint and repaint 27 14-Mar-26* 13-Apr-26 External Walls - Removal of Existing Paint and repaint
A5870 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles 21 09-Apr-26* 03-May-26 Replace Kitchen and Toilet Tiles with Glossy Ceramic Tiles
A5880 Replace the Ceiling Finishes 25 16-Mar-26* 13-Apr-26 Replace the Ceiling Finishes
A5890 External Wall Finishes Natural Stone 25 15-Mar-26* 12-Apr-26 External Wall Finishes Natural Stone
A5900 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles 31 29-Mar-26* 03-May-26 Replace Kitchen Stage Concrete Korean Top Ceramic Wall Tiles
A5910 Replace Kitchen Hood Range Cabinet above and below Cabinet. 21 09-Apr-26* 03-May-26 Replace Kitchen Hood Range Cabinet above and below Cabinet.
EWF-HI.8.1.5 Metal Works 63 31-Jan-26 13-Apr-26 13-Apr-26, EWF-HI.8.1.5 Metal Works
A5390 Removal of Old Handrails 12 31-Jan-26* 12-Feb-26 Removal of Old Handrails
A5400 Installation of Handrails 23 18-Feb-26 16-Mar-26 Installation of Handrails
A5410 Galvanized steel cat Ladder 16 26-Mar-26* 13-Apr-26 Galvanized steel cat Ladder
EWF-HI.8.1.4 Door & Windows 69 31-Jan-26 20-Apr-26 20-Apr-26, EWF-HI.8.1.4 Door & Windows
A5350 Remove All Doors 23 18-Mar-26* 13-Apr-26 Remove All Doors
A5360 Maintain Old door Frames 35 31-Jan-26* 11-Mar-26 Maintain Old door Frames
A5370 Install New Wooden Doors (Replacement) with Accessories 29 18-Mar-26* 20-Apr-26 Install New Wooden Doors (Replacement) with Accessories
A5380 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessories 19 18-Mar-26* 08-Apr-26 Install New UPVC Doors Toilets & Roof (Replacement) W ith Accessorie
A6130 Maintain Exiting Aluminium Windows 40 31-Jan-26* 17-Mar-26 Maintain Exiting Aluminium Windows
EWF-HI.8.1.7 Sanitary Wares & Installations 121 01-Mar-26 19-Jul-26 19-Jul-26, EWF-HI.8.1.7 Sanitary Wares & Installations
A5500 Remove all sanitary that were fixed 28 18-Mar-26* 19-Apr-26 Remove all sanitary that were fixed
A5510 Supply and install Vent cowl 21 20-Apr-26* 13-May-26 Supply and install Vent cowl

Actual Level of Effort Remaining Work Page 4 of 6 Eng. Muhammad Ahmed


Actual Work Critical Remaining Work [email protected]
PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT. 2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

A5520 Floor Drain trap 23 01-Mar-26* 26-Mar-26 Floor Drain trap


A5530 Gully Trap 8 19-Mar-26 28-Mar-26 Gully Trap
A5920 Semi pedestal wash basin 8 20-Apr-26* 28-Apr-26 Semi pedestal wash basin
A5930 Stainless Steel Sink 7 29-Apr-26* 06-May-26 Stainless Steel Sink
A5940 European Water Closet 8 07-May-26* 16-May-26 European Water Closet
A5950 shower tray 7 17-May-26* 24-May-26 shower tray
A5960 Ablution Faucet 9 25-May-26* 03-Jun-26 Ablution Faucet
A5970 shower Mixer 9 04-Jun-26* 14-Jun-26 shower Mixer
A5980 Wash Basin Mixer 9 15-Jun-26* 24-Jun-26 Wash Basin Mixer
A5990 Sink Mixer 8 25-Jun-26* 04-Jul-26 Sink Mixer
A6000 Toilet tissue holder 7 05-Jul-26* 12-Jul-26 Toilet tissue holder
A6010 Towel rail & Mirrors 6 13-Jul-26* 19-Jul-26 Towel rail & Mirrors
EWF-HI.8.1.8 Water Supply & Rain Water Installations 64 09-Mar-26 21-May-26 21-May-26, EWF-HI.8.1.8 Water Supply & Rain Water Installatio
A5460 Pressure Test and Replace defects/Polypropylene random copolymer pipe 28 09-Mar-26* 09-Apr-26 Pressure Test and Replace defects/Polypropylene random copolymer p
A5470 Cold and Hot water Valves 32 09-Mar-26* 14-Apr-26 Cold and Hot water Valves
A5480 Remove of all Equipment and Accessories that were fixed 28 09-Mar-26* 09-Apr-26 Remove of all Equipment and Accessories that were fixed
A5490 Water Tank Including Connection and Accessories 31 09-Mar-26* 13-Apr-26 Water Tank Including Connection and Accessories
A6100 Water Heater Connection and Accessories 32 09-Mar-26* 14-Apr-26 Water Heater Connection and Accessories
A6110 Rain Water UPVC Pipeswith outlet 39 09-Mar-26* 22-Apr-26 Rain Water UPVC Pipeswith outlet
A6120 Tap and Ablution Faucet 28 20-Apr-26* 21-May-26 Tap and Ablution Faucet
EWF-HI.8.1.9 Electrical Installations 98 30-Mar-26 21-Jul-26 21-Jul-26, EWF-HI.8.1.9 Electrical Installations
A5420 Checking to Identify any issue in Existing Power Distribution System 5 08-Apr-26* 13-Apr-26 Checking to Identify any issue in Existing Power Distribution System
A5430 Installtion of Solar system 90 30-Mar-26* 12-Jul-26 Installtion of Solar system
A5440 Replace the existing with new weatherproof IP 65 Main 15 14-Apr-26 30-Apr-26 Replace the existing with new weatherproof IP 65 Main
A5450 Small Power Accessories removing 10 02-May-26 12-May-26 Small Power Accessories removing
A6040 Small Power Accessories Installation 10 13-May-26 24-May-26 Small Power Accessories Installation
A6050 Small Power Lighting Fixture removing 11 25-May-26 06-Jun-26 Small Power Lighting Fixture removing
A6060 Small Power Lighting Fixture Installations 9 07-Jun-26 16-Jun-26 Small Power Lighting Fixture Installations
A6070 Ceiling Fan Installation with All Accessories 11 17-Jun-26 29-Jun-26 Ceiling Fan Installation with All Accessories
A6080 Earthing Installations 10 30-Jun-26 11-Jul-26 Earthing Installations
A6090 TV Points and Dish Installations 9 12-Jul-26 21-Jul-26 TV Points and Dish Installations
EWF-HI.8.1.10 Air Conditioning Work 42 24-Mar-26 11-May-26 11-May-26, EWF-HI.8.1.10 Air Conditioning Work
A5540 Remove all Equipments and Accessories Fixed Indoor/Outdoor 30 24-Mar-26* 27-Apr-26 Remove all Equipments and Accessories Fixed Indoor/Outdoor
A5550 Replace Wall mounted Split AC with DX unit 22 04-Apr-26* 29-Apr-26 Replace Wall mounted Split AC with DX unit
A5560 Install Wall mounted Split AC with DX unit In Kitchen With Connections 19 13-Apr-26* 05-May-26 Install Wall mounted Split AC with DX unit In Kitchen With Connect
A5570 Install Wall mounted Split AC with DX unit in Salah & Majles 18 18-Apr-26* 07-May-26 Install Wall mounted Split AC with DX unit in Salah & Majles
A6030 Replace the Existing Ventilation Fans 17 21-Apr-26* 11-May-26 Replace the Existing Ventilation Fans
EWF-HI.8.1.1 Partial Handing Over of 21-29/29 Units 50 18-May-26 15-Jul-26 15-Jul-26, EWF-HI.8.1.1 Partial Handing Over of 21-29/2
A6140 Handingover of Drawings 15 18-May-26* 04-Jun-26 Handingover of Drawings
A6150 Handing Over of Material Approvals 12 04-Jun-26* 18-Jun-26 Handing Over of Material Approvals
A6160 Handing over of Waranty Guarantee Documents 9 18-Jun-26* 29-Jun-26 Handing over of Waranty Guarantee Documents
A6170 Handing Over of Inspection, Testing and Comissioning Reports 8 29-Jun-26* 08-Jul-26 Handing Over of Inspection, Testing and Comissioning Re
A6180 Handingover of Keys 6 08-Jul-26* 15-Jul-26 Handingover of Keys
A6190 Progress Report Compliance with Invesntory and Sanglist 12 29-Jun-26* 13-Jul-26 Progress Report Compliance with Invesntory and Sanglist

EWF-HI.4 Storm Water and Drainage Work 494 21-Jan-25 19-Aug-26 19-Aug-26, EWF-HI.4 Storm Water and Drainage W

EWF-HI.4.4 Storm Water and Drainage Work (Re-Constructed Units) 424 21-Jan-25 31-May-26 31-May-26, EWF-HI.4.4 Storm Water and Drainage Work (Re-C
EWF-HI.4.4.1 Line 1 281 21-Jan-25 14-Dec-25 14-Dec-25, EWF-HI.4.4.1 Line 1
A3980 Survey and Marking for Line 1 85 21-Jan-25* 30-Apr-25 Survey and Marking for Line 1
A3990 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1 80 30-Apr-25 02-Aug-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1
A4000 Crosschecking of Levels 120 25-Feb-25* 15-Jul-25 Crosschecking of Levels
A4010 Bedding for Pipes with approved Material 90 22-Apr-25* 04-Aug-25 Bedding for Pipes with approved Material
A4030 Laying of Pipes and Welding 45 18-Jun-25* 10-Aug-25 Laying of Pipes and Welding
A4190 Testing 30 09-Jul-25* 12-Aug-25 Testing
A4200 Concreting Work for Pipes and till Transition Slab 60 03-Aug-25* 11-Oct-25 Concreting Work for Pipes and till Transition Slab
A4210 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 24-Aug-25* 25-Nov-25 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin
A6200 Pre-Cast Concrete Cover Slab Work 20 02-Nov-25 25-Nov-25 Pre-Cast Concrete Cover Slab Work
A6210 Backfilling & Compaction 40 12-Oct-25* 26-Nov-25 Backfilling & Compaction
A6220 Block Work With Ring for Opening and Grating 35 01-Nov-25* 11-Dec-25 Block Work With Ring for Opening and Grating
A6230 Connections with Existing Network 15 27-Nov-25* 14-Dec-25 Connections with Existing Network
EWF-HI.4.4.2 Line 1-1 259 30-Apr-25 26-Feb-26 26-Feb-26, EWF-HI.4.4.2 Line 1-1
A6240 Survey and Marking for Line 1-1 85 30-Apr-25* 07-Aug-25 Survey and Marking for Line 1-1
A6250 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1 80 07-Aug-25 09-Nov-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1
A6260 Crosschecking of Levels 120 15-Jul-25* 02-Dec-25 Crosschecking of Levels
A6270 Bedding for Pipes with approved Material 90 05-Aug-25* 17-Nov-25 Bedding for Pipes with approved Material
A6280 Laying of Pipes and Welding 45 10-Aug-25* 01-Oct-25 Laying of Pipes and Welding
A6290 Testing 30 13-Aug-25* 16-Sep-25 Testing
A6300 Concreting Work for Pipes and till Transition Slab 60 12-Oct-25* 20-Dec-25 Concreting Work for Pipes and till Transition Slab
A6310 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 25-Nov-25* 26-Feb-26 Chamber Including Reinforcement and Concreting with Connection from Cat
A6320 Pre-Cast Concrete Cover Slab Work 20 03-Feb-26 26-Feb-26 Pre-Cast Concrete Cover Slab Work
A6330 Backfilling & Compaction 40 27-Nov-25* 12-Jan-26 Backfilling & Compaction
A6340 Block Work With Ring for Opening and Grating 35 11-Dec-25* 21-Jan-26 Block Work With Ring for Opening and Grating
A6350 Connections with Existing Network 15 12-Jan-26* 28-Jan-26 Connections with Existing Network
EWF-HI.4.4.3 Line 1-1-6 254 07-Aug-25 31-May-26 31-May-26, EWF-HI.4.4.3 Line 1-1-6
A6360 Survey and Marking for Line 1-1-6 85 07-Aug-25* 15-Nov-25 Survey and Marking for Line 1-1-6
A6370 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6 80 15-Nov-25 16-Feb-26 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6
A6380 Crosschecking of Levels 120 02-Dec-25* 21-Apr-26 Crosschecking of Levels
A6390 Bedding for Pipes with approved Material 90 02-Dec-25* 17-Mar-26 Bedding for Pipes with approved Material
A6400 Laying of Pipes and Welding 45 15-Nov-25* 06-Jan-26 Laying of Pipes and Welding
A6410 Testing 30 15-Nov-25* 20-Dec-25 Testing
A6420 Concreting Work for Pipes and till Transition Slab 60 21-Dec-25* 28-Feb-26 Concreting Work for Pipes and till Transition Slab
A6430 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 26-Feb-26* 31-May-26 Chamber Including Reinforcement and Concreting with Connect
A6440 Pre-Cast Concrete Cover Slab Work 20 07-May-26 31-May-26 Pre-Cast Concrete Cover Slab Work
A6450 Backfilling & Compaction 40 26-Feb-26* 14-Apr-26 Backfilling & Compaction
A6460 Block Work With Ring for Opening and Grating 35 08-Mar-26* 16-Apr-26 Block Work With Ring for Opening and Grating
A6470 Connections with Existing Network 15 09-Apr-26* 26-Apr-26 Connections with Existing Network
EWF-HI.4.1 Storm Water and Drainage Work (Maintenance Units) 441 08-Feb-25 06-Jul-26 06-Jul-26, EWF-HI.4.1 Storm Water and Drainage Work (M
EWF-HI.4.1.1 Line 2 266 08-Feb-25 14-Dec-25 14-Dec-25, EWF-HI.4.1.1 Line 2
A6480 Survey and Marking for Line 1 85 08-Feb-25* 17-May-25 Survey and Marking for Line 1
A6490 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1 80 18-May-25 18-Aug-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1
A6500 Crosschecking of Levels 120 08-Mar-25* 24-Jul-25 Crosschecking of Levels
A6510 Bedding for Pipes with approved Material 90 22-Apr-25* 04-Aug-25 Bedding for Pipes with approved Material
A6520 Laying of Pipes and Welding 45 18-Jun-25* 10-Aug-25 Laying of Pipes and Welding
A6530 Testing 30 09-Jul-25* 12-Aug-25 Testing
A6540 Concreting Work for Pipes and till Transition Slab 60 03-Aug-25* 11-Oct-25 Concreting Work for Pipes and till Transition Slab
A6550 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 24-Aug-25* 25-Nov-25 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin
A6560 Pre-Cast Concrete Cover Slab Work 20 02-Nov-25 25-Nov-25 Pre-Cast Concrete Cover Slab Work
A6570 Backfilling & Compaction 40 12-Oct-25* 26-Nov-25 Backfilling & Compaction
A6580 Block Work With Ring for Opening and Grating 35 01-Nov-25* 11-Dec-25 Block Work With Ring for Opening and Grating

Actual Level of Effort Remaining Work Page 5 of 6 Eng. Muhammad Ahmed


Actual Work Critical Remaining Work [email protected]
PROJECT: CLIENT: MINISTRY OF HOUSING AND URBAN PLANNING MOBILIZATION: 03 JUNE 2024 TO 30 SEPT. 2024
CONSTRUCTION, COMPLETION AND MAINTENANCE OF CONSULTANT: AL MANARAH ENGINEERING PROJECT DURATION: 730 Days
(20NOS) HOUSING UNITS AND MAINTENANCE OF CONSULTANCY PROJECT COMMENCEMENT DATE: 01st Oct, 2024
(32NOS) HOUSING UNITS AT HALANIYAT ISLAND IN CONTRACTOR: EAST WATERFALLS TRADING & PROJECT COMPLETION DATE: 30th Sep, 2026
DHOFAR GOVERNORATE (TENDER NO : 213/2023) CONTRACTING COMPANY
Activity ID Activity Name Original Start Finish
Duration 2024 2025 2026 2027

A6590 Connections with Existing Network 15 27-Nov-25* 14-Dec-25 Connections with Existing Network
EWF-HI.4.1.2 Line 2-4 245 18-May-25 26-Feb-26 26-Feb-26, EWF-HI.4.1.2 Line 2-4
A6600 Survey and Marking for Line 1-1 85 18-May-25* 24-Aug-25 Survey and Marking for Line 1-1
A6610 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1 80 25-Aug-25 25-Nov-25 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1
A6620 Crosschecking of Levels 120 26-Jul-25* 11-Dec-25 Crosschecking of Levels
A6630 Bedding for Pipes with approved Material 90 05-Aug-25* 17-Nov-25 Bedding for Pipes with approved Material
A6640 Laying of Pipes and Welding 45 25-Aug-25* 15-Oct-25 Laying of Pipes and Welding
A6650 Testing 30 25-Aug-25* 28-Sep-25 Testing
A6660 Concreting Work for Pipes and till Transition Slab 60 12-Oct-25* 20-Dec-25 Concreting Work for Pipes and till Transition Slab
A6670 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 25-Nov-25* 26-Feb-26 Chamber Including Reinforcement and Concreting with Connection from Cat
A6680 Pre-Cast Concrete Cover Slab Work 20 03-Feb-26 26-Feb-26 Pre-Cast Concrete Cover Slab Work
A6690 Backfilling & Compaction 40 27-Nov-25* 12-Jan-26 Backfilling & Compaction
A6700 Block Work With Ring for Opening and Grating 35 11-Dec-25* 21-Jan-26 Block Work With Ring for Opening and Grating
A6710 Connections with Existing Network 15 12-Jan-26* 28-Jan-26 Connections with Existing Network
EWF-HI.4.1.3 Line 2-4-3 & 2-4-5 256 11-Sep-25 06-Jul-26 06-Jul-26, EWF-HI.4.1.3 Line 2-4-3 & 2-4-5
A6720 Survey and Marking for Line 1-1-6 85 11-Sep-25* 20-Dec-25 Survey and Marking for Line 1-1-6
A6730 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6 80 20-Dec-25 23-Mar-26 Excavation for Surface/ Pipe Drainage and Manhole Work Line 1-1-6
A6740 Crosschecking of Levels 120 13-Dec-25* 30-Apr-26 Crosschecking of Levels
A6750 Bedding for Pipes with approved Material 90 17-Jan-26* 30-Apr-26 Bedding for Pipes with approved Material
A6760 Laying of Pipes and Welding 45 10-Mar-26* 02-May-26 Laying of Pipes and Welding
A6770 Testing 30 05-Apr-26* 09-May-26 Testing
A6780 Concreting Work for Pipes and till Transition Slab 60 05-Apr-26* 13-Jun-26 Concreting Work for Pipes and till Transition Slab
A6790 Chamber Including Reinforcement and Concreting with Connection from Catchin Basin 80 05-Apr-26* 06-Jul-26 Chamber Including Reinforcement and Concreting with Con
A6800 Pre-Cast Concrete Cover Slab Work 20 14-Jun-26 06-Jul-26 Pre-Cast Concrete Cover Slab Work
A6810 Backfilling & Compaction 40 13-Apr-26* 30-May-26 Backfilling & Compaction
A6820 Block Work With Ring for Opening and Grating 35 22-Apr-26* 01-Jun-26 Block Work With Ring for Opening and Grating
A6830 Connections with Existing Network 15 20-May-26* 07-Jun-26 Connections with Existing Network
EWF-HI.4.2 Protection Work 377 07-Jun-25 19-Aug-26 19-Aug-26, EWF-HI.4.2 Protection Work
EWF-HI.4.2.2 Establishment of Dyke 1 Near Existing Dyke 117 20-Dec-25 04-May-26 04-May-26, EWF-HI.4.2.2 Establishment of Dyke 1 Near Existing D
A6840 Survey and Existing levels of the location 20 20-Dec-25 12-Jan-26 Survey and Existing levels of the location
A6850 Filling Material to Establish Dyke 1 in layers 90 20-Dec-25 04-Apr-26 Filling Material to Establish Dyke 1 in layers
A6860 Compaction of material in layers and slopes 80 06-Jan-26* 09-Apr-26 Compaction of material in layers and slopes
A6870 Final Inspection of the Dype 1 80 01-Feb-26* 04-May-26 Final Inspection of the Dype 1
EWF-HI.4.2.3 Establishement of Dyke 2 151 29-Jan-26 23-Jul-26 23-Jul-26, EWF-HI.4.2.3 Establishement of Dyke 2
A6890 Survey and Existing levels of the location 15 29-Jan-26* 15-Feb-26 Survey and Existing levels of the location
A6900 filling the material as per approved/excavated material 80 04-Apr-26 06-Jul-26 filling the material as per approved/excavated material
A6910 Compaction of material in layers and slopes 70 27-Apr-26* 16-Jul-26 Compaction of material in layers and slopes
A6920 Filling the material up to the proposed level 65 05-May-26* 20-Jul-26 Filling the material up to the proposed level
A6930 Final Inspection of the Dyke 2 2 20-Jul-26 22-Jul-26 Final Inspection of the Dyke 2
A6980 Handing Over with Related Dcoments 1 22-Jul-26 23-Jul-26 Handing Over with Related Dcoments
EWF-HI.4.2.4 Rehaping of Proposed Wadi 139 16-Feb-26 27-Jul-26 27-Jul-26, EWF-HI.4.2.4 Rehaping of Proposed Wadi
A6940 Survey to take initial levels 25 16-Feb-26 16-Mar-26 Survey to take initial levels
A6950 Proposed levels to maintain the flow 15 16-Feb-26* 04-Mar-26 Proposed levels to maintain the flow
A6960 Cutting and Filling Work 80 04-Apr-26 06-Jul-26 Cutting and Filling Work
A6970 Dressing of the Sides and Compaction 75 30-Apr-26* 26-Jul-26 Dressing of the Sides and Compaction
A6990 Handing Over with Related Dcoments 1 27-Jul-26 27-Jul-26 Handing Over with Related Dcoments
EWF-HI.4.2.1 Concrete Work/Box Curvert 326 07-Jun-25 22-Jun-26 22-Jun-26, EWF-HI.4.2.1 Concrete Work/Box Curvert
A4080 Box culvert N2 Size 2x1.5m concrete class Blinding C15 200 07-Jun-25* 26-Jan-26 Box culvert N2 Size 2x1.5m concrete class Blinding C15
A4090 Concrete Class 35 in box culverts wing walls apron slab 166 06-Sep-25* 17-Mar-26 Concrete Class 35 in box culverts wing walls apron slab
A4100 Concrete Class 35 in box culverts Retaining walls 150 25-Oct-25* 16-Apr-26 Concrete Class 35 in box culverts Retaining walls
A4110 Reinforcement as per HDS 2017 104 18-Jan-26* 18-May-26 Reinforcement as per HDS 2017
A4120 High tensile steel bar factory epoxy coated reinforcement 50 25-Apr-26* 22-Jun-26 High tensile steel bar factory epoxy coated reinforcement
EWF-HI.4.2.5 Bitumen/Asphalt Work 161 26-Jan-26 01-Aug-26 01-Aug-26, EWF-HI.4.2.5 Bitumen/Asphalt Work
A3940 2 Coats of Bitumen Paint for concrete structure 35 26-Jan-26 08-Mar-26 2 Coats of Bitumen Paint for concrete structure
A3950 4mm Geotextile Memberane for concrete structure 25 09-Feb-26* 10-Mar-26 4mm Geotextile Memberane for concrete structure
A3960 Subgrade Sub Base work 45 15-Mar-26* 05-May-26 Subgrade Sub Base work
A3970 Bituminous Prime Coat Application rate 1.5 KgSq.m 40 06-May-26 21-Jun-26 Bituminous Prime Coat Application rate 1.5 KgSq.m
A4040 Bituminous Wearing Course Class B 35 22-Jun-26 01-Aug-26 Bituminous Wearing Course Class B
EWF-HI.4.2.6 Slope Protection & Stabilization Work 120 02-Apr-26 19-Aug-26 19-Aug-26, EWF-HI.4.2.6 Slope Protection & Stabili
A7000 Levelling and Compaction of the slopes 40 02-Apr-26* 18-May-26 Levelling and Compaction of the slopes

A7010 Mortard Riprap work including filter memberance 50 19-May-26 15-Jul-26 Mortard Riprap work including filter memberance

A7020 finishing work and cleaning 30 16-Jul-26 19-Aug-26 finishing work and cleaning

EWF-HI.7 Demobilization 42 02-Aug-26 19-Sep-26 19-Sep-26, EWF-HI.7 Demobilization

A4220 Demobilization of Machinery & Equipment 15 02-Aug-26* 18-Aug-26 Demobilization of Machinery & Equipment
A4230 Engineering Facility 15 19-Aug-26 05-Sep-26 Engineering Facility
A4240 Successive/Completion Certificate 12 06-Sep-26 19-Sep-26 Successive/Completion Certificate
A4260 Project Signout Document 5 14-Sep-26 19-Sep-26 Project Signout Document

EWF-HI.6 Project Handing Over 98 09-Jun-26 30-Sep-26 30-Sep-26, EWF-HI.6 Project Handing Over

A4130 Handing Over of Drawings 30 09-Jun-26* 13-Jul-26 Handing Over of Drawings


A4140 Handing Over of Testing & Comissioning Reports 18 14-Jul-26 03-Aug-26 Handing Over of Testing & Comissioning Reports
A4150 Handing Over of Material Approval Docuements 15 04-Aug-26 20-Aug-26 Handing Over of Material Approval Docuements
A4160 Handing Over of Warannty Guaranttee Documenta 12 22-Aug-26* 03-Sep-26 Handing Over of Warannty Guaranttee Documenta
A4170 Finally Progress Report Incompliance with Inventory 10 05-Sep-26 15-Sep-26 Finally Progress Report Incompliance with Invento
A4180 Reports By Consultant 5 16-Sep-26 21-Sep-26 Reports By Consultant
A4250 Handing Over of Keys 5 26-Sep-26* 30-Sep-26 Handing Over of Keys