Module 2 Part 2 and 3
Module 2 Part 2 and 3
8. Finishing
5. Installation of Forms
9. Installation of RC Box Culvert easy compaction of material done
using hand tampers to ensure a
thoroughly tampered backfill
➢ After backfilling, pipe culverts are
protecting by providing extra fill as
cover before any heavy equipment is
permitted to cross during the
construction of the roadway to
protect the job from possible
damage by excessive loads
10. R.C. Pipe Culvert Slope Protection/Retaining Structures
a. Installation of RC Pipes
❖ These are constructed along the side of the
➢ Pipes are installed in the original
road as protection from erosion or if there
streambed with their grades and flow
are space constrictions
line conforming to the natural channel
❖ Erosion of Side Slope
or canal
➢ Laying begins at downstream end
of the culvert line to use gravity in
properly installing the pipes
➢ Grove ends are placed such that the
pipe ends fit at its nearest ends
➢ Lower segment of each pipe should
be in contact with the shape of the
bedding throughout its full length
b. Collaring of RC Pipes
➢ Mortar proportion is 1:2 with
enough water to obtain the desired ❖ Some of the Types of Slope Protection
consistency Structures:
➢ The collar is to form a continuous 1. Grouted Riprap
bead around the outside of the
pipe
➢ The inside of pipe is finished smooth
c. Backfilling
➢ Backfill are place and compacted in
layers not exceeding 15cm on both
sides up to an elevation of 30cm
above the top of the culvert a. Excavation of Foundation – a
➢ Spreading may be done manually backhoe is an ideal equipment to
using rakes and shovels at a thin use in the excavation of foundation for
layer which is most ideal to produce grouted riprap
b. Use of Batterboards as Guide – 2. Stone Masonry (specifications)
good workmanship requires a ➢ Boulders – thickness of not less
reliable reference to guide the work than 150 mm, and widths of not less
up to completion. The unevenness of than one and one-half times their
the embankment slopes is then respective thickness, and lengths of
trimmed using shovels and rakes. not less than one and one-half
The high areas are removed and times their respective widths
patched and compacted to low areas ➢ Mortar – composed of one part of
until a flat surface is attained Portland Cement and two parts of
c. Laying of Boulders and Grout – fine aggregate by volume and
boulders and grout are placed later sufficient water to make the mortar
by layer alternately. Each stone is such consistency that it can be
laid with its longest axis handled easily and spread with a
perpendicular to the slope in close trowel
contact with the adjacent stone. The a. Excavating Stone Masonry
riprap is thoroughly rammed into Foundation – the foundation bed
place and the finished stone are laid where the masonry is to be placed
to an even tight surface. Spaces should be firm and normal to the
between stones are filled with cement face of the wall. The bed that will
mortar sufficient enough to fill receive the stone should be clean
completely all the voids and moistened before the mortar is
d. Finishing Work – cement grout is spread
placed starting from the bottom to b. Use of Batterboards Essential to
the top of the surface and then Produce Good Workmanship – as
swept with a stiff broom. After in grouted riprap, batter boards are
grouting, the surface is cured for a necessary to keep the lines and
period of at least 3 days from the grades of the finished stone
date of installation masonry structure in accordance
e. Measurement of Thickness to the lines and grades of the plans
f. What is the importance of weep c. Laying of Boulders and Grout –
holes in slope protection/retaining large stones are used in the corners.
structure? – weep holes are Bunching of small stones of the
opening provided to permit same size is not allowed. Stones
draining of water in filter layer or soil are laid with their longest face
layer from behind the structure. If no horizontal in full beds of mortar. Joints
or insufficient weep holes are are flushed with mortar. The exposed
installed, this will cause face of the individual stone should be
oversaturation of the embankment parallel to the face of the wall in
and the subsequent failure of the road which stones are set. The stones
structure are handled carefully so as no to ajar
or displace the stones already set
d. Finishing Work – immediately after c. The lids are then stretched over
laying and while the mortar is still the stone fill and laced down
fresh, all face should be thoroughly d. Corners are secured first to
cleaned of mortar stains and make sure the lid can be laced
should be kept clean until the work down without overstretching the
is completed. mesh
3. Gabions e. The lids are then laced down
securely
4. Reinforced Concrete
c. Informatory Sign
Completed Parapet
Specifications
o Sign assembly/fabrication
o Surface preparation of sign blanks
o Application of reflectorized sheeting
o Installation