RADIANT SQUARE AT CITY OF LIGHTS

ITP FOR TESTING AND COMMISSIONING OF LIGHTING CONTROL SYSTEM

Survey, Test INSPECTION


Activity Specification and/or or Acceptance CHECKLIST FORM Verification CRITERIA
No. Frequency Record
Description Drawing No. Inspection criteria REFERENCE NO. Responsibility
S C E/C
Method
All documents
should have
Review of the As per approved Shop Validation Of Final Approved Method
1 approved methods N/A H H H
relevant drawing drawings Document Approval Statement/ Drawings
statements and
drawing
Check Materials
Visual/ Review All documents to
approvals and
of documents/ have approval
conformity checks As per approved MAR , (all WIR Nos from
2 Material Method Statement, As applicable Inspection form H H H
on arrival of DO Main Contractor)
Inspection with materials submittal
associated
Consultant and drawings
materials
Material As per MAR, Delivery Approved Method
3 Inspection and Note and Country of Visual Statement and All delivery MIR Checklist Materia Inspection Form H H H
Storage Origin material
TESTING AND COMMISSIONING INSPECTION
Approved Method
As per Project Every
4 Pre- Statement, Approved Shop Drawing
Specification and Visual completed ITP-EL-LCS-CTS-0001 H H W
commissioning applicable standard and Method Statement
approved shop drawings area
and Drawing
Approved Method
As per Project Every
Statement, Approved Shop Drawing
5 Commissioning Specification and Visual completed ITP-EL-LCS-CTS-0002 H H W
applicable standard and Method Statement
approved shop drawings area
and Drawing
SURVEY TEST OR INSPECTION METHOD - LEGEND:

W = Witness (attendance expected, signature on check sheet) C = Main Contractor


H = Hold Point (signature required to proceed) S = Subcontractor
S = Surveillance (random attendance, no signature required) E/C = Engineer / Client
A = Approval
R = Review record
IR= Inspection request

Rev. Date Description By Approved


INSPECTION AND TEST PLAN FOR LIGHTING
00 12/10/2024 ATGC ENGR