13 Pile Load Test
13 Pile Load Test
Kentledge Bi-
The bearing capacity of
deep foundations Load Test Directional
Pile Jack-in Load Test
Load Test
To study the behavior of
pile settlement under the
applied loads
Static Load Test
a) The general testing method is to impose a static vertical load on a test pile for certain duration
and with increment on loads intervals and required cycles.
b) Static load test differs from the statnamic load test and dynamic load testing in that the
pressure applied to the pile is slower.
c) Static load test can be executed by Kentledge or Pile Jack-in Machine.
Prior to testing, load test equipment should be completely set out on firm ground.
The kentledge / pile jack-in machine shall be placed directly on top of the centroid of a mild
steel plate which rest directly on top of the pile.
When vertical load is imposed, the pressure applied to the jack shall be measured by
calibrated pressure gauge.
LOAD
CELLS
LOAD
CELLS
HYDRAULIC
Scales JACKS HYDRAULIC
For JACKS
Precise
Level
V W Strain
Gauge
CABLES
LVDTs LVDTs
Method of Testing for
Static Load Test
The pile is tested from zero landing to 2 times of the working load design for the pile.
Testing will be done in 2 cycles, 1st cycles for 100% of working load, 2nd cycle for 200% of
working load.
The load increments shall be 25% of working load with
minimum holding time of 2 hours. For load decrement, Working Min holding
Cycles
the test load shall be decreased in 4 equal stages with load (%) time (hour)
60 minutes interval. 25 2
50 2
Working Min holding 75 2
Cycles
load (%) time (hour) 100 2
25 2 125 2
50 2 150 2
nd
75 2 2 Cycles
175 2
1st Cycles 100 12 200 24
75 1 150 1
50 1 100 1
25 1 50 1
0 1 0 1
Method of Testing for
Static Load Test
Introduction
➢ The Osterberg Cell® (O-Cell®) is one of alternative method of static load testing for drilled
shafts and piles.
➢ The O-Cell is a hydraulically driven, individually calibrated, sacrificial loading device installed
within the foundation unit.
➢ Working in two directions, upward against side-shear resistance and downward against end-
bearing resistance, the O-Cell automatically separates the resistance and displacement data
for each component of the pile. The jack provides the static loading which required no
external loading / reaction system.
➢ Testing is performed until either ultimate upward or downward capacity is reached or the
maximum O-Cell stroke or load capacity is reached. Use of strain gages within the foundation
can help to determine the distribution of load throughout the foundation length.
Bi-Directional
Load Test
(Osterberg Cell)
Objectives :
Principle of Testing
a) The test analyses and determine shear resistance and end bearing capacity of piles under
test especially is restricted site access. The cells assembly location will ideally be located
at the middle of total pile capacity (= skin friction + end bearing).
b) The main aim of positioning the assembly will be to “balance” the bi -directional forces in the
pile so that failure in one direction does not occur prematurely.
c) Two main features of bi-directional testing, which can make it preferable over top down static
load testing, are:
i. Saving in terms of cost, transport, installation and erection of kentledge, anchors or anchor
piles as well as the associated reaction system required above ground level.
ii. Significant improvement in terms of safety; assembly of a loading system at the head of
the pile is not required and the loads applied are buried.
Bi-Directional
Load Test
(Osterberg Cell)
Test Results
5. Attachment of the
sensors and measuring 6. Lifting of rebar 7. Rebar cages lower
apparatus. cages into bored hole. down to bored hole.
Bi-Directional
Load Test
(Osterberg Cell)
Bi-Directional Installation
Dynamic Load Testing is performed using the Pile Driving Analyser (PDA). The CAPWAP
computer software is develop for PDA test data acquisition which allow full and
accurate analysis of the PDA filed data.
PDA tests is a High Strain Dynamic Load Tests which can be applied after pile
installation for concrete piles. The test consists of estimating soil resistance and its
distribution from force and velocity measurements obtained near the top of a
foundation impacted by a hammer or drop weight. The impact produces a compressive
wave that travels down the shaft of the foundation.
Dynamic Load
Test
Test Operation
When vertical load is imposed, the pressure applied to the jack shall be measured by
calibrated pressure gauge.
Dynamic Load
Test
Test Operation
A pair of strain transducers obtains the signals necessary to compute force, while
measurements from a pair of accelerometers are integrated to yield velocity. These
sensors are connected to an instrument, that records, processes and displays data and
results.
Dynamic Load
Test
Test Operation
These reflections travel upward along the shaft and arrive at the pile top at times that
are related to their location along the shaft.
The sensors near the pile top take measurements that translate what is happening to
the traveling waves and make it possible to estimate soil resistance and its
distribution.
Dynamic Load
Test
Termination of Test