Steady State Simulation of 33 KV Power Grid
Steady State Simulation of 33 KV Power Grid
http://www.scirp.org/journal/jpee
ISSN Online: 2327-5901
ISSN Print: 2327-588X
Electrical and Electronics Engineering, University Malaysia Sabah, Kota Kinabalu, Malaysia
Keywords
Load Flow, Contingency Analysis, PV Curve, Voltage Stability, Overload,
Voltage Deviation Violation
1. Introduction
In Sabah grid, the power demand is increasing annually but the generated capac-
ities is less than the power demand, especially in the east coast [1]. The current
equipments in transmission system such as electricity cable are getting old and
are found operated closer to their limits of stability and cannot withstand with
increased power supply [2]. Due to these, the grid system is exposed to distur-
bances or contingencies which can cause system collapse and blackout. Sabah
faced two major serious blackouts [1]. The most severe blackout happened in
2014 for 10 hours of state-wide blackout. The collapse is triggered by flashover
which is from conductor of 132 KV transmission line. Another one is blackout
in the whole east coast due to outage of 275 KV transmission line.
DOI: 10.4236/jpee.2018.66007 Jun. 29, 2018 106 Journal of Power and Energy Engineering
K. H. Teck, N. Barsoum
As stated in Sabah grid Code [3], most of transmission lines, distribution and
transformers fulfil N-1 contingency requirement, but in fact studies showed that
there is no N-1 contingency in aging existing transformer and existing line con-
figuration [2]. Therefore, when N-1 contingency happens, overload conditions
occur on those transformers, distribution and transmission lines.
Contingency analysis has been developed by [4] using sensitivity factors to
approximate power flow on branches whereas voltage performance index is used
by [5] to approximate the contingency voltage on a certain bus in a power sys-
tem. For voltage stability part, [6] reviewed four commonly used voltage stability
analysis tools which are PV/QV curve analysis, L index, Modal analysis and
V/Vo index. Authors have done comparison of accuracy results on IEEE bus
power system.
This paper focuses on steady state stability for distribution level of power grid.
Thus, 33 KV Sandakan network of Sabah Grid System is chosen to simulate
steady state stability which consists of load flow simulation, contingency simula-
tion and P-V curve. Contingency scenarios are created to test its overall steady
state stability of the grid in terms of contingency voltage deviation violation and
percentage overload. Moreover, P-V analysis is performed to determine the
weakest buses in the network. The process of analysing the stability can be
daunting and challenging if the power network is highly complex, large size and
non-linear. The process takes a lot of time in the calculations to access all the
power variables and contingencies [7]. Therefore, a Power System Simulation for
Engineers (PSS/E) software is utilized to perform all power flow computations in
this steady state analysis.
powers, power losses for generators, load and generator buses, distribution and
transformer branches, and loads in the Power network. There are two types of
solutions in PSS/E: Newton Raphson and Gauss Seidel load flows. Due to com-
plexity and large number of buses in N-1 power network, Newton Raphson is
chosen due to faster converging rate and repetitive complicated computation of
Jacobian matrix and its minimal sensitivity. For contingency cases, Fixed Slope
Decoupled load flow which is part of Newton Raphson created by Siemens
Company is chosen as it performs better in difficult and complicated cases
Table 2. Total generated power in sandakan before and after N-1 outage.
main supply outage from 275 KV transmission line with respect to the total gen-
erated capacity. The table shows that the power demand increase by 13.34 MW
from 98.76 MW after the outage, but they are within the total generated capacity.
Table 3 shows the load flow results for all in-service branches (transformer
and distribution). Note: DB is distribution branch, TB is transformer branch.
Transformer branches are found higher active and reactive power losses, higher
percent of voltage drop, higher current flows and higher active and reactive
power flows than that in distribution branches. Only transformer branches have
higher loadings problem compared to distribution branches. For distribution
branches, DB10_1 is recorded with highest power losses. For transformer
branches, TB3 is recorded with highest reactive power loss and TB5 and TB6
share the highest active power losses. TB2 is recorded with highest percent of
voltage drop among all branches, followed by DB2_1 and DB2_2. DB14_1,
DB14_2, DB17_1 and DB17_2 are recorded with zero among all variables.
Table 4 and Table 5 show the load flow results for all in-service buses. Load
buses are represented by bus code 1 while generator buses are represented by bus
code 2. UB_33 and BM_33 are recoded zero in active and reactive power flows
and current flows due to no loads connected to them. Generator buses are rec-
orded higher current flows compared to load buses. All bus voltages are within
contingency voltage range stated by Distribution Code of Energy Commission.
The voltage range is from 0.9 pu to 1.1pu. That means all bus voltages are safe
and secure under N-1 case which is disconnected from main grid supply.
This load flow analysis shows that all bus voltages are slightly higher than
100% and 2 load buses are overloaded as well as 3 generators generating out of
limits.
4. Contingency Analysis
To compute the branch power flows after certain level of outage, contingency
sensitivity factors are used to approximate the change in line flows and the
changes in generation in a power system. It is one of fastest way to calculate
possible overloads in a power system network. The main two sensitivity factors
are Generation Shift Factors (GSF) and Line Outage Distribution Factors
(LODF).
For GSF part, the generation factor is defined as changes in power flow in par-
ticular line when a change in power generation at reference bus occurs.
Generation shift factors,
∆PFl
α li = (1)
∆PGi
DB14_1 0 0 0 0 0
DB14_2 0 0 0 0 0
Buses Bus Code Bus Voltage (pu) MW Loading MVAr Loading Amp Loading
BM_33 1 1.0316 0 0 0
UB_33 1 1.032 0 0 0
∆PFl
dli = (2)
Pi o
Load Buses Id MW Flows (kW) MVAr Flows (kVAr) Current Flows % PF % Loading
It informs load flow simulator the branches needed to be monitored when N-1
*mon.file contingency happens. It also monitors and records the bus voltages within specific
ranges or outside the range.
It tells load flow analysis to consider and perform at specific zone. It includes all
*sub.file
involved power network elements in the case study.
It is used to trip line or power elements to create contingency scenarios. Three types
*con.file of contingencies: N-0 (system intact), N-1 (single power element outage) and N-2
(two power elements outage). In this case, N-1 is chosen.
Table 7. List of affected branches with respective total number of involved cases and overload percent.
Affected Branches
No. of Cases Involved Overload Percent
From Bus To Bus
Id from Total 38 contingency Cases Ranges (%)
No Name No Name
1 KB_6.6 4 KB_33 1 38 174.0 - 228.1
2 SB_6.6 3 SB_33 1 38 173.4 - 238.3
6 TS_33 8 BS_33 2 1 110.2
8 BS_33 28 BN_11 1 38 110.5 - 142.0
14 SA_33 16 LP_33 1 8 101.8 - 165.0
14 SA_33 16 LP_33 2 8 101.8 - 165.0
Figure 3. N-1-1 case with affected buses when outage of transformer branch from bus 8 to bus 28.
Table 8. List of unaffected branches throughout all contingency cases (N-1 and N-1-1
cases).
Unaffected Branches
16 LP_33 29 LD1_11 1
16 LP_33 32 LD2_11 1
16 LP_33 33 LD3_11 1
16 LP_33 34 LD4_11 1
11 PI_33 23 GN_11 1
3 SB_33 26 SD2_33 1
4 KB_33 26 SD2_33 2
5 SD_33 14 SA_33 1
5 SD_33 14 SA_33 2
5 SD_33 26 SD2_33 1
6 TS_33 7 SM_33 1
6 TS_33 7 SM_33 2
6 TS_33 8 BS_33 1
6 TS_33 8 BS_33 2
6 TS_33 26 SD2_33 1
6 TS_33 26 SD2_33 2
9 KG_33 10 LD_33 1
9 KG_33 10 LD_33 2
9 KG_33 11 PI_33 1
9 KG_33 11 PI_33 2
11 PI_33 12 MS_33 1
11 PI_33 12 MS_33 2
11 PI_33 14 SA_33 1
11 PI_33 18 SC_33 1
14 SA_33 16 LP_33 1
14 SA_33 16 LP_33 2
14 SA_33 18 SC_33 1
14 SA_33 20 BM_33 1
14 SA_33 20 BM_33 2
15 SR_33 17 LK_33 1
17 LK_33 26 SD2_33 1
17 LK_33 26 SD2_33 2
18 SC_33 19 UB_33 1
18 SC_33 19 UB_33 2
Figure 4. PV curve.
by 6 cases with 306.25 MW and 5 cases with 287.50 MW. The only one case with
the lowest maximum additional power transfer (143.75 MW) happened when
outage of transformer branch from bus 8 to bus 28. That means all buses can
only withstand incremental power transfer up to 143.75 MW when this outage
happens. That is why this case has only voltage violation cases, referring to
Table 8. They cannot withstand higher power flows compared to other cases.
Among all P-V curves, almost all buses except generator buses have their vol-
tage collapse point at below 0.9 pu. That is not reasonable that the steady state
operating voltage is within 10% of the nominal voltage, from 0.9 pu to 1.1 pu.
Since the weakest case is SINGLE 8-28 (1), in order to determine weakest buses,
the maximum incremental power transfer at 0.9 pu of the nominal voltage is de-
termined for each bus. Any voltage which is outside of the tolerance is not ac-
ceptable. Figure 5 shows the finding of maximum additional power transfer at
Table 10. List of number of contingency cases and the maximum additional power transfer.
0.9 pu. Table 11 shows the maximum additional power transfer at 0.9 pu for
each bus with respective voltage collapse point at contingency case named
SINGLE 8-28.
From Table 11, the generator buses (KB_6.6, SB_6.6, BN_11, GN_11,
LD1_11, LD2_11, LD3_11 and LD4_11) have maintained constant bus voltage
along all incremental power transfer. This is because no losses involved when the
generators generate the output voltage to the nearest buses. The loss will be very
small. Any bus that withstand below 50% of the 143.75 MW is considered as
weakest buses. Therefore, the weakest buses are SB_33, KB_33, SD_33, TS_33,
Table 11. List of all buses with their respective maximum additional power transfer at 0.9
puin weakest contingency case (Single 8-28).
9 KG_33 80 0.812
10 LD_33 80 0.807
11 PI_33 83 0.827
12 MS_33 86 0.821
14 SA_33 92 0.843
18 SC_33 91 0.834
19 UB_33 91 0.834
20 BM_33 92 0.843
16 LP_33 98 0.850
3 SB_33 26 0.618
4 KB_33 26 0.618
5 SD_33 26 0.618
6 TS_33 8 0.349
7 SM_33 6 0.334
8 BS_33 8 0.333
15 SR_33 29 0.618
17 LK_33 29 0.618
26 SD2_33 27 0.618
SM_33, BS_33, SR_33, LK_33, and SD2_33. The results from P-V actually corre-
late with the Contingency Voltage Violation results shown in Table 9.
6. Conclusions
Sandakan power network has serious overload condition on generating units
compared to other distribution lines. This paper shows that 3 generators out of 8
are generating out of the limits. For all loads, a vast majority of loads are margi-
nally overload. There are 9 weakest buses determined at weakest N-1-1 contin-
gency case via P-V curve and Contingency analysis. The buses are found
dropped out of the contingency voltage deviation criterion and can withstand
smaller power transfer after the power exceeds their bus power limit.
Contingency analysis is a very important and useful tool in planning the un-
planned electrical outages. It can predict the future power system conditions
under outages. It evaluates how many those buses survive under outages and
those didn’t. In this case, PSS/E is able to perform contingency analysis within
seconds and provide with accurate results. To improve its stability, two types of
FACTS devices are recommended: UPFC and STATCOM. UPFC is used to
compensate power flows to reduce overload condition whereas STATCOM is
used to maintain bus voltage for better voltage profile.
References
[1] (2015) Sabah Electricity Outlook 2015. Energy Commission Malaysia, 1-60.
[2] Songkin, M., Barsoum, N.N., Wong, F. and Lim, P.Y. (2017) A Study on Sabah Grid
System Stability. 2017 IEEE 2nd International Conference on Automatic Control
and Intelligent Systems (I2CACIS 2017), 207-212.
[3] Grid Code for Sabah and Labuan (Amendments) 2017 (2017) Energy Commission
Malaysia (Suruhanjaya Tenaga Malaysia). 1-206.
[4] Satyanarayana, B., Deepak, J. and Khyati, D. (2016) Contingency Analysis of Power
System by Using Voltage and Active Power Performance Index. 1st IEEE Interna-
tional Conference on Power Electronics, Intelligent Control and Energy Systems
(ICPEICES), 1-5.
[5] Roman, V. and Lucie, N. (2015) Sensitivity Factors for Contingency Analysis. Insti-
tute of Electrical and Electronics Engineering (IEEE), 1-5.
[6] Reis, C., Andrade, A. and Maciel, F.P. (2009) Voltage Stability Analysis of Electrical
Power System. Institute of Electrical and Electronics Engineering (IEEE), 244-248.
[7] Barsoum, N., Asok, C.B., SzuKwong, D.T. and Kit, C.G.T. (2017) Effect of Distri-
buted Generators on Stability in a limited bus Power Grid System. Journal of Power
and Energy Engineering, Scientific Research Publishing, 5, 74-91.
Appendix
Table A1. Buses Data Used in PSS/E.
Bus No. Bus Name Bus Code Base kV Voltage (pu) Angle (deg)
Transformer Branches
Tap Winding
From Bus To Bus
Id Positions MVA Base
No Name No Name
Distribution Branches
RATE1 Length
From Bus To Bus Line R (pu) Line X (pu)
Id (MVA) (mile)
No Name No Name