How To Create A PERT Chart Step by Step
How To Create A PERT Chart Step by Step
Part of project planning and critical path calculation by the PERT method requires the development of a
network diagram that clarifies the relationships between activities of a project. In this post you will find
out how to create a PERT Chart step by step with practical examples.
It is important to point out that in this article we will only focus on the elaboration of the PERT network
diagram; the calculations for the determination of the critical path will be dealt with in another topic.
The PERT chart is a graphical representation of the project network, which shows the sequence of
activities of a project and the dependency relationships between them, in order to facilitate and help
managers to monitor and control projects.
An activity “B” depends on another “A”, when activity “B” cannot start until activity “A” is finished. To
give an example, we have the following project activities:
If the plans aren't designed first (A), they cannot be printed (B); therefore, activity “B” is
considered to be dependent on activity “A“. You can also say that activity “A” precedes activity
“B“.
The relationship between the activities described is known as “Finish to start (FS)“. There are 3
types of relationships for other types of more complex projects; however, for our network
diagram we will use FS.
What Is the Difference Between PERT Chart and CPM Chart?
It is also important to note that, although the PERT and CPM methods have some differences in
their application, both techniques require the development of the network diagram. That is
why, in other literature, this graph is known as CPM network diagram or CPM chart. Even so, at
present the differences between the two techniques are minimal and, on the contrary, they
complement each other to form a broader theory.
Depending on the way the activities are represented, our PERT network can be drawn one of
two ways:
1. Activities on nodes (AON): The nodes in the graph represent the activities of the project,
and the arrows show the relationship with the immediate predecessor.
2. Activities on arrows (AOA): The arrow indicate the activity and their starting and
terminating points are represented by the nodes.
Our PERT chart can be represented using both ways; however, here we'll explain the AON
network diagram.
Below are the AON graphical representations for certain relationships that occur in project
activities:
5. C cannot begin until both A and B are completed; D cannot begin until B is completed.
6. B and C cannot begin until A is completed. D cannot begin until both B and C are completed.
At this point you should already have a clearer idea of how to draw and link your activities according to
the relationships they have.
Step 4: Mapping dependencies: Once the activities have been represented, the nodes should be
joined with arrows according to the dependency relationships. Crossings between the lines
should be avoided as much as possible.
To better understand how to create a PERT diagrams, we will examine some examples:
Draw the activity-on-node (AON) project network associated with the following activities for Dave
Carhart's consulting company project.
Solution 1:
To start our network diagram, we place a fictitious node that establishes the
beginning of our project and from where the first activities, which have no
precedents, will come from (Activity A):
Activity F has activity C as its immediate precedent and activity G depends on activity D:
Activity H depends on two activities: E and F; therefore, it must be connected to both nodes:
Activities G and H, which are the final activities, are joined to a dummy node representing the end of the
project:
The above graph represents our PERT network diagram of the example project.
Example 2:
The director of continuing education at Bluebird University just approved the planning for a sales
training seminar. Her administrative assistant identified the various activities that must be done and
their relationships to each other, as shown in Table 1.
G Accept students D
We start our graph with the start node connected to the activities that have no precedents (A, B and C):
Finally, we connect the last nodes to the finish node, and we will have our complete diagram:
Final Reflection
The PERT chart gives us a simple view of the activities of a project and their precedence relationships; it
also represents the starting point for the determination of the critical path of the project; therefore, it is
very important for project managers to elaborate it correctly.