2012 ASCEGeocongress Oakland
2012 ASCEGeocongress Oakland
net/publication/268589293
CITATIONS READS
3 1,855
3 authors, including:
All content following this page was uploaded by Y. S. Ünsever on 05 May 2015.
ABSTRACT
The deformation behavior of Muratli Dam, the first asphalt faced rockfill dam
in Turkey, is investigated for the “end of construction” and “reservoir impoundment”
loading conditions. Two dimensional plane strain finite element analyses are carried
out in order to assess the total stresses, displacements and pore water pressures.
Hardening soil model is used to represent the non-linear, inelastic and stress
dependent behavior of rockfill material. Material model parameters are selected
mainly referring to the previous studies on the dams consisting of similar materials
and then back analyses are performed to determine the parameters which represent
the behavior of the dam. Calculated stresses and displacements by utilizing these
parameters are compared with the observed values for both end of construction and
reservoir filling conditions. It is observed that the overall agreement is quite
encouraging. It can be stated that two dimensional finite element analyses may be
used to predict displacements and stresses with a reasonable agreement.
INTRODUCTION
Rockfill dams with impervious face have been preferred since late 1960’s due
to significant reduction in leakage rate and post-construction deformation (Hunter and
Fell, 2003). Although impervious faced rockfill dams have become popular in recent
years, the design of these structures is largely based on past experience rather than
theory (Cooke, 1984). The study on such type of dams has a significant importance to
investigate the dam safety and define new design criteria for dams which will be
constructed in the future. Finite element method is used to assess the stresses and
deformations in earth and rockfill dams, where the soil behavior is modeled by
nonlinear, inelastic models.
In this study, stresses and deformations both for end of construction and for
full reservoir loading conditions obtained by the finite element (FE) analyses of
Muratli Dam (first asphalt faced rockfill dam in Turkey) are compared with those of
actual observations (Ünsever, 2007). Due to the fact that the dam has a large
length/height ratio, 2D FE analyses are carried out by using Plaxis v7.2 program and
GeoCongress 2012 © ASCE 2012 527
utilizing Hardening Soil Model to capture the nonlinear, inelastic and stress
dependent behavior of rockfill material (Schanz et al., 1999).
Muratli Dam is the first asphalt faced rockfill dam in Turkey and it is located
in East Black Sea Region on Çoruh River. Height of the dam is 42 m from the river
bed and the slope of the dam is 2:1 (H:V) for both upstream and downstream sides.
Volume of the dam body is 1,981 million m3 and crest length of the dam is 280 m.
Muratli Dam has 36 cm thick asphalt impervious face. This technique, applied
mainly on medium height dams, decreases the cost of the project by considerable
amount. Asphalt face provides excellent water-tightness, durability and flexibility
(Singh and Varshney, 1995).
Since the basic geological formation under the dam is approximately 60 m
thick alluvium lying on rock formation, a cutoff wall is constructed down to the rock
surface. Cutoff wall is constructed of impermeable plastic concrete and is designed
with compatible deformability with the subsoil (alluvium). Main rock beneath the
subsoil is agglomerate and lithic-andesite tuff which is hard and sound. The cross
section of the dam is given in Figure 1 with material zoning (all the dimensions are in
meters). The legend for the materials and detailed information about the main zones
of the dam are presented in Table 1.
Instrumentation:
Muratli Dam is heavily instrumented to observe the behavior of the dam. The
instruments used in the dam body are:
• Inclinometers (IC): Measure horizontal and vertical deformations in dam body and
subsoil (alluvium).
• Fill-extensometers (EW): Measure longitudinal displacement between two points in
fill such as horizontal and vertical deformations behind the asphalt face, vertical
deformations at upstream and downstream of cutoff wall and horizontal deformations
along the dam body.
• Earthcells (EC): Measure earth pressures (total normal stresses) in dam body.
• Piezometers (PW): Measure excess pore water pressures to check the cutoff wall’s
impermeability.
In the dam body and cofferdam, 48 fill-extensometers, 4 inclinometers, 51
piezometers and 34 earthcells are placed at two different cross sections (Section A1
and A2). Figure 2 shows the placement of fill-extensometers and Figure 3 illustrates
the piezometers, inclinometers and earthcells locations at cross section A1 (all the
dimensions are in meters).
Table 1. (Continued)
Zone Type
3B Rock Material (Type 2)
3C Random Rockfill
4 Impervious Material
5 Filter Material
6 Riprap
7 Surface Protection Layer
(ICOLD, 1985). Asphalt face material properties are taken as Young’s modulus,
E = 1.0x107 kPa and Poisons ratio, υ = 0.15 based on the studies of Lollino et al.,
2005.
Loading conditions at Muratli Dam can be handled in two parts: the end of
construction (EOC) condition and the reservoir impounding (RI) condition. In the
first case, the dam deformed under its own weight and in the second case, the
deformation is due to the application of water load on the impervious face. In finite
element analyses, stage of construction has a significant effect on stress distributions,
horizontal deformations and especially on vertical deformations (Clough et al., 1967).
Therefore, analyses are carried out in stages to reflect the construction condition. The
finite element mesh with 15-node elements used in the analyses for cross section A1
is given in Figure 4.
reduction factors should be used to account for the valley shape. However, for
Muratli Dam both stress reduction factors are “1.0” since river width to height ratio is
greater than 1.0 (Hunter and Fell, 2003). In Figure 6, calculated and observed total
stresses for cross section A1 are shown for EOC case. Almost all of the data fall in
the region defined by lines with slopes 2:1 and 1:2. But it is seen that some of the
earthcell readings are really smaller than the calculated ones which is assumed to be
arching effect, a common consideration in earthcell placement. Therefore, the contact
between the instrument and the earth fill during placement might have been poor.
calculated to be 0.29% of dam height for section A1, which is in accordance with
Singh and Varshney’s suggestion. From Figure 10, it can be seen that the shear
stresses at dam axes are zero and increase significantly towards the faces. Maximum
shear stresses at upstream and downstream regions are 143 kPa and 93 kPa,
respectively.
the upstream face, whereas downstream half of the dam body is not significantly
affected from impounding (Figure 12). Maximum horizontal and vertical
displacement is 50 mm and 70 mm, respectively.
When reservoir is filled with water, water load pushes the dam body towards
the downstream direction as shown in Figure 13. As a result, negative shear stresses
at upstream decrease considerably and positive shear stresses at downstream increase
significantly. Also, it is observed that shear stress increments are concentrated near
the dam axis.
CONCLUSION
In this study, deformation behavior of Muratli Dam, the first asphalt faced
rockfill dam in Turkey is investigated by two-dimensional finite element program
Plaxis v7.2. Nonlinear, stress dependent and inelastic behavior of the fill materials are
incorporated into the hardening soil model to assess the displacements and stresses
GeoCongress 2012 © ASCE 2012 535
which are compared with the measured values for both end of construction and
reservoir impoundment conditions.
In general, measurements and calculation results are in acceptable range. It
can be said that two-dimensional finite element analyses may yield displacement and
stresses in a range of 50% to 200% of the observed ones. It may have been possible to
predict the stresses and displacements more realistically should there be sufficient
experimental data available.
The study indicates that the locations of the displacement and stress
measuring instruments are generally suitable for the purpose. Maximum displacement
values found at the dam center cannot be compared with the related instrument
readings since inclinometers at these locations have not operated properly. The
malfunctioning of inclinometer casings is attributed to the improper installation and
lack of experience of the maintenance team on these devices. Therefore, maintenance
of instruments during and after the construction is a vital issue.
For further studies, a 3-D analysis can be carried out to understand the effect
of the third dimension.
REFERENCES