Blue Nova - Crane Control Valve Leak
Blue Nova - Crane Control Valve Leak
Portman House
2 Portman Street
London
CONTENTS
INTRODUCTION ....................................................................................................................... 2
SHIPS PARTICULARS................................................................................................................. 2
VESSEL MANNING AT THE TIME OF THE INCIDENT ................................................................ 3
KEY PERSONNEL DURING THE INCIDENT……………..………………………………………………………….… 3
NARRATIVE .............................................................................................................................. 4
REPORTING ............................................................................................................................. 4
INVESTIGATION ....................................................................................................................... 5
IMMEDIATE CAUSE ................................................................................................................. 6
BASIC ROOT CAUSE ................................................................................................................. 6
NON CONTRIBUTORY FACTORS .............................................................................................. 6
CORRECTIVE ACTIONS ............................................................................................................. 6
PREVENTATIVE ACTIONS AND MEASURES ............................................................................. 7
1 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
INTRODUCTION
Vessel on voyage no. 15L, loaded with Egina Crude oil was scheduled for discharging at
SPM-Canaport, Canada.
On 18th Jan 2022, whilst approaching the SPM, vessel commenced heaving SPM tool box from the
tug, during which hoisting speed of Hose handling crane runner was noticed to be slower than
designed.
Consequently, berthing was aborted, and vessel was shifted to anchorage for further investigation.
Attendance from Crane Maker’s approved service technician was arranged for detailed
assessment of the hose handling crane. During planned attendance, internal leak in hoisting
control valve was identified and subject valve was replaced with a spare to restore normal
operation.
Subsequently, vessel safely berthed at SBM at Canaport for planned discharge operations.
SHIPS PARTICULARS
Tonnages:
Gross: 157225
Net: 98981
Summer DWT: 297085 MT @ 21.50 m
Dimensions:
Length O.A: 330.00 m
Length B.P: 316.00 m
Breadth: 60.00 m
Depth: 29.70 m
Machinery:
M/E: Number & Type: 1 x MAN B&W 7S80MC X 1SET.
Power: MCR: 25,480 Kw @ 79 RPM, NCR: 22,940 Kw @ 76.3 RPM
Bow Thruster: None
2 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
The vessel was manned with 27 crew members at the time as follows:
3 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
NARRATIVE
At 1924LT: Terminal inspection completed, during which crane was tested and confirmed to be
working satisfactorily.
At 1930LT: Vessels commenced picking up SPM toolboxes (2 Pcs picked, one at a time).
At 1954LT: SPM toolboxes onboard.
During hoisting the speed of the runner was noticed to be slower than designed.
Consequently, berthing at SBM was aborted and vessel was shifted to the anchorage for further
investigation.
During planned attendance, internal leak in hoisting control valve was identified by technicians
and the hoisting control valve was replaced with a spare to restore normal operation.
REPORTING:
The vessel reported the subject failure to the DPA and Technical Manager.
The vessel made the requisite reports to the designated Charterers and port authorities.
4 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
INVESTIGATION
Prior arrival Canaport, requisite cold weather precautions checks were completed in accordance
with existing QMS procedures.
Further, Hose handling crane was satisfactorily tested and found to be in good working condition.
In accordance with Maker’s guidance for operating the cranes below (-)10°C, the oil temperature
is required to be raised to (+)10°C prior being put in use. Basis same, crane is required to be kept
running in idle condition, to increase the temperature of the oil accordingly up to (+)10°C, prior to
the crane being put in use.
At the time of incident, the ambient weather temperature was around (-)15°C.
Detailed investigation undertaken inferred that ship’s staff had satisfactorily tested the crane,
prior berthing though on completion of planned test, crane power was turned off instead of crane
being run in idle conditions, as recommended by makers.
This occasioned in lowering of hydraulic oil temperature to sub-zero temperature, thereby causing
an increase in viscosity.
Plausibility of minor levels of water content in oil, which would have frozen at such low
temperatures, could have resulted in internal leak of the hoist winch control valve, while crane
was subjected to load.
Additional information:
The subject vessel is fitted with two hydraulic midship hose handling crane with SWL of 20Tons,
with independent hydraulic oil tanks.
Managers confirms that hose handling cranes onboard undergo regular maintenance / inspections
schedules as per approved Planned Maintenance System (PMS), compiled in accordance with
Maker’s recommendation.
Vessel completed dry dock in month of May 2021, during which thorough inspection and extensive
overhaul of the cranes was undertaken by makers approved service engineers.
NON-CONTRIBUTORY FACTORS
The work/ rest hours have been verified and fatigue is not a contributary factor in the incident.
Review of periodic oil analysis results was carried out, and oil analysis was found to be within
limits and suitable for use.
5 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
- Equipment Failure: Hydraulic control valve for hoisting circuit was found with internal leak.
ROOT CAUSES:
NON-CONTRIBUTORY FACTORS
The work/ rest hours have been verified and fatigue is not a contributary factor in the incident.
Review of periodic oil analysis results was carried out, and oil analysis was found to be within
limits and suitable for use.
CORRECTIVE ACTION:
Shore service Technician was arranged for detailed assessment and repairs.
Partial oil was drained and renewed.
Requisite leaking control valve was replaced.
Occasional Class survey was undertaken and normal working of the crane was accredited.
Extensive testing of crane was carried prior berthing.
DOCUMENTS ATTACHED
Shore service Technician service report.
Occasional Class survey attendance report.
6 of 7
Zodiac Maritime
Limited
Zodiac Maritime limited
Portman House
2 Portman Street
London
PREVENTIVE ACTION
7 of 7
Zodiac Maritime
Limited