Method Statement For Testing & Commissioning of RMU and Transformer
Method Statement For Testing & Commissioning of RMU and Transformer
Contractor:
MALAIH INVESTMENT & PROJECT DEVELOPMENT L.L.C.
Consultant:
Document Title
Method Of Statement for Sat 22kv RMU and Transformer
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 2 of 20 Rev.00
Contents
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 3 of 20 Rev.00
1. VISUAL CHECKS
2. REFERENCES
• Project Specification
• Approved Materials
• Manufacturer user Manuals
3. RESOURCES
➢ To ensure that all the preparation and application works are carried out according to
the Contract Specification.
➢ To ensure that the progress of works is carried out according to the planned program
and as per the approved Method Statement.
➢ To ensure that all the equipment’s and materials required to execute the work are
available according to the planned construction program.
➢ To coordinate with the Main Contractor MEP Coordinator & Safety Officer for a safe
and proper execution of the works.
➢ To provide all necessary information and distribute responsibilities to his construction
team.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 4 of 20 Rev.00
➢ To monitor the progress of work in relation with the work program and report to the
Project Manager.
3.3. The Project Engineer/ Site Engineer will be responsible for the following:
➢ The Project Engineer/ Site Engineer will carry out his duties by maintaining continuous
coordination with the Construction Manager on daily basis and ensure proper
distribution of the workforce in the required and planned locations.
➢ To ensure that his assistant foreman/ charge hand is aware of the job requirements
and they have enough information to carry out their duties properly.
➢ To ensure in consultation with the Construction Manger that the manpower involved in
the works are moving as agreed and planned for the work.
➢ To ensure that the daily work is progressing as planned and as advised by the
Construction Manager of any requirement for additional resources
➢ To control disposal of waste materials according to the instructions received from the
Construction Manager.
➢ To ensure full coordination with the Safety Officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure
that all his working team are aware of the same to prevent accident and losses.
➢ To inform the Construction Manager of the areas ready for inspection.
➢ The foreman will carry out his duties by maintaining continuous coordination with the
Site Engineer on daily basis and ensure proper distribution of the workforce in the
required and planned locations.
➢ To ensure that his assistant foreman/ charge hand is aware of the job requirements
and they have enough information to carry out their duties properly.
➢ To ensure in consultation with the Project Engineer that the manpower in volved in the
works are moving as agreed and planned for the work.
➢ To ensure that the daily work is progressing as planned and as advised by the Site
Engineer of any requirement for additional resources
➢ To control disposal of waste materials according to the instructions received from the
Site Engineer.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 5 of 20 Rev.00
➢ To ensure full coordination with the Safety Officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure
that all his working team are aware of the same to prevent accident and losses.
➢ To inform the Project Engineer of the areas ready for inspection.
➢ The HSE Officer shall verify the hazard and risk assessment form and make sure that
the controls are being implemented as per the approved Risk Assessment.
➢ The HSE Officer shall conduct HSE Induction for new workers and all HSE related
trainings.
➢ HSE Officer shall ensure that all needed Personal Protective Equipment’s (PPEs) are
available.
➢ The HSE Officer shall verify all work permits issued to ensure that necessary hazard
controls are in place.
➢ Laptop
➢ Multi meter
➢ Electrician hand tools
➢ Testing kits
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 6 of 20 Rev.00
PRE-COMMISSIONING
Before testing of the system, the following activities and checks shall be performed:
➢ Verify that the factory and site testing of panels completed and all
documentation accepted by the consultant.
➢ Verify completion of installation including termination of all cables.
➢ Verify that copies of up to date load schedules and drawings are available.
➢ Perform visual inspection prior to start the commissioning.
Insulation value measured between phase to earth and between phases with the help of 5
KV megger for 60 seconds.
After HV test to find out any detonation of insulation material after the HV test voltage
stress. And to be compare with the IR values taken before the HV test.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 7 of 20 Rev.00
7. CURRENT TRANSFORMER
To know the insulation value of CT windings. We will be applying primary to Earth 5kv for 60
seconds, primary to secondary 2.5 kv for 60 seconds & secondary to Earth 1000v for 60
seconds.
Winding Resistance Test, Polarity Test, Knee Point Voltage Test and Ratio Tests are carried
out with equipment named CT Analyzer.
The following are the basic wiring for a CT Analyzer to perform the above
mentioned Tests,
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 8 of 20 Rev.00
Once the basic wirings are completed, Name Plate details of the Current
Transformer should be feed as provided by manufacturer. Tests will be carried out
in reference with the details mentioned by the operator. Software results will be
attached with assessements.
To verify the ratio error of the CT this test is performed with help of primary injection kit. Inject
the current through P1- P2 (primary of CT Terminals) and measure the corresponding
secondary side output current and calculate the ratio error from actual and measured values.
Also Measure the relay side and meter side check the status.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 9 of 20 Rev.00
8. OVER CURRENT AND EARTH FAULT RELAY TEST (Secondary Injection Test)
Pick up test :
Set TMS to 0.1 and plug setting to the desired value. Inject the current above than the
plug setting value and note down the disc starting & closing currents. Starting current
should be in the range of 102 % -105 % and closing current should be in the range of
105% to 120%.
If any error this should be adjusted with the spring provided at bottom of the relay disc
the relay.
The same procedure is followed for earth fault pick up test also.
With desired current plug setting TMS 0.1 the tripping time should be Measured
for 2 Is value and 5 Is value. For normal inverse curve 2 times of fault current the
tripping time should be 10 seconds at TMS 1.0 For 5 times of fault current the tripping
time should be 4.4 seconds at TMS 1.0.
Set the desired instantaneous value. Inject the current and measure the pickup value
of instantaneous element. Apply 2 times of pick up value and note done the reading.
This should be in the range of 50 milli-seconds.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 10 of 20 Rev.00
9. FUNCTIONAL CHECKS
During the functional test the overall operation of the switchgear is checked in
accordance to the approved and as manufactured schematic drawings, the general
functional like closing/opening/tripping/indication/annunciation from Local/Remote.
Finally subsequent to the second injection relay test and completion of function tests, a
trip test is conducted for each feeder by primary injection and the tripping of CB is
confirmed.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 11 of 20 Rev.00
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 12 of 20 Rev.00
• Connect Voltage and Current leads of test set to Transformer HV Terminal R Phase
as fig.2
• Inject the specified dc voltage. The resistance will appear on the winding
resistance test set after measured current by test set. Record the value in the
attached test form.
• Repeat the same above for the other phases and LV windings as well. Record the
value in the test form.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 13 of 20 Rev.00
The voltage ratios will be measured for each tapping connection of the transformer. In the
report the relevant tapping voltage ratios will appear, the measured ratios and their deviations
as well will appear.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 14 of 20 Rev.00
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 15 of 20 Rev.00
This test is to verify there is no internal fault on transformer. Test voltage will be applied
across primary side of transformer and secondary side kept open circuited. The current in the
in the primary side will be measured which is magnetizing current drawn by the winding.
The purpose of test is to check whether the transformer core is magnetically balanced
or not and also about winding conditions.
• Apply the 3 phase 415 V to the Primary of transformer and cut one phase(R Phase)
supply.
• Measure the voltages in other two phases and record the values in the attached
test form.
• Repeat the above same steps to other phase in any of two Phases (Y and B Phases)
and record the value.
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 16 of 20 Rev.00
Highly Extremely
Corrosive Oxidizing Toxic Irritating Harmful Explosive
flammable flammable
Danger for
Constrained Slippery Danger of Falling from
the Other
Space Surface Electrocution Height
Environment
__________________
__________________
__________________
__________________
The hazards identified above will be controlled under the overall Project Safety Plan which is a separate
document communicated to all parties on the project.
The works subject of this document requires that the following PPE be used:
Gloves Safety Shoes Protective Safety Equipment
Lifejacket Other
Required Required Clothing Harness Guards
Scaffolding is
required______________
____________________
RADIANT SQUARE
AT CITY OF LIGHTS
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 17 of 20 Rev.00
____________________
____________________
Before commencing any works, all employees will attend a site safety induction training to
ensure all safety measures are understood and implemented and to cover specific procedures
in case of emergency. If necessary, practical training exercises will be conducted on escape
routes, signage, evacuation and rescue.
Regular Toolbox talks shall be conducted in order to prevent complacency within the crew.
The Supervisor shall conduct a Pre-start toolbox talk for the new person/s prior to starting
work.
Method Statement for Testing & Commissioning Sat 22kv RMU and Transformer Page 18 of 20 Rev.00
No personnel shall be assigned tasks that they have not received appropriate training in or
have been assessed for competency. Further training shall be given as required and when
additional training is identified during the risk assessment process.
13. ATTACHMENTS
• ITP
• CHECKLIST
• RISK ASSESSMENT