Setting Out Bench Mark Control Procedure F1
Setting Out Bench Mark Control Procedure F1
Subcontractor
ISSUE PURPOSE
□FA □FR □FI □FC □AB
Approval or review hereunder shall not be construed to relieve Vendor /
Subcontractor of his responsibilities and liability under the Contract.
CTR DEPT. /
Contractor Review Result
SIGNATURE
√ 1. Approved / No comments
NOTES
1 i) Revisions after 01 are denoted by a vertical line in the left hand margin against the
revised text, with the revision number displayed next to the revision line as shown by
the example on the left.
ii) Revision no. 01 is issued for Contractor’s review and approval, subsequent revisions
shall be 02, 03, etc... until its approval.
iii) Upon Contractor’s approval, Revision no. A1 shall be issued to Company for review.
Subsequent revisions thereafter shall be A2, A3, etc...
iv) Upon Company approval, Revision no. F1 shall be issued for Construction.
Subsequent revisions thereafter shall be F2, F3, etc…
CONTENTS
1.0 PURPOSE 4
2.0 SCOPE 4
3.0 REFERENCES 4
4.0 DEFINITIONS 4
5.0 PROCEDURE 5
5.1 Responsibility 5
5.6 Documentation 6
5.7 Structure 6
5.10 Personnel 7
5.11 Safety 7
1.0 PURPOSE
1.1 The purpose of this Procedure is to provide minimum requirement for Setting out
Benchmark and Survey Works at KNPC for Clean Fuels Project.
2.0 SCOPE
2.1 This Procedure applies to Clean Fuels Project (CFP).
3.0 REFERENCES
3.1 DEP 34.11.00.10-Gen - DEP for Site Investigations
3.2 DEP 34.11.00.11-Gen - DEP for Site preparation and earthworks including
tank foundations and tank farms
3.3 P6000CFP-000-PV-B - Project Variation to DEP 34.11.00.11
3.4 DEP 34.13.20.31-Gen - Roads, Paving, Surfacing, Cable Trenches, Slope
Protection & Fencing
3.5 DEP 34.14.20.31-Gen - Drainage System & Primary Treatment Facilities
3.6 DEP 34.19.20.31-Gen - Shell DEP for Reinforced Concrete Structures
3.7 PIP CVS 02100 - Site Preparation, Excavation & Backfill
Specification
3.8 VG3100-001-A-1001 - Project HSE Plan
3.9 VG3100-001-A-2001 - Site Quality plan
3.10 S-000-1670-0301V-01 - ITP for Earth Works (Contractor)
3.11 VG3100-001-A-2009 - Inspection and Test plan – Slit Trench Works
4.0 DEFINITIONS
4.1 Company - Kuwait National Petroleum Company (K.S.C)
4.2 Contractor - G.S. Engineering & Construction
4.3 Subcontractor - Kharafi National (KN)
4.4 Project - Clean Fuels Project (CFP)
4.5 Abbreviations
4.5.1 AASHTO - American Association for State Highway
Transport Officials
4.5.2 AFCD - Approved for Construction Drawings
4.5.3 ASTM - American Society for Testing and Materials
4.5.4 AWI / TWI - Administrative work instruction / Technical work
Instructions
4.5.5 BS - British Standard
4.5.6 HSE - Health, Safety & Environment
4.5.7 ITP - Inspection and Test Plan
4.5.8 MDD - Maximum Dry Density
4.5.9 OMC - Optimum Moisture Content
4.5.10 PPE - Personal Protective Equipments
4.5.11 QA/QC - Quality Assurance / Quality Control
5.3.4 For primary setting out of grid points, GPS or Total Station shall be used.
5.3.5 For establishing the bench mark suitable check level shall be performed with known
reference to ensure the accuracy of transferred level.
5.4 Setting Out
5.4.1 For primary setting out of grid points, Theodolite / Total Station / Auto Level shall be
used which is periodically calibrated every six months to ensure accuracy of the
instruments, and current calibration certificate shall be available.
5.4.2 For setting out of the principal grid points, a Total Station shall be used.
5.4.3 For fixing of bench mark elevations Dumpy level shall be used, which shall be
calibrated every six months to ensure accuracy of the instruments, and current
calibration certificate shall be available.
5.5 Frequency & Accuracy of Readings
5.5.1 Frequency of readings shall provide sufficient details to enable preparation of cut &
fill calculations, grading drawings and pipe routing drawing.
5.5.2 Ground levels should be taken based on drawing layout area.
5.5.3 Accuracy of the readings shall be as per DEP34.11.00.11-Gen.
5.6 Documentation
5.6.1 Sub Contractor shall draft the drawings/ documents with the minimum requirements
of plan, contours, uniform grid intervals, identification of existing facilities, Under
Ground services and structures including their details, levels etc.
5.6.2 All survey & setting out works shall be recorded in the JGSK-QC-1000-01. Any
deviation from the required shall be brought to contractor / company for proper re-
solutions.
5.6.3 Contractor deliverable shall be strictly in accordance with DEP 34.11.00.10-Gen.
5.7 Structure
5.7.1 Temporary reference points shall be established around proposed new structures from
the approved bench marks. Number of reference points according to site condition.
5.7.2 These points shall be maintained up to end of the construction period.
5.7.3 Setting out of new structures shall be established from the reference points.
5.8 Survey Works
5.8.1 The necessary bench marks required to execute the survey work, and drawings
showing the approximate locations, for main structures, shall be determined with
Company’s approval.
5.8.2 Protective barriers wherever required shall be installed at sufficient distance from the
monuments so not to disturb it. Allow suitable access/space to set up instrument above
the monuments whenever required.
5.8.3 Stacks, temporary benchmarks and permanent benchmarks shall be regularly
maintained and protected with barricades during the contract period. The bench mark
pillars shall be made of concrete. The bench mark pillars shall be minimum 450 mm
square in plan, projecting at least 100 mm above the finished grade level / adjacent
road level.
5.8.4 A steel plate bearing the unique Identification shall be embedded on the top. These
bench marks shall be protected against damage.
5.8.5 Minimum of three (03) numbers of bench mark pillars shall be installed according to
the site requirement. These pillars shall be embedded into the ground by about 400mm
to 500mm. A brass plate shall be fixed by embedding lugs into the concrete.
5.8.6 A metal detector will be run through the work locations and all the underground
services shall be marked and exposed accordingly. The service level shall be
recorded. Refer to slit trenching reports and drawings.
5.8.7 The bottom of the trench will be determined according to the specification and AFC
drawings.
5.9 As-Built Surveying Data
5.9.1 Any type of change which has a deviation from the contract drawing shall be
incorporated in the As-built drawings.
5.9.2 “As built” surveying data shall be prepared and submitted to Contractor/Company for
review and approval.
5.9.3 The survey drawings shall be plotted to sufficient scale to allow all survey details to
be clearly shown and relevant information to be annotated without obscuring such
details. These drawings shall be submitted to Contractor/Company after completion of
construction work and verified by respective site Engineers.
5.10 Personnel
5.10.1 Setting out and the establishment of permanent bench marks shall be undertaken by
the qualified surveyors.
5.11 Safety
5.11.1 Safety aspects of the operation shall be in accordance with Project HSE plan and
Company Fire and Safety regulations.
5.11.2 All workmen shall wear the required PPE at all times on site.
6.0 REFERENCE ATTACHMENT
6.1 S-000-1670-0401V (JGSK-QC-1000-01) - Survey Report
REMARKS / COMMENTS
Sub Contractor Surveyor Sub Contractor QC Inspector Contractor Surveyor Contractor QC Inspector Company QC Inspector
Name
Signature
Date
D R A
N
I 24-JUN - 2 0 15
JGSK-1000-01 Rev.1