01 - PQP S5 - Method Statement For Demolition Works

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

WANGSA DELIMA SDN.

WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 1 of 5
Demolition Works

 Method Statement for


Demolition Works

CONTENTS

Effective Date: 8-March-2021 Revision: 0


WANGSA DELIMA SDN.
WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 2 of 5
Demolition Works

No. Description Page No.

1.0 SCOPE 3

2.0 MATERIALS 3

3.0 EQUIPMENT AND RESOURCES 3

4.0 WORK METHODOLOGY 4

5.0 QUALITY CONTROL PROCEDURE 5

6.0 SAFETY, HEALTH AND EVIRONMENT 5

Effective Date: 8-March-2021 Revision: 0


WANGSA DELIMA SDN.
WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 3 of 5
Demolition Works

1.0 SCOPE

This method statement specifically describe the procedure involved in


demolition works to ensure that the works is completed in accordance with
the specification and applicable standard codes of practice and that the
activities are documented.

2.0 MATERIALS

Not applicable

3.0 EQUIPMENT AND RESOURCES

3.1 Machinery/ Equipment

The basic equipment to be used is as follow:

a) Backhoe
b) Backhoe Mounted with Concrete Breaker
c) Crane
d) Oxy-cutter with flash back arrestor
e) Lorry
f) Air compressor
g) Pneumatic breaker/ hacker

3.2 Manpower

Manpower involved:

a) Supervisor
b) Surveyor
c) Machine Operator
d) Lorry Driver
e) General Workers

Effective Date: 8-March-2021 Revision: 0


WANGSA DELIMA SDN.
WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 4 of 5
Demolition Works

4.0 WORK METHODOLOGY

To be submitted later as work at site progress.

Effective Date: 8-March-2021 Revision: 0


WANGSA DELIMA SDN.
WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 5 of 5
Demolition Works

5.0 QUALITY CONTROL PROCEDURE

On site quality control shall be carried out in accordance with the


inspection and test plan.

6.0 SAFETY, HEALTH AND ENVIRONMENT

6.1 Work will be carried out according to the Project safety


Requirement.

6.2 Provide signboards to warn workers and publics of dangers


associated with construction works.

6.3 Proper and adequate provisions of Temporary Signage and


Barricades at diversion and temporary haul need as necessary.

Effective Date: 8-March-2021 Revision: 0


WANGSA DELIMA SDN.
WDSB/SMK-BSP/MTS/DEM
BHD.
Method Statements For
Page: 6 of 5
Demolition Works

 Appendix A

Effective Date: 8-March-2021 Revision: 0