Help: - In case you want to change email ID or your Mobile Number then click on the link
<<Click Here>>
2. Request ID/Application ID
Help: With this Request ID / Application ID or consumer number you can track the
application status as on date.
3. Pending Arrears
Help: - Your application will not be considered / processed unless pending arrears are
cleared.
8. Sanctioned Load
Help: - It is the sanctioned load in KW for the said consumer number.
9. Contract Demand
Help: - It is the sanctioned Contract Demand in KVA for the said consumer number.
Only Rooftop mounted Solar System will be considered under MNRE Phase-II Rooftop Solar
Scheme.
Consumer can select empanelled agency to carry out the work. Consumer has to make
payment to the agency after deducting the eligible subsidy amount. Consumer has to borne
the cost of Net Meter along with testing charges provided by the Agency and cost towards
additional customization as per site requirement if any.
The components of a Grid Connected Rooftop Solar PV System shall essentially comprise
but not be limited to crystalline solar PV Panels/modules of required number,
Inverters/PCU, module mounting structures of minimum 300 mm ground clearance at the
lowest point from the roof surface, total Cable/wiring up to 30 m in length.
13. RE Arrangements
Help :-
a. Net Metering – An arrangement, under which a Renewable Energy Generating
System with Net Meter installed at an Eligible Consumer’s premises, delivers
surplus electricity, if any, to the MSEDCL after setting off the quantum of
electricity supplied by MSEDCL during the applicable Billing Period;
b. Banked units at the end of financial year will be purchased by MSEDCL at Generic
Tariff Rate.
d. RE Generating System Behind the meter without Net Metering/Net Billing – Grid
Connected Renewable Energy Generating Systems connected behind the
Consumer’s meter, and not opting for either Net Metering Arrangement or Net
Billing Arrangement, shall be allowed only after prior intimation to the MSEDCL.
Permission of Electrical Inspector for RTS plants above 200KW or Test report
from licensed Electrical Contractor for RTS plants below 200KW will be required
to upload at the time of submission of intimation.
14. Proposed Rooftop Solar Capacity
Help:- It is the rooftop solar system capacity which a consumer want to install at his
premises.
15. Voltage level at which the RE Generating system is to be connected with Grid
Help:- The voltage at the output of inverter to be selected from the drop
down list as applicable.
18. Do you want to maintain the Chronology in case of there is inadequate distribution
transformer capacity?
Help :-
a. If you select this option as YES then your application will be kept in pending stage
due to inadequate distribution transformer capacity for sanctioning. When
distribution transformer capacity will be upgraded then your application will get
process as per the chronology.
b. If you select this option as NO then your application will get rejected
automatically if distribution capacity is not available.