Sub-Contractor Management Plan
Sub-Contractor Management Plan
4
Document History
Revision code Description of changes Purpose of issue Date
Document Approval
Prepared by Reviewed by Approved by
The use of sub-contractor can range from occasional work such as window cleaning right
through to high-risk specialized work on construction sites. Each will have their own risks
and will need to be managed by the NBC that is engaging them.
A common error made when engaging a sub-contractor is the presumption that it is the sole
responsibility of the sub-contractor to manage OSH issues related to the works. Although
the sub-contractor does have a duty to manage OSH, the NBC who engages the sub-
contractor also has a duty to ensure that the sub-contractor is competent to undertake the
tasks and that they follow the standards that have been agreed.
A Subcontractor Management Plan (SMP) outlines the relationship between NBC and his
sub-contractors while they are performing work for a certain project, and it outlines the
methods by which the NBC will ensure the production of quality deliverables from each of its
subcontractors and ensure the development of long-term business relationships between
the companies.
This SMP provides guidance for subcontract management activities, including the following:
Insurance considerations
Beginning work
Safety inspections
2 Definitions
a. A sub-contractor has been defined within the NBC as:
c. Although the risks involved with engaging suppliers are in many cases lower than those
associated with the engagement of sub-contractor, organizations do still have a duty to
ensure that their supplier is competent and meets their OSH requirements. Further,
Does the subcontractor’s safety record prove that the job can be done in
a safe manner?
Prequalification should let a potential bidder know exactly what to expect from
project start to finish. Giving a bidder every piece of relevant information, along with
being available to answer any questions he or she might have, will make the
process fair and objective.
Not all subcontractors will qualify for the bid. To weed out bids that fall short of your
standards, consider implementing minimum requirements for the subcontractor,
such as making sure the subcontractor:
Has not been nor is currently debarred by any federal, state or local
government authority in the past 2 years
Has not had any professional license revoked in the past 2 years
Has not committed a serious or willful OSHA, ISO or state safety violation in
the past 2 years
Prior to awarding the contract to a qualified bidder, the NBC or owner should
document:
A quality control plan that includes a copy and/or description of the quality
control program to be used on the project and any implementing documents
applicable to its program; and
A cost control plan that includes a description of the cost control program
being used for the project.
4 Insurance Considerations
4.1 Certificate of Insurance
Prior to the beginning of the project, the subcontractor should provide two certificates of
insurance to the NBC showing that the subcontractor has coverage for him- or herself and
his or her employees, agents and subcontractors. The subcontractor’s insurance must
provide adequate coverage for any workers’ compensation obligations, employer’s liability
and automobile liability. If any of these policies are terminated, the subcontractor should
provide certificates of insurance showing replacement coverage. All coverage must be
placed with insurance companies duly admitted in the state or in the desired licensing
jurisdiction in which the work is being done, and all coverage must be reasonably
acceptable to the NBC.
The certificate of insurance should provide that the insurer give the contractor a written
notice of cancellation and termination of the contractor’s coverage at least 30 days prior.
If a subcontractor does not have his or her own work comp insurance, you may see
your work comp premium rise during an audit. This is why it is so important that the
subcontractors you hire provide proof of insurance before any work is done.
There should be no endorsement or modification of the CGL for risks arising from pollution,
explosion, collapse, underground property damage or work performed by the subcontractor.
Auto liability
The subcontractor should secure an automobile liability insurance policy to cover
the damages that become due in case of bodily injury, death of a person or property
damage arising out of ownership, maintenance or use of any motor vehicle or trailer
owned, hired, leased, used on behalf of or borrowed by the subcontractor. The
policy must also include coverage for any equipment subject to motor vehicle laws,
contractor and owner (if different than the contractor) and any subcontractor liability
or responsibility.
Because a contractor or other involved party could be held liable for defects in a
subcontractor’s work, years after it has been completed, and filing the claim under
the contractor’s CGL policy could cause the premium to rise, many construction
contracts require subcontractors to provide insurance coverage for claims resulting
from their completed work for a finite period of time, typically the one- to five-year
range. Typical contracts also require that the subcontractor name the owner, the
architect, the general contractor and other third parties as “additional insured”
parties, entitled to coverage under the insured subcontractor’s CGL policy. Naming
additional insured parties requires a separate endorsement to that policy.
This means that subcontractors can be held liable for claims of property damage or
bodily injury resulting from a defect in a contractor’s work. It is also critical to
maintain this coverage into the future; failure to do so could lead to a breach-of-
contract lawsuit brought by the contractor or other party.
What can subcontractors do to reduce the risk of a claim being filed against them for
a defect in their completed work? To avoid litigation, it is crucial to know local
regulations and adequately document proper performance. Subcontractors must
know their company’s documentation practices relative to each subcontract, and
carefully keep records of all processes.
5 Beginning Work
After a subcontractor has been selected, each subcontractor should have a legally binding,
written contract that defines the following items:
The appropriate terms and conditions that will be imposed on both the NBC and the
subcontractor
An acceptance process
They all have clear and unambiguous subcontracts established that include an
SOW.
The efforts of all subcontractors are integrated into a cohesive project plan with all
subcontractors understanding where their efforts fit into the overall picture.
The formal and informal interfaces between the NBC and the subcontractors, as
well as among the subcontractors, are documented.
The work of all subcontractors should be coordinated by the NBC to ensure that the efforts
of all parties are integrated into a cohesive unit throughout the entire project process. A
master schedule should be developed to establish schedule constraints and identify
contractual and significant internal milestones.
Subcontractors should have a single point of contact with the NBC for contractual matters.
On a day-to-day basis, all subcontractor personnel will be free to interact with any NBC
personnel as needed.
Designate a safety representative to handle all safety and health issues during the
job
Report all injuries, spills, property damage incidents and near misses
Obtain phone numbers and directions for the nearest hospital, ambulance service
and fire department, should an accident occur
Know, follow and train his or her employees about the safety policy of the
contracting company
Obtain the Safety Data Sheets (SDS) of any chemicals used during the job
6.1 Introduction
Lists the overall goal of the safety program and conveys the importance of following
it while on the job
May include a mission statement, outlining the company’s goals for the safety
program
Employees may be responsible for reporting accidents and injuries, reporting unsafe
conditions, attending any safety training and obeying all safety and health
regulations.
For example, OSHA regulations for lockout/tagout procedures (29 CFR 1910.147)
may be spelled out for workers.
Fall protection
Hearing protection
Housekeeping
Ladder safety
Lockout/tagout procedures
Respiratory protection
Subcontractors should also submit their site-specific safety plans before work
begins. These plans should include job-specific safety requirements, roles and
responsibilities of the subcontractor’s team, potential project risks and
countermeasures to those risks.
The subcontractor’s employees should also be aware of proper first-aid procedures and
know what to do in the event of a medical emergency. Stress to the subcontractor that it is
his or her responsibility to notify his or her employees of any safety information provided by
the contracting company to the subcontractor.
As the contracting company, your employees should be trained on any specific hazards
introduced by the subcontractor’s work.
7.2 Recordkeeping
A strong recordkeeping policy will ensure the job is done in compliance with various federal
and state regulations and will be useful should you ever be audited.
Keep copies on file of all forms you provide to the subcontractor throughout the
contract
Have a list of telephone numbers for the nearest hospital, ambulance service and
fire department
Have copies of all necessary SDSs and other required information regarding
chemicals used for the job
Keep an OSHA recordable injury and illness log (Form 300 and 300A, if applicable)
for the project, along with copies of accident reports for all accidents that occur on
the job
Training records for your company’s workers regarding hazards that may be caused
by the subcontracting company
Copies of all forms related to the contract that are required to be filled out by the
company before or during contract work
OSHA recordable injury and illness logs for the job, along with copies of accident
reports filed throughout the project
Meeting minutes
Contract status
Permit forms
These impacts could be in a variety of forms, such as restricting the working hours
due to the surrounding neighborhood, the times that goods can be delivered to the
project or specific OSH requirements that the sub-contractor must adhere to whilst
on site.
All this information should be gathered and included within the tender
documentation to ensure that all sub-contractor is aware of the OSH requirements
for the project and have allowed enough cost, time and resources to meet those
requirements.
The scope of works should include enough detail to allow a competent sub-
contractor to fully understand the requirements of the project.
Further if the NBC requires that the hazard is managed in a particular manner or
has defined parameters that are different from those defined in legislation or best
practice, these should also be stipulated within the tender document.
An example of this could be noise. The NBC may have identified noise as a general
hazard on the project, however due to their own risk management systems, the
NBC has a lower noise action level than that is set within the current legal
standards. This information must be provided to the sub-contractor at this stage
otherwise it would be reasonable for the sub-contractor to provide costs and
information to only manage the noise to the levels as defined in current standards.
Other issues the NBC may wish to highlight when discussing project hazards and
risks could be the way they are managed. The NBC may wish to have set criteria for
different hazards or may require the use of permit to work systems for set hazards
and risks. This should be highlighted to the tendering sub-contractor to allow them
to include this in their considerations.
Legal Compliance;
OSH reporting
Incident Investigation
Emergency Management
If it is a high-risk project, the NBC may require a high level of OSH management
and supervision. As part of the tender documents, this should be specified, including
the competency levels that are required for each role. This again ensures that all
parties are clear on the requirements prior to the project commencing.
Further to the NBC highlighting the minimum requirements that the successful sub-
contractor have in place, they should also provide information on the systems they
will have to comply with whilst on the project.
NBC should ensure that the sub-contractor is fully aware of any requirements that
will be in place that may be a burden (in terms of time, resource or cost) to the
successful sub-contractor.
Examples of this could be that the NBC require all staff who are working on the
project to undergo a specific induction program, the content of which is developed
by the NBC. This would be an additional induction to the project specific OSH
induction that the sub-contractor would normally provide and would be a burden
upon the sub-contractor in terms of time and cost.
Other examples could include the requirement that the NBC undertake site
inspections or regular audits or require the project OSH manager to attend a weekly
OSH meeting. The sub-contractor should be aware of these facts prior to tendering
for the project.
The review for OSH should be integrated into an overall sub-contractor review
process to ensure that the successful sub-contractor has not only solid OSH
systems and performance, but has adequate resources, financial ability and
experience to undertake the project.
The process that is utilized for the review should take into account the complexity
and risk of the project that is going to be undertaken, for example for a high risk
contract the NBC should consider meeting with prospective sub-contractor to review
their systems and examine how they have undertaken previous similar works. They
NBCs should also give preference to those sub-contractors that already have an
approved OSHMS, as they will already have a documented approved OSHMS that
has been independently reviewed and is implemented (or in the process of) into the
NBC. Further, sub-contractor who do already have an approved OSHMS should be
able to demonstrate solid risk management processes and will be regularly audited
and inspected by NBC.
The scope of the evaluation of OSH performance and systems should be defined by
the risks and complexity of the project. If the risk is deemed low then as a minimum
the sub-contractor should be implementing the requirements of NEOM-NPR-GFR- If
the risk is seen as medium to high, then ideally the sub-contractor selected should
hold an approved OSHMS, however if this is not the case then the following should
be in place as a minimum:
Statement of intent - will be a top line statement that outlines the company
objectives for safety and health;
Organization - outlines the company organization for Safety and Health, including
roles and responsibilities within that project; and
Arrangements – will detail how the company intends to achieve the objectives
delineated in the statement of intent.
The sub-contractor should also define a clear organization structure for the project
as part of his submission. For more complex projects, the sub-contractor should
have been requested to submit CVs of the staff he is planning to utilise on the
projects. These should be reviewed to ensure they meet the competency
requirements that have been set as part of the pre-tender information
Further NBCs with robust management systems will be able to demonstrate how
these requirements are communicated within their firm and responsibilities for the
upkeep and review of the legal registers etc.
Also, as part of the submission the sub-contractor should outline who will have
overall responsibility for the risk management program, including the review and
approval of all risk assessments / method statements for the project.
Further it is important to ensure that this program covers the review and approval of
any subcontractor’s risk assessments as these are often overlooked.
The procedure should also include information on any known hazard’s that have
been defined in the pre-tender information and how the sub-contractor will manage
the said hazard / risk.
Dependent on the current status of the projects or information known, the sub-
contractor may be in a position to submit some specific project risk assessments.
Further to discussing what the performance targets are, the sub-contractor should
also show how these will be managed and achieved. This, ideally, should come in
the form of an action plan that identifies the required actions, timescales and owners
for each individual target.
The NBC should also review the past performance of the sub-contractor, as this will
give information on how they have performed on previous contracts. Again,
dependent on the risks involved, it may be prudent to contact previous clients to
review past performance and gain references.
The sub-contractor should define how this will be managed during the contract,
including the communication with all external and internal parties such as sub-sub-
contractor, regulatory authorities or the client.
The sub-contractor should also define how he will communicate with his employees
on OSH matter including how they will be consulted on these matters.
The NBC should ensure that the sub-contractor has identified all foreseeable
emergency situations and that the arrangements are reasonable for managing the
situation.
Also, the contract should provide information on who will form the emergency
management team or crisis management team.
The procedure should clearly show how incidents will be managed from the point of
initial notification right through until close out and corrective actions.
The procedure should also show how incidents will be reported, both internally and
externally.
Further, the sub-contractor should also include information on how they will train
employees on any specific hazards or risks that have been identified as part of the
pre-tender information.
The sub-contractor should also discuss how they will ensure compliance to any
client audit and inspection requirements that have been set as part of the pre-tender
information.
When developing a preferred suppliers list, NBC should consider how many sub-
contractors you wish to hold on the preferred list for each type of activity you use
sub-contractor for. If your NBC uses sub-contractor on a regular basis, then it may
be best to have up to three different sub-contractors / suppliers for each different
activity. For those NBCs that only seldom use sub-contractors, then the preferred
list may be smaller.
Regardless of the complexity of the preferred list, this register should be used as a
tool to manage sub-contractor and track performance. Sub-contractor and suppliers
should be revaluated on an annual basis, including an examination of past
performance during the year
While the tradition and spirit of shaking hands on a verbal deal between two friends
in business is helpful in underpinning a good trading relationship, it is sensible for
significant supply arrangements to be documented and agreed, usually by
signatures.
Aside from the process of clearly agreeing and understanding the expectations
between supplier and client, contracts or agreements also help if one or both of the
original dealmakers one day move on, which can then give other people the
problem of how to make sense of what might or might not have been agreed
between the two parties.
NBC can reduce the formality and detail according to their own situation and the
risks involved with the works being undertaken, however NBC needs to be aware of
the risks if potentially contentious matters are vague and open to dispute.
Robust contracts and agreements provide an essential reference point upon which
to discuss and negotiate effective outcomes whenever situations change, in terms
of the client's requirements and the provider's capability.
NBCs should ensure that all OSH requirements are clearly stipulated within the
service contract. The complexity or level of detail required will be defined by the risk
Nomination of a main focal point within the NBC for the sub-contractor;
Providing all sub-contractor staff with the relevant OSH information; and
Checking that the staff that have been allocated by the sub-contractor are
competent.
The person that is nominated by the NBC should have a working knowledge of the
work that is being undertaken to allow them to make informed decisions when
required.
The focal point should have full responsibility to ensure that the contract and works
are managed in line with the NBC and legal requirements.
When developing a sub-contractor’s induction, the NBC should consider not only
what OSH information is required but should also ensure that other vital information
such as site rules, what facilities are available etc. are included as part of the
induction.
The NBC should also ensure that it includes information on the risks that are
present within their facility and what procedures are in place to manage the risks.
Site rules;
Reporting procedures;
Restricted areas;
Emergency procedures;
The issues that are covered within the induction will be determined by the risks and
complexity of the works and the environment they will be undertaken within. For
example, if the contract is considered a low risk and is undertaken within a very
controlled environment, the amount of information that is required by the sub-
contractor is probably minimal.
Dependent on the size, complexity duration of the contract, the NBC may choose to
allow the sub-contractor to deliver the induction, however the NBC still has a duty to
ensure that all staff have undertaken the induction and that the information passed
is factually correct and understood by the attendees. This can be done through a
series of audits or ongoing inspections.
Dependent on the risk and complexity of the works, the NBC should develop an
audit and inspection program to cover the works that are being undertaken. The
frequency of the audit and inspection program should be defined by the risks and
complexity of the works.
If the works are identified as high risk, then as a minimum, daily checks should be
undertaken out on the work activities. If the works are not defined as high risk, then
checks must still be carried out, but on a less frequent basis.
Further if the work is being undertaken under a permit to work system, additional
control measures and requirements will be needed.
The NBC should inform the sub-contractor of what the audit and inspection plans
are for the contract as part of the pretender information so he is fully aware and also
to allow them to include any additional requirements within his own systems, costs
It is important that the work is inspected to ensure that the safe systems of work and
risk assessments that the supplier provided are being followed and correctly
implemented. The sub-contractor’s staff should be questioned on site to ensure they
are aware of the content of the risk assessments and the actions they should take to
mitigate any risks.
Other stakeholders, such as the finance or security, should also be asked for
feedback on the sub-contractor’ performance during the works. This should also be
gathered and used as part of the evaluation of performance.
The NBC should ensure that the sub-contractor’s performance against these KPI’s
is regularly measured and that feedback is given to ensure they are aware of their
current performance.
For longer fixed contracts, such as cleaning services etc., it is good practice to meet with the
sub-contractor at least four times a year. The frequency of these meetings should be
defined by the risks and complexity of the works being undertaken.
Incidents;
8.6 Commissioning
Depending on the work that have been undertaken, the NBC shall ensure that all activities
related to the commissioning of plant and equipment are undertaken by trained and
competent persons and that prior to any activities being undertaken, the sub-contractor has
full documented operating procedures for the commissioning activity.
These procedures shall include the following steps (not an exhaustive list):
Restrictive access;
Start-up protocol;
Shut-down protocol;
Handover.
The NBC should also ensure that the area of the works has been returned to the original
state or to an agreed condition.