I. TECHNICAL SPECIFICATIONS
A. Design of each cell
Each Battery Cell shall have individual Positive Plates, Negative Plates, Separators,
Safety Valves, Container and Positive & Negative Terminals. These components shall
meet following requirements:
1. Positive Plate: Flat pasted type with Lead-Calcium High Tin alloy grid to resist
corrosion & provide longer life or SRS Grid Flat Pasted Type equivalent.
2. Negative Plate: Flat pasted type with Lead-Calcium alloy grid for maintenance free
characteristics or equivalent.
3. Separator: Low resistance, high porosity and highly absorbent type glass mat
separator (AGM) type.
4. Electrolyte: High purity Sulphuric Acid (H2SO4) to maximize its shelf life.
5. Terminals: Lead plated Copper inserts for high conductivity.
6. Safety Valve: Self resealing, pressure regulated and explosion proof type.
7. Container: The container and cover shall be made of lightweight, sturdy and acid &
weatherproof materials. It shall be of high impact flame retardant material and design
for better heat dissipation and strength.
II. Accessories:
The Vendor shall supply following accessories along with the Battery bank:
1. Glass Thermometer: 1 no.
2. Digital Multi-meter (Intrinsically Safe) for measuring Cell Voltages, Total bank Voltage
& UPS 3 Phase AC voltage upto 1000 VAC, DC voltage upto 1000 VDC and currents of
brand Preferred Fluke: 1 no with accessories and calibration certificate.
3. Suitable sized insulated Spanner of requisite size for battery maintenance: 2 no.
4. Nuts, bolts, terminals, and other fasteners suitable for battery applications as
required for commissioning. Additional 10 % extra to be supplied as spares.
5.Two Battery bank isolators with appropriate rating and Box to be provided along with
cables with proper lug, glands required for connecting from isolator to the two terminals
of each battery bank.
III. Markings:
1. Marking on the Battery cells:
All the Battery cells shall be marked with manufacturer's name, recognized trademarks,
Serial No., Type, Nominal Cell Voltage, individual Amp Hr capacity, Cell weight and Year
of Manufacturer.
2. The steel racks shall have provision for indicating battery cell No. (1 to 108) for
easier identification during maintenance. The Steel Rack shall be well grounded.
IV. Documents:
The Vendor shall supply, as part of the order 2 sets of the following documents in hard
bound form, along with supply of the battery bank:
1. Operating/ Service instruction booklets.
2. Original test reports/ Certificates of tests (Type & Routine)/Environmental Clearance
Certificates.
3. The Dimensional drawing of Battery Cells.
4. The General Arrangement drawing with minimum clearances required on all sides of
the battery stack.
Page 2 of 4
VI. INSTALLATION & COMMISSIONING
1. Installation and commissioning procedure of the new battery bank shall be carried
out as per approved OEM SOPs or manual.
2. Battery capacity test shall also be carried out during commissioning stage as per IS
1651.
3. Dismantling of old banks and installation and commissioning of new banks at site to
be done by successful vendor.
4. The vendor (Contractor) shall be required to take back the old batteries at his own
cost and shall pay OIL the quoted buyback price for old batteries. Installation and
commissioning shall be deemed as completed only after the vendor takes back the old
batteries and pay the quoted buy back price to OIL. Applicable GST against the buyback
of old batteries shall be borne by the vendor.
5. Unloading of the new batteries (216 nos.) and erection/installation and
commissioning shall be within the scope of the Vendor (Contractor)
6. Technical literature, instruction Manual for Initial charging & routine maintenance,
test and calibration certificate shall be provided along with the quotation.
7. Transportation of the batteries from the storage area of OIL (The Owner) to the battery
room for installation and commissioning is under the scope of the vendor. Also, it is the
responsibility of the vendor to decommission, dismantle and pick up the old batteries
along with the rack from the owner's premises and the same is solely under the scope
of the vendor.
8. Delivery, Installation & Commissioning: Two banks, each comprising of 108 nos. of
batteries and accessories as per clause II above shall be delivered, installed &
commissioned at:
Pump Station-8, Oil India Limited, PO- Haptiagach, Near Dhumdangi Rly Station,
Sonapur, Dist: Uttar Dinajpur, West Bengal, Pin code 733202 (Haptiagach).
VIII. Warranty:
The warranty shall be 12 months reckon from the date of commissioning of the entire
battery bank. Warranty shall cover free replacement of faulty or defect items supplied
under this contract. Warranty shall also cover rectification of any defect in workmanship
without any cost to OIL.
Page 3 of 4
4. The vendor's personnel shall follow and take necessary work permit before carrying
out any work.
5. The vendor's personnel shall take every possible care to keep the environment clean
and free from pollution during delivery & I&C of the material.
6. The vendor's personnel should understand the implication of the known hazards
related to the work undertaken by them and the necessity of having an emergency plan
ready to counter them, should anything go wrong.
7. While providing the services, the vendor's personnel shall follow the procedures and
systems taking all control measures in all the stages of works to avoid any untoward
incidents.
8. The vendor shall fully understand OIL's safety policy and should take necessary steps
to align their safety policy with OIL's; so as to accommodate and implement OIL's safety
policy in the jobs undertaken by them.
9. The vendor shall have to report all sorts of near misses, incidents and accidents to
OIL Engineer immediately. For any clarification with regard to the above, the Vendor
may contact concerned OIL Engineer.
&&&&&&&&&&&