Temporary Works Procedure SAMPLE
Temporary Works Procedure SAMPLE
f-
FI
NA
LD
RA
FT
- v8
(1
7.9
.19
)
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
Disclaimer:
Although the Temporary Works Forum (TWf) does its best to ensure that any
advice, recommendations or information it may give either in this publication
or elsewhere is accurate, no liability or responsibility of any kind (including
liability for negligence) howsoever and from whatsoever cause arising, is
accepted in this respect by the Forum, its servants or agents. TW19.065
(8.12.19)
2
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
Insert logo
Company: _________________
Prepared by: _________________ (Designated individual)
Date: _________________
Approved by: _________________ (Main board director)
Date: _________________
Revision Number: _________________
Review Date: _________________
1.0 Introduction
1.1 This procedure is mandatory for all company operations (unless, on a particular
project, another Principal Contractor’s procedure is to be adopted by agreement). It is
the responsibility of the company’s Designated Individual (DI) to ensure that this
procedure is appropriate and kept up-to-date.
1.2 All temporary works instigated by the company shall be subject to the control
procedures contained within this document. This is to satisfy the company’s
legislative duties - as well as that of its employees - and to enhance the company’s
health and safety performance.
2.0 Definition
2.1 Temporary works can be defined, broadly, as parts of the works that allow or enable
construction of protect, support or provide access to the permanent works and which
might or might not remain in place at the completion of the works. Examples include:
Earthworks
Support to trenches; excavations; temporary slopes and stockpiles; open
batters.
Structures
Concrete formwork; edge protection; falsework; propping and needling; façade
retention; shoring; edge protection; access and support scaffolding; temporary
bridges; site hoarding and signage; site fencing; cofferdams; rebar cages.
Equipment and Plant Foundations
Mortar silo bases; tower crane bases; supports, anchors and ties for construction
hoists and mast climbing work platforms; groundworks to provide suitable areas
for plant erection, e.g. mobile cranes, piling rigs and MEWPs; outrigger pads; site
cabin foundations; site access and haul roads; and hard standing for plant and
material storage.
3
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
2.2 It is also necessary to consider permanent works that are part-built or under
temporary loading conditions. This includes deteriorated, damaged or part-
demolished structures as well as those that are under construction and/or being
structurally refurbished. In all these cases these structures may not - without suitable
temporary works - be able to support themselves, let alone additional construction
loadings.
3.0 Appointment of Key Personnel
3.1 The company shall appoint a Designated Individual (DI). This shall be the Director
responsible for health and safety1. A formal appointment shall be made by the
Managing Director with the agreement of the board.
Name of Designated Individual (DI): ____________________________
Date appointed: ____________________________
Appointment approved by: ____________________________
3.2 For each project, a Temporary Works Co-ordinator (TWC) shall be appointed formally
by the DI (see Form No. 1). One person may be appointed to more than one project if
resources and project size permit. A Deputy TWC shall be appointed to cover illness
and absences. These appointments shall be displayed on the project office
noticeboard or other prominent location and recorded in the Construction-phase
Health and Safety Plan.
NOTE: The TWC may be nominated by the project manager (or other person(s) responsible for
resourcing).
3.3 In the event of the company being contracted to undertake work for another
contractor - who may be a Principal Contractor - the company’s project TWC should
liaise with their TWC. The Principal Contractor’s TWC shall have overall control on
temporary works.
3.4 For each project, where required, one or more Temporary Works Supervisors (TWS)
shall be formally appointed by the TWC (see Form No. 2). The TWS shall normally be
the foreman in charge of a team of tradespersons or operatives. At least one TWS
shall be based on site at all times. All company TWSs report to the company TWC.
The lines of responsibility, on each project, should be set out in an organogram (see
Form No. 3).
3.5 The Temporary Works Designer (TWD) shall be nominated by the TWC on evidence
that the designer has appropriate experience and engineering qualifications if
required. There shall be a single point of contact established and maintained between
the TWD and the TWC. The TWD shall, as required, liaise with the Principal Designer
(under CDM2015) and Permanent Works Designer (PWD), e.g. structural engineer.
4
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
3.6 The Temporary Works Design Checker (TWDC) shall be nominated by the TWC on
evidence that the design checker has appropriate experience and engineering
qualifications if required. The TWDC shall be independent from the TWD (see Annex
A).
3.7 On each project, a record of appointments should be maintained by the TWC (see
Form No. 4).
4.0 Roles and Responsibilities
4.1 Designated Individual (DI)
The DI is responsible for establishing and maintaining a procedure for the control of
temporary works used during the company’s operations; as well as the appointment
of TWCs (and their on-going training).
4.2 Temporary Works Co-ordinator (TWC)
Any TWC is responsible to the company Designated Individual (DI) for the
implementation of the company temporary works procedure, as well as the
appointment of TWSs (where required).
NOTE: They may have a different line manager.
2 BS 5975:2019, Code of practice for temporary works procedures and the permissible stress design of
falsework
5
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
5.3 On contract award, the Temporary Works Register shall be passed to the TWC who
shall develop and maintain it. It shall be considered as a ‘live’ document, be updated
on a regular basis and the current version displayed on the project office noticeboard
(or other prominent location).
5.3 A unique identification number should be assigned to each item in the Register.
5.4 The BS 5975 Design Check Categories 0, 1, 2 and 3 (see Annex A) shall be assigned to
each item by the TWC.
6.0 Design Brief
6.1 Following consultation with all relevant parties, including the PWD (where required),
the TWC shall ensure that a Design Brief (see Form No. 6) is prepared for each item in
the Temporary Works Register. The brief shall contain sufficient information to permit
the TWD to prepare an appropriate solution that meets the project’s requirements.
6.2 A single design brief may apply to more than one similar item in the Temporary Works
Register.
6.3 The Design Brief item number should accord with the item number in the Temporary
Works Register.
6.4 The TWC should sign to confirm the content of any Design Brief prior to it being issued
to the TWD.
7
Temporary Works forum Temporary Works Procedure: SAMPLE – TWf2019: 03
10.2 The permit-to-work identification number should accord with the item number in the
Temporary Works Register.
10.3 The permit-to-work shall indicate clearly the extent of its application and any
date/time constraints. All relevant design drawing references, risk assessments and
method statements should be included on the permit. A unique identification number
should reference the relevant design brief(s) and the item(s) in the Temporary Works
Register.
10.4 At the TWC’s discretion, a single permit-to-work may be issued for multiple, identical
operations - covered by the same design - on the basis that each operation is
appropriately checked/inspected prior to the operation commencing.
11.0 Temporary Works Training Requirements
11.1 Any TWC and TWS should have current CITB Site Safety Plus TWC (2-day) and TWS (1-
day) certificates, respectively.
11.2 Other training should be identified, e.g. SMSTS, SSSTS, etc. (see TWf Information
Sheet No. 24).
12.0 Auditing of Temporary Works procedure
12.1 The DI shall arrange for formal audits on the application of this procedure in order to
ensure compliance and effectiveness within the business.
12.2 Issues identified shall be recorded in writing and remedial action implemented.
12.3 The frequency of audits shall be identified by the DI.
Frequency: ______________________________ (EDITORIAL NOTE: Insert)
ANNEXES:
FORMS:
ANNEX A
Design check category
0 Restricted to standard solutions only, to ensure the This applies to the use of standard solutions
site conditions do not conflict with the scope or and not the original design, which requires bot
9
limitations of the chosen standard solution. These structural calculation and checking to Category member of the site or design team.
may include standard trench boxes. 1, 2 or 3, as appropriate.
1 For simple designs. These may include: formwork; Such designs would be undertaken using simple The check may be carried out by
falsework; needling and propping to brickwork methods of analysis and be in accordance with another member of the design team.
openings in single storey construction. the relevant standards, supplier’s technical
literature or other reference publications.
2 On more complex or involved designs. Designs for Category 2 checks would include designs where The check should be carried out by
excavations including excavation support using sheet a considerable degree of interpretation of an individual not involved in the
piles, for foundations, for structural steelwork loading or soils’ information is required before design and not consulted by the
connections, for reinforced concrete. Designs where the design of the foundation or excavation designer.
stability is obtained by restraint at the top of the support or slope is carried out.
temporary works (e.g. top-restrained falsework).
3 For complex or innovative designs, which result in These designs include unusual designs or where The check should be carried out by
complex sequences of moving and/or construction of significant departures from standards, novel another organization and should
either the temporary works or permanent works. It methods of analysis or considerable exercise of include an overall check to assure
also includes basement excavations and tunnels. engineering judgment are involved. co-ordination of the whole design.
10
Formally appoint TWC (and Deputy TWC) for the Project DI 1
Nominate designer(s) and issue design brief for each item of TWC
6
temporary works in the Register
Verify that the temporary works designs accord with site TWC
7
requirements
Contract stage
Ensure design checks are undertaken at appropriate category TWC (with TWDCs) 8
Ensure that the final design, RAMS and inspection checklists are TWC (with TWSs)
distributed to site (and understood by all)
Ensure that any materials are inspected on delivery TWC (with TWSs) 9
Ensure that any changes and/or deviations are notified to the TWD TWC
and TWDC, for approval
Hold Points: Issue any permit-to-work, e.g. load, put into use or TWC
10
dismantle (as appropriate)
11
FORMS
Examples
12
Form No. 1
EXAMPLE - Appointment of a Temporary Works Co-ordinator (TWC)
To: Project:
Appointment:
You have been appointed as the Temporary Works Coordinator for the above Project.
This appointment satisfies the recommendation in BS 5975: 2019 to appoint a Temporary Works Coordinator.
The duties and competencies are summarised below and are detailed in the Company Temporary Works Procedure.
Signed:
ACKNOWLEDGEMENT
Duties:
The TWC has overall responsibility to ensure that all temporary works under their control are undertaken in
accordance with the company Temporary Works Procedure.
NOTE: A PC’s TWC takes precedence.
For temporary works in Design Check Category 1, 2 and 3 ensure there is an agreement in place to formally allocate
design responsibility to the design and design checking organisations.
Prepare, maintain and regularly review the Temporary Works Register for the above project.
Ensure each temporary works item is allocated an appropriate ‘construction risk’ category.
Ensure that a written Design Brief is prepared for all appropriate temporary works and issued to the design and
design checking organisations identified on the Temporary Works Register.
Review Risk Assessments and Method Statements (RAMS) to ensure particular requirements are incorporated.
Ensure that a Project Site File is established and maintained; to include a record of all relevant documents.
Liaise with the Principal Contractor’s TWC (and seek approvals, where required).
Distribute information to all interested parties, including the Principal Designer and Client where appropriate.
Ensure that any proposed changes in material or construction are referred to the Temporary Works Designer and
that any agreed changes or corrections of faults are correctly carried out on site.
Ensure that all appropriate inspections and hold points (including those noted in the design) are undertaken and
recorded on the permit-to-work.
Sign and issue the permit-to-work, e.g. permit to load, permit for putting into use, permit to strike, permit to
remove, etc.; and agree in writing where the TWS may do this (not high-risk work).
Identify and instigate any requirements for periodic inspections, monitoring and maintenance of the temporary
works.
Competency Requirements:
Have undertaken and passed the 2-day CITB-accredited TWC Course; and have proven experience.
Understand the company procedure for the control of temporary works.
Have the resource, personal skills and authority to carry out the TWC duties; including the suspension of work where
necessary.
I have read, understand the responsibilities as noted and am able to undertake the duties placed on me by this
appointment.
Signed:
Date:
Copied to:
13
Form No. 2
EXAMPLE - Appointment of a Temporary Works Supervisor (TWS)
From: Date:
Temporary Works Coordinator
To: Project:
Appointment
You have been appointed as the Temporary Works Supervisor for the above Project.
This appointment satisfies the recommendation in BS 5975: 2019 to appoint, where required, a Temporary Works
Supervisor.
The duties and competencies are summarised below and are detailed in the Company Temporary Works Procedure.
Signed:
ACKNOWLEDGEMENT
Duties
Competency Requirements
Have undertaken and passed the 1-day CITB-accredited TWS Course; and have proven experience.
Understand the company procedure for the control of temporary works.
Have the resource, personal skills and authority to carry out the TWS duties; including the suspension of work where
necessary.
I have read, understand the responsibilities as noted and am able to undertake the duties placed on me by this
appointment.
Signed:
Date:
Copied to:
14
Form No. 3
EXAMPLE - Organogram - Lines of responsibility for temporary works (Typical)
Construction teams
Client
Name:
Name:
Name:
TWC TWC
Name: Name:
15
Design teams
Permanent Principal
Works Designer Designer (PD)
(PWD)
Name:
Name:
Temporary
Works
Coordinator Principal
(TWC) Contractor
Name:
16
Form No. 4
EXAMPLE - Record of Project Appointments
3. Deputy TWC:
Date appointed:
Date accepted:
Date appointed:
Contact:
NOTE: If more than one record them all
17
Date appointed:
Contact:
NOTE: If more record them all
Date appointed:
Contact:
NOTE: If more than one record them all
8. Principal Designer:
Scope of work:
Date appointed:
Contact:
NOTE: See CDM2015
18
Form No. 5
EXAMPLE - Temporary Works Register
)
19
Ref. Rev.: Date: Page No.:
No.:
9.
7.
(1
Project: Title TWC: Name
v8
Item Description Construction Design check Designer Design TWS Temporary Design brief Design Temporary
No. risk category category Checker works in use received works on
site
T-
Low/Medium/High 0/1/2/3 Programme date Issue date Date Date
AF
DR
N AL
FI
f-
TW
19
Form No. 6
EXAMPLE - Design Brief
20
Form No. 7
EXAMPLE - Design Certificate
Calculations Reference
Lead Designer:
To be signed by the temporary works designer (or other person authorised to sign):
Design Manager:
To be signed by the person authorised to sign on behalf of the organisation responsible for the temporary works design:
I certify that the staff who have prepared the above-noted design are competent to carry out their
duties and that (so far as I can reasonably ascertain) they have used reasonable professional skill and
care.
Signed: Name: Title: Date:
21
Form No. 8
EXAMPLE - Design Check Certificate
Calculations Reference
Action required:
Design Manager:
To be signed by the person authorised to sign on behalf of the organisation responsible for the temporary works design check:
I certify that the staff who have prepared the above-noted design check are competent to carry out their duties
and that (so far as I can reasonably ascertain) they have used reasonable professional skill and care.
Signed: Name: Title: Date:
22
Form No. 9
EXAMPLE - Record of Inspection
Ref: Date and time: Location and Matters observed that Details of action taken at Details of any further Name, signature and
description of item may give rise to health time of inspection: action considered position of Inspector:
inspected: and safety risks: necessary:
23
Form No. 10
EXAMPLE - Permit-to-work
PERMIT-TO-WORK FORM No. 10
Contract: Contract No:
Temporary Works Co-ordinator: Temporary Works Supervisor:
As appointed As appointed
Temporary works:
As described in Temporary Works Register (with reference number)
Specific location(s) on site: Further clarification may be required, e.g. specific bay or group of bays to be poured or specific floor level
etc.
DRAWINGS
Drawing Number Rev. Item Other
Identification number of
drawing(s) showing the design Potential to add reference to
Latest issue
from which the temporary RAMS
works will be built
If the temporary works scheme is not loaded by the following date then the Date:
scheme requires to be re-inspected prior to loading:
Signed (TWC): Date:
EDITORIAL NOTE:
The company should check whether this template needs to reflect any other requirements, e.g. client,
etc. (particularly on large projects, where additional signature(s) may be required).