0% found this document useful (0 votes)
12 views

Project Management Calculation

calculating

Uploaded by

jack.finey03
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views

Project Management Calculation

calculating

Uploaded by

jack.finey03
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

BR - BUS3501 -Operations Management: GB4S6

Professor Name- Professor Doshi

Submitted by- Jugraj Singh


Project Management Calculation

1) Expected Duration Calculations

The formula for expected duration (TE) is given by:

TE = (T_O + 4T_M + T_P) / 6

Where:

- T_O is the optimistic time

- T_M is the most likely time

- T_P is the pessimistic time

Expected duration (TE) for each activity:

1. Activity A (1-2): TE_A = (2 + 4(4) + 9) / 6 = 4.5

2. Activity B (1-3): TE_B = (5 + 4(8) + 14) / 6 = 8.5

3. Activity C (1-4): TE_C = (4 + 4(10) + 13) / 6 = 9.5

4. Activity D (2-5): TE_D = (4 + 4(7) + 10) / 6 = 7

5. Activity E (3-5): TE_E = (11 + 4(14) + 20) / 6 = 14.5

6. Activity F (4-6): TE_F = (9 + 4(13) + 16) / 6 = 12.83

7. Activity G (6-7): TE_G = (2 + 4(4) + 6) / 6 = 4

8. Activity H (5-7): TE_H = (1 + 4(3) + 6) / 6 = 3.17


2) Network Diagram

The network diagram can be drawn based on the paths given, with nodes representing

activities and edges showing the expected durations:

3) Critical Path

To find the critical path, the total duration for each path through the network is calculated:

- Path 1-2-5-7: TE_A + TE_D + TE_H = 4.5 + 7 + 3.17 = 14.67

- Path 1-3-5-7: TE_B + TE_E + TE_H = 8.5 + 14.5 + 3.17 = 26.17

- Path 1-4-6-7: TE_C + TE_F + TE_G = 9.5 + 12.83 + 4 = 26.33

The critical path is **1-4-6-7** with a duration of **26.33 units**.