NEC4 Engineering and Construction Subcontract (ECS)
NEC4 Engineering and Construction Subcontract (ECS)
on
engineering and
construction
cco
onst subcontract
s
t
ec
oj
pr
M
O
C
AE
on
se
ru
Fo
June 2017
Expires 20/11/20
Fo
ru
Expires 20/11/20
se
on
AE
C
O
M
pr
oj
ec
ts
on
ly
ly
on
Engineering and Construction
ts
Subcontract
ec
oj
This contract should be used for the appointment of a subcontractor for engineering and
construction work including any level of design responsibility where the contractor has been
pr
appointed under an NEC4 main contract
An NEC document
M
June 2017
(with amendments January 2019)
O
C
AE
on
se
ru
Expires 20/11/20
ly
NEC is a division of Thomas Telford Ltd, which is a wholly owned subsidiary of the Institution
on
of Civil Engineers (ICE), the owner and developer of the NEC.
The NEC is a suite of standard contracts, each of which has these characteristics:
• Its use stimulates good management of the relationship between the two parties to the
ts
contract and, hence, of the work included in the contract.
• It can be used in a wide variety of commercial situations, for a wide variety of types of
ec
work and in any location.
• It is a clear and simple document – using language and a structure which are
straightforward and easily understood.
oj
NEC4 Engineering and Construction Subcontract is one of the NEC suite and is consistent
with all other NEC4 documents. Also available are the Engineering and Construction
pr
Contract User Guides and Flow Charts which include guidance and flowcharts on this
subcontract.
M
ISBN (complete box set) 978-0-7277-6391-4
ISBN (this document) 978-0-7277-6211-5
O
British Library Cataloguing in Publication Data for this publication is available from the
British Library.
ru
All rights, including translation, reserved. The owner of this document may reproduce
Fo
the Subcontract Data and forms for the purpose of obtaining tenders, awarding and
administering contracts. Except as permitted by the Copyright, Designs and Patents Act
1988, no part of this publication may be otherwise reproduced, stored in a retrieval system
or transmitted in any form or by any means, electronic, mechanical, photocopying, recording
or otherwise, without the prior written permission of the NEC Director, Thomas Telford Ltd,
One Great George Street, Westminster, London SW1P 3AA.
Printed and bound in Great Britain by Bell & Bain Limited, Glasgow, UK
Expires 20/11/20
Contents
Contents
ly
Foreword v
on
Preface vii
Acknowledgements ix
ts
Amendments January 2019 x
ec
Schedule of Options 1
Core Clauses 3
oj
1 General 3
2 The Subcontractor’s main responsibilities 8
3 Time 10
4
5
6
Quality management
Payment
Compensation events
pr 13
15
17
M
7 Title 23
8 Liabilities and insurance 24
O
9 Termination 27
Expires 20/11/20
Contents
ly
Option X20: Key Performance Indicators (not used with Option X12) 56
Option X21: Whole life cost 57
on
Option Y(UK)1: Project Bank Account 58
Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996 60
Option Y(UK)3: The Contracts (Rights of Third Parties) Act 1999 61
ts
Option Z: Additional conditions of subcontract 61
ec
Schedule of Cost Components 62
oj
Short Schedule of Cost Components 66
Subcontract Data 69
pr
Part one – Data provided by the Contractor
Part two – Data provided by the Subcontractor
69
82
M
Index 87
O
C
AE
on
se
ru
Fo
Expires 20/11/20
Foreword
Foreword
ly
Continuous improvement in project delivery is required to build confidence in the UK
construction sector so that we can attract more investment. The Infrastructure and Projects
on
Authority (IPA) is the government’s centre of expertise for infrastructure and major projects.
We sit at the heart of government, reporting to the Cabinet Office and HM Treasury.
The application of the right contract is central to the success of the overall project delivery
system. The NEC suite of contracts has been in existence for over the 20 years and has linked
ts
the projects, people and processes together to create the correct environment for successful
delivery.
ec
This new and updated NEC4 contract embraces the digital changes that are happening in the
construction industry, especially around BIM, which I believe will be central to creating a step
change in performance. Whilst looking forward it also builds on the fundamentals required
oj
for an effective contract.
The use of NEC4 on public sector projects will help to deliver the Government Construction
pr
Strategy as we seek to improve central government’s capability as a construction client to
deliver further savings in the order of £1.7bn across the Government estate. The IPA looks
forward to collaborating with industry to make the delivery of projects more efficient and
effective.
M
Tony Meggs, Chief Executive, Infrastructure and Projects Authority
O
C
AE
Expires 20/11/20
Fo
ru
Expires 20/11/20
se
on
AE
C
O
M
pr
oj
ec
ts
on
ly
Preface
Preface
ly
NEC was first published as a new and innovative way of managing construction contracts in
1993 – some 24 years ago. It was designed to facilitate and encourage good management of
on
risks and uncertainties, using clear and simple language.
The NEC approach to managing contracts was endorsed in “Constructing the team – The
Latham Report”, which was a government/industry review of procurement and contractual
arrangements in the UK construction industry. This led to a second edition in 1995
ts
incorporating the further recommendations of that review. This contract was used increasingly
in the UK and overseas, and a major revision was made with the third edition in 2005.
ec
NEC has played a part in helping the industry do things differently and better. It has done
so by introducing effective project management procedures into the contract itself. These
require pro-active management of risk and change, and the day-to-day use of an up-to-date
oj
programme. The range of pricing options has given Clients flexibility in the allocation of risk
and the ability to share risk and manage it, collaboratively.
pr
The NEC suite has evolved over three decades, embedding consultation responses and user
feedback, and reflecting industry development, including new procurement approaches and
management techniques such as alliances, management of information (BIM) and supply
chain engagement. This feedback and the new procurement approaches formed the driver
M
for the development of the next generation contracts and the launch of NEC4.
• a new design build and operate contract to allow flexibility between construction and
operational requirements in timing and extent
on
• a new multi-party alliance contract based upon an integrated risk and reward model
NEC has always been known for its innovative approach to contract management, and this
revision continues that approach. No other contract suite has had such a transformative effect
on the built environment industry as NEC. It has put the collaborative sharing of risk and
reward at the heart of modern procurement. It is also unique in providing a complete, back-to-
back procurement solution for all works, services and supplies in any sector and any country.
NEC4 continues to set the benchmark for best practice procurement worldwide.
Expires 20/11/20
Fo
ru
Expires 20/11/20
se
on
AE
C
O
M
pr
oj
ec
ts
on
ly
Acknowledgements
Acknowledgements
ly
The original NEC was designed and drafted by Dr Martin Barnes then of Coopers and
Lybrand with the assistance of Professor J. G. Perry then of the University of Birmingham,
on
T. W. Weddell then of Travers Morgan Management, T. H. Nicholson, Consultant to the
Institution of Civil Engineers, A. Norman then of the University of Manchester Institute of
Science and Technology and P. A. Baird, then Corporate Contracts Consultant, Eskom, South
Africa.
ts
This fourth edition of the NEC suite was produced by the Institution of Civil Engineers
through its NEC4 Contract Board.
ec
The NEC4 Contract Board is:
oj
P. T. Cousins, BEng (Tech), DipArb, CEng, MICE, FCIArb
I. Heaphy, BSc (Hons), FRICS, FCIArb, MCInstCES, MACostE
J. N. Hughes-D’Aeth, BA (Hons), MA (Cantab)
pr
S. Rowsell, BSc, CEng, FCIHT, FICE, MCIPS
Proofreading by:
The Institution of Civil Engineers acknowledges the help in preparing the fourth edition
on
given by the NEC4 Contract Board and NEC4 drafting team and the support of the following
organisations in releasing their staff:
CEMAR
Costain plc
Mott MacDonald Ltd
ru
Fo
Expires 20/11/20
Amendments January 2019
ly
The following amendments have been made to the June 2017 edition.
on
Page Clause/location Amendments
ts
27 90.2 Clause amended
ec
35, 38, 42 50.9 Clause amended
oj
55 X15.6 Clause added
58
58
Y1.1(5)
Y1.1(6) pr
Clause amended
Clause amended
M
59 Y1.10 Clause amended
contract
Section 3 time
Expires 20/11/20
Schedule of Options
Schedule of Options
ly
MAIN OPTIONS The strategy for choosing the form of contract starts with a decision between six main
on
Options, one of which must be chosen.
Option A Priced subcontract with activity schedule
Option B Priced subcontract with bill of quantities
ts
Option C Target subcontract with activity schedule
Option D Target subcontract with bill of quantities
ec
Option E Cost reimbursable subcontract
RESOLVING AND One of the following procedures for resolving and avoiding disputes must be selected to
oj
AVOIDING DISPUTES complete the chosen main Option.
Option W1 Used when the United Kingdom Housing Grants, Construction and Regeneration Act 1996
pr
does not apply
Option W2 Used when the United Kingdom Housing Grants, Construction and Regeneration Act 1996
applies
M
SECONDARY OPTIONS The following secondary Options should then be considered. It is not necessary to use any of
them. Any combination other than those stated may be used.
O
Option X1 Price adjustment for inflation (used only with Options A, B, C and D)
Option X2 Changes in the law
C
Expires 20/11/20
SCHEDULE OF OPTIONS
The following Options dealing with national legislation should be included if required.
Option Y(UK)1 Project Bank Account
Option Y(UK)2 The Housing Grants, Construction and Regeneration Act 1996
ly
Option Y(UK)3 The Contracts (Rights of Third Parties) Act 1999
on
Option Z Additional conditions of subcontract
Note Option X19 is not used
ts
ec
oj
pr
M
O
C
AE
on
se
ru
Fo
Expires 20/11/20
Core Clauses
Core Clauses
CORE CLAUSES
ly
1. GENERAL
on
Actions 10
10.1 The Parties shall act as stated in this subcontract.
10.2 The Parties act in a spirit of mutual trust and co-operation.
ts
Identified and 11
defined terms 11.1 In these conditions of subcontract, terms identified in the Subcontract Data are in italics and
defined terms have capital initials.
ec
oj
(2) Completion is when the Subcontractor has
pr
• done all the work which the Subcontract Scope states is to be done by the Subcontract
Completion Date and
• corrected notified Defects which would have prevented the Client or the Contractor
M
from using the subcontract works and Others from doing their work.
If the work which the Subcontractor is to do by the Subcontract Completion Date is not
work necessary for the Client or the Contractor to use the subcontract works or for Others to
do their work.
C
in connection with this subcontract or any other contract with the Contractor. This includes
on
any commission paid as an inducement which was not declared to the Contractor before the
Subcontract Date.
COST COMPONENTS
(4) A Defect is
se
• a part of the subcontract works which is not in accordance with the Subcontract Scope
or
accordance with the applicable law or the Subcontractor’s design which the Contractor
has accepted.
(5) The Defects Certificate is either a list of Defects that the Contractor has notified before
the defects date which the Subcontractor has not corrected or, if there are no such Defects,
Fo
It includes a description of the matter and the way in which the effects of the matter are to
be avoided or reduced.
Expires 20/11/20
Core Clauses
(7) Equipment is items provided and used by the Subcontractor to Provide the Subcontract
Works and which the Subcontract Scope does not require the Subcontractor to include in the
subcontract works.
CORE CLAUSES
ly
(8) The Fee is the amount calculated by applying the fee percentage to the amount of
Defined Cost.
on
(9) A Key Date is the date by which work is to meet the Condition stated. The Key Date is
the key date stated in the Subcontract Data and the Condition is the condition stated in the
Subcontract Data unless later changed in accordance with the subcontract.
(10) Others are people or organisations who are not the Client, the Project Manager,
ts
the Supervisor, the Adjudicator, the Contractor, Subcontractor or any employee,
Subsubcontractor or supplier of the Subcontractor.
ec
(11) The Parties are the Contractor and the Subcontractor.
MAIN OPTION CLAUSES
(12) Plant and Materials are items intended to be included in the subcontract works.
oj
(13) To Provide the Subcontract Works means to do the work necessary to complete the
subcontract works in accordance with the subcontract and all incidental work, services and
actions which the subcontract requires.
pr
(14) The Site is the area within the boundaries of the site and the volumes above and below it
which are affected by work included in the subcontract.
M
(15) Site Information is information which
SECONDARY OPTION CLAUSES
(16) The Subcontract Completion Date is the subcontract completion date unless later
C
(17) The Subcontract Date is the date when the subcontract came into existence.
• states any constraints on how the Subcontractor Provides the Subcontract Works
and is either
COST COMPONENTS
• design all or part of the subcontract works, except the design of Plant and Materials
Fo
• provide a service in the Working Areas which is necessary to Provide the Subcontract
SUBCONTRACT DATA
–– hire of Equipment or
–– supply of people paid for by the Subcontractor according to the time they work.
Expires 20/11/20
Core Clauses
(20) The Working Areas are the Site and those parts of the subcontract working areas which
are
CORE CLAUSES
ly
• used only for work in the subcontract
on
unless later changed in accordance with the subcontract.
Interpretation and 12
the law 12.1 In the subcontract, except where the context shows otherwise, words in the singular also
mean in the plural and the other way round.
ts
12.2 The subcontract is governed by the law of the subcontract.
12.3 No change to the subcontract, unless provided for by these conditions of subcontract, has
ec
effect unless it is has been agreed and confirmed in writing and signed by the Parties.
Communications 13
oj
13.1 Each communication which the subcontract requires is communicated in a form which can
be read, copied and recorded. Writing is in the language of the subcontract.
13.2
pr
If the Subcontract Scope specifies the use of a communication system, a communication
has effect when it is communicated through the communication system specified in the
Subcontract Scope.
M
If the Subcontract Scope does not specify a communication system, a communication
has effect when it is received at the last address notified by the recipient for receiving
Subcontract Data.
13.3 If the subcontract requires the Contractor or the Subcontractor to reply to a communication,
C
unless otherwise stated in these conditions of subcontract, they reply within the period for
reply.
13.4 The Contractor replies to a communication submitted or resubmitted by the Subcontractor
AE
for acceptance. If the reply is not acceptance, the Contractor states the reasons in sufficient
detail to enable the Subcontractor to correct the matter. The Subcontractor resubmits
the communication within the period for reply taking account of these reasons. A reason
for withholding acceptance is that more information is needed in order to assess the
Subcontractor’s submission fully.
on
13.5 The Contractor may extend the period for reply to a communication if the Contractor and
the Subcontractor agree to the extension before the reply is due. The Contractor informs the
COST COMPONENTS
Subcontractor of the extension which has been agreed.
13.6 The Contractor issues certificates to the Subcontractor.
se
13.7 A notification or certificate which the subcontract requires is communicated separately from
other communications.
13.8 The Contractor may withhold acceptance of a submission by the Subcontractor. Withholding
ru
The Contractor 14
Fo
Expires 20/11/20
Core Clauses
Early warning 15
15.1 The Subcontractor and the Contractor give an early warning by notifying the other as soon
as either becomes aware of any matter which could
CORE CLAUSES
ly
• increase the total of the Prices,
• delay Completion,
on
• delay meeting a Key Date or
The Contractor or Subcontractor may give an early warning by notifying the other of any
ts
other matter which could increase the Subcontractor’s total cost. The Contractor enters
early warning matters in the Early Warning Register. Early warning of a matter for which a
ec
compensation event has previously been notified is not required.
MAIN OPTION CLAUSES
15.2 The Contractor prepares a first Early Warning Register and issues it to the Subcontractor
within one week of the subcontract starting date. The Contractor instructs the Subcontractor
to attend a first early warning meeting within two weeks of the subcontract starting date.
oj
Later early warning meetings are held
•
meeting, and, in any case,
pr
if either the Contractor or Subcontractor instructs the other to attend an early warning
at no longer interval than the interval stated in the Subcontract Data until Completion of
M
the whole of the subcontract works.
SECONDARY OPTION CLAUSES
The Contractor or Subcontractor may instruct other people to attend an early warning
O
The Contractor may instruct the Subcontractor to attend an early warning meeting between
C
the Project Manager and the Contractor if the early warning matter under the main contract
also affects the subcontract.
AE
• making and considering proposals for how the effects of each matter in the Early
Warning Register can be avoided or reduced,
• seeking solutions that will bring advantage to all those who will be affected,
on
• deciding on the actions which will be taken and who, in accordance with the
subcontract, will take them,
COST COMPONENTS
• deciding which matters can be removed from the Early Warning Register and
se
• reviewing actions recorded in the Early Warning Register and deciding if different actions
need to be taken and who, in accordance with the subcontract, will take them.
15.4 The Contractor revises the Early Warning Register to record the decisions made at each early
ru
warning meeting and issues the revised Early Warning Register to the Subcontractor within
one week of the early warning meeting. If a decision needs a change to the Subcontract
Scope, the Contractor instructs the change at the same time as the revised Early Warning
Register is issued.
Fo
Subcontractor’s 16
SUBCONTRACT DATA
proposals 16.1 The Subcontractor may propose to the Contractor that the Subcontract Scope provided
by the Contractor is changed in order to reduce the amount the Contractor pays to the
Subcontractor for Providing the Subcontract Works. The Contractor consults with the Project
Manager, Client and the Subcontractor about the change.
Expires 20/11/20
Core Clauses
16.2 Within five weeks of the Subcontractor making the proposal the Contractor
• accepts the Subcontractor’s proposal and issues an instruction changing the Subcontract
Scope,
CORE CLAUSES
ly
• informs the Subcontractor that the Contractor or Client is considering the proposal and
instructs the Subcontractor to submit a quotation for a proposed instruction to change
on
the Subcontract Scope or
The Contractor may give any reason for not accepting the proposal.
ts
16.3 The Subcontractor may submit a proposal for adding an area to the Working Areas to the
Contractor for acceptance. A reason for not accepting is that the proposed area is
ec
• not necessary for Providing the Subcontract Works or
oj
Requirements for 17
instructions 17.1 The Contractor or the Subcontractor notifies the other as soon as either becomes aware
of an ambiguity or inconsistency in or between the documents which are part of the
17.2
pr
subcontract. The Contractor states how the ambiguity or inconsistency should be resolved.
The Contractor or the Subcontractor notifies the other as soon as either becomes aware that
M
the Subcontract Scope includes an illegal or impossible requirement. If the Subcontract Scope
does include an illegal or impossible requirement, the Contractor gives an instruction to
Corrupt Acts 18
18.1 The Subcontractor does not do a Corrupt Act.
C
18.2 The Subcontractor takes action to stop a Corrupt Act of a Subsubcontractor or supplier of
which it is, or should be, aware.
AE
18.3 The Subcontractor includes equivalent provisions to these in subsubcontracts and contracts
for the supply of Plant and Materials and Equipment.
Prevention 19
19.1 If an event occurs which
on
COST COMPONENTS
• stops the Subcontractor completing the whole of the subcontract works by the date for
planned Completion shown on the Accepted Programme,
se
and which
• an experienced subcontractor would have judged at the Subcontract Date to have such a
small chance of occurring that it would have been unreasonable to have allowed for it,
the Contractor gives an instruction to the Subcontractor stating how the event is to be dealt
Fo
with.
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
Providing the 20
Subcontract Works 20.1 The Subcontractor Provides the Subcontract Works in accordance with the Subcontract
CORE CLAUSES
ly
Scope.
The 21
on
Subcontractor’s 21.1 The Subcontractor designs the parts of the subcontract works which the Subcontract Scope
design states the Subcontractor is to design.
21.2 The Subcontractor submits the particulars of its design as the Subcontract Scope requires to
the Contractor for acceptance. A reason for not accepting the Subcontractor’s design is that
ts
it does not comply with either the Subcontract Scope or the applicable law.
The Subcontractor does not proceed with the relevant work until the Contractor has
ec
accepted its design.
MAIN OPTION CLAUSES
21.3 The Subcontractor may submit its design for acceptance in parts if the design of each part
can be assessed fully.
oj
Using the 22
Subcontractor’s 22.1 The Client and the Contractor may use and copy the Subcontractor’s design for any
design purpose connected with construction, use, alteration or demolition of the subcontract
pr
works or the works in the main contract, unless otherwise stated in the Subcontract Scope
and for other purposes as stated in the subcontract. The Subcontractor obtains from a
Subsubcontractor equivalent rights for the Contractor and Client to use material prepared by
the Subsubcontractor.
M
Design of 23
SECONDARY OPTION CLAUSES
Equipment 23.1 The Subcontractor submits particulars of the design of an item of Equipment to the
O
Contractor for acceptance if the Contractor instructs the Subcontractor to. A reason for
not accepting is that the design of the item will not allow the Subcontractor to Provide the
C
People 24
on
24.1 The Subcontractor either provides each key person named to do the job stated in the
Subcontract Data or provides a replacement person who has been accepted by the
COST COMPONENTS
Contractor.
The Subcontractor submits the name, relevant qualifications and experience of a proposed
se
replacement person to the Contractor for acceptance. A reason for not accepting the person
is that their relevant qualifications and experience are not as good as those of the person
who is to be replaced.
24.2
ru
The Contractor may, having stated the reasons, instruct the Subcontractor to remove a
person. The Subcontractor then arranges that, after one day, the person has no further
connection with the work included in the subcontract.
Contractor and 25.1 The Subcontractor co-operates with Others including in obtaining and providing information
Others which they need in connection with the subcontract works. The Subcontractor shares the
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
CORE CLAUSES
on the same project, the additional cost which Contractor has paid or will incur is paid by
ly
the Subcontractor. The Contractor assesses the additional cost within five weeks of the date
when the Condition for the Key Date is met. The Contractor’s right to recover the additional
on
cost is its only right in these circumstances.
Subsubcontracting 26
26.1 If the Subcontractor subsubcontracts work, it is responsible for Providing the Subcontract
Works as if it had not subsubcontracted. The subcontract applies as if a Subsubcontractor’s
ts
employees and equipment were the Subcontractor’s.
26.2 The Subcontractor submits the name of each proposed Subsubcontractor to the Contractor
ec
for acceptance. A reason for not accepting the Subsubcontractor is that the appointment will
oj
• accepted the Subsubcontractor and, to the extent these conditions of subcontract require,
pr
The Subcontractor submits the proposed subsubcontract documents, except any pricing
information, for each subsubcontract to the Contractor for acceptance unless
• the proposed subsubcontract is an NEC contract which has not been amended other
M
than in accordance with the additional conditions of subcontract or
• their use will not allow the Subcontractor to Provide the Subcontract Works or
• they do not include a statement that the parties to the subsubcontract shall act in a spirit
AE
Other 27
responsibilities 27.1 The Subcontractor obtains approval of its design from Others where necessary.
27.2 The Subcontractor provides access to work being done and to Plant and Materials being
on
• the Contractor,
COST COMPONENTS
• the Project Manager,
se
27.3 The Subcontractor obeys an instruction which is in accordance with the subcontract and is
given by the Contractor.
27.4 The Subcontractor acts in accordance with the health and safety requirements stated in the
Subcontract Scope.
Fo
Assignment 28
SUBCONTRACT DATA
28.1 Either Party notifies the other Party if they intend to transfer the benefit of the subcontract
or any rights under it. The Contractor does not transfer a benefit or any rights if the party
receiving the benefit or right does not intend to act in a spirit of mutual trust and co-operation.
Disclosure 29
29.1 The Parties do not disclose information obtained in connection with the subcontract works
except when necessary to carry out their duties under the subcontract.
29.2 The Subcontractor may publicise the subcontract works only with the Contractor’s
agreement.
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 9
Expires 20/11/20
Core Clauses
3. TIME
Starting, 30
Completion and 30.1 The Subcontractor does not start work on the Site until the first subcontract access date and
CORE CLAUSES
ly
Key Dates does the work so that Completion is on or before the Subcontract Completion Date.
30.2 The Contractor decides the date of Completion and certifies it within one week of the date.
on
30.3 The Subcontractor does the work so that the Condition stated for each Key Date is met by
the Key Date.
The programme 31
31.1 If a programme is not identified in the Subcontract Data, the Subcontractor submits a first
ts
programme to the Contractor for acceptance within the period stated in the Subcontract
Data.
ec
31.2 The Subcontractor shows on each programme submitted for acceptance
MAIN OPTION CLAUSES
• the subcontract starting date, subcontract access dates, Key Dates and Subcontract
Completion Date,
oj
• planned Completion,
pr
• the order and timing of the operations which the Subcontractor plans to do in order to
Provide the Subcontract Works,
• the order and timing of the work of the Client, the Contractor and Others as last agreed
with them by the Subcontractor or, if not so agreed, as stated in the Subcontract Scope,
M
• the dates when the Subcontractor plans to meet each Condition stated for the Key Dates
SECONDARY OPTION CLAUSES
and to complete other work needed to allow the Client, the Contractor and Others to do
O
their work,
• provisions for
C
–– float,
AE
• the dates when, in order to Provide the Subcontract Works in accordance with the
programme, the Subcontractor will need
COST COMPONENTS
–– access to a part of the Site if later than its subcontract access date,
se
–– acceptances,
–– Plant and Materials and other things to be provided by the Client and the Contractor
and
ru
• for each operation, a statement of how the Subcontractor plans to do the work
Fo
identifying the principal Equipment and other resources which will be used and
• other information which the Subcontract Scope requires the Subcontractor to show on a
SUBCONTRACT DATA
A programme issued for acceptance is in the form stated in the Subcontract Scope.
Expires 20/11/20
Core Clauses
31.3 Within three weeks of the Subcontractor submitting a programme for acceptance, the
Contractor notifies the Subcontractor of the acceptance of the programme or the reasons for
not accepting it. A reason for not accepting a programme is that
CORE CLAUSES
ly
• the Subcontractor’s plans which it shows are not practicable,
on
• it does not represent the Subcontractor’s plans realistically or
If the Contractor does not notify acceptance or non-acceptance within the time allowed,
ts
the Subcontractor may notify the Contractor of that failure. If the failure continues for a
further two weeks after the Subcontractor’s notification, it is treated as acceptance by the
ec
Contractor of the programme.
oj
• the actual progress achieved on each operation and its effect upon the timing of the
remaining work,
• pr
how the Subcontractor plans to deal with any delays and to correct notified Defects and
any other changes which the Subcontractor proposes to make to the Accepted
Programme.
M
32.2 The Subcontractor submits a revised programme to the Contractor for acceptance
• within the period for reply after the Contractor has instructed the Subcontractor to,
• at no longer interval than the interval stated in the Subcontract Data from the
subcontract starting date until Completion of the whole of the subcontract works.
AE
Instructions to stop 34
COST COMPONENTS
or not to start work 34.1 The Contractor may instruct the Subcontractor to stop or not to start any work. The
Contractor subsequently gives an instruction to the Subcontractor to
se
Take over 35
35.1 The Contractor need not take over the subcontract works before the Subcontract
Completion Date if the Subcontract Data states it is not willing to do so. Otherwise the
Contractor takes over the subcontract works not later than two weeks after Completion.
Fo
35.2 The Client or the Contractor may use any part of the subcontract works before Completion
has been certified. The Contractor takes over the part of the subcontract works when the
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
Acceleration 36
36.1 The Subcontractor and the Contractor may propose to the other an acceleration to achieve
Completion before the Subcontract Completion Date. If the Contractor and Subcontractor
are prepared to consider the proposed change, the Contractor instructs the Subcontractor
CORE CLAUSES
ly
to provide a quotation. The instruction states changes to the Key Dates to be included in the
quotation. The Subcontractor provides a quotation within two weeks of the instruction to do
so. The Contractor replies to the quotation within four weeks. The reply is
on
• a notification that the quotation is accepted or
• a notification that the quotation is not accepted and that the Subcontract Completion
Dates and Key Dates are not changed.
ts
36.2 A quotation for an acceleration comprises proposed changes to the Prices and a revised
programme showing the earlier Subcontract Completion Date and the changed Key Dates.
ec
The Subcontractor submits details of the assessment with each quotation.
MAIN OPTION CLAUSES
36.3 When a quotation for an acceleration is accepted, the Contractor changes the Prices,
the Subcontract Completion Date and the Key Dates accordingly and accepts the revised
oj
programme.
pr
M
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
4. QUALITY MANAGEMENT
Quality 40
management 40.1 The Subcontractor operates a quality management system which complies with the
CORE CLAUSES
ly
system requirements stated in the Subcontract Scope.
40.2 Within the period stated in the Subcontract Data, the Subcontractor provides the Contractor
on
with a quality policy statement and a quality plan for acceptance. A reason for not accepting
a quality policy statement or quality plan is that it does not allow the Subcontractor to
Provide the Subcontract Works.
If any changes are made to the quality plan, the Subcontractor provides the Contractor with
ts
the changed quality plan for acceptance.
40.3 The Contractor may instruct the Subcontractor to correct a failure to comply with the quality
plan. This instruction is not a compensation event.
ec
oj
41.2 The Subcontractor and the Contractor provide materials, facilities and samples for tests and
inspections as stated in the Subcontract Scope.
41.3
pr
The Subcontractor and the Contractor informs the other of each of their tests and
inspections before the test or inspection starts and afterwards informs the other of the
results. The Subcontractor informs the Contractor in time for a test or inspection to be
arranged and done before doing work which would obstruct the test or inspection. The
M
Contractor and the Supervisor may watch any test done by the Subcontractor.
if
• the Contractor or the Supervisor has not done the test or inspection and
41.6 The Contractor assesses the cost incurred by it in repeating a test or inspection after a Defect
is found. The Subcontractor pays the amount assessed.
COST COMPONENTS
Testing and 42
inspection before 42.1 The Subcontractor does not bring to the Working Areas those Plant and Materials which the
se
delivery Subcontract Scope states are to be tested or inspected before delivery until the Contractor
has notified the Subcontractor that they have passed the test or inspection.
notifying Defects 43.1 Until the defects date, the Contractor may instruct the Subcontractor to search for a Defect.
The Contractor gives reason for the search with the instruction. Searching may include
• providing facilities, materials and samples for tests and inspections done by the
Contractor or the Supervisor and
SUBCONTRACT DATA
• doing tests and inspections which the Subcontract Scope does not require.
43.2 Until the defects date the Contractor and Subcontractor notifies the other as soon as they
become aware of a Defect.
Correcting Defects 44
44.1 The Subcontractor corrects a Defect whether or not the Contractor has notified it.
Expires 20/11/20
Core Clauses
44.2 The Subcontractor corrects a notified Defect before the end of the defect correction period.
The defect correction period begins at Completion for Defects notified before Completion
and when the Defect is notified for other Defects.
44.3 The Contractor issues the Defects Certificate at the defects date if there are no notified
CORE CLAUSES
ly
Defects, or otherwise at the earlier of
on
• the date when all notified Defects have been corrected.
The Client’s or the Contractor’s rights in respect of a Defect which the Contractor has not
found or notified are not affected by the issue of the Defects Certificate.
ts
44.4 The Contractor arranges for the Client and the Contractor to allow the Subcontractor access
to and use of a part of the subcontract works which has been taken over if it is needed for
ec
correcting a Defect. In this case the defect correction period begins when the necessary
MAIN OPTION CLAUSES
Accepting Defects 45
oj
45.1 The Subcontractor and the Contractor may each propose to the other that the Subcontract
Scope should be changed so that a Defect does not have to be corrected.
pr
45.2 If the Subcontractor and the Contractor are prepared to consider the change, the
Subcontractor submits a quotation for reduced Prices or an earlier Subcontract Completion
Date or both to the Contractor for acceptance. If the quotation is accepted, the Contractor
changes the Subcontract Scope, the Prices and the Subcontract Completion Date accordingly
M
and accepts the revised programme.
SECONDARY OPTION CLAUSES
Uncorrected 46
O
Defects 46.1 If the Subcontractor is given access in order to correct a notified Defect but the Defect is
not corrected within its defect correction period, the Contractor assesses the cost to it of
having the Defect corrected by other people and the Subcontractor pays this amount. The
C
defects date, the Contractor assesses the cost to the Subcontractor of correcting the Defect
and the Subcontractor pays this amount. The Subcontract Scope is treated as having been
changed to accept the Defect.
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
5. PAYMENT
Assessing the 50
amount due 50.1 The Contractor assesses the amount due at each assessment date. The first assessment date
CORE CLAUSES
ly
is decided by the Contractor to suit the procedures of the Parties and is not later than the
assessment interval after the subcontract starting date. Later assessment dates occur at the
end of each assessment interval until
on
• the Contractor issues the Defects Certificate or
ts
assessment date setting out the amount the Subcontractor considers is due at the
assessment date. The Subcontractor’s application for payment includes details of how the
ec
amount has been assessed and is in the form stated in the Subcontract Scope.
oj
50.3 If the Subcontractor submits an application for payment before the assessment date, the
amount due at the assessment date is
•
the Price for Work Done to Date,
pr
plus other amounts to be paid to the Subcontractor,
M
• less amounts to be paid by or retained from the Subcontractor.
50.4 If the Subcontractor does not submit an application for payment before the assessment date,
• the amount the Contractor assesses as due at the assessment date, assessed as though
the Subcontractor had submitted an application before the assessment date, and
C
50.5 If no programme is identified in the Subcontract Data, one quarter of the Price for Work
Done to Date is retained in assessments of the amount due until the Subcontractor has
submitted a first programme to the Contractor for acceptance showing the information
which the subcontract requires.
50.6 The Contractor corrects any incorrectly assessed amount due in a later payment certificate.
on
Payment 51
51.1 The Contractor certifies a payment within two weeks of each assessment date. The
COST COMPONENTS
Contractor’s certificate includes details of how the amount due has been assessed. The
first payment is the amount due. Other payments are the change in the amount due since
se
51.2 Each certified payment is made within four weeks of the assessment date or, if a different
period is stated in the Subcontract Data, within the period stated. If a certified payment is
late, or if a payment is late because the Contractor has not issued a certificate which should
Fo
be issued, interest is paid on the late payment. Interest is assessed from the date by which
the late payment should have been made until the date when the late payment is made, and
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
interest on the correcting amount is paid. Interest is assessed from the date when the
incorrect amount was certified until the date when the changed amount is certified and is
included in the assessment which includes the changed amount.
51.4 Interest is calculated on a daily basis at the interest rate and is compounded annually.
CORE CLAUSES
ly
51.5 Any tax which the law requires a Party to pay to the other Party is added to any payment
made under the subcontract.
on
Defined Cost 52
52.1 All the Subcontractor’s costs which are not included in the Defined Cost are treated as included
in the Fee. Defined Cost includes only amounts calculated using rates and percentages stated in
the Subcontract Data and other amounts at open market or competitively tendered prices with
ts
deductions for all discounts, rebates and taxes which can be recovered.
Final assessment 53
ec
53.1 The Contractor makes an assessment of the final amount due and certifies a final payment, if
MAIN OPTION CLAUSES
oj
• fourteen weeks after the Contractor issues a termination certificate.
53.2
pr
The Contractor gives the Subcontractor details of how the amount due has been assessed.
The final payment is made within three weeks of the assessment or, if a different period is
stated in the Subcontract Data, within the period stated.
If the Contractor does not make this assessment within the time allowed, the Subcontractor
M
may issue to the Contractor an assessment of the final amount due, giving details of how the
final amount due has been assessed. If the Contractor agrees with this assessment, a final
SECONDARY OPTION CLAUSES
payment is made within three weeks of the assessment or, if a different period is stated in
O
conclusive evidence of the final amount due under or in connection with the subcontract
unless a Party takes the following actions.
AE
• refers a dispute about the assessment of the final amount due to the Senior
Representatives within four weeks of the assessment being issued,
• refers any issues not agreed by the Senior Representatives to the Adjudicator within
on
three weeks of the list of the issues not agreed being produced or when it should have
been produced and
COST COMPONENTS
• refers to the tribunal its dissatisfaction with a decision of the Adjudicator as to the final
assessment of the amount due within four weeks of the decision being made.
se
• refers a dispute about the assessment of the final amount due to the Senior
ru
Representatives or to the Adjudicator within four weeks of the assessment being issued,
• refers any issues referred to but not agreed by the Senior Representatives to the
Adjudicator within three weeks of the list of issues not agreed being produced or when
it should have been produced and
Fo
• refers to the tribunal its dissatisfaction with a decision of the Adjudicator as to the final
SUBCONTRACT DATA
assessment of the amount due within four weeks of the decision being made.
53.4 The assessment of the final amount due is changed to include
• a decision of the Adjudicator which has not been referred to the tribunal within four
weeks of that decision.
A changed assessment becomes conclusive evidence of the final amount due under or in
connection with the subcontract.
Expires 20/11/20
Core Clauses
6. COMPENSATION EVENTS
Compensation 60
events 60.1 The following events are compensation events.
CORE CLAUSES
ly
(1) The Contractor gives an instruction changing the Subcontract Scope except
on
• a change made in order to accept a Defect or
• a change to the Subcontract Scope provided by the Subcontractor for its design which is
made
ts
–– in order to comply with the Subcontract Scope provided by the Contractor.
ec
(2) The Contractor does not allow access to and use of each part of the Site by the later of its
(3) The Contractor does not provide something which it is to provide by the date shown on
oj
the Accepted Programme.
pr
(4) The Contractor gives an instruction to stop or not to start any work or to change a Key
Date.
• carry out work on the Site that is not stated in the Subcontract Scope.
C
(6) The Contractor does not reply to a communication from the Subcontractor within the
period required by the subcontract.
AE
(7) The Contractor gives an instruction for dealing with an object of value or of historical or
other interest found within the Site.
(8) The Contractor changes a decision which it has previously communicated to the
Subcontractor.
on
(9) The Contractor withholds an acceptance (other than acceptance of a quotation for
acceleration or for not correcting a Defect) for a reason not stated in the subcontract.
COST COMPONENTS
(10) The Contractor instructs the Subcontractor to search for a Defect and no Defect is found
unless the search is needed only because the Subcontractor gave insufficient notice of doing
se
(11) A test or inspection done by the Contractor or the Supervisor causes unnecessary delay.
ru
• an experienced subcontractor would have judged at the Subcontract Date to have such
SUBCONTRACT DATA
a small chance of occurring that it would have been unreasonable to have allowed for
them.
Only the difference between the physical conditions encountered and those for which
it would have been reasonable to have allowed is taken into account in assessing a
compensation event.
Expires 20/11/20
Core Clauses
• before the Subcontract Completion Date for the whole of the subcontract works and
ly
• at the place stated in the Subcontract Data
on
the value of which, by comparison with the weather data, is shown to occur on average less
frequently than once in ten years.
Only the difference between the weather measurement and the weather which the weather
data show to occur on average less frequently than once in ten years is taken into account in
ts
assessing a compensation event.
(14) An event occurs for which the Contractor or Client is liable as stated in these conditions
ec
MAIN OPTION CLAUSES
of subcontract.
(15) The Contractor certifies take over of a part of the subcontract works before both
oj
Completion and the Subcontract Completion Date.
(16) The Contractor does not provide materials, facilities and samples for tests and
pr
inspections as stated in the Subcontract Scope.
(17) The Contractor notifies the Subcontractor of a correction to an assumption which the
Contractor stated about a compensation event.
M
(18) A breach of contract by the Contractor which is not one of the other compensation
events in the subcontract.
SECONDARY OPTION CLAUSES
• stops the Subcontractor completing the whole of the subcontract works by the date for
AE
and which
• an experienced subcontractor would have judged at the Subcontract Date to have such
on
a small chance of occurring that it would have been unreasonable to have allowed for it
and
COST COMPONENTS
(20) The Contractor notifies the Subcontractor that a quotation for a proposed instruction is
not accepted.
60.2 In judging the physical conditions for the purpose of assessing a compensation event, the
Subcontractor is assumed to have taken into account
Expires 20/11/20
Core Clauses
Notifying 61
compensation 61.1 For a compensation event which arises from the Contractor giving an instruction or
events notification, issuing a certificate or changing an earlier decision, the Contractor notifies the
Subcontractor of the compensation event at the time of that communication.
CORE CLAUSES
ly
61.2 The Contractor includes in the notification of a compensation event an instruction to the
Subcontractor to submit quotations unless
on
• the event arises from a fault of the Subcontractor or
• the event has no effect upon Defined Cost, Completion or meeting a Key Date.
61.3 The Subcontractor notifies the Contractor of an event which has happened or which is
ts
expected to happen as a compensation event if
ec
If the Subcontractor does not notify a compensation event within seven weeks of becoming
oj
aware that the event has happened, the Prices, the Subcontract Completion Date or a Key
Date are not changed unless the event arises from the Contractor giving an instruction or
notification, issuing a certificate or changing an earlier decision.
61.4
pr
The Contractor replies to the Subcontractor’s notification of a compensation event within
• has not been notified within the timescales set out in these conditions of subcontract,
AE
the Contractor notifies the Subcontractor that the Prices, the Subcontract Completion
on
Date and the Key Dates are not to be changed and states the reasons in the notification.
Otherwise, the Contractor notifies the Subcontractor that the event is a compensation event
COST COMPONENTS
and includes in the notification an instruction to the Subcontractor to submit quotations.
within the time allowed, the Subcontractor may notify the Contractor of that failure. If the
failure continues for a further three weeks after the Subcontractor’s notification it is treated
as acceptance by the Contractor that the event is a compensation event and an instruction to
submit quotations.
ru
61.5 If the Contractor decides that the Subcontractor did not give an early warning of the event
which an experienced subcontractor could have given, the Contractor states this in the
instruction to the Subcontractor to submit quotations.
Fo
61.6 If the effects of a compensation event are too uncertain to be forecast reasonably, the
Contractor states assumptions about the compensation event in the instruction to the
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
Quotations for 62
compensation 62.1 After discussing with the Subcontractor different ways of dealing with the compensation
events event which are practicable, the Contractor may instruct the Subcontractor to submit
alternative quotations. The Subcontractor submits the required quotations to the Contractor
CORE CLAUSES
ly
and may submit quotations for other methods of dealing with the compensation event which
it considers practicable.
on
62.2 Quotations for a compensation event comprise proposed changes to the Prices and any
delay to the Subcontract Completion Date and Key Dates assessed by the Subcontractor.
The Subcontractor submits details of the assessment with each quotation. If the programme
for remaining work is altered by the compensation event, the Subcontractor includes the
alterations to the Accepted Programme in the quotation.
ts
62.3 The Subcontractor submits quotations within two weeks of being instructed to do so by the
Contractor. The Contractor replies within four weeks of the submission. The reply is
ec
• a notification of acceptance of the quotation,
MAIN OPTION CLAUSES
oj
• that the Contractor will be making the assessment.
62.4 The Contractor instructs the Subcontractor to submit a revised quotation only after
62.5 pr
explaining the reasons for doing so to the Subcontractor. The Subcontractor submits the
revised quotation within two weeks of being instructed to do so.
The Contractor extends the time allowed for
M
• the Subcontractor to submit quotations for a compensation event and
SECONDARY OPTION CLAUSES
if the Contractor and the Subcontractor agree to the extension before the submission or
reply is due. The Contractor informs the Subcontractor of the extension which has been
C
agreed.
62.6 If the Contractor does not reply to a quotation within the time allowed, the Subcontractor
AE
may notify the Contractor of that failure. If the Subcontractor submitted more than
one quotation for the compensation event, the notification states which quotation the
Subcontractor proposes is to be used. If the failure continues for a further three weeks
after the Subcontractor’s notification it is treated as acceptance by the Contractor of the
quotation.
on
Assessing 63
compensation 63.1 The change to the Prices is assessed as the effect of the compensation event upon
COST COMPONENTS
events
• the actual Defined Cost of the work done by the dividing date,
se
• the forecast Defined Cost of the work not done by the dividing date and
For a compensation event that arises from the Contractor giving an instruction or
notification, issuing a certificate or changing an earlier decision, the dividing date is the date
of that communication.
Fo
For other compensation events, the dividing date is the date of the notification of the
compensation event.
SUBCONTRACT DATA
63.2 The Contractor and the Subcontractor may agree rates or lump sums to assess the change to
the Prices.
63.3 If the effect of a compensation event is to reduce the total Defined Cost, the Prices are not
reduced unless otherwise stated in these conditions of subcontract.
Expires 20/11/20
Core Clauses
63.4 If the effect of a compensation event is to reduce the total Defined Cost and the event is
• a change to the Subcontract Scope other than a change to the Subcontract Scope
provided by the Contractor, which the Subcontractor proposed and the Contractor
CORE CLAUSES
ly
accepted or
on
compensation event
ts
the Accepted Programme current at the dividing date.
A delay to a Key Date is assessed as the length of time that, due to the compensation event,
ec
the planned date when the Condition stated for a Key Date will be met is later than the date
oj
• any delay caused by the compensation event already in the Accepted Programme and
63.6
•
dividing date.
pr
events which have happened between the date of the Accepted Programme and the
The rights of the Contractor and the Subcontractor to changes to the Prices, the Subcontract
M
Completion Date and the Key Dates are their only rights in respect of a compensation event.
63.7 If the Contractor has stated in the instruction to submit quotations that the Subcontractor
given, the compensation event is assessed as if the Subcontractor had given the early
warning.
C
63.8 The assessment of the effect of a compensation event includes risk allowances for cost and
time for matters which have a significant chance of occurring and are not compensation
events.
AE
63.9 The assessment of the effect of a compensation event is based upon the assumptions that
the Subcontractor reacts competently and promptly to the event and that any Defined Cost
and time due to the event are reasonably incurred.
63.10 A compensation event which is an instruction to change the Subcontract Scope in order to
on
COST COMPONENTS
63.11 If a change to the Subcontract Scope makes the description of the Condition for a Key Date
incorrect, the Contractor corrects the description. This correction is taken into account in
se
assessing the compensation event for the change to the Subcontract Scope.
The Contractor’s 64
assessments 64.1 The Contractor assesses a compensation event
ru
• if the Subcontractor has not submitted the quotation and details of its assessment within
the time allowed,
Fo
• if the Contractor decides that the Subcontractor has not assessed the compensation
event correctly in the quotation and has not instructed the Subcontractor to submit a
SUBCONTRACT DATA
revised quotation,
• if, when the Subcontractor submits quotations for the compensation event, it has not
submitted a programme or alterations to a programme which the subcontract requires it
to submit or
• if, when the Subcontractor submits quotations for the compensation event, the
Contractor has not accepted the Subcontractor’s latest programme for one of the
reasons stated in the subcontract.
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 21
Expires 20/11/20
Core Clauses
64.2 The Contractor assesses the programme for the remaining work and uses it in the assessment
of a compensation event if
ly
• the Subcontractor has not submitted a programme or alterations to a programme for
acceptance as required by the subcontract or
on
• the Contractor has not accepted the Subcontractor’s latest programme for one of the
reasons stated in the subcontract.
64.3 The Contractor notifies the Subcontractor of the assessment of a compensation event and
gives details of the assessment within the period allowed for the Subcontractor’s submission
ts
of its quotation for the same compensation event. This period starts when the need for the
Contractor’s assessment becomes apparent.
ec
64.4 If the Contractor does not assess a compensation event within the time allowed, the
MAIN OPTION CLAUSES
Subcontractor may notify the Contractor of that failure. If the Subcontractor submitted more
than one quotation for the compensation event, the notification states which quotation
the Subcontractor proposes is to be used. If the failure continues for a further three weeks
oj
after the Subcontractor’s notification it is treated as acceptance by the Contractor of the
Subcontractor’s quotation.
Proposed
instructions
65
65.1
pr
The Contractor may instruct the Subcontractor to submit a quotation for a proposed
instruction. The Contractor states in the instruction the date by which the proposed
instruction may be given. The Subcontractor does not put a proposed instruction into effect.
M
65.2 The Subcontractor submits quotations for a proposed instruction within two weeks of being
SECONDARY OPTION CLAUSES
The Contractor replies to the Subcontractor’s quotation by the date when the proposed
instruction may be given. The reply is
C
• an instruction to submit a revised quotation including the reasons for doing so,
If the Contractor does not reply to the quotation within the time allowed, the quotation is
not accepted.
on
65.3 If the quotation is not accepted, the Contractor may issue the instruction, notify the
instruction as a compensation event and instruct the Subcontractor to submit a quotation.
COST COMPONENTS
Implementing 66
se
Expires 20/11/20
Core Clauses
7. TITLE
The Contractor’s 70
title to Plant and 70.1 Whatever title the Subcontractor has to Plant and Materials which are outside the Working
CORE CLAUSES
ly
Materials Areas passes to the Contractor if the Contractor has marked them as for the subcontract.
70.2 Whatever title the Subcontractor has to Plant and Materials passes to the Contractor if they
on
have been brought within the Working Areas. The title to Plant and Materials passes back
to the Subcontractor if they are removed from the Working Areas with the Contractor’s
permission.
Marking 71
ts
Equipment, Plant 71.1 The Contractor marks Equipment, Plant and Materials which are outside the Working Areas if
and Materials
outside the • the subcontract identifies them for payment and
ec
Working Areas
• the Subcontractor has prepared them for marking as the Subcontract Scope requires.
oj
Equipment 72.1 The Subcontractor removes Equipment from the Site when it is no longer needed unless the
Contractor allows it to be left in the subcontract works.
pr
Objects and 73
materials within 73.1 The Subcontractor has no title to an object of value or of historical or other interest within
the Site the Site. The Subcontractor informs the Contractor when such an object is found and the
Contractor instructs the Subcontractor how to deal with it. The Subcontractor does not move
M
the object without instructions.
73.2 The Subcontractor has title to materials from excavation and demolition unless the
The Subcontractor’s 74
use of material 74.1 The Subcontractor has the right to use material provided by the Contractor or the Client
C
only to Provide the Subcontract Works. The Subcontractor may make this right available to a
Subsubcontractor.
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
Client’s and 80
Contractor’s 80.1 The following are Client’s and Contractor’s liabilities.
CORE CLAUSES
ly
liabilities
• Claims and proceedings from Others and compensation and costs payable to Others
which are due to
on
–– use or occupation of the Site by the works or for the purpose of the works which is
the unavoidable result of the works or
–– negligence, breach of statutory duty or interference with any legal right by the
ts
Client or the Contractor or by any person employed by or contracted to them except
the Subcontractor.
ec
• A fault of the Client or the Contractor or any person employed by or contracted to them,
MAIN OPTION CLAUSES
oj
–– the Subcontract Scope provided by the Contractor or
pr
–– an instruction from the Contractor changing the Subcontract Scope.
• Loss of or damage to Plant and Materials supplied to the Subcontractor by the Client or
Contractor, or by Others on the Client’s or Contractor’s behalf, until the Subcontractor
M
has received and accepted them.
–– strikes, riots and civil commotion not confined to the Subcontractor’s employees or
C
–– radioactive contamination.
AE
• Loss of or damage to the parts of the subcontract works taken over by the Contractor,
except loss, wear or damage occurring before the issue of the Defects Certificate which
is due to
–– an event occurring before take over which was not itself a Client’s or Contractor’s
liability or
COST COMPONENTS
• Loss of or damage to the subcontract works and any Equipment, Plant and Materials
retained on the Site by the Client or Contractor after a termination, except loss or
damage due to the activities of the Subcontractor on the Site after the termination.
ru
• Loss of or damage to property owned or occupied by the Client or Contractor other than
the subcontract works, unless the loss or damage arises from or in connection with the
Subcontractor Providing the Subcontract Works.
Fo
Subcontractor’s 81
liabilities 81.1 The following are Subcontractor’s liabilities unless they are stated as being Client’s or
Contractor’s liabilities.
• Claims and proceedings from Others and compensation and costs payable to Others
which arise from or in connection with the Subcontractor Providing the Subcontract
Works.
Expires 20/11/20
Core Clauses
• Loss of or damage to the subcontract works, Plant and Materials and Equipment.
CORE CLAUSES
ly
Providing the Subcontract Works.
on
Recovery of costs 82
82.1 Any cost which the Contractor has paid or will pay as a result of an event for which the
Subcontractor is liable is paid by the Subcontractor.
82.2 Any cost which the Subcontractor has paid or will pay to Others as a result of an event for
ts
which the Contractor or the Client is liable is paid by the Contractor.
82.3 The right of a Party to recover these costs is reduced if an event for which it was liable
ec
contributed to the costs. The reduction is in proportion to the extent that the event for which
oj
Insurance cover 83
83.1 The Client or Contractor provides the insurances which the Client or Contractor are to
provide as stated in the Subcontract Data.
83.2
pr
The Subcontractor provides the insurances stated in the Insurance Table except any insurance
which the Client or the Contractor is to provide as stated in the Subcontract Data. The
Subcontractor provides additional insurances as stated in the Subcontract Data.
M
83.3 The insurances in the Insurance Table are in the joint names of the Parties except the fourth
insurance stated. The insurances provide cover for events which are the Subcontractor’s
INSURANCE TABLE
C
Loss of or damage to the subcontract works, The replacement cost, including the amount
Plant and Materials stated in the Subcontract Data for the
replacement of any Plant and Materials provided
by the Client or the Contractor
COST COMPONENTS
Loss of or damage to property (except the The amount stated in the Subcontract Data for
subcontract works, Plant and Materials and any one event with cross liability so that the
Equipment) and liability for bodily injury to or insurance applies to the Parties separately
se
Death of or bodily injury to employees of the The greater of the amount required by the
Subcontractor arising out of and in the course applicable law and the amount stated in the
of their employment in connection with the Subcontract Data for any one event
subcontract
Fo
Insurance policies 84
SUBCONTRACT DATA
84.1 Before the subcontract starting date and on each renewal of the insurance policy until the
defects date, the Subcontractor submits to the Contractor for acceptance certificates which
state that the insurance required by the subcontract is in force. The certificates are signed by
the Subcontractor’s insurer or insurance broker. The Contractor accepts the certificates if the
insurance complies with the subcontract and if the insurer’s commercial position is strong
enough to carry the insured liabilities.
Expires 20/11/20
Core Clauses
84.2 Insurance policies include a waiver by the insurers of their subrogation rights against the
Parties and the directors and other employees of every insured except where there is fraud.
84.3 The Parties comply with the terms and conditions of the insurance policies to which they are
a party.
CORE CLAUSES
ly
If the 85
Subcontractor does 85.1 The Contractor may insure an event or liability which the subcontract requires the
on
not insure Subcontractor to insure if the Subcontractor does not submit a required certificate. The cost
of this insurance to the Contractor is paid by the Subcontractor.
Insurance by 86
the Client or the 86.1 The Contractor submits certificates for insurances provided by the Client or the Contractor to
ts
Contractor the Subcontractor for acceptance before the subcontract starting date and afterwards as the
Subcontractor instructs. The Subcontractor accepts the certificates if the insurance complies
ec
with the subcontract and if the insurer’s commercial position is strong enough to carry the
MAIN OPTION CLAUSES
insured liabilities.
86.2 The Subcontractor’s acceptance of an insurance policy or certificate provided by the Client
oj
or Contractor does not change the responsibility of the Client or Contractor to provide the
insurances stated in the Subcontract Data.
86.3 The Subcontractor may insure an event or liability which the subcontract requires the
pr
Contractor or Client to insure if the Contractor does not submit a required policy or
certificate. The cost of this insurance to the Subcontractor is paid by the Contractor.
M
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Core Clauses
9. TERMINATION
Termination 90
90.1 If either Party wishes to terminate the Subcontractor’s obligation to Provide the Subcontract
CORE CLAUSES
ly
Works it notifies the other Party giving details of the reason for terminating. The Contractor
issues a termination certificate promptly if the reason complies with the subcontract.
on
90.2 A Party may terminate for a reason identified in the Termination Table. The procedures
followed and the amounts due on termination are in accordance with the Termination Table.
TERMINATION TABLE
ts
TERMINATING PARTY REASON PROCEDURE AMOUNT DUE
ec
R17 or R20 P1 and P4 A1 and A2
oj
R23 P4 A1, A2 and A4
90.3
R17 or R20
pr P1 and P4 A1 and A2
The procedures for termination are implemented immediately after the Contractor has issued
M
a termination certificate.
payment has not been made at the date of the termination certificate, the Contractor need
not make the certified payment unless these conditions of subcontract state otherwise.
90.4 After a termination certificate has been issued, the Subcontractor does no further work
C
Reasons for 91
termination 91.1 Either Party may terminate if the other Party has done one of the following or its equivalent.
COST COMPONENTS
–– had a receiver appointed over its assets (R3) or
reconstruct) (R7),
it (R8),
–– had a receiver, receiver and manager, or administrative receiver appointed over the
whole or a substantial part of its undertaking or assets (R9) or
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 27
Expires 20/11/20
Core Clauses
91.2 The Contractor may terminate if it has notified the Subcontractor that the Subcontractor
has not put one of the following defaults right within three weeks of the date when the
Contractor notified the Subcontractor of the default.
CORE CLAUSES
ly
• Substantially failed to comply with its obligations (R11).
on
• Appointed a Subsubcontractor for substantial work before the Contractor has accepted
the Subsubcontractor (R13).
91.3 The Contractor may terminate if it has notified the Subcontractor that the Subcontractor
has not stopped one of the following defaults within three weeks of the date when the
ts
Contractor notified the Subcontractor of the default.
ec
MAIN OPTION CLAUSES
oj
subcontract within thirteen weeks of the date that it should have been paid (R16).
91.5 Either Party may terminate if the Parties have been released under the law from further
pr
performance of the whole of the subcontract (R17).
91.6 If the Contractor has instructed the Subcontractor to stop or not to start any substantial work
or all work and an instruction allowing the work to re-start or start or removing work from
the Subcontract Scope has not been given within fourteen weeks,
M
• the Contractor may terminate if the instruction was due to a default by the
SECONDARY OPTION CLAUSES
Subcontractor (R18),
O
• the Subcontractor may terminate if the instruction was due to a default by the
Contractor (R19) and
C
• either Party may terminate if the instruction was due to any other reason (R20).
AE
• stops the Subcontractor completing the whole of the subcontract works by the date
for planned Completion shown on the Accepted Programme and is forecast to delay
on
and which
COST COMPONENTS
• an experienced subcontractor would have judged at the Subcontract Date to have such
a small chance of occurring that it would have been unreasonable to have allowed for it
(R21).
ru
91.8 The Contractor may terminate if the Subcontractor does a Corrupt Act, unless it was done by
a Subsubcontractor or supplier and the Subcontractor
• was not and should not have been aware of the Corrupt Act or
Fo
• informed the Contractor of the Corrupt Act and took action to stop it as soon as the
Subcontractor became aware of it (R22).
SUBCONTRACT DATA
91.9 The Contractor may terminate if its obligation to provide the works in the main contract has
been terminated (R23).
Procedures on 92
termination 92.1 On termination, the Contractor may complete the subcontract works and may use any Plant
and Materials to which it has title (P1).
Expires 20/11/20
Core Clauses
92.2 The procedure on termination also includes one or more of the following as set out in the
Termination Table.
P2 The Contractor may instruct the Subcontractor to leave the Site, remove any
CORE CLAUSES
ly
Equipment, Plant and Materials from the Site and assign the benefit of any
subsubcontract or other contract related to performance of the subcontract to the
Contractor.
on
P3 The Contractor may use any Equipment to which the Subcontractor has title
to complete the subcontract works. The Subcontractor promptly removes the
Equipment from Site when the Contractor informs the Subcontractor that the
Contractor no longer requires it to complete the subcontract works.
ts
P4 The Subcontractor leaves the Working Areas and removes the Equipment.
ec
Payment on 93
oj
• the Defined Cost for Plant and Materials
––
––
pr
within the Working Areas or
to which the Contractor has title and of which the Subcontractor has to accept
delivery,
M
• other Defined Cost reasonably incurred in expectation of completing the whole of the
subcontract works,
93.2 The amount due on termination also includes one or more of the following as set out in the
Termination Table.
AE
COST COMPONENTS
• for Options A, B, C and D, any excess of the total of the Prices at the Subcontract Date
over the Price for Work Done to Date or
se
• for Option E any excess of the first forecast of the Defined Cost for the subcontract
works over the Price for Work Done to Date less the Fee.
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Main Option Clauses
ly
OPTION A: PRICED SUBCONTRACT WITH ACTIVITY SCHEDULE
on
Identified and 11
defined terms 11.2 (21) The Activity Schedule is the activity schedule unless later changed in accordance with
these conditions of subcontract.
(23) Defined Cost is the cost of the components in the Short Schedule of Cost Components.
ts
(26) The People Rates are the people rates unless later changed in accordance with the
ec
subcontract.
MAIN OPTION CLAUSES
(27) The Price for Work Done to Date is the total of the Prices for
oj
• each completed activity which is not in a group.
following work.
pr
A completed activity is one without notified Defects the correction of which will delay
(30) The Prices are the lump sum prices for each of the activities on the Activity Schedule
M
unless later changed in accordance with the subcontract.
SECONDARY OPTION CLAUSES
The programme 31
O
31.4 The Subcontractor provides information which shows how each activity on the Activity
Schedule relates to the operations on each programme submitted for acceptance.
C
The Activity 55
Schedule 55.1 Information in the Activity Schedule is not Subcontract Scope or Site Information. If the
AE
activities on the Activity Schedule do not relate to the Subcontract Scope, the Subcontractor
corrects the Activity Schedule.
55.3 If the Subcontractor
• changes a planned method of working at its discretion so that the activities on the
Activity Schedule do not relate to the operations on the Accepted Programme or
on
• corrects the Activity Schedule so that the activities on the Activity Schedule relate to the
COST COMPONENTS
Subcontract Scope
the Subcontractor submits a revision of the Activity Schedule to the Contractor for
se
acceptance.
55.4 A reason for not accepting a revision of the Activity Schedule is that
• any changed Prices are not reasonably distributed between the activities which are not
completed or
Fo
Assessing 63
compensation 63.12 If the effect of a compensation event is to reduce the total Defined Cost and the event is
events a change to the Subcontract Scope provided by the Contractor, which the Subcontractor
proposed and the Contractor accepted, the Prices are reduced by an amount calculated
by multiplying the assessed effect of the compensation event by the value engineering
percentage.
63.14 Assessments for changed Prices for compensation events are in the form of changes to the
Activity Schedule.
Expires 20/11/20
Main Option Clauses
63.16 If, when assessing a compensation event the People Rates do not include a rate for a
category of person required, the Contractor and Subcontractor may agree a new rate. If they
do not agree the Contractor assesses the rate based upon the People Rates. The agreed or
assessed rate becomes the People Rate for that category of person.
CORE CLAUSES
ly
Payment on 93
termination 93.3 The amount due on termination is assessed without taking grouping of activities into
on
account.
ts
ec
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Main Option Clauses
Identified and 11
defined terms 11.2 (22) The Bill of Quantities is the bill of quantities unless later changed in accordance with
CORE CLAUSES
ly
these conditions of subcontract.
(23) Defined Cost is the cost of the components in the Short Schedule of Cost Components.
on
(26) The People Rates are the people rates unless later changed in accordance with the
subcontract.
ts
• the quantity of the work which the Subcontractor has completed for each item in the Bill
of Quantities multiplied by the rate and
ec
MAIN OPTION CLAUSES
• a proportion of each lump sum which is the proportion of the work covered by the item
which the Subcontractor has completed.
oj
Completed work is work which is without notified Defects the correction of which will delay
following work.
pr
(31) The Prices are the lump sums and the amounts obtained by multiplying the rates by the
quantities for the items in the Bill of Quantities.
The Bill of 56
M
Quantities 56.1 Information in the Bill of Quantities is not Subcontract Scope or Site Information.
Compensation 60
SECONDARY OPTION CLAUSES
events 60.4 A difference between the final total quantity of work done and the quantity stated for an
O
• the difference does not result from a change to the Subcontract Scope,
• the difference causes the Defined Cost per unit of quantity to change and
AE
• the rate in the Bill of Quantities for the item multiplied by the final total quantity of work
done is more than 0.5% of the total of the Prices at the Subcontract Date.
If the Defined Cost per unit of quantity is reduced, the affected rate is reduced.
60.5 A difference between the final total quantity of work done and the quantity for an item
on
stated in the Bill of Quantities which delays Completion or the meeting of the Condition
stated for a Key Date is a compensation event.
COST COMPONENTS
60.6 The Contractor gives an instruction to correct a mistake in the Bill of Quantities which is
se
• a departure from the rules for item descriptions or division of the work into items in the
method of measurement or
Each such correction is a compensation event which may lead to reduced Prices.
60.7 In assessing a compensation event which results from a correction of an inconsistency
between the Bill of Quantities and another document, the Subcontractor is assumed to have
Fo
Assessing 63
compensation 63.12 If the effect of a compensation event is to reduce the total Defined Cost and the event is
events a change to the Subcontract Scope provided by the Contractor, which the Subcontractor
proposed and the Contractor accepted, the Prices are reduced by an amount calculated
by multiplying the assessed value of the compensation event by the value engineering
percentage.
Expires 20/11/20
Main Option Clauses
63.15 Assessments for changed Prices for compensation events are in the form of changes to the
Bill of Quantities.
For the whole or a part of a compensation event for work not yet done and for which there
CORE CLAUSES
ly
is an item in the Bill of Quantities, the changes are
• a changed rate,
on
• a changed quantity or
For the whole or a part of a compensation event for work not yet done and for which
ts
there is no item in the Bill of Quantities, the change is a new priced item which, unless the
Contractor and the Subcontractor agree otherwise, is compiled in accordance with the
ec
method of measurement.
oj
63.16 If, when assessing a compensation event the People Rates do not include a rate for a
category of person required, the Contractor and Subcontractor may agree a new rate. If
pr
they do not agree the Contractor assesses the rate based on the People Rates. The agreed or
assessed rate becomes the People Rate for that category of person.
M
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Main Option Clauses
Identified and 11
defined terms 11.2 (21) The Activity Schedule is the activity schedule unless later changed in accordance with
CORE CLAUSES
ly
these conditions of subcontract.
(24) Defined Cost is the cost of the components in the Schedule of Cost Components less
on
Disallowed Cost.
ts
• should not have been paid to a Subsubcontractor or supplier in accordance with its
contract,
ec
MAIN OPTION CLAUSES
oj
–– give an early warning which the subcontract required it to give or
pr
–– give notification to the Contractor of the preparation for and conduct of an
adjudication or proceedings of a tribunal between the Subcontractor and a
Subsubcontractor or supplier
• correcting Defects caused by the Subcontractor not complying with a constraint on how
it is to Provide the Subcontract Works stated in the Subcontract Scope,
C
• Plant and Materials not used to Provide the Subcontract Works (after allowing for
reasonable wastage) unless resulting from a change to the Subcontract Scope,
AE
• resources not used to Provide the Subcontract Works (after allowing for reasonable
availability and utilisation) or not taken away from the Working Areas when the
Contractor requested and
the Parties.
(29) The Price for Work Done to Date is the total Defined Cost which the Contractor forecasts
COST COMPONENTS
will have been paid by the Subcontractor before the next assessment date plus the Fee.
(30) The Prices are the lump sum prices for each of the activities on the Activity Schedule
se
Providing the 20
ru
Subcontract Works 20.2 The Subcontractor advises the Contractor on the practical implications of the design of the
subcontract works and on subsubcontracting arrangements.
20.3 The Subcontractor prepares forecasts of the total Defined Cost for the whole of the
subcontract works in consultation with the Contractor and submits them to the Contractor.
Fo
Forecasts are prepared at the intervals stated in the Subcontract Data from the subcontract
starting date until Completion of the whole of the subcontract works. An explanation of the
SUBCONTRACT DATA
changes made since the previous forecast is submitted with each forecast.
Subsubcontracting 26
26.4 The Subcontractor submits the pricing information in the proposed subsubcontract
documents for each subsubcontract to the Contractor unless the Contractor has agreed that
no submission is required.
Expires 20/11/20
Main Option Clauses
Tests and 41
inspections 41.7 When the Contractor assesses the cost incurred by it in repeating a test or inspection after a
Defect is found, it does not include the Subcontractor’s cost of carrying out the repeat test
or inspection.
CORE CLAUSES
ly
Assessing the 50
amount due 50.7 Payments of Defined Cost made by the Subcontractor in a currency other than the currency
on
of the subcontract are included in the amount due as payments to be made to it in the
same currency. Such payments are converted to the currency of the subcontract in order to
calculate the Fee and any Subcontractor’s share using the exchange rates.
50.9 The Subcontractor notifies the Contractor when the Defined Cost for a part of the
ts
subcontract works has been finalised, and makes available for inspection the records
necessary to demonstrate that it has been correctly assessed. The Contractor reviews
the records made available, and no later than fourteen weeks after the Subcontractor’s
ec
notification
oj
• notifies the Subcontractor that further records are needed or
pr
The Subcontractor provides any further records requested or advises the correction of the
errors in its assessment within three weeks of the Contractor’s notification. The Contractor
reviews the records provided, and within five weeks
M
• accepts that part of Defined Cost as correct or
• notifies the Subcontractor of the correct assessment of that part of Defined Cost.
If the Subcontract does not notify a decision on that part of Defined Cost within the time
C
Defined Cost 52
AE
COST COMPONENTS
• other records as stated in the Subcontract Scope.
52.3 The Subcontractor allows the Contractor and Project Manager to inspect at any time within
se
The 54
Subcontractor’s 54.1 The Contractor assesses the Subcontractor’s share of the difference between the total of the
ru
share Prices and the Price for Work Done to Date. The difference is divided into increments falling
within each of the share ranges. The limits of a share range are the Price for Work Done
to Date divided by the total of the Prices, expressed as a percentage. The Subcontractor’s
share equals the sum of the products of the increment within each share range and the
Fo
54.2 If the Price for Work Done to Date is less than the total of the Prices, the Subcontractor is
paid its share of the saving. If the Price for Work Done to Date is greater than the total of the
Prices, the Subcontractor pays its share of the excess.
54.3 The Contractor makes a preliminary assessment of the Subcontractor’s share at Completion
of the whole of the subcontract works using forecasts of the final Price for Work Done to
Date and the final total of the Prices. This share is included in the amount due following
Completion of the whole of the subcontract works.
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 35
Expires 20/11/20
Main Option Clauses
54.4 The Contractor makes a final assessment of the Subcontractor’s share using the final Price for
Work Done to Date and the final total of the Prices. This share is included in the final amount
due.
CORE CLAUSES
ly
The Activity 55
Schedule 55.2 Information in the Activity Schedule is not Subcontract Scope or Site Information.
on
Assessing 63
compensation 63.13 If the effect of a compensation event is to reduce the total Defined Cost and the event is
events a change to the Subcontract Scope provided by the Contractor, which the Subcontractor
proposed and the Contractor accepted, the Prices are not reduced.
63.14 Assessments for changed Prices for compensation events are in the form of changes to the
ts
Activity Schedule.
ec
Payment on 93
MAIN OPTION CLAUSES
termination 93.4 If there is a termination, the Contractor assesses the Subcontractor’s share after certifying
termination. The assessment uses as the Price for Work Done to Date the total of the Defined
Cost which the Subcontractor has paid and which it is committed to pay for work done
oj
before termination, and uses as the total of the Prices
• the lump sum price for each activity which has been completed and
93.6
•
pr
a proportion of the lump sum price for each incomplete activity which is the proportion
of the work in the activity which has been completed.
The Contractor’s assessment of the Subcontractor’s share is added to the amount due to the
M
Subcontractor on termination if there has been a saving or deducted if there has been an
excess.
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Main Option Clauses
Identified and 11
defined terms 11.2 (22) The Bill of Quantities is the bill of quantities unless later changed in accordance with
CORE CLAUSES
ly
these conditions of subcontract.
(24) Defined Cost is the cost of the components in the Schedule of Cost Components less
on
Disallowed Cost.
ts
• should not have been paid to a Subsubcontractor or supplier in accordance with its
contract,
ec
oj
–– give an early warning which the subcontract required it to give or
pr
–– give notification to the Contractor of the preparation for and conduct of an
adjudication or proceedings of a tribunal between the Subcontractor and a
Subsubcontractor or supplier
• correcting Defects caused by the Subcontractor not complying with a constraint on how
it is to Provide the Subcontract Works stated in the Subcontract Scope,
C
• Plant and Materials not used to Provide the Subcontract Works (after allowing for
reasonable wastage) unless resulting from a change to the Subcontract Scope,
AE
• resources not used to Provide the Subcontract Works (after allowing for reasonable
availability and utilisation) or not taken away from the Working Areas when the
Contractor requested and
the Parties.
(29) The Price for Work Done to Date is the total Defined Cost which the Contractor forecasts
COST COMPONENTS
will have been paid by the Subcontractor before the next assessment date plus the Fee.
(31) The Prices are the lump sums and the amounts obtained by multiplying the rates by the
se
• the quantity of the work which the Subcontractor has completed for each item in the Bill
of Quantities multiplied by the rate and
• a proportion of each lump sum which is the proportion of the work covered by the item
Fo
following work.
Providing the 20
Subcontract Works 20.2 The Subcontractor advises the Contractor on the practical implications of the design of the
subcontract works and on subsubcontracting arrangements.
Expires 20/11/20
Main Option Clauses
20.3 The Subcontractor prepares forecasts of the total Defined Cost for the whole of the
subcontract works in consultation with the Contractor and submits them to the Contractor.
Forecasts are prepared at the intervals stated in the Subcontract Data from the subcontract
starting date until Completion of the whole of the subcontract works. An explanation of the
CORE CLAUSES
ly
changes made since the previous forecast is submitted with each forecast.
Subsubcontracting 26
on
26.4 The Subcontractor submits the pricing information in the proposed subsubcontract
documents for each subsubcontract to the Contractor unless the Contractor has agreed that
no submission is required.
Tests and 41
ts
inspections 41.7 When the Contractor assesses the cost incurred by it in repeating a test or inspection after a
Defect is found, it does not include the Subcontractor’s cost of carrying out the repeat test
or inspection.
ec
MAIN OPTION CLAUSES
Assessing the 50
amount due 50.7 Payments of Defined Cost made by the Subcontractor in a currency other than the currency
oj
of the subcontract are included in the amount due as payments to be made to it in the
same currency. Such payments are converted to the currency of the subcontract in order to
calculate the Fee and any Subcontractor’s share using the exchange rates.
50.9
pr
The Subcontractor notifies the Contractor when the Defined Cost for a part of the subcontract
works has been finalised, and makes available for inspection the records necessary to
demonstrate that it has been correctly assessed. The Contractor reviews the records made
available, and no later than fourteen weeks after the Subcontractor’s notification
M
• accepts that part of Defined Cost as correct,
SECONDARY OPTION CLAUSES
The Subcontractor provides any further records requested or advises the correction of the
errors in its assessment within three weeks of the Contractor’s notification. The Contractor
AE
• notifies the Subcontractor of the correct assessment of that part of Defined Cost.
on
If the Subcontract does not notify a decision on that part of Defined Cost within the time
stated, the Subcontractor’s assessment is treated as correct.
COST COMPONENTS
Defined Cost 52
52.2 The Subcontractor keeps these records
se
52.3 The Subcontractor allows the Contractor and Project Manager to inspect at any time within
SUBCONTRACT DATA
The 54
Subcontractor’s 54.5 The Contractor assesses the Subcontractor’s share of the difference between the Total of the
share Prices and the Price for Work Done to Date. The difference is divided into increments falling
within each of the share ranges. The limits of a share range are the Price for Work Done
to Date divided by the Total of the Prices, expressed as a percentage. The Subcontractor’s
share equals the sum of the products of the increment within each share range and the
corresponding Subcontractor’s share percentage.
38 Engineering and Construction Subcontract This page has been amended in 2019 neccontract.com © nec 2017
Expires 20/11/20
Main Option Clauses
54.6 If the Price for Work Done to Date is less than the Total of the Prices, the Subcontractor is
paid its share of the saving. If the Price for Work Done to Date is greater than the Total of the
Prices, the Subcontractor pays its share of the excess.
54.7 The Contractor makes a preliminary assessment of the Subcontractor’s share at Completion
CORE CLAUSES
ly
of the whole of the subcontract works using forecasts of the final Price for Work Done to
Date and the final Total of the Prices. This share is included in the amount due following
on
Completion of the whole of the subcontract works.
54.8 The Contractor makes a final assessment of the Subcontractor’s share using the final Price for
Work Done to Date and the final Total of the Prices. This share is included in the final amount
due.
ts
The Bill of 56
Quantities 56.1 Information in the Bill of Quantities is not Subcontract Scope or Site Information.
ec
Compensation 60
oj
• the difference does not result from a change to the Subcontract Scope,
• the difference causes the Defined Cost per unit of quantity to change and
•
pr
the rate in the Bill of Quantities for the item multiplied by the final total quantity of work
done is more than 0.5% of the total of the Prices at the Subcontract Date.
M
If the Defined Cost per unit of quantity is reduced, the affected rate is reduced.
60.5 A difference between the final total quantity of work done and the quantity for an item
• departures from the rules for item descriptions or division of the work into items in the
method of measurement or
AE
Each such correction is a compensation event which may lead to reduced Prices.
60.7 In assessing a compensation event which results from a correction of an inconsistency
on
between the Bill of Quantities and another document, the Subcontractor is assumed to have
taken the Bill of Quantities as correct.
COST COMPONENTS
Assessing 63
compensation 63.13 If the effect of a compensation event is to reduce the total Defined Cost and the event is
se
events a change to the Subcontract Scope provided by the Contractor, which the Subcontractor
proposed and the Contractor accepted, the Prices are not reduced.
63.15 Assessments for changed Prices for compensation events are in the form of changes to the
ru
Bill of Quantities.
For the whole or a part of a compensation event for work not yet done and for which there
is an item in the Bill of Quantities, the changes are
Fo
• a changed rate,
SUBCONTRACT DATA
• a changed quantity or
For the whole or a part of a compensation event for work not yet done and for which
there is no item in the Bill of Quantities, the change is a new priced item which, unless the
Contractor and the Subcontractor agree otherwise, is compiled in accordance with the
method of measurement.
Expires 20/11/20
Main Option Clauses
For the whole or a part of a compensation event for work already done, the change is a new
lump sum item.
Payment on 93
CORE CLAUSES
ly
termination 93.5 If there is a termination, the Contractor assesses the Subcontractor’s share after certifying
termination. The assessment uses, as the Price for Work Done to Date, the total of the
Defined Cost which the Subcontractor has paid and which it is committed to pay for work
on
done before termination.
93.6 The Contractor’s assessment of the Subcontractor’s share is added to the amount due to the
Subcontractor on termination if there has been a saving or deducted if there has been an
excess.
ts
ec
MAIN OPTION CLAUSES
oj
pr
M
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Main Option Clauses
Identified and 11
defined terms 11.2 (24) Defined Cost is the cost of the components in the Schedule of Cost Components less
CORE CLAUSES
ly
Disallowed Cost.
on
• is not justified by the Subcontractor’s accounts and records,
• should not have been paid to a Subsubcontractor or supplier in accordance with its
contract,
ts
• was incurred only because the Subcontractor did not
ec
–– follow an acceptance or procurement procedure stated in the Subcontract Scope,
oj
adjudication or proceedings of a tribunal between the Subcontractor and a
Subsubcontractor or supplier
• pr
correcting Defects after Completion,
M
• correcting Defects caused by the Subcontractor not complying with a constraint on how
it is to Provide the Subcontract Works stated in the Subcontract Scope,
• Plant and Materials not used to Provide the Subcontract Works (after allowing for
reasonable wastage) unless resulting from a change to the Subcontract Scope,
C
• resources not used to Provide the Subcontract Works (after allowing for reasonable
availability and utilisation) or not taken away from the Working Areas when the
AE
(29) The Price for Work Done to Date is the total Defined Cost which the Contractor forecasts
on
will have been paid by the Subcontractor before the next assessment date plus the Fee.
(32) The Prices are the forecast of the total Defined Cost for the whole of the subcontract
COST COMPONENTS
works plus the Fee.
Providing the 20
se
Subcontract Works 20.2 The Subcontractor advises the Contractor on the practical implications of the design of the
subcontract works and on subsubcontracting arrangements.
20.3 The Subcontractor prepares forecasts of the total Defined Cost for the whole of the
ru
subcontract works in consultation with the Contractor and submits them to the Contractor.
Forecasts are prepared at the intervals stated in the Subcontract Data from the subcontract
starting date until Completion of the whole of the subcontract works. An explanation of the
changes made since the previous forecast is submitted with each forecast.
Fo
Subsubcontracting 26
SUBCONTRACT DATA
26.4 The Subcontractor submits the pricing information in the proposed subsubcontract
documents for each subsubcontract to the Contractor unless the Contractor has agreed that
no submission is required.
Tests and 41
inspections 41.7 When the Contractor assesses the cost incurred by it in repeating a test or inspection after a
Defect is found, it does not include the Subcontractor’s cost of carrying out the repeat test
or inspection.
Expires 20/11/20
Main Option Clauses
Assessing the 50
amount due 50.8 Payments of Defined Cost made by the Subcontractor in a currency other than the currency
of the subcontract are included in the amount due as payments to be made to it in the
same currency. Such payments are converted to the currency of the subcontract in order to
CORE CLAUSES
ly
calculate the Fee using the exchange rates.
50.9 The Subcontractor notifies the Contractor when the Defined Cost for a part of the subcontract
on
works has been finalised, and makes available for inspection the records necessary to
demonstrate that it has been correctly assessed. The Contractor reviews the records made
available, and no later than fourteen weeks after the Subcontractor’s notification
ts
• notifies the Subcontractor that further records are needed or
ec
• notifies the Subcontractor of errors in its assessment.
MAIN OPTION CLAUSES
The Subcontractor provides any further records requested or advises the correction of the
errors in its assessment within three weeks of the Contractor’s notification. The Contractor
oj
reviews the records provided, and within five weeks
pr
notifies the Subcontractor of the correct assessment of that part of Defined Cost.
If the Subcontract does not notify a decision on that part of Defined Cost within the time
stated, the Subcontractor’s assessment is treated as correct.
M
Defined Cost 52
SECONDARY OPTION CLAUSES
and
se
ru
Fo
SUBCONTRACT DATA
42 Engineering and Construction Subcontract This page has been amended in 2019 neccontract.com © nec 2017
Expires 20/11/20
Resolving and Avoiding Disputes
CORE CLAUSES
ly
OPTION W1
on
Used when the United Kingdom Housing Grants, Construction and Regeneration Act 1996
does not apply.
Resolving disputes W1
W1.1 (1) A dispute arising under or in connection with the subcontract is referred to the Senior
ts
Representatives in accordance with the Dispute Reference Table. If the dispute is not resolved
by the Senior Representatives, it is referred to and decided by the Adjudicator. A Party
ec
may replace a Senior Representative after notifying the other Party of the name of the
(2) The Party referring a dispute notifies the Senior Representatives and the other Party of the
oj
nature of the dispute it wishes to resolve. Each Party submits to the other their statement of
case within one week of the notification. Each statement of case is limited to no more than
ten sides of A4 paper together with supporting evidence, unless otherwise agreed by the
Parties.
pr
(3) The Senior Representatives attend as many meetings and use any procedure they consider
necessary to try to resolve the dispute over a period of no more than three weeks. At the
M
end of this period the Senior Representatives produce a list of the issues agreed and issues
not agreed. The Contractor and the Subcontractor put into effect the issues agreed.
(4) No evidence of the statement of case or discussions is disclosed, used or referred to in any
subsequent proceedings before the Adjudicator or the tribunal.
C
An action or inaction of The Subcontractor Not more than four weeks after
Contractor the Subcontractor becomes
aware of the action or inaction
on
A programme, compensation The Contractor Not more than four weeks after
event or quotation for a it was treated as accepted
COST COMPONENTS
compensation event which
is treated as having been
se
accepted
An assessment of Defined Cost Either Party Not more than four weeks after
which is treated as correct the assessment was treated as
correct
ru
The Adjudicator W1.2 (1) The Parties appoint the Adjudicator under the NEC Dispute Resolution Service Contract
Fo
(2) The Adjudicator acts impartially and decides the dispute as an independent adjudicator
and not as an arbitrator.
(3) If the Adjudicator is not identified in the Subcontract Data or if the Adjudicator resigns or
is unable to act, the Parties choose a new adjudicator jointly. If the Parties have not chosen
an adjudicator, either Party may ask the Adjudicator nominating body to choose one. The
Adjudicator nominating body chooses an adjudicator within seven days of the request. The
chosen adjudicator becomes the Adjudicator.
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 43
Expires 20/11/20
Resolving and Avoiding Disputes
(4) A replacement Adjudicator has the power to decide a dispute referred to a predecessor
but not decided at the time when the predecessor resigned or became unable to act.
The Adjudicator deals with an undecided dispute as if it had been referred on the date of
appointment as replacement Adjudicator.
CORE CLAUSES
ly
(5) The Adjudicator, and the Adjudicator’s employees and agents are not liable to the Parties
for any action or failure to take action in an adjudication unless the action or failure to take
on
action was in bad faith.
The adjudication W1.3 (1) A Party disputing any issue not agreed by the Senior Representatives issues a notice of
adjudication to the other Party within two weeks of the production of the list of agreed
and not agreed issues, or when it should have been produced. The dispute is referred to the
ts
Adjudicator within two weeks of the notice of adjudication unless the Contractor refers the
dispute to the main contract Adjudicator.
ec
(2) The times for notifying and referring a dispute may be extended by the Contractor if
MAIN OPTION CLAUSES
the Subcontractor and the Contractor agree to the extension before the notice or referral
is due. The Contractor informs the Subcontractor of the extension that has been agreed. If
a disputed matter is not notified and referred within the times set out in the subcontract,
oj
neither Party may subsequently refer it to the Adjudicator or the tribunal.
(3) The Party referring the dispute to the Adjudicator includes with its referral information to
pr
be considered by the Adjudicator. Any more information from a Party to be considered by the
Adjudicator is provided within four weeks of the referral. This period may be extended if the
Adjudicator and the Parties agree.
M
(4) If a matter disputed by the Subcontractor under or in connection with a subsubcontract is
also a matter disputed under or in connection with the subcontract and if the subsubcontract
SECONDARY OPTION CLAUSES
allows, the Subcontractor may refer the subsubcontract dispute to the Adjudicator at the
O
same time as the subcontract referral. The Adjudicator then decides the disputes together
and references to the Parties for the purposes of the dispute are interpreted as including the
Subsubcontractor.
C
(5) Within one week of the notification of the dispute by the Subcontractor to the Contractor,
AE
the Contractor notifies the Subcontractor that the matter disputed is a matter disputed under
or in connection with the main contract and that it will be referred to the main contract
Adjudicator.
The Contractor submits the subcontract dispute to the main contract Adjudicator at the
same time as the main contract submission. The Subcontractor becomes a party to the main
on
contract adjudication and the main contract Adjudicator decides the disputes together.
• review and revise any action or inaction of the Contractor related to the dispute and
se
• take the initiative in ascertaining the facts and the law related to the dispute,
ru
• instruct a Party to provide further information related to the dispute within a stated time
and
• instruct a Party to take any other action which is considered necessary for the
Adjudicator to reach a decision and to do so within a stated time.
Fo
(7) A communication between a Party and the Adjudicator is communicated to the other
SUBCONTRACT DATA
(8) If the Adjudicator’s decision includes assessment of additional cost or delay caused to the
Subcontractor, the assessment is made in the same way as a compensation event is assessed.
(9) The Adjudicator decides the dispute and informs the Parties of the decision and reasons
within four weeks of the end of the period for receiving information. This four week period
may be extended if the Parties agree.
Expires 20/11/20
Resolving and Avoiding Disputes
(10) Unless and until the Adjudicator has informed the Parties of the decision, the Parties
proceed as if the matter disputed was not disputed.
(11) The Adjudicator’s decision is binding on the Parties unless and until revised by the
CORE CLAUSES
ly
tribunal and is enforceable as a matter of contractual obligation between the Parties and
not as an arbitral award. The Adjudicator’s decision is final and binding if neither Party has
notified the other within the times required by the subcontract that it is dissatisfied with a
on
decision of the Adjudicator and intends to refer the matter to the tribunal. A Party does not
refer a dispute to the Adjudicator that is the same or substantially the same as one that has
already been referred to the Adjudicator.
(12) The Adjudicator may, within two weeks of giving the decision to the Parties, correct any
ts
clerical mistake or ambiguity.
The tribunal W1.4 (1) A Party does not refer any dispute under or in connection with the subcontract to
ec
the tribunal unless it has first been referred to the Adjudicator in accordance with the
(2) If, after being informed of the Adjudicator’s decision, a Party is dissatisfied, that Party may
oj
notify the other Party of the matter which is disputed and state that it intends to refer the
matter to the tribunal. The dispute is not referred to the tribunal unless this notification is
pr
given within four weeks of being informed of the Adjudicator’s decision.
(3) If the Adjudicator does not inform the Parties of the decision within the time provided
by the subcontract, a Party may notify the other Party that it intends to refer the dispute to
the tribunal. A Party does not refer a dispute to the tribunal unless this notification is given
M
within four weeks of the date by which the Adjudicator should have informed the Parties of
the decision.
(4) The tribunal settles the dispute referred to it. The tribunal has the powers to reconsider
any decision of the Adjudicator and review and revise any action or inaction of the
C
Contractor related to the dispute. A Party is not limited in the tribunal proceedings to the
information, evidence or arguments put to the Adjudicator.
AE
(5) If the tribunal is arbitration, the arbitration procedure, the place where the arbitration is to
be held and the method of choosing the arbitrator are those stated in the Subcontract Data.
(6) A Party does not call the Adjudicator as a witness in tribunal proceedings.
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Resolving and Avoiding Disputes
OPTION W2
Used when the United Kingdom Housing Grants, Construction and Regeneration Act 1996
applies.
CORE CLAUSES
ly
Resolving disputes W2
W2.1 (1) If the Parties agree, a dispute arising under or in connection with the subcontract
on
is referred to the Senior Representatives. If the dispute is not resolved by the Senior
Representatives, it is referred to and decided by the Adjudicator. A Party may replace a Senior
Representative after notifying the other Party of the name of the replacement.
(2) The Party referring a dispute notifies the Senior Representatives and the other Party of the
ts
nature of the dispute it wishes to resolve. Each Party submits to the other their statement of
case within one week of the notification. Each statement of case is limited to no more than
ten sides of A4 paper together with supporting evidence, unless otherwise agreed by the
ec
Parties.
MAIN OPTION CLAUSES
(3) The Senior Representatives attend as many meetings and use any procedure they consider
necessary to try to resolve the dispute over a period of up to three weeks. At the end of this
oj
period the Senior Representatives produce a list of the issues agreed and issues not agreed.
The Contractor and the Subcontractor put into effect the issues agreed.
(1) A dispute arising under or in connection with the subcontract is referred to and decided
M
by the Adjudicator. A Party may refer a dispute to the Adjudicator at any time whether or not
the dispute has been referred to the Senior Representatives.
SECONDARY OPTION CLAUSES
(2) In this Option, time periods stated in days exclude Christmas Day, Good Friday and bank
holidays.
C
(3) The Parties appoint the Adjudicator under the NEC Dispute Resolution Service Contract
current at the subcontract starting date.
AE
(4) The Adjudicator acts impartially and decides the dispute as an independent adjudicator
and not as an arbitrator.
(5) If the Adjudicator is not identified in the Subcontract Data or if the Adjudicator resigns or
becomes unable to act
on
The Adjudicator nominating body chooses an adjudicator within four days of the request.
se
(6) A replacement Adjudicator has the power to decide a dispute referred to a predecessor
but not decided at the time when the predecessor resigned or became unable to act.
ru
The Adjudicator deals with an undecided dispute as if it had been referred on the date of
appointment as replacement Adjudicator.
(7) A Party does not refer a dispute to the Adjudicator that is the same or substantially the
Fo
(8) The Adjudicator, and the Adjudicator’s employees and agents are not liable to the Parties
for any action or failure to take action in an adjudication unless the action or failure to take
action was in bad faith.
The adjudication W2.3 (1) Before a Party refers a dispute to the Adjudicator, it gives a notice of adjudication to
the other Party with a brief description of the dispute and the decision which it wishes the
Adjudicator to make. If the Adjudicator is named in the Subcontract Data, the Party sends a
copy of the notice of adjudication to the Adjudicator when it is issued. Within three days of the
receipt of the notice of adjudication, the Adjudicator informs the Parties that the Adjudicator
46 Engineering and Construction Subcontract This page has been amended in 2019 neccontract.com © nec 2017
Expires 20/11/20
Resolving and Avoiding Disputes
CORE CLAUSES
If the Adjudicator does not so inform within three days of the issue of the notice of
ly
adjudication, either Party may act as if the Adjudicator has resigned.
on
(2) Within seven days of a Party giving a notice of adjudication it
• provides the Adjudicator with the information on which it relies, including any
supporting documents and
ts
• provides a copy of the information and supporting documents it has provided to the
Adjudicator to the other Party.
ec
oj
agree.
pr
is also a matter disputed under or in connection with the subcontract, the Subcontractor
may, with the consent of the Subsubcontractor, refer the subsubcontract dispute to the
Adjudicator at the same time as the subcontract referral. The Adjudicator then decides
the disputes together and references to the Parties for the purposes of the dispute are
M
interpreted as including the Subsubcontractor.
(4) If a matter disputed under the subcontract is a matter disputed under the main contract,
the Contractor may, with the consent of the Subcontractor, submit the subcontract dispute
to the main contract Adjudicator at the same time as the main contract submission. The
Subcontractor becomes a party to the main contract adjudication and the main contract
C
• review and revise any action or inaction of the Contractor related to the dispute and
alter a matter which has been treated as accepted or correct,
• take the initiative in ascertaining the facts and the law related to the dispute,
on
• instruct a Party to provide further information related to the dispute within a stated time
and
COST COMPONENTS
• instruct a Party to take any other action which is considered necessary to reach a
decision and to do so within a stated time.
se
(6) If a Party does not comply with any instruction within the time stated by the Adjudicator,
the Adjudicator may continue the adjudication and make a decision based upon the
information and evidence received.
ru
(7) A communication between a Party and the Adjudicator is communicated to the other
Party at the same time.
Fo
(8) If the Adjudicator’s decision includes assessment of additional cost or delay caused to the
Subcontractor, the assessment is made in the same way as a compensation event is assessed.
SUBCONTRACT DATA
If the Adjudicator’s decision changes an amount notified as due, the date on which payment
of the changed amount becomes due is seven days after the date of the decision.
(9) The Adjudicator decides the dispute and informs the Parties of the decision and reasons
within twenty-eight days of the dispute being referred. This period may be extended by up
to fourteen days with the consent of the referring Party or by any other period agreed by
the Parties. The Adjudicator may in the decision allocate the Adjudicator’s fees and expenses
between the Parties.
Expires 20/11/20
Resolving and Avoiding Disputes
(10) Unless and until the Adjudicator has informed the Parties of the decision, the Parties
proceed as if the matter disputed was not disputed.
(11) If the Adjudicator does not inform the Parties of the decision within the time provided by
CORE CLAUSES
ly
the subcontract, the Parties and the Adjudicator may agree to extend the period for making
a decision. If they do not agree to an extension, either Party may act as if the Adjudicator has
resigned.
on
(12) The Adjudicator’s decision is binding on the Parties unless and until revised by the
tribunal and is enforceable as a matter of contractual obligation between the Parties and
not as an arbitral award. The Adjudicator’s decision is final and binding if neither Party has
notified the other within the times required by the subcontract that it is dissatisfied with a
ts
matter decided by the Adjudicator and intends to refer the matter to the tribunal.
(13) The Adjudicator may, within five days of giving the decision to the Parties, correct the
ec
decision to remove a clerical or typographical error arising by accident or omission.
MAIN OPTION CLAUSES
The tribunal W2.4 (1) A Party does not refer any dispute under or in connection with the subcontract to
the tribunal unless it has first been decided by the Adjudicator in accordance with the
oj
subcontract.
(2) If, after the Adjudicator makes a decision, a Party is dissatisfied, that Party may notify the
pr
other Party of the matter which is disputed and state that it intends to refer the disputed
matter to the tribunal. The dispute may not be referred to the tribunal unless this notification
is given within four weeks of the notification of the Adjudicator’s decision.
M
(3) The tribunal settles the dispute referred to it. The tribunal has the power to reconsider any
decision of the Adjudicator and to review and revise any action or inaction of the Contractor
SECONDARY OPTION CLAUSES
related to the dispute. A Party is not limited in tribunal proceedings to the information,
O
(4) If the tribunal is arbitration, the arbitration procedure, the place where the arbitration is to
C
be held and the method of choosing the arbitrator are those stated in the Subcontract Data.
AE
(5) A Party does not call the Adjudicator as a witness in tribunal proceedings.
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Secondary Option Clauses
CORE CLAUSES
ly
OPTION X1: PRICE ADJUSTMENT FOR INFLATION (USED ONLY WITH OPTIONS A, B, C AND D)
on
Defined terms X1
X1.1 (a) The Base Date Index (B) is the latest available index before the base date.
(b) The Latest Index (L) is the latest available index before the date of assessment of an
amount due.
ts
(c) The Price Adjustment Factor (PAF) at each date of assessment of an amount due is the
ec
total of the products of each of the proportions stated in the Subcontract Data multiplied by
Price Adjustment X1.2 If an index is changed after it has been used in calculating a PAF, the calculation is not
oj
Factor changed. The PAF calculated at the last assessment date before the Subcontract Completion
Date for the whole of the subcontract works is used for calculating an amount for price
adjustment after that date.
Price adjustment
Options A and B
X1.3
pr
Each amount due includes an amount for price adjustment which is the sum of
• the change in the Price for Work Done to Date since the last assessment of the amount
M
due multiplied by the PAF and
• the amount for price adjustment included in the previous amount due.
Price adjustment X1.4 Each time the amount due is assessed, an amount for price adjustment is added to the
Options C and D total of the Prices which is the change in the Price for Work Done to Date since the last
C
Compensation X1.5 The Defined Cost for compensation events is assessed using the
AE
events
• Defined Cost at base date levels for amounts calculated from rates stated in the
Subcontract Data for people and Equipment and
• Defined Cost current at the dividing date used in assessing the compensation event,
adjusted to the base date by dividing by one plus the PAF for the last assessment of the
on
COST COMPONENTS
OPTION X2: CHANGES IN THE LAW
se
the law is to reduce the total Defined Cost, the Prices are reduced.
Fo
Multiple currencies X3
X3.1 The Subcontractor is paid in currencies other than the currency of the subcontract for the
items or activities listed in the Subcontract Data. The exchange rates are used to convert
from the currency of the subcontract to other currencies.
X3.2 Payments to the Subcontractor in currencies other than the currency of the subcontract do
not exceed the maximum amounts stated in the Subcontract Data. Any excess is paid in the
currency of the subcontract.
Expires 20/11/20
Secondary Option Clauses
Ultimate holding X4
company guarantee X4.1 If the Subcontractor is a subsidiary of another company, the Subcontractor gives to the
CORE CLAUSES
ly
Contractor a guarantee of the Subcontractor’s performance from the ultimate holding
company of the Subcontractor in the form set out in the Subcontract Scope. If the guarantee
was not given by the Subcontract Date, it is given to the Contractor within four weeks of the
on
Subcontract Date.
X4.2 The Subcontractor may propose an alternative guarantor who is also owned by the ultimate
holding company for acceptance by the Contractor. A reason for not accepting the guarantor
is that its commercial position is not strong enough to carry the guarantee.
ts
ec
OPTION X5: SECTIONAL COMPLETION
MAIN OPTION CLAUSES
Sectional X5
Completion X5.1 In these conditions of subcontract, unless stated as the whole of the subcontract works, each
oj
reference and clause relevant to
•
Completion and
Completion X6.1 The Subcontractor is paid a bonus calculated at the rate stated in the Subcontract Data for
each day from the earlier of
• Completion and
• the date on which the Contractor takes over the subcontract works
on
se
Delay damages X7
X7.1 The Subcontractor pays delay damages at the rate stated in the Subcontract Data from the
ru
• Completion and
Fo
• the date on which the Contractor takes over the subcontract works.
X7.2 If the Subcontract Completion Date is changed to a later date after delay damages have
SUBCONTRACT DATA
been paid, the Contractor repays the overpayment of damages with interest. Interest is
assessed from the date of payment to the date of repayment and the date of repayment is
an assessment date.
X7.3 If the Contractor takes over a part of the subcontract works before Completion, the delay
damages are reduced from the date on which the part is taken over. The Contractor assesses
the benefit of taking over the part of the subcontract works as a proportion of the benefit
of taking over the whole of the subcontract works not previously taken over. The delay
damages are reduced in this proportion.
Expires 20/11/20
Secondary Option Clauses
Undertakings to X8
the Client or Others X8.1 The Subcontractor gives undertakings to Others and undertakings to the Client as stated in
CORE CLAUSES
ly
the Subcontract Data.
X8.2 The undertakings to Others and undertakings to the Client are in the form set out in the
on
Subcontract Scope.
X8.3 The Contractor sends the undertakings to the Subcontractor for signature. The Subcontractor
signs the undertakings, and returns them to the Contractor within two weeks.
ts
OPTION X9: TRANSFER OF RIGHTS
ec
Transfer of rights X9
oj
may transfer these rights to the Client. The Subcontractor obtains other rights for the Client
or Contractor as stated in the Subcontract Scope and obtains from a Subsubcontractor
equivalent rights for the Client or Contractor over the material prepared by the
pr
Subsubcontractor. The Subcontractor provides to the Contractor or the Client the documents
which transfer these rights to the Contractor or Client.
M
OPTION X10: INFORMATION MODELLING
(2) Project Information is information provided by the Subcontractor which is used to create
AE
(3) The Information Model is the electronic integration of Project Information and similar
information provided by the Client, Contractor and other Information Providers and is in the
form stated in the Information Model Requirements.
on
(4) The Information Model Requirements are the requirements identified in the Subcontract
Scope for creating or changing the Information Model.
COST COMPONENTS
(5) Information Providers are the people or organisations who contribute to the Information
Model and are identified in the Information Model Requirements.
se
Collaboration X10.2 The Subcontractor collaborates with other Information Providers as stated in the Information
Model Requirements.
ru
Early warning X10.3 The Subcontractor and the Contractor give an early warning by notifying the other as soon
as either becomes aware of any matter which could adversely affect the creation or use of
the Information Model.
Fo
Information X10.4 (1) If an Information Execution Plan is not identified in the Subcontract Data, the
Execution Plan Subcontractor submits a first Information Execution Plan to the Contractor for acceptance
SUBCONTRACT DATA
(2) Within two weeks of the Subcontractor submitting an Information Execution Plan for
acceptance, the Contractor notifies the Subcontractor of the acceptance of the Information
Execution Plan or the reasons for not accepting it. A reason for not accepting an Information
Execution Plan is that
Expires 20/11/20
Secondary Option Clauses
If the Contractor does not notify acceptance or non-acceptance within the time allowed, the
Subcontractor may notify the Contractor of that failure. If the failure continues for a further
one week after the Subcontractor’s notification, it is treated as acceptance by the Contractor
of the Information Execution Plan.
CORE CLAUSES
ly
(3) The Subcontractor submits a revised Information Execution Plan to the Contractor for
acceptance
on
• within the period for reply after the Contractor has instructed it to and
ts
(4) The Subcontractor provides the Project Information in the form stated in the Information
Model Requirements and in accordance with the accepted Information Execution Plan.
ec
Compensation X10.5 If the Information Execution Plan is altered by a compensation event, the Subcontractor
MAIN OPTION CLAUSES
events includes the alterations to the Information Execution Plan in the quotation for the
compensation event.
oj
Use of the X10.6 The Client owns the Information Model and the Subcontractor’s rights over Project
Information Model Information except as stated otherwise in the Information Model Requirements. The
Subcontractor obtains from a Subsubcontractor equivalent rights for the Client over
Liability X10.7
pr
information prepared by the Subsubcontractor. The Subcontractor provides to the Contractor
the documents which transfer these rights to the Client.
(2) The Subcontractor is not liable for a fault or error in the Project Information unless it failed
C
to provide the Project Information using the skill and care normally used by professionals
providing information similar to the Project Information.
AE
(3) The Subcontractor provides insurance for claims made against it arising out of its failure
to provide the Project Information using the skill and care normally used by professionals
providing information similar to the Project Information. The minimum amount of this
insurance is as stated in the Subcontract Data. This insurance provides cover from the
subcontract starting date until the end of the period stated in the Subcontract Data.
on
COST COMPONENTS
Contractor X11.1 The Contractor may terminate the Subcontractor’s obligation to Provide the Subcontract
Works for a reason not identified in the Termination Table by notifying the Subcontractor.
X11.2 If the Contractor terminates for a reason not identified in the Termination Table the
ru
termination procedures followed are P1 and P2 and the amounts due on termination are A1,
A2 and A4.
Fo
Expires 20/11/20
Secondary Option Clauses
(2) The Schedule of Partners is a list of the Partners which is in the document the Subcontract
Data states it is in and Partners subsequently added by agreement of the Partners. It sets out
the objectives of the Partners and includes targets for performance.
CORE CLAUSES
ly
(2) An Own Contract is a contract between two Partners.
(4) The Core Group comprises the Partners selected to take decisions on behalf of the
on
Partners.
(5) The Schedule of Core Group Members is a list of the Partners forming the Core Group.
(4) Partnering Information is information which specifies how the Partners work together and
ts
is either in the documents which the Subcontract Data states it is in or in an instruction given
in accordance with the subcontract.
ec
(5) A Key Performance Indicator is an aspect of performance for which a target is stated in
Actions X12.2 (1) The Partners collaborate with each other to achieve the Promoter’s objective stated in
oj
the Subcontract Data and the objectives of every other Partner stated in the Schedule of
Partners.
pr
(2) Each Partner nominates a representative to act for it in dealings with other Partners.
(3) The Core Group acts and takes decisions on behalf of the Partners on those matters
stated in the Partnering Information.
M
(4) The Partners select the members of the Core Group. The Core Group decides how they
will work and decides the dates when each member joins and leaves the Core Group. The
Promoter’s representative leads the Core Group unless stated otherwise in the Partnering
Information.
C
(5) The Core Group keeps the Schedule of Core Group Members and the Schedule of
Partners up to date and issues copies of them to the Partners each time either is revised.
AE
(6) This Option does not create a legal partnership between Partners who are not one of the
Parties in the subcontract.
Working together X12.3 (1) The Partners work together as stated in the Partnering Information and in a spirit of
mutual trust and co-operation.
on
(2) A Partner may ask another Partner to provide information which it needs to carry out the
work in its Own Contract and the other Partner provides it.
COST COMPONENTS
(3) Each Partner gives an early warning to the other Partners when it becomes aware of
any matter that could affect the achievement of another Partner’s objectives stated in the
se
Schedule of Partners.
(4) The Partners use common information systems as set out in the Partnering Information.
ru
(5) A Partner implements a decision of the Core Group by issuing instructions in accordance
with its Own Contracts.
(6) The Core Group may give an instruction to the Partners to change the Partnering
Fo
Information. Each such change to the Partnering Information is a compensation event which
may lead to reduced Prices.
SUBCONTRACT DATA
(7) The Core Group prepares and maintains a timetable showing the proposed timing of the
contributions of the Partners. The Core Group issues a copy of the timetable to the Partners
each time it is revised. The Subcontractor changes its programme if it is necessary to do so in
order to comply with the revised timetable. Each such change is a compensation event which
may lead to reduced Prices.
Expires 20/11/20
Secondary Option Clauses
(8) A Partner gives advice, information and opinion to the Core Group and to other Partners
when asked to do so by the Core Group. This advice, information and opinion relates to work
that another Partner is to carry out under its Own Contract and is given fully, openly and
objectively. The Partners show contingency and risk allowances in information about costs,
CORE CLAUSES
ly
prices and timing for future work.
(9) A Partner informs the Core Group before subsubcontracting any work.
on
Incentives X12.4 (1) A Partner is paid the amount stated in the Schedule of Partners if the target stated for
a Key Performance Indicator is improved upon or achieved. Payment of the amount is due
when the target has been improved upon or achieved and is made as part of the amount
due in the Partner’s Own Contract.
ts
(2) The Promoter may add a Key Performance Indicator and associated payment to the
Schedule of Partners but may not delete or reduce a payment stated in the Schedule of
ec
Partners.
MAIN OPTION CLAUSES
oj
OPTION X13: PERFORMANCE BOND
pr
Performance bond X13
X13.1 The Subcontractor gives the Contractor a performance bond, provided by a bank or insurer
which the Contractor has accepted, for the amount stated in the Subcontract Data and in the
form set out in the Subcontract Scope. A reason for not accepting the bank or insurer is that
M
its commercial position is not strong enough to carry the bond. If the bond was not given
by the Subcontract Date, it is given to the Contractor within four weeks of the Subcontract
SECONDARY OPTION CLAUSES
Date.
O
Advanced X14
AE
payment X14.1 The Contractor makes an advanced payment to the Subcontractor of the amount stated in
the Subcontract Data. The advanced payment is included in the assessment made at the first
assessment date or, if an advanced payment bond is required, at the next assessment date
after the Contractor receives the advanced payment bond.
X14.2 The advanced payment bond is issued by a bank or insurer which the Contractor has
on
accepted. A reason for not accepting the proposed bank or insurer is that its commercial
position is not strong enough to carry the bond. The bond is for the amount of the
COST COMPONENTS
advanced payment which the Subcontractor has not repaid and is in the form set out in
the Subcontract Scope. Delay in making the advanced payment in accordance with the
subcontract is a compensation event.
se
X14.3 The advanced payment is repaid to the Contractor by the Subcontractor in instalments of
the amount stated in the Subcontract Data. An instalment is included in each amount due
assessed after the period stated in the Subcontract Data has passed until the advanced
ru
The X15
Subcontractor’s X15.1 The Subcontractor is not liable for a Defect which arose from its design unless it failed to
design carry out that design using the skill and care normally used by professionals designing works
similar to the subcontract works.
X15.2 If the Subcontractor corrects a Defect for which it is not liable under the subcontract it is a
compensation event.
Expires 20/11/20
Secondary Option Clauses
X15.3 The Subcontractor may use the material provided by it under the subcontract for other work
unless
CORE CLAUSES
ly
• it is stated otherwise in the Subcontract Scope.
X15.4 The Subcontractor retains copies of drawings, specifications, reports and other documents
on
which record the Subcontractor’s design for the period for retention. The copies are retained
in the form stated in the Subcontract Scope.
X15.5 The Subcontractor provides insurance for claims made against it arising out of its failure
to use the skill and care normally used by professionals designing works similar to the
ts
subcontract works. The minimum amount of this insurance is as stated in the Subcontract
Data. This insurance provides cover from the subcontract starting date until the end of the
period stated in the Subcontract Data.
ec
oj
After the defects date and on each renewal of the insurance policy until the end of
the period stated in the Subcontract Data for which insurance is to be maintained, the
pr
Subcontractor submits to the Contractor for acceptance a certificate which states that the
insurance required by this clause is in force. The certificate is signed by the Subcontractor’s
insurer or insurance broker.
M
The Contractor accepts the certificate if the insurance complies with this clause and if the
insurer’s commercial position is strong enough to carry the insured liability.
Retention X16
X16.1 After the Price for Work Done to Date has reached the retention free amount, an amount is
AE
• the date on which the Contractor takes over the whole of the subcontract works
on
the amount retained is the retention percentage applied to the excess of the Price for Work
Done to Date above the retention free amount.
COST COMPONENTS
X16.2 The amount retained is halved
se
• in the next assessment made after Completion of the whole of the subcontract works or
• in the next assessment after the Contractor has taken over the whole of the subcontract
works if this is before Completion of the whole of the subcontract works.
ru
The amount retained remains at this amount until the date when the Defects Certificate
is due to be issued. No amount is retained in the assessments made after the Defects
Certificate is due to be issued.
Fo
X16.3 If stated in the Subcontract Data or agreed by the Contractor, the Subcontractor may give
the Contractor a retention bond, provided by a bank or insurer which the Contractor has
SUBCONTRACT DATA
accepted, for the total amount to be retained and in the form set out in the Subcontract
Scope. A reason for not accepting the bank or insurer is that its commercial position is not
strong enough to carry the bond. Any amount retained after the Subcontractor gives the
Contractor a retention bond is paid to the Subcontractor in the next assessment.
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 55
Expires 20/11/20
Secondary Option Clauses
ly
performance level stated in the Subcontract Data, the Subcontractor pays the amount of low
performance damages stated in the Subcontract Data.
on
OPTION X18: LIMITATION OF LIABILITY
Limitation of X18
ts
liability X18.1 Each of the limits to the Subcontractor’s liability in this clause apply if a limit is stated in the
Subcontract Data.
ec
X18.2 The Subcontractor’s liability to the Contractor for the Contractor’s indirect or consequential
MAIN OPTION CLAUSES
oj
to the Client’s or Contractor’s property is limited to the amount stated in the Subcontract
Data.
X18.4 The Subcontractor’s liability to the Contractor for Defects due to its design which are not
X18.5
pr
listed on the Defects Certificate is limited to the amount stated in the Subcontract Data.
The Subcontractor’s total liability to the Contractor for all matters arising under or in
connection with the subcontract, other than the excluded matters, is limited to the amount
M
stated in the Subcontract Data and applies in contract, tort or delict and otherwise to the
extent allowed under the law of the subcontract.
SECONDARY OPTION CLAUSES
The excluded matters are amounts payable by the Subcontractor as stated in the subcontract
for
C
OPTION X20: KEY PERFORMANCE INDICATORS (NOT USED WITH OPTION X12)
se
Incentives X20
X20.1 A Key Performance Indicator is an aspect of performance by the Subcontractor for which a
target is stated in the Incentive Schedule. The Incentive Schedule is the incentive schedule
ru
not achieve the target stated in the Incentive Schedule, it submits to the Contractor its
proposals for improving performance.
X20.4 The Subcontractor is paid the amount stated in the Incentive Schedule if the target stated for
a Key Performance Indicator is improved upon or achieved. Payment of the amount is due
when the target has been improved upon or achieved.
X20.5 The Contractor may add a Key Performance Indicator and associated payment to the
Incentive Schedule but may not delete or reduce a payment stated in the Incentive Schedule.
Expires 20/11/20
Secondary Option Clauses
CORE CLAUSES
ly
order to reduce the cost of operating and maintaining an asset.
X21.2 If the Contractor and Client are prepared to consider the change, the Subcontractor submits
on
a quotation which comprises
• a detailed description,
• the forecast cost reduction to the Client of the asset over its whole life,
ts
• an analysis of the resulting risks to the Client,
ec
oj
X21.3 The Contractor consults with the Client and the Subcontractor about a quotation. The
Contractor replies within the period for reply. The reply is acceptance of the quotation or
the reasons for not accepting it. The Contractor may give any reason for not accepting the
X21.4
quotation.
pr
The Contractor does not change the Subcontract Scope as proposed by the Subcontractor
unless the Subcontractor’s quotation is accepted.
M
X21.5 When a quotation to reduce the costs of operating and maintaining an asset is accepted
the Contractor changes the Subcontract Scope, the Prices, the Subcontract Completion
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
SECONDARY OPTION CLAUSES
Option Y
CORE CLAUSES
ly
OPTION Y(UK)1: PROJECT BANK ACCOUNT
on
Project Bank Y(UK)1
Account
Definitions Y1.1 (1) The Authorisation is a document authorising the project bank to make payments to the
Contractor, the Subcontractor and Subcontract Named Suppliers.
ts
(2) Subcontract Named Suppliers are named suppliers and other Suppliers who have signed
ec
the Joining Deed.
MAIN OPTION CLAUSES
(3) Project Bank Account is the account established by the Contractor and used to make
payments to the Subcontractor and Subcontract Named Suppliers.
oj
(4) A Supplier is a person or organisation who has a contract to
pr
• construct or install part of the subcontract works,
Account and is in the document which the Subcontract Data states it is in.
O
(6) Joining Deed is an agreement under which the Supplier joins the Trust Deed and is in the
document which the Subcontract Data states it is in.
C
Named Suppliers Y1.2 The Subcontractor includes in its contracts with Subcontract Named Suppliers the
arrangements in the subcontract for the operation of the Project Bank Account and Trust
AE
Deed. The Subcontractor notifies the Subcontract Named Suppliers of the details of the
Project Bank Account and the arrangements for payment of amounts due under their
contracts.
Y1.3 The Subcontractor submits proposals for adding a Supplier to the Subcontract Named
Suppliers to the Contractor for acceptance. A reason for not accepting is that the addition
on
of the Supplier does not comply with the Subcontract Scope. The Contractor, the Client, the
Subcontractor and the Supplier sign the Joining Deed after acceptance.
COST COMPONENTS
Payments Y1.4 The Subcontractor shows in the application for payment the amounts due to Subcontract
Named Suppliers in accordance with their contracts.
se
Y1.5 The Contractor prepares the Authorisation, setting out the sums due to Subcontract Named
Suppliers as assessed by the Contractor and to the Subcontractor for the balance of the
payment due under the subcontract. The Contractor notifies the Subcontractor of the sums
ru
due to the Subcontractor and Subcontract Named Suppliers stated in the Authorisation.
Y1.6 The Client and the Contractor make payment into the project bank of the amount stated in
the Authorisation.
Fo
Y1.7 The Subcontractor and Subcontract Named Suppliers receive payment from the Project Bank
Account of the sums set out in the Authorisation as soon as practicable after the Project
SUBCONTRACT DATA
58 Engineering and Construction Subcontract This page has been amended in 2019 neccontract.com © nec 2017
Expires 20/11/20
SECONDARY OPTION CLAUSES
Effect of Y1.9 Payments made from the Project Bank Account are treated as payments from the Contractor
payment to the Subcontractor in accordance with the subcontract or from the Subcontractor or
Subsubcontractor to Subcontract Named Suppliers in accordance with their contracts as
applicable. A delay in payment due to a failure of the Subcontractor to comply with the
CORE CLAUSES
ly
requirements of this clause is not treated as late payment under the subcontract.
If the Subcontractor is identified as a Named Supplier in the Contract Data for the main
on
contract
Trust Deed Y1.10 The Client, the Contractor, the Subcontractor and named suppliers sign the Trust Deed
before the first assessment date in the contract between the Contractor and the Client.
If the Subcontractor is added as a Named Supplier after the Contract Date in the main contract
ts
Joining Deed Y1.11 The Client, the Contractor, the Subcontractor and the Named Supplier sign the Joining Deed
before the first assessment date.
ec
oj
pr
M
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 59
Expires 20/11/20
SECONDARY OPTION CLAUSES
OPTION Y(UK)2: THE HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
ly
Construction and
Regeneration Act
1996
on
Definitions Y2.1 In this Option, time periods stated in days exclude Christmas Day, Good Friday and bank
holidays.
Dates for Y2.2 The date on which a payment becomes due is fourteen days after the assessment date. The
ts
payment date on which the final payment becomes due is
• if the Contractor makes an assessment after the issue of a Defect Certificate, five weeks
ec
after the issue of the Defects Certificate,
MAIN OPTION CLAUSES
• if the Contractor does not make an assessment after the issue of a Defects Certificate,
one week after the Subcontractor issues its assessment or
oj
• if the Contractor has issued a termination certificate, fourteen weeks after the issue of
the certificate.
pr
The final date for payment is fourteen days after the date on which payment becomes due or
a different period for payment if stated in the Subcontract Data.
M
The Contractor’s certificate is the notice of payment specifying the amount due at the
payment due date (the notified sum, which might be zero) and stating the basis on which the
SECONDARY OPTION CLAUSES
amount was calculated. If the Contractor does not make an assessment after the issue of a
O
Notice of Y2.3 If either Party intends to pay less than the notified sum, it notifies the other Party not later
C
intention to pay than seven days (the prescribed period) before the final date for payment by stating the
less amount considered to be due and the basis on which that sum is calculated. A Party does not
AE
withhold payment of an amount due under the subcontract unless it has notified its intention
to pay less than the notified sum as required by the subcontract.
Y2.4 If the Contractor terminates for one of reasons R1 to R15, R18 or R22 and a certified
payment has not been made at the date of the termination certificate, the Contractor makes
the certified payment unless
on
• it has notified the Subcontractor in accordance with the subcontract that it intends to
pay less than the notified sum or
COST COMPONENTS
• the termination is for one of reasons R1 to R10 and the reason occurred after the
last date on which it could have notified the Subcontractor in accordance with the
se
Suspension of Y2.4 If the Subcontractor exercises its right under the Housing Grants, Construction and
performance Regeneration Act 1996 as amended by the Local Democracy, Economic Development and
ru
Expires 20/11/20
SECONDARY OPTION CLAUSES
CORE CLAUSES
ly
the Contracts (Rights of Third Parties) Act 1999.
Y3.2 Other than the Parties or a beneficiary, no person can enforce any of the terms of the
on
subcontract under the Contracts (Rights of Third Parties) Act 1999.
Y3.3 If a beneficiary is identified by class or description and not as a named person or
organisation, the Contractor notifies the Subcontractor of the name of the beneficiary once
it has been identified.
ts
OPTION Z: ADDITIONAL CONDITIONS OF SUBCONTRACT
ec
oj
subcontract subcontract.
pr
M
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Schedule of Cost Components
ly
This schedule is part of these conditions of subcontract only when Option C, D or E is used.
on
An amount is included
ts
People 1 The following components of
• the cost of people who are directly employed by the Subcontractor and whose normal
ec
place of working is within the Working Areas and
MAIN OPTION CLAUSES
• the cost of people who are directly employed by the Subcontractor and whose normal
place of working is not within the Working Areas but who are working in the Working
oj
Areas, proportionate to the time they spend in the Working Areas.
11 Wages, salaries and amounts paid by the Subcontractor for people paid according to the
12
time worked on the subcontract.
pr
Payments related to work on the subcontract and made to people for
(f) severance.
13 Payments made in relation to people in accordance their employment contract for
(a) travel
(c) relocation
COST COMPONENTS
(n) a vehicle
Expires 20/11/20
Schedule of Cost Components
14 The following components of the cost of people who are not directly employed by the
Subcontractor but are paid for by the Subcontractor according to the time worked while they
are within the Working Areas.
CORE CLAUSES
ly
Amounts paid by the Subcontractor.
Equipment 2 The following components of the cost of Equipment which is used within the Working Areas.
on
21 Payments for the hire or rent of Equipment not owned by
• the Subcontractor,
ts
• by a company with the same ultimate holding company
ec
at the hire or rental rate multiplied by the time for which the Equipment is required.
oj
• purchased by the Subcontractor under a hire purchase or lease agreement or
pr
hired by the Subcontractor from the Subcontractor’s ultimate holding company or from
a company with the same ultimate holding company
at open market rates multiplied by the time for which the Equipment is required.
M
23 Payments for Equipment purchased for work included in the subcontract listed with a time-
related on cost charge, in the Subcontract Data, of
• the change in value over the period for which the Equipment is required and
• the time-related on cost charge stated in the Subcontract Data for the period for which
C
The change in value is the difference between the purchase price and either the sale price
or the open market sale price at the end of the period for which the Equipment is required.
Interim payments of the change in value are made at each assessment date. A final payment
is made in the next assessment after the change in value has been determined.
If the Contractor agrees, an additional item of Equipment may be assessed as if it had been
on
COST COMPONENTS
stated in the Subcontract Data multiplied by the time for which the Equipment is required.
If the Contractor agrees, an additional item of special Equipment may be assessed as if it had
se
• transporting Equipment to and from the Working Areas other than for repair and
maintenance
Fo
Expires 20/11/20
Schedule of Cost Components
Plant and Materials 3 The following components of the cost of Plant and Materials.
31 Payments for
ly
• delivery to and removal from the Working Areas,
on
• providing and removing packaging and
ts
Subsubcontractors 4 The following components of the cost of Subsubcontractors.
ec
41 Payments to Subsubcontractors for work which is subsubcontracted without taking into
MAIN OPTION CLAUSES
account any amounts paid to or retained from the Subsubcontractor by the Subcontractor,
which would result in the Contractor paying or retaining the amount twice.
oj
Charges 5 The following components of the cost of charges paid or received by the Subcontractor.
51 Payments for the provision and use in the Working Areas of
•
water,
gas, pr
M
• electricity,
SECONDARY OPTION CLAUSES
• telephone and
O
• internet.
52 Payments to public authorities and other properly constituted authorities of charges which
C
(d) royalties
COST COMPONENTS
(h) consumables and equipment provided by the Subcontractor for the Contractor’s offices.
54 Payments made and received by the Subcontractor for the removal from Site and disposal or
sale of materials from excavation and demolition.
Fo
Manufacture and 6 The following components of the cost of manufacture and fabrication of Plant and Materials
fabrication by the Subcontractor which are
SUBCONTRACT DATA
Expires 20/11/20
Schedule of Cost Components
Design 7 The following components of the cost of design of the subcontract works and Equipment
done outside the Working Areas.
71 Amounts calculated by multiplying each of the rates for people in the Subcontract Data
by the total time appropriate to that rate spent on design of the subcontract works and
CORE CLAUSES
ly
Equipment outside the Working Areas.
72 The cost of travel to and from the Working Areas for the categories of design people listed in
on
the Subcontract Data.
• the cost of events for which the subcontract requires the Subcontractor to insure and
ts
• other costs paid to the Subcontractor by insurers.
ec
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 65
Expires 20/11/20
Short Schedule of Cost Components
ly
This schedule is part of these conditions of subcontract only when Option A or B is used. An
on
amount is included
ts
People 1 The following components of the cost of
• people who are directly employed by the Subcontractor and whose normal place of
ec
working is within the Working Areas,
MAIN OPTION CLAUSES
• people who are directly employed by the Subcontractor and whose normal place of
working is not within the Working Areas but who are working in the Working Areas,
oj
proportionate to the time they spend working in the Working Areas and
pr
• people who are not directly employed by the Subcontractor but are paid for by it
according to the time worked while they are within the Working Areas.
11 Amounts calculated by multiplying each of the People Rates by the total time appropriate to
that rate spent within the Working Areas.
M
Equipment 2 The following components of the cost of Equipment which is used within the Working Areas.
SECONDARY OPTION CLAUSES
21 Amounts for Equipment which is in the published list stated in the Subcontract Data. These
O
amounts are calculated by applying the percentage adjustment for listed Equipment stated in
the Subcontract Data to the rates in the published list and by multiplying the resulting rate by
C
24 Unless the item is in the published list and the rate includes the cost component, payments
for
COST COMPONENTS
• transporting Equipment to and from the Working Areas other than for repair and
maintenance,
se
25 Unless the item is in the published list and the rate includes the cost component, the
purchase price of Equipment which is consumed.
26 Unless included in the rate in the published list, the cost of operatives is included in the cost
of people.
Fo
27 Amounts for Equipment which is neither in the published list, stated in the Subcontract Data
SUBCONTRACT DATA
nor listed in the Subcontract Data, at competitively tendered or open market rates, multiplied
by the time for which the Equipment is required.
Plant and Materials 3 The following components of the cost of Plant and Materials.
Expires 20/11/20
Short Schedule of Cost Components
31 Payments for
CORE CLAUSES
• delivery to and removal from the Working Areas,
ly
• providing and removing packaging and
on
• samples and tests.
32 Cost is credited with payments received for disposal of Plant and Materials unless the cost is
disallowed.
ts
Subsubcontractors 4 The following components of the cost of Subsubcontractors.
41 Payments to Subsubcontractors for work which is subsubcontracted.
ec
Charges 5 The following components of the cost of charges paid or received by the Subcontractor.
oj
• water,
•
gas,
electricity,
telephone and
pr
M
• internet.
52 Payments to public authorities and other properly constituted authorities of charges which
they are authorised to make in respect of the subcontract works.
53 Payments for
C
(d) royalties
on
COST COMPONENTS
(f) charges for access to the Working Areas
(h) consumables and equipment provided by the Subcontractor for the Contractor’s offices.
54 Payments made and received by the Subcontractor for the removal from Site and disposal or
ru
Manufacture and 6 The following components of the cost of manufacture and fabrication of Plant and Materials
fabrication by the Subcontractor which are
Fo
Design 7 The following components of the cost of design of the subcontract works and Equipment
done outside the Working Areas.
Expires 20/11/20
Short Schedule of Cost Components
71 Amounts calculated by multiplying each of the rates for people in the Subcontract Data
by the total time appropriate to that rate spent on design of the subcontract works and
Equipment outside the Working Areas.
72 The cost of travel to and from the Working Areas for the categories of design people listed in
CORE CLAUSES
ly
the Subcontract Data.
on
• the cost of events for which the subcontract requires the Subcontractor to insure and
ts
ec
MAIN OPTION CLAUSES
oj
pr
M
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
68 Engineering and Construction Subcontract This page has been amended in 2019 neccontract.com © nec 2017
Expires 20/11/20
Subcontract Data
Subcontract Data
CORE CLAUSES
ly
PART ONE – DATA PROVIDED BY THE CONTRACTOR
on
Completion of the data in full, according to the Options chosen, is essential to create a
complete contract.
ts
1 General
The conditions of subcontract are the core clauses and the clauses for the following main
ec
Option, the Option for resolving and avoiding disputes and secondary Options of the NEC4
oj
Secondary Options
pr
M
The works in the
main contract are
The subcontract
C
works are
AE
The Contractor is
Name
Name
ru
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 69
Expires 20/11/20
Subcontract Data
Name
ly
on
Address for electronic communications
ts
Name
ec
Address for communications
MAIN OPTION CLAUSES
oj
Address for electronic communications
O
C
Expires 20/11/20
Subcontract Data
CORE CLAUSES
ly
on
Early warning meetings are to be held at intervals no longer than
ts
ec
2 The Subcontractor’s main responsibilities
oj
to meet a stated condition condition to be met key date
by a key date
(1)
(2)
(3) pr
M
3 Time
AE
(1)
COST COMPONENTS
(2)
(3)
se
no longer than
Fo
If the Contractor has decided The subcontract completion date for the whole of the
the subcontract completion subcontract works is
SUBCONTRACT DATA
Taking over the subcontract The Contractor is / is not willing to take over the subcontract
works before the Subcontract works before the Subcontract Completion Date.
Completion Date (Delete as applicable)
Expires 20/11/20
Subcontract Data
If no programme is identified The period after the Subcontract Date within which the
in part two of the subcontractor is to submit a first programme for
Subcontract Data acceptance is
CORE CLAUSES
ly
4 Quality management
on
The period after the Subcontract Date within which the
Subcontractor is to submit a quality policy statement and
quality plan is
ts
subcontract works and the defects date is
ec
MAIN OPTION CLAUSES
oj
5 Payment
The interest rate is % per annum (not less than 2) above the
O
If the period in which The period within which payments are made is
AE
If Option C or D is used The Subcontractor’s share percentages and the share ranges are
COST COMPONENTS
less than % %
from % to % %
ru
from % to % %
greater than % %
Fo
on (date)
Expires 20/11/20
Subcontract Data
6 Compensation events
CORE CLAUSES
The weather measurements to be recorded for each calendar month are
ly
• the cumulative rainfall (mm)
on
• the number of days with rainfall more than 5 mm
• the number of days with minimum air temperature less than 0 degrees Celsius
ts
and these measurements:
ec
Where no recorded data are Assumed values for the ten year weather return weather data for each weather
AE
COST COMPONENTS
se
If Option A or B is used The value engineering percentage is 50%, unless another percentage %
is stated here, in which case it is
ru
Expires 20/11/20
Subcontract Data
ly
(2)
on
(3)
ts
Contractor’s liabilities
(1)
ec
(2)
MAIN OPTION CLAUSES
(3)
oj
The minimum amount of cover for insurance against loss of or damage to property (except
the subcontract works, Plant and Materials and Equipment) and liability for bodily injury to or
death of a person (not an employee of the Subcontractor) arising from or in connection with
event is
pr
the Subcontractor Providing the Subcontract Works for any one
The minimum amount of cover for insurance against death of or bodily injury to employees
M
of the Subcontractor arising out of and in the course of their employment in connection with
the subcontract for any one event is
SECONDARY OPTION CLAUSES
If the Client or Contractor is The insurance against loss of or damage to the subcontract works, Plant and Materials is to
C
to provide Plant and Materials include cover for Plant and Materials provided by the Client or Contractor for an amount of
AE
If the Client or Contractor The Client or Contractor provides these insurances from the Insurance Table
is to provide any of the
insurances stated in the (1) Insurance against
Insurance Table
on
If additional insurances are The Client or Contractor provides these additional insurances
to be provided
(1) Insurance against
Expires 20/11/20
Subcontract Data
CORE CLAUSES
The deductibles are
ly
(3) Insurance against
on
Minimum amount of cover is
ts
(1) Insurance against
ec
Minimum amount of cover is
oj
(2) Insurance against
The tribunal is
to be held is
COST COMPONENTS
The person or organisation who will choose an arbitrator if the Parties cannot agree a choice
or if the arbitration procedure does not state who selects an arbitrator is
se
ru
Name (1)
Fo
Expires 20/11/20
Subcontract Data
Name (2)
ly
on
Address for electronic communications
Name
ts
Address for communications
ec
MAIN OPTION CLAUSES
oj
Address for electronic communications
Name
X1: Price adjustment for inflation (used only with Options A, B, C and D)
If Option X1 is used The proportions used to calculate the Price Adjustment Factor are
0.
COST COMPONENTS
0.
se
0.
0.
ru
0.
0. non-adjustable
1.00
Fo
Expires 20/11/20
Subcontract Data
CORE CLAUSES
ly
payment in the currency
on
ts
The exchange rates are those published in
on (date)
ec
oj
If Option X5 is used The subcontract completion date for each section of the subcontract works is
pr
section description subcontract completion date
(1)
(2)
M
(3)
(4)
C
If Option X6 is used without The bonus for the whole of the subcontract works is per day
Option X5
If Option X6 is used with The bonus for each section of the subcontract works is
on
Option X5
section description amount per day
COST COMPONENTS
(1)
se
(2)
(3)
ru
(4)
If Option X7 is used without Delay damages for Completion of the whole of the subcontract works are per day
Option X5
Expires 20/11/20
Subcontract Data
If Option X7 is used with Delay damages for each section of the subcontract works are
Option X5
ly
(1)
(2)
on
(3)
(4)
ts
The delay damages for the remainder of the subcontract works are
ec
MAIN OPTION CLAUSES
oj
provided to
O
C
AE
If no information execution The period after the Subcontract Date within which the Subcontractor is to submit a first
plan is identified in part two Information Execution Plan for acceptance is
COST COMPONENTS
The period following Completion of the whole of the subcontract works or earlier
termination for which the Subcontractor maintains insurance for claims made against it
ru
Expires 20/11/20
Subcontract Data
CORE CLAUSES
ly
on
The Promoter’s objective is
ts
ec
pr
M
COST COMPONENTS
If Option X14 is used The amount of the advanced payment is
se
Advanced payment bond An advanced payment bond is / is not reqired. (Delete as applicable)
SUBCONTRACT DATA
The minimum amount of insurance cover for claims made against the Subcontractor arising
out of its failure to use the skill and care normally used by professionals designing works
similar to the subcontract works is, in respect of each claim
Expires 20/11/20
Subcontract Data
The period following Completion of the whole of the subcontract works or earlier
termination for which the Subcontractor maintains insurance for claims made against it
arising out of its failure to use the skill and care is
CORE CLAUSES
ly
X16: Retention
on
If Option X16 is used The retention free amount is
ts
Retention bond The Subcontractor may / may not give the Contractor a retention bond. (Delete as
ec
applicable)
MAIN OPTION CLAUSES
oj
If Option X17 is used The amounts for low performance damages are
amount
for
O
for
C
If Option X18 is used The Subcontractor’s liability to the Contractor for indirect or
consequential loss is limited to
The end of liability date is years after the Completion of the whole of the
subcontract works
Fo
If Option X20 is used The incentive schedule for Key Performance Indicators is in
Expires 20/11/20
Subcontract Data
CORE CLAUSES
The Joining Deed is in
ly
on
Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
If Option Y(UK)2 is used and The period for payment is days after the date on which payment becomes due
the final date for payment
ts
is not fourteen days after
the date on which payment
becomes due
ec
oj
If Option Y(UK)3 is used term beneficiary
pr
M
Y(UK)3
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 81
Expires 20/11/20
Subcontract Data
ly
1 General
on
The Subcontractor is
Name
ts
Address for communications
ec
MAIN OPTION CLAUSES
oj
pr
The fee percentage is %
Name (1)
C
Job
AE
Responsibilities
Qualifications
Experience
on
Name (2)
COST COMPONENTS
Job
Responsibilities
se
Qualifications
Experience
ru
Expires 20/11/20
Subcontract Data
If the Subcontractor is to The Subcontract Scope provided by the Subcontractor for its
provide Subcontract Scope design is in
CORE CLAUSES
ly
for its design
on
3 Time
If a programme is to be The programme identified in the Subcontract Data is
identified in the Subcontract
ts
Data
ec
oj
whole of the subcontract
works
5 Payment pr
M
If Option A or C is used The activity schedule is
Name (1)
COST COMPONENTS
Address for communications
se
Name (2)
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 83
Expires 20/11/20
Subcontract Data
ly
If an information execution The information execution plan identified in the Subcontract
plan is to be identified in the Data is
on
Subcontract Data
ts
If Option Y(UK)1 is used named suppliers are
ec
MAIN OPTION CLAUSES
oj
Data for the Schedule of Cost Components (used only with Options C, D or E)
The listed items of Equipment purchased for work on the contract, with an on cost charge,
are
Equipment pr
time-related on cost charge per time period
M
SECONDARY OPTION CLAUSES
O
C
Equipment rate
on
COST COMPONENTS
The rates for Defined Cost of manufacture and fabrication outside the Working Areas by the
se
Subcontractor are
Expires 20/11/20
Subcontract Data
The rates for Defined Cost of design outside the Working Areas are
CORE CLAUSES
ly
on
The categories of design people whose travelling expenses to and from the Working Areas
ts
are included as a cost of design of the subcontract works and Equipment done outside the
Working Areas are
ec
COST COMPONENTS
The percentage for adjustment for Equipment in the published
list is % (state plus or minus)
se
Equipment rate
ru
Fo
SUBCONTRACT DATA
© nec 2017 neccontract.com This page has been amended in 2019 Engineering and Construction Subcontract 85
Expires 20/11/20
Subcontract Data
The rates for Defined Cost of manufacture and fabrication outside the Working Areas by the
Subcontractor are
ly
on
ts
The rates for Defined Cost of design outside the Working Areas are
ec
MAIN OPTION CLAUSES
oj
pr
The categories of design people whose travelling expenses to and from the Working Areas
are included in Defined Cost are
M
SECONDARY OPTION CLAUSES
O
C
AE
on
COST COMPONENTS
se
ru
Fo
SUBCONTRACT DATA
Expires 20/11/20
Index
Index
ly
Index by clause numbers (Option clauses indicated by their letters, main clause heads by bold numbers).
on
Terms in italics are identified in Subcontract Data, and defined terms have capital initial letters.
ts
Activity Schedule 55.1, 55.3–4 definition X1.1(a)
assessing compensation events 63.5 Price Adjustment Factor (PAF) X1.1(c)
compensation events 60.1(2–5), 60.1(19)
Bill of Quantities 56
ec
definition 11.2(1)
Prevention 19.1 assessing compensation events 63.15
quotations for compensation events 62.2 compensation events 60.4, 60.6–7
reasons for termination 91.7 definition 11.2(22)
revising the programme 32.1 Price for Work Done to Date 11.2(28)
oj
see also programme Prices 11.2(31)
Total of the Prices 11.2(32)
accepting Defects 45
bill of quantities 11.2(22)
pr
access
Site 33 bodily harm 81.1
to work being done 27.2 bonus for early Completion X6
actions 10, X12.2 boundaries of the site 11.2(14)
Activity Schedule 55
M
assessing compensation events 63.14 changes in the law X2
definition 11.2(21)
Prices 11.2(30) Client
O
additional costs 25.3, 93.2, W1.3(8), W2.3(7) Information Model X10.1(3), X10.6
insurance by Client or Contractor 86
adjudication W1.3, W2.3 insurance cover 83.1–2
AE
Expires 20/11/20
Index
ly
definition 11.2(2) Joining Deed Y1.10
delay damages X7.1, X7.3 Key Date(s) 14.4
notifying compensation events 61.2, 61.4 key person 24.1–2
on
Prevention 19.1 limitations of liability X18.2–6
programme 31.2 marking Equipment, Plant and Materials outside Working
Provide the Subcontract Works 20.3 Areas 71.1
reasons for termination 91.7 notifying compensation events 61.1–7
retention X16.1–2 objects and materials within the Site 73.1
ts
revising the programme 32.2 other responsibilities 27.2, 27.2–3
sectional completion X5.1 Parties 11.2(11)
starting work 30.1 payment on termination 93.1–2, 93.4, 93.5–6, 93.6
Subcontractor’s share 54.3, 54.7 payment(s) 51.1–3, Y1.5–6, Y1.8
ec
take over 35.1–2 performance bond X13.1
Condition Prevention 19.1
programme 31.2 Price for Work Done to Date 11.2(29)
Subcontract Data 11.2(9) procedures on termination 92.1–2
oj
programme 31.1, 31.2–3
condition(s), definition 11.2(9) Project Bank Account Y1.1(1), Y1.1(3)
conditions of subcontract proposed instructions 65.1–3
pr
activity schedule 11.2(21) Provide the Subcontract Works 20.2–3
assessing compensation events 63.3 quality management system 40.2–3
bill of quantities 11.2(22) quotations for compensation events 62.1, 62.3–6
communications 13.3, 13.8 reasons for termination 91.2–4, 91.6–9
compensation events 60.1(14) recovery of costs 82.1–2
M
implementing compensation events 66.2 removing Equipment 72.1
interpretation 12.3 requirements for instructions 17.1–2
notifying compensation events 61.4 resolving disputes W1(3), W2.1(3)
sectional completion X5.1 retention X16.1–3
O
Expires 20/11/20
Index
ly
whole life costs X21
see also Defined Cost disclosure 29
currency of the subcontract 50.7, 50.8, 51.1, X3.1–2 Dispute Reference Table W1(1), W1(4)
on
Dispute Resolution Service Contract W1.2(1), W2.2(3)
damages disputes, resolving disputes W1, W2
delay damages X7, X18.5
low performance damages X17, X18.5 early warning
defect correction period assessing compensation events 63.7
ts
correcting Defects 44.2–4 Disallowed Cost 11.2(25)
uncorrected Defects 46.1 information modelling X10.3
Defect(s) early warning meeting 15.2–3
ec
accepting Defects 45 Early Warning Register 15
Client’s and Contractor’s liabilities 80.1 definition of 11.2(6)
compensation events 60.1(1), 60.1(9–10) early warning meeting 15.2–3
Completion 11.2(2)
effect of payment Y1.9
oj
Defects Certificate 11.2(5)
definition 11.2(4) end of liability date X18.6
Disallowed Cost 11.2(25) Equipment
pr
limitations of liability X18.4 Client’s and Contractor’s liabilities 80.1
low performance damages X17.1 compensation events X1.5
notifying Defects 32.1 Corrupt Act(s) 18.2
searching for and notifying 43 definition 11.2(7)
Subcontractor’s design X15.1–2 design 23
M
tests and inspections 40.3–5, 41.7 marking Equipment outside Working Areas 71.1
uncorrected Defects 46 payment on termination 93.2
see also correcting Defects procedures on termination 92.2
Defects Certificate 44.3 programme 31.2
O
assessing the amount due 50.7, 50.8, 50.9 additional costs 93.2
changes in the law X2.1 compensation events 61.6
compensation events 60.4, X1.5 cost reduction X21.2
definition 11.2(23), 11.2(24) Defined Cost 11.2(29), 11.2(32), 20.3, 63.1, 93.2
ru
Expires 20/11/20
Index
ly
Bill of Quantities 60.6–7 language of the subcontract 13.1
compensation events 60.6 Latest Index (L)
requirements for instructions 17.1
on
definition X1.1(b)
Site Information 60.3 Price Adjustment Factor (PAF) X1.1(c)
Information Execution Plan X10.4 law of the subcontract 12.2, X18.5
compensation events X10.5
definition X10.1(1) liabilities see Client’s liabilities; Contractor’s liabilities; limitations of
liability; Subcontractor’s liabilities
information execution plan X10.1
ts
limitations of liability X18
Information Model
definition X10.1(3) low performance damages X17, X18.5
early warning X10.3
ec
Information Model Requirements X10.1(4) marking Equipment, Plant and Materials outside Working Areas 71
Information Providers X10.1(5)
Project Information X10.1(2), X10.7(1) materials see Plant and Materials
use of X10.6 method of measurement 60.6
oj
Information Model Requirements assessing compensation events 63.15
collaboration X10.2 multiparty collaboration X12
definition X10.1(4) multiple currencies X3
pr
Information Execution Plan X10.4(2), X10.4(4)
Information Model X10.1(3)
Information Providers X10.1(5) named suppliers Y1.1(2), Y1.10
Information Providers notifying
collaboration X10.2 acceleration 36.1
M
definition X10.1(5) Defect(s) 32.1
Information Model X10.1(3) notifying compensation events 61
liabilities X10.7(1)
O
by Client or Contractor 86
option W2 53.2
insurance cover 83
insurance policies 84 other responsibilities 27
Project Information X10.7(3) Others
if Subcontractor does not insure 85 access to work being done 27.2
Subcontractor’s design X15.5 Client’s and Contractor’s liabilities 80.1
Insurance Table 83.2–3 compensation events 60.1(5)
on
Completion 11.2(2)
interest, payment(s) 51.3–4
definition 11.2(10)
interest rate, payment(s) 51.4 other responsibilities 27.1
interpretation, legal 12 programme 31.2
reasons for termination 91.3
recovery of costs 82.2
se
Own Contract
key date 11.2(9) definition X12.1(2)
Key Date(s) working together X12.3(2), X12.3(5), X12.3(8)
acceleration 36.1–3
Fo
Expires 20/11/20
Index
ly
assessing compensation events 63.1–4, 63.10, 63.12, 63.13–14,
resolving disputes W1(2), W2.1(1–2) 63.14, 63.15
tax 51.5 changes in the law X2.1
termination 90.1–2
on
compensation events 60.4
tribunal W1.4(1–4), W1.4(6), W2.4(1–3), W2.4(5) definition 11.2(30), 11.2(31)
Partnering Information implementing compensation events 66.2
actions X12.2(3–4) notifying compensation events 61.3–4
definition X12.1(4) payment on termination 93.2, 93.4
working together X12.3(1), X12.3(4), X12.3(6) price adjustment X1.4
ts
Partners quotations for compensation events 62.2
actions X12.2(1–4), X12.2(6) Subcontractor’s share 54.1–4
Core Group X12.1(4) whole life costs X21.2, X21.5
ec
definition X12.1(1) working together X12.3(6–7)
incentives X12.4(1) see also Price for Work Done to Date
Own Contract X12.1(2) procedures on termination 92
Partnering Information X12.1(4) programme
oj
Schedule of Core Group Members X12.1(5) accepting 31
Schedule of Partners X12.1(2) revising the programme 32
working together X12.3(1–9) see also Accepted programme
pr
payment(s) 51, Y1.4–8 project bank
advanced payment X14 Authorisation Y1.1(1)
effect of payment Y1.9 payment(s) Y1.6
incentives X12.4(1–2)
on termination 93 Project Bank Account Y(UK)1
definition Y1.1(3)
M
people 24 effect of payment Y1.9
People Rates payment(s) Y1.7–8
assessing compensation events 63.16 Subcontract Named Suppliers Y1.2
O
definition X10.1(2)
period for reply Information Model X10.7(1)
communications 13.3–5 liabilities X10.7(2–3)
Information Execution Plan X10.4(3)
AE
Expires 20/11/20
Index
ly
resolving disputes W1, W2
programme 31.2
retention X16 quotations for compensation events 62.2
retention free amount X16.1 sectional completion X5.1
on
retention percentage X16.1 starting work 30.1
take over 35.1
review by tribunal W2.4
whole life costs X21.5
revising the programme 32
subcontract completion date, definition 11.2(15)
rights, transfer of rights X9
Subcontract Data
ts
risk allowances 31.2, 63.8, X12.3(8) Accepted programme 11.2(1)
actions X12.2(1)
adjudication W2.3(1)
Schedule of Core Group Members
ec
Adjudicator W1.2(3), W2.2(5)
actions X12.2(5)
advanced payment X14.1, X14.3
definition X12.1(5)
assessing the amount due 50.5
Schedule of Partners bonus for early Completion X6.1
actions X12.2(1), X12.2(5)
oj
changes in the law X2.1
definition X12.1(2) Client’s and Contractor’s liabilities 80.1
incentives X12.4(1–2) communications 13.2
Key Performance Indicator X12.1(5) compensation events 60.1(13), 60.1(21), 60.4, X1.5
working together X12.3(3)
searching for and notifying Defects 43
sectional completion X5
Senior Representative
pr
Defined Cost 52.1
delay damages X7.1
early warning meeting 15.2
Early Warning Register 11.2(6)
final assessment 53.1–2
M
adjudication W1.3(1) incentives X20.2
final assessment 53.2 Information Execution Plan X10.4
resolving disputes W1(1–3), W2.1(1–3) insurance by Client or Contractor 86.2
O
share ranges, Subcontractor’s share 54.1, 54.5 insurance cover 83.1–2, X10.7(3)
Site Key Date 11.2(9)
access 33 key person 24.1
C
Expires 20/11/20
Index
ly
Subcontractor
Contractor 14.4 acceleration 36.1–2
Defect(s) 11.2(4) accepting Defects 45.1–2
Defined Cost 52.2
on
access to Site 33.1
definition 11.2(15) Activity Schedule 55.1, 55.3
Disallowed Cost 11.2(25) additional costs 25.3
Equipment 11.2(7), 23.1 adjudication W1.3(2), W1.3(4–5), W1.3(8), W2.3(3b), W2.3(7)
health and safety requirements 27.4 advanced payment X14.1–3
Information Model Requirements X10.1(4) assessing compensation events 63.2, 63.4–7, 63.9, 63.12,
ts
instructions to stop or not to start work 34.1 63.13, 63.15–16, 63.16, 64.1–4
objects and materials within the Site 73.1 assessing the amount due 50.2–5, 50.7, 50.8, 50.9
other responsibilities 27.4 Assignment 28.1
Others 25.1
ec
bonus for early Completion X6.1
performance bond X13.1 Client’s and Contractor’s liabilities 80.1
programme 31.1–3 collaboration X10.2
Provide the Subcontract Works 20.1 communications 13.3–6, 13.8
quality management system 40.1 compensation events 60.1(1), 60.1(6), 60.1(8), 60.1(9–10),
oj
reasons for termination 91.6 60.1(17–18), 60.1(20), 60.2–3, 60.7, X10.5
requirements for instructions 17.2 Completion 11.2(2)
Subcontract Data 11.2(15) Contractor 14.1–4
pr
Subcontract Named Suppliers Y1.3 Contractor’s title to Plant and Materials 70.1–2
Subcontractor’s design 21.1–2, 22.1, X15.3–4 correcting Defects 44.1–2, 44.4
Subcontractor’s proposal 16.1–2 Corrupt Act(s) 18.1–3
take over 35.2 Defect(s) 11.2(4)
tests and inspections 40.1–2, 42.1 Defects Certificate 11.2(5)
M
transfer of rights X9.1 Defined Cost 52.1, 52.2–3
ultimate holding company guarantee X4.1 delay damages X7.1
uncorrected Defects 46.1–2 Disallowed Cost 11.2(25)
undertakings to the Client or Others X8.2
O
disclosure 29.1–2
whole life costs X21.1, X21.4–5 does not insure 85
subcontract starting date early warning X10.3
Adjudicator W1.2(1), W2.2(3) early warning meeting 15.2
C
assessing the amount due 50.1 Early Warning Register 11.2(6), 15.1–2, 15.4
early warning meeting 15.2 effect of payment Y1.9
incentives X20.2 Equipment 11.2(7), 23.1
AE
Plant and Materials 11.2(12) objects and materials within the Site 73.1
Prevention 19.1 other responsibilities 27
Price Adjustment Factor (PAF) X1.2 Others 11.2(10), 25.1
procedures on termination 92.1–2 Parties 11.2(11)
Provide the Subcontract Works 11.2(13), 20.2–3 payment on termination 93.1, 93.4, 93.5–6
reasons for termination 91.7 payment(s) 51.1, Y1.4–5, Y1.7–8
removing Equipment 72.1 performance bond X13.1
retention X16.1–2 Prevention 19.1
revising the programme 32.2 Price for Work Done to Date 11.2(28), 11.2(29)
sectional completion X5.1 procedures on termination 92.2
Subcontract Scope 11.2(15) programme 31.1–3
Subcontractor’s design 21.1, 22.1, X15.1 Project Bank Account Y1.1(1), Y1.1(3)
Subcontractor’s liabilities 81.1 Project Information X10.1(2), X10.6
Expires 20/11/20
Index
ly
recovery of costs 82.1–2 termination 90, Y1.11
removing Equipment 72.1 by Contractor X11
requirements for instructions 17.1–2
on
procedures on termination 92
resolving disputes W1(3), W2.1(3) reasons for 91
responsibilities 20–36
revising the programme 32.1–2 termination certificate
searching for and notifying Defects 43.1–2 assessing the amount due 50.1
starting/completing work 30.1, 30.3 final assessment 53.1
insurance cover 83.3
ts
Subcontract Named Suppliers Y1.2–3
Subcontract Scope 11.2(15) termination 90.1, Y1.11
subsubcontracting 26.1–3, 26.4 Termination Table 90.2, 92.2
Subsubcontractor 11.2(19) payment on termination 93.2
ec
termination 90.1, 90.4 termination by Contractor X11.1–2
termination by Contractor X11.1 tests and inspections 41
tests and inspections 40.2–6, 41.7, 42.1 compensation events 60.1(11)
Total of the Prices 11.2(32) before delivery 42
oj
transfer of rights X9.1
time risk allowances, programme 31.2
tribunal W1.4(5)
Trust Deed Y1.10 Total of the Prices
definition 11.2(32)
pr
ultimate holding company guarantee X4.1–2
uncorrected Defects 46.1–2 Subcontractor’s share 54.5–8
undertakings to the Client or Others X8.1, X8.3 transfer of rights X9
use of material 74
tribunal W1.4, W2.4
whole life costs X21.1–4
adjudication W1.3(2), W1.3(11), W2.3(11)
M
working together X12.3(7)
Disallowed Cost 11.2(25)
see also Subcontractor’s design; Subcontractor’s liabilities
final assessment 53.2–3
Subcontractor’s design 21, 22, X15 payment(s) 51.3
O
Working Areas
reasons for termination 91.8 Contractor’s title to Plant and Materials 70.1–2
Subcontractor’s design 22.1 definition 11.2(20)
subsubcontracting 26.2 Disallowed Cost 11.2(25)
Supervisor Others 25.1
ru
Expires 20/11/20