Raw Effluent Volume =40 TPH x 16 Hours x 1.0 = 640 tonnes / day ( Normal Production-16 hrs./day )
40 TPH x 20 Hours x 1.0 = 800 tonnes / day ( Peak Production-20 hrs./day )
45 TPH x 24 Hours x 1.0 = 1080 tonnes / day ( Maximum Production-24hrs./day )