Assignments For Week 2-Revised Version
Assignments For Week 2-Revised Version
1
5. Predict quarterly demand for a certain loveseat. The series has both trend and seasonality and
the Quarterly relatives are: Q1= 1.20, Q2 = 1.10, Q3 = 0.75, Q4 =0.95. If the trend equation equals
to yt=124+7.5t (t = quarter 15), Predict demand for quarter 2 (where t 15 = quarter 2).
6. Given the following data, compute MAD, MSE, and MAPE for the following data. Then, please
compute the standard deviation of forecast error using the first eight months.
7. Below are a pharmacy’s actual sales and forecasted demand for a certain prescription drug for 5
months. How accurate is their forecast? Calculate MAD and MSE and create a control chart.
a) Compute a linear trend line for freight car loadings using of Excel’s Trendline, with display
Equation on chart option.
b) Use the trend equation to predict loadings for weeks 15 and 16.
2
9. Given the following data, determine the total annual cost of making with each of process A
and B and of buying. Estimated demand is 8,500 units a year. The operations manager has said
that it would be possible to achieve a 12 percent reduction in the fixed cost of Process B and a
12 percent reduction in B’s variable cost per unit. Would that be enough to change your answer
if the estimated annual cost to achieve those savings was $5,000?
Make
Process A Process B Process C
Variable cost per unit $49 $51 $50
Annual fixed cost $42000 $34000
Transportation cost per unit $2
10. A manager must decide on delivery alternatives. There are two carriers, A and B. Both offer a
two-day rate. In addition, A offers a three-day rate and a nine-day rate, and B offers a four-day
rate and a seven-day rate. Three hundred boxes are to be delivered and the freight cost for the
whole lot for each option is given below. Annual holding cost is 20 percent of unit cost, and
each box has a cost of $120. Assume 365 days per year. Which delivery alternative would you
recommend?
Cashier A Cashier B
Options Freight Cost Options Freight Cost
2 days $580 2 days $510
3 days $520 4 days $440
9 days $450 7 days $400
11. Analyze the following data to determine the total annual cost of making or buying a part.
Freight Cost Make Buy
Expected annual quantity 20,000 units 20,000 units
Variable cost per unit $5.00 $6.00
Annual fixed costs $30,000
12. Multiple choice question: The use of simpler linear regression analysis assumes that:
a) Variations around the line are non-random.
b) A straight line will be determined that maximizes the sum of deviations of the data points.
c) Predictions are to be made only within the range of observed values of the predictor
variable.
3
d) Deviations around the line are not normally distributed.
e) Predictions can be made outside the range of observed values of the predictor variable.