Compilation of Estimate
Compilation of Estimate
C1F1(dimensions)
Footing:
Thickness- 0.60m
Width- 4.00m
Length- 4.00m
Column:
Height- 3.40m
Width- 0.45m
Length- 0.45m
Volume of footings:
= (0.60m) (4.00m) (4.00m)
= 9.6 cu.m
Volume of columns:
= (0.45m) (0.45m) (3.40m)
= 0.6885 cu.m
Sand:
= (164.616 cu.m) (0.5)
= 82.308 cu.m
Gravel:
= (164.616 cu.m) (1) + (0.10m) (4.00m) (4.00m)
= 166.216 cu.m
C2F2(dimensions)
Footing:
Thickness- 0.30m
Width- 0.80m
Length- 0.80m
Column:
Height- 0.50m
Width- 0.25m
Length- 0.25m
Volume of footings:
= (0.30m) (0.80m) (0.80m)
= 0.192 cu.m
Volume of columns:
= (0.50m) (0.25m) (0.25m)
= 0.03125 cu.m
Total volume of C2F2:
= (2) (0.192 cu.m) + (2) (0.03125 cu.m)
= 0.4465 cu.m
Sand:
= (0.4465 cu.m)(0.5)
= 0.22325 cu.m
Gravel:
= (0.4465 cu.m) (1) + (0.10m) (0.80m) (0.80m)
= 0.5105 cu.m
C1C1F2(dimensions)
Footing:
Thickness- 0.60m
Width- 4.00m
Length- 7.60m
Column:
Height- 3.40m
Width- 0.45m
Length- 0.45m
Volume of footings:
= (0.60m) (4.00m) (7.60m)
= 18.24 cu.m
Volume of columns:
= (0.45m) (0.45m) (3.40m)
= 0.6885 cu.m
Sand:
= (333.489 cu.m) (0.5)
= 166.7445 cu.m
Gravel:
= (333.489 cu.m) (1) + (0.10m) (4.00m) (7.60m)
= 336.529 cu.m
C3F3(dimensions)
Footing:
Thickness- 0.40m
Width- 1.80m
Length- 1.80m
Column:
Height- 1.40m
Width- 0.45m
Length- 0.45m
Volume of footings:
= (0.40m) (1.80m) (1.80m)
= 1.296 cu.m
Volume of columns:
= (1.40m) (0.45m) (0.45m)
= 0.2835 cu.m
Sand:
= (6.318 cu.m) (0.5)
= 3.159 cu.m
Gravel:
= (6.318 cu.m)(1) + (0.10m)(1.80m)(1.80m)
= 6.642 cu.m
C4F4(dimensions)
Footing:
Thickness- 0.40m
Width- 1.50m
Length- 1.50m
Column:
Height- 1.10m
Width- 0.30m
Length- 0.30m
Volume of footings:
= (0.40m) (1.50m) (1.50m)
= 0.9 cu.m
Volume of columns:
= (1.10m) (0.30m) (0.30m)
= 0.099 cu.m
Sand:
= (1.998 cu.m) (0.5)
= 0.999 cu.m
Gravel:
= (1.998 cu.m) (1) + (0.10m) (1.50m)(1.50m)
= 2.223 cu.m
C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m
C2:
= (3.00m) (0.25m) (0.25m) (2)
= 0.1875 cu.m
C3:
= (3.00m) (0.45m) (0.45m) (4)
= 2.43 cu.m
C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m
Sand:
= (33.5325 cu.m) (0.5)
= 16.76625 cu.m
Gravel:
= (33.5325 cu.m) (1)
= 33.5325 cu.m
2nd Floor:
C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m
C3:
= (3.00m) (0.45m) (0.45m) (4)
= 2.43 cu.m
C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m
Sand:
= (33.345 cu.m) (0.5)
= 16.6725 cu.n
Gravel:
= (33.345 cu.m) (1)
= 33.345 cu.m
3rd Floor:
C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m
C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m
Sand:
= (30.915 cu.m) (0.5)
= 15.4575 cu.m
Gravel:
= (30.915 cu.m) (1)
= 30.915 cu.m
4th Floor:
C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m
Sand:
= (30.375 cu.m) (0.5)
= 15.1875 cu.m
Gravel:
= (30.375 cu.m) (1)
= 30.375 cu.m
5th Floor:
C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m
Sand:
= (30.375 cu.m)(0.5)
= 15.1875 cu.m
Gravel:
= (30.375 cu.m) (1)
= 30.375 cu.m
B1 V= L x W x T
(C1C2) V= 8.90x0.80x0.35x14
V= 34.888 m³
B1 V= L x W x T
(BD16) V= 7.93x0.80x0.35x1
V= 2.2204 m³
B1 V= L x W x T
(horizontal) V= 7.0x0.80x0.35x2
V= 3.92 m³
V= L x W x T
B1a V= 11.36x1.0x0.40x1
V= 4.544 m³
V= L x W x T
B1b V= 12.38x1.0x0.40x1
V= 4.952 m³
B2 V= L x W x T
(ABCD2) V= 6.30x0.60x0.30x4
V= 4.536 m³
V= L x W x T
B2 V= 3.17x0.60x0.30x2
V= 1.1412 m³
B3 V= L x W x T
(ABCD2-ABCD8) V= 4.5x0.60x0.30x44
(ABCD9-ABCD14) V= 35.64 m³
B3 V= L x W x T
(ABCD8-ABCD9) V= 4.0x0.60x0.30x4
V= 2.88 m³
B3 V= L x W x T
(ABCD14-ABCD15) V= 5.17x0.60x0.30x44
V= 3.7224 m³
B3 V= L x W x T
(ABCD15-ABCD16) V= 4.91x0.60x0.30x3
V= 2.6514 m³
B4 V= L x W x T
CD1-CD14 V= 3.48x0.60x0.30x14
V= 8.7696 m³
B9 V= L x W x T
(horizontal) V= 4.91x0.50x0.30x2
V= 1.473 m³
B9 V= L x W x T
(vertical) V= 2.38x0.50x0.30x2
V= 0.714 m³
B10 V= L x W x T
(horizontal) V= 4.91x0.45x0.25x1
V= 0.552375 m³
V= L x W x T
B11 V= 2.57x0.40x0.25x2
V= 8.7696 m³
V= L x W x T
EB V= 4.5x0.40x0.25x4
V= 1.8 m³
V= L x W x T
RB V=4.45x0.30x0.20x1
(vertical) V=0.267
V= L x W x T
RB V=2.60x0.30x0.20x2
(horizontal) V=0.312
V= L x W x T
CB1 V= 2.35x0.60x0.30x5
V= 2.115 m³
Total Volume= B1+B1a+B1b+B2+B3+B4+B9+B10+B11+EB+RB+CB1
Total Volume=41.0204+4.544+4.952+5.6772+44.8938+8.7696+2.187+0.552375+0.514+1.8
+0.579+2.115
THIRD FLOOR
V= L x W x T
B1 V= 8.90x0.80x0.35x14
V= 34.888 m³
V= L x W x T
B1 V= 7.09x0.80x0.35x3
V= 5.9556 m³
V= L x W x T
V=7.93x0.80x0.35x1
B1 V= 2.2204 m³
V= L x W x T
B1a V= 11.36x1.0x0.40x2
V= 9.088 m³
V= L x W x T
B1b V= 12.38x1.0x0.40x1
V= 4.952 m³
V= L x W x T
B2 V= 6.30x0.60x0.30x5
V= 5.67 m³
V= L x W x T
B2 V= 3.17x0.60x0.30x3
V= 1.7118 m³
V= L x W x T
B3 V= 4.5x0.60x0.30x44
V= 35.64 m³
V= L x W x T
B3 V= 4.0x0.60x0.30x4
V= 2.88 m³
V= L x W x T
B3 V= 5.17x0.60x0.30x4
V= 3.7224 m³
V= L x W x T
B3 V= 4.90x0.60x0.30x4
V= 3.528 m³
V= L x W x T
B4 V= 3.48x0.60x0.30x14
V= 8.7696 m³
V= L x W x T
B4 V= 2.57x0.60x0.30x2
V= 0.9252 m³
V= L x W x T
B9 V= 4.90x0.50x0.30x2
V= 1.47 m³
V= L x W x T
B9 V= 2.38x0.50x0.30x2
V= 0.714 m³
V= L x W x T
EB V= 6.30x0.40x0.25x1
V= 0.63 m³
V= L x W x T
EB V= 16.08x0.40x0.25x1
V= 1.608 m³
V= L x W x T
EB V= 4.5x0.40x0.25x11
V= 4.95 m³
V= L x W x T
EB V= 4.0x0.40x0.25x1
V= 0.4 m³
V= L x W x T
EB V= 5.17x0.40x0.25x1
V= 0.517 m³
V= L x W x T
CB1 V= 2.17x0.60x0.30x6
V= 2.3436 m³
V= L x W x T
CB1 V= 2.48x0.60x0.30x2
V= 0.8928 m³
V= L x W x T
CB1 V= 1.22x0.60x0.30x13
V= 2.8548 m³
V= L x W x T
V= 1.22x0.50x0.30x1
CB2 V= 0.183 m³
V= L x W x T
CB2 V= 2.35x0.50x0.30x12
V= 4.23 m³
=1266.7 =140.7442 m³
FOURTH FLOOR
V= L x W x T
B1 V= 8.90x0.80x0.35x16
V= 39.872 m³
V= L x W x T
B5 V= 6.30x0.55x0.30x3
V= 3.1185 m³
V= L x W x T
B5 V=4.0x0.55x0.30x1
V= 0.66 m³
V= L x W x T
B7 V= 6.30x0.50x0.30x1
V= 0.945 m³
V= L x W x T
B7 V= 4.5x0.50x0.30x22
V= 14.85 m³
V= L x W x T
B7 V= 4.0x0.50x0.30x1
V= 0.6 m³
V= L x W x T
B7 V= 5.17x0.50x0.30x2
V= 1.551 m³
V= L x W x T
B7 V= 4.90x0.50x0.30x2
V= 1.47 m³
V= L x W x T
B8 V= 3.48x0.50x0.30x16
V= 1 m³
V= L x W x T
B9 V= 4.5x0.50x0.30x22
V= 14.85 m³
V= L x W x T
B9 V= 4.0x0.50x0.30x2
V= 1.2 m³
V= L x W x T
B9 V= 5.17x0.50x0.30x2
V= 1.551 m³
V= L x W x T
B9 V= 4.90x0.50x0.30x3
V= 2.205 m³
V= L x W x T
B9 V= 2.38x0.50x0.30x22
V= 0.714 m³
V= L x W x T
CB2 V= 1.22x0.50x0.30x16
V= 2.928 m³
V= L x W x T
B1 V= 8.90x0.80x0.35x16
V= 39.872 m³
V= L x W x T
B5 V= 6.30x0.55x0.30x3
V= 3.1185 m³
V= L x W x T
B7 V= 6.3x0.50x0.30x1
V= 0.945 m³
V= L x W x T
B7 V= 4.5x0.50x0.30x22
V= 14.85 m³
V= L x W x T
B7 V= 4.0x0.50x0.30x2
V= 1.2 m³
V= L x W x T
B7 V= 5.17x0.50x0.30x2
V= 1.551 m³
V= L x W x T
B7 V= 4.90x0.50x0.30x2
V= 1.47 m³
V= L x W x T
B8 V= 3.48x0.50x0.30x16
V= 8.352 m³
V= L x W x T
B9 V= 4.5x0.50x0.30x22
V= 14.85 m³
V= L x W x T
B9 V= 4.0x0.50x0.30x2
V= 1.2 m³
V= L x W x T
B9 V= 5.17x0.50x0.30x2
V= 1.551 m³
V= L x W x T
B9 V= 4.90x0.50x0.30x2
V= 1.47 m³
V= L x W x T
B9 V= 2.38x0.50x0.30x2
V= 0.714 m³
V= L x W x T
CB2 V= 1.22x0.50x0.30x16
V= 2.928 m³
V= L x W x T
ACD 1 TO 2 V= 6.30x0.45x0.30x3
V= 2.5515 m³
ACD 2 to 3
ACD 3 to 4 V= L x W x T
ACD 4 to 5 V= 4.5x0.45x0.30x3
ACD 5 to 6 V= 1.8225 m³
ACD 6 to 7
ACD 7 to 8
V= L x W x T
ACD 8 to 9 V= 4.0x0.45x0.30x3
V= 1.62 m³
ACD 9 to 10
ACD 10 to 11 V= L x W x T
ACD 11 to 12 V= 4.5x0.45x0.30x3
ACD 12 to 13 V= 1.8225 m³
ACD 13 to 14
V= L x W x T
ACD 14 to 15 V= 5.18x0.45x0.30x3
V= 2.0979 m³
V= L x W x T
ACD 15 to 16 V= 4.90x0.45x0.30x3
V= 1.9845 m³
COLUMN VOLUME
(vertical)
V= L x W x T
A to D V= 12.38x0.45x0.30x16
V= 26.7408 m³
Horizontal
(6.3+4.5(11) +4.0+5.18+4.9-.45(16) = 62.68m
4.9-0.46(2) = 4m
(6.3+4.5(11) +4.0+5.18+4.9-.45(14) = 58.68m
(6.3+4.5(11) +4.0+5.18+4.9-.45(16) = 62.68m
Total Length = 72.48 + 72.48 + 58.77 + 14.99 + 183.68 + 21.82 + 12. 825
Total Length = 437.045 m
TOTAL VOLUME
111.05+7.87+12.74+19.05+6.35= 157.06 cu.m
157.06 x 9 = 1413.54 say 1414 bags cement
157.06 x 0.5 = 78.53 cu.m.sand
157.06 x 1 = 1567.06 cu.m gravel
SUSPENDED SLAB
SECOND FLOOR
17.15 x 8.47 x 0.15 = 21.79 cu.m
16.85 x 53.5 x 0.15 = 135.22 cu.m
(16.85 x 5.17) -(4.45 x 2.59) = 75.59 x 0.15 = 11.34 cu.m
17.15 x 4.90 x 0.15 =12.61 cu.m
11.36 x 10.26 x 0.15 = 17.48 cu.m
TOTAL VOLUME
21.79+135.22+11.34+12.61+17.48 = 198.44 cu.m
198.44 x 9 =1785.96 say 1786 bags cement
198.44 x 0.5 = 99.22 cu.m sand
198.44 x 1 = 198.44 cu.m gravel
THIRD FLOOR
13.6 x 59.8 x 0.15 = 121.99 cu.m
(13.6 x 5.17) -(4.45 x 2.59) = 58.79 x 0.15 = 8.81 cu.m
15.98 x 4.90 x 0.15 = 11.75 cu.m
TOTAL VOLUME
121.99+8.81+11.75 = 142.55 cu.m
142.55 x 9 = 1282.95 say 1283 bags cement
142.55 x 0.5 = 71.28 cu.m sand
142.55 x 1 = 142.55 cu.m gravel
FOURTH FLOOR
13.6 x 59.8 x 0.15 = 121.99 cu.m
(13.6 x 5.17) -(4.45 x 2.59) = 58.79 x 0.15 = 8.81 cu.m
15.98 x 4.90 x 0.15 = 11.75 cu.m
TOTAL VOLUME
121.99+8.81+11.75 = 142.55 cu.m
142.55 x 9 = 1282.95 say 1283 bags cement
142.55 x 0.5 = 71.28 cu.m sand
142.55 x 1 = 142.55 cu.m gravel
FIFTH FLOOR
12.38 x 4 x 0.15 = 7.43 cu.m
7.43 x 9 = 66.87 say 67 bags cement
7.43 x 0.5 = 3.72 cu.m sand
7.43x 1 = 7.43 cu.m gravel
TOTAL VOLUME
TOTAL SAND
TOTAL GRAVEL