0% found this document useful (0 votes)
7 views30 pages

Compilation of Estimate

Uploaded by

herald reyes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views30 pages

Compilation of Estimate

Uploaded by

herald reyes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 30

FOUNDATION

C1F1(dimensions)

Footing:
Thickness- 0.60m
Width- 4.00m
Length- 4.00m

Column:
Height- 3.40m
Width- 0.45m
Length- 0.45m

Volume of footings:
= (0.60m) (4.00m) (4.00m)
= 9.6 cu.m

Volume of columns:
= (0.45m) (0.45m) (3.40m)
= 0.6885 cu.m

Total volume of C1F1:


= (16) (9.6 cu.m) + (16) (0.6885 cu.m)
= 164.616 cu.m

No. of cement bags:


= (164.616) (9)
= 1482.544
= 1483 bags of cement

Sand:
= (164.616 cu.m) (0.5)
= 82.308 cu.m

Gravel:
= (164.616 cu.m) (1) + (0.10m) (4.00m) (4.00m)
= 166.216 cu.m

C2F2(dimensions)

Footing:
Thickness- 0.30m
Width- 0.80m
Length- 0.80m

Column:
Height- 0.50m
Width- 0.25m
Length- 0.25m

Volume of footings:
= (0.30m) (0.80m) (0.80m)
= 0.192 cu.m

Volume of columns:
= (0.50m) (0.25m) (0.25m)
= 0.03125 cu.m
Total volume of C2F2:
= (2) (0.192 cu.m) + (2) (0.03125 cu.m)
= 0.4465 cu.m

No. of cement bags:


= (0.4465) (9)
= 4.0185
= 5 bags of cement

Sand:
= (0.4465 cu.m)(0.5)
= 0.22325 cu.m

Gravel:
= (0.4465 cu.m) (1) + (0.10m) (0.80m) (0.80m)
= 0.5105 cu.m

C1C1F2(dimensions)

Footing:
Thickness- 0.60m
Width- 4.00m
Length- 7.60m

Column:
Height- 3.40m
Width- 0.45m
Length- 0.45m

Volume of footings:
= (0.60m) (4.00m) (7.60m)
= 18.24 cu.m

Volume of columns:
= (0.45m) (0.45m) (3.40m)
= 0.6885 cu.m

Total volume of C1C1F2:


= (17) (18.24 cu.m) + (34) (0.6885 cu.m)
= 333.489 cu.m

No. of cement bags:


= (333.489 cu.m) (9)
= 3001.401
= 3002 bags of cement

Sand:
= (333.489 cu.m) (0.5)
= 166.7445 cu.m

Gravel:
= (333.489 cu.m) (1) + (0.10m) (4.00m) (7.60m)
= 336.529 cu.m
C3F3(dimensions)

Footing:
Thickness- 0.40m
Width- 1.80m
Length- 1.80m

Column:
Height- 1.40m
Width- 0.45m
Length- 0.45m

Volume of footings:
= (0.40m) (1.80m) (1.80m)
= 1.296 cu.m

Volume of columns:
= (1.40m) (0.45m) (0.45m)
= 0.2835 cu.m

Total volume of C3F3:


= (4) (1.296 cu.m) + (4) (0.2835 cu.m)
= 6.318 cu.m

No. of cement bags:


= (6.318 cu.m) (9)
= 56.862
= 57 bags of cement

Sand:
= (6.318 cu.m) (0.5)
= 3.159 cu.m

Gravel:
= (6.318 cu.m)(1) + (0.10m)(1.80m)(1.80m)
= 6.642 cu.m

C4F4(dimensions)

Footing:
Thickness- 0.40m
Width- 1.50m
Length- 1.50m

Column:
Height- 1.10m
Width- 0.30m
Length- 0.30m

Volume of footings:
= (0.40m) (1.50m) (1.50m)
= 0.9 cu.m

Volume of columns:
= (1.10m) (0.30m) (0.30m)
= 0.099 cu.m

Total volume of C4F4:


= (2) (0.9 cu.m) + (2) (0.099 cu.m)
= 1.998 cu.m
No. of cement bags:
= (1.998 cu.m) (9)
= 17.982
= 18 bags of cement

Sand:
= (1.998 cu.m) (0.5)
= 0.999 cu.m

Gravel:
= (1.998 cu.m) (1) + (0.10m) (1.50m)(1.50m)
= 2.223 cu.m

Total bags of cement for Foundation


= 1483 bags + 5 bags + 3002 bags + 57 bags + 18 bags
= 4565 bags of cement

Total sand per cu.m for Foundation


= 82.308 cu.m + 0.22325 cu.m + 166.7445 cu.m + 3.159 cu.m + 0.999 cu.m
= 253.43375 cu.m

Total gravel per cu.m for Foundation


= 166.216 cu.m + 0.5105 cu.m + 336.529 cu.m + 6.642 cu.m + 2.223 cu.m
= 512.1205 cu.m
COLUMNS
1st Floor:

C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m

C2:
= (3.00m) (0.25m) (0.25m) (2)
= 0.1875 cu.m

C3:
= (3.00m) (0.45m) (0.45m) (4)
= 2.43 cu.m

C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m

Total volume of columns:


= C1+C2+C3+C4
= 30.375 cu.m + 0.1875 cu.m + 2.43 cu.m + 0.54 cu.m
= 33.5325 cu.m

No. of cement bags:


= (33.5325) (9)
= 301.7925
= 302 bags of cement

Sand:
= (33.5325 cu.m) (0.5)
= 16.76625 cu.m

Gravel:
= (33.5325 cu.m) (1)
= 33.5325 cu.m

2nd Floor:

C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m

C3:
= (3.00m) (0.45m) (0.45m) (4)
= 2.43 cu.m

C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m

Total volume of columns:


= C1+C3+C4
= 30.375 cu.m + 2.43 cu.m + 0.54 cu.m
= 33.345 cu.m

No. of cement bags:


= (33.345) (9)
= 300.105
= 301 bags of cement

Sand:
= (33.345 cu.m) (0.5)
= 16.6725 cu.n

Gravel:
= (33.345 cu.m) (1)
= 33.345 cu.m

3rd Floor:

C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m

C4:
= (3.00m) (0.30m) (0.30m) (2)
= 0.54 cu.m

Total volume of columns:


= C1+C4
= 30.375 cu.m + 0.54 cu.m
= 30.915 cu.m

No. of cement bags:


= (30.915) (9)
= 278.235
= 279 bags of cement

Sand:
= (30.915 cu.m) (0.5)
= 15.4575 cu.m

Gravel:
= (30.915 cu.m) (1)
= 30.915 cu.m

4th Floor:

C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m

Total volume of columns:


= 30.375 cu.m

No. of cement bags:


= (30.375) (9)
= 273.375
= 274 bags of cement

Sand:
= (30.375 cu.m) (0.5)
= 15.1875 cu.m
Gravel:
= (30.375 cu.m) (1)
= 30.375 cu.m

5th Floor:

C1:
= (3.00m) (0.45m) (0.45m) (50)
= 30.375 cu.m

Total volume of columns:


= 30.375 cu.m

No. of cement bags:


= (30.375) (9)
= 273.375
= 274 bags of cement

Sand:
= (30.375 cu.m)(0.5)
= 15.1875 cu.m

Gravel:
= (30.375 cu.m) (1)
= 30.375 cu.m

Total bags of cement from 1st Floor to 5th Floor:


= 302 bags + 301 bags + 279 bags + 274 bags + 274 bags
= 1430 bags of cement

Total sand per cu.m from 1st Floor to 5th Floor:


= 16.76625 cu.m + 16.6725 cu.m + 15.4575 cu.m + 15.1875 cu.m + 15.1875 cu.m
= 79.27125 cu.m

Total gravel per cu.m from 1st Floor to 5th Floor


= 33.5325 cu.m + 33.345 cu.m + 30.915 cu.m + 30.375 cu.m + 30.375 cu.m
= 158.5425 cu.m
SUSPENDED BEAM
SECOND FLOOR

B1 V= L x W x T
(C1C2) V= 8.90x0.80x0.35x14
V= 34.888 m³

B1 V= L x W x T
(BD16) V= 7.93x0.80x0.35x1
V= 2.2204 m³

B1 V= L x W x T
(horizontal) V= 7.0x0.80x0.35x2
V= 3.92 m³

V= L x W x T
B1a V= 11.36x1.0x0.40x1
V= 4.544 m³

V= L x W x T
B1b V= 12.38x1.0x0.40x1
V= 4.952 m³

B2 V= L x W x T
(ABCD2) V= 6.30x0.60x0.30x4
V= 4.536 m³

V= L x W x T
B2 V= 3.17x0.60x0.30x2
V= 1.1412 m³

B3 V= L x W x T
(ABCD2-ABCD8) V= 4.5x0.60x0.30x44
(ABCD9-ABCD14) V= 35.64 m³

B3 V= L x W x T
(ABCD8-ABCD9) V= 4.0x0.60x0.30x4
V= 2.88 m³
B3 V= L x W x T
(ABCD14-ABCD15) V= 5.17x0.60x0.30x44
V= 3.7224 m³

B3 V= L x W x T
(ABCD15-ABCD16) V= 4.91x0.60x0.30x3
V= 2.6514 m³

B4 V= L x W x T
CD1-CD14 V= 3.48x0.60x0.30x14
V= 8.7696 m³

B9 V= L x W x T
(horizontal) V= 4.91x0.50x0.30x2
V= 1.473 m³

B9 V= L x W x T
(vertical) V= 2.38x0.50x0.30x2
V= 0.714 m³

B10 V= L x W x T
(horizontal) V= 4.91x0.45x0.25x1
V= 0.552375 m³

V= L x W x T
B11 V= 2.57x0.40x0.25x2
V= 8.7696 m³

V= L x W x T
EB V= 4.5x0.40x0.25x4
V= 1.8 m³

V= L x W x T
RB V=4.45x0.30x0.20x1
(vertical) V=0.267
V= L x W x T
RB V=2.60x0.30x0.20x2
(horizontal) V=0.312

V= L x W x T
CB1 V= 2.35x0.60x0.30x5
V= 2.115 m³
Total Volume= B1+B1a+B1b+B2+B3+B4+B9+B10+B11+EB+RB+CB1

Total Volume=41.0204+4.544+4.952+5.6772+44.8938+8.7696+2.187+0.552375+0.514+1.8

+0.579+2.115

Total Volume= 117.60 cu.m

Cement Sand Gravel


117.60x9 =117.60x0.5 =117.60x1
=1058.4 =58.8 m³ =117.60 m³
Say 1059 bags

THIRD FLOOR

V= L x W x T
B1 V= 8.90x0.80x0.35x14
V= 34.888 m³

V= L x W x T
B1 V= 7.09x0.80x0.35x3
V= 5.9556 m³

V= L x W x T
V=7.93x0.80x0.35x1
B1 V= 2.2204 m³

V= L x W x T
B1a V= 11.36x1.0x0.40x2
V= 9.088 m³

V= L x W x T
B1b V= 12.38x1.0x0.40x1
V= 4.952 m³

V= L x W x T
B2 V= 6.30x0.60x0.30x5
V= 5.67 m³

V= L x W x T
B2 V= 3.17x0.60x0.30x3
V= 1.7118 m³
V= L x W x T
B3 V= 4.5x0.60x0.30x44
V= 35.64 m³

V= L x W x T
B3 V= 4.0x0.60x0.30x4
V= 2.88 m³

V= L x W x T
B3 V= 5.17x0.60x0.30x4
V= 3.7224 m³

V= L x W x T
B3 V= 4.90x0.60x0.30x4
V= 3.528 m³

V= L x W x T
B4 V= 3.48x0.60x0.30x14
V= 8.7696 m³

V= L x W x T
B4 V= 2.57x0.60x0.30x2
V= 0.9252 m³

V= L x W x T
B9 V= 4.90x0.50x0.30x2
V= 1.47 m³

V= L x W x T
B9 V= 2.38x0.50x0.30x2
V= 0.714 m³

V= L x W x T
EB V= 6.30x0.40x0.25x1
V= 0.63 m³

V= L x W x T
EB V= 16.08x0.40x0.25x1
V= 1.608 m³
V= L x W x T
EB V= 4.5x0.40x0.25x11
V= 4.95 m³

V= L x W x T
EB V= 4.0x0.40x0.25x1
V= 0.4 m³

V= L x W x T
EB V= 5.17x0.40x0.25x1
V= 0.517 m³

V= L x W x T
CB1 V= 2.17x0.60x0.30x6
V= 2.3436 m³

V= L x W x T
CB1 V= 2.48x0.60x0.30x2
V= 0.8928 m³

V= L x W x T
CB1 V= 1.22x0.60x0.30x13
V= 2.8548 m³

V= L x W x T
V= 1.22x0.50x0.30x1
CB2 V= 0.183 m³

V= L x W x T
CB2 V= 2.35x0.50x0.30x12
V= 4.23 m³

Total volume= B1+B1a+B1b+B2+B3+B4+B9+EB+CB1+CB2

Total volume = 43.064+9.088+4.952+7.3818+45.7704+9.6948+2.184+8.105+6.0912+4.413

Total volume = 140.7442 cu.m

Cement Sand Gravel


=140.7442 x0.5

=140.7442 x9 =70.3721 m³ =140.7442 x1

=1266.7 =140.7442 m³

Say 1267 bags

FOURTH FLOOR

V= L x W x T
B1 V= 8.90x0.80x0.35x16
V= 39.872 m³

V= L x W x T
B5 V= 6.30x0.55x0.30x3
V= 3.1185 m³

V= L x W x T
B5 V=4.0x0.55x0.30x1
V= 0.66 m³

V= L x W x T
B7 V= 6.30x0.50x0.30x1
V= 0.945 m³

V= L x W x T
B7 V= 4.5x0.50x0.30x22
V= 14.85 m³

V= L x W x T
B7 V= 4.0x0.50x0.30x1
V= 0.6 m³

V= L x W x T
B7 V= 5.17x0.50x0.30x2
V= 1.551 m³

V= L x W x T
B7 V= 4.90x0.50x0.30x2
V= 1.47 m³
V= L x W x T
B8 V= 3.48x0.50x0.30x16
V= 1 m³

V= L x W x T
B9 V= 4.5x0.50x0.30x22
V= 14.85 m³

V= L x W x T
B9 V= 4.0x0.50x0.30x2
V= 1.2 m³

V= L x W x T
B9 V= 5.17x0.50x0.30x2
V= 1.551 m³

V= L x W x T
B9 V= 4.90x0.50x0.30x3
V= 2.205 m³

V= L x W x T
B9 V= 2.38x0.50x0.30x22
V= 0.714 m³

V= L x W x T
CB2 V= 1.22x0.50x0.30x16
V= 2.928 m³

Total volume= B1+B5+B7+B8+B9+CB2

Total volume = 39.872+3.7785+19.416+8.352+20.52+2.928

Total volume = 94.8665 m³

CEMENT SAND GRAVEL

=94.8665x9 =94.8665x0.5 =94.8665x1

=853.7985 =47.43325 m³ =94.8665 m³


Say 854 bags
FIFTH FLOOR

V= L x W x T
B1 V= 8.90x0.80x0.35x16
V= 39.872 m³

V= L x W x T
B5 V= 6.30x0.55x0.30x3
V= 3.1185 m³

V= L x W x T
B7 V= 6.3x0.50x0.30x1
V= 0.945 m³

V= L x W x T
B7 V= 4.5x0.50x0.30x22
V= 14.85 m³

V= L x W x T
B7 V= 4.0x0.50x0.30x2
V= 1.2 m³

V= L x W x T
B7 V= 5.17x0.50x0.30x2
V= 1.551 m³

V= L x W x T
B7 V= 4.90x0.50x0.30x2
V= 1.47 m³

V= L x W x T
B8 V= 3.48x0.50x0.30x16
V= 8.352 m³

V= L x W x T
B9 V= 4.5x0.50x0.30x22
V= 14.85 m³
V= L x W x T
B9 V= 4.0x0.50x0.30x2
V= 1.2 m³

V= L x W x T
B9 V= 5.17x0.50x0.30x2
V= 1.551 m³

V= L x W x T
B9 V= 4.90x0.50x0.30x2
V= 1.47 m³

V= L x W x T
B9 V= 2.38x0.50x0.30x2
V= 0.714 m³

V= L x W x T
CB2 V= 1.22x0.50x0.30x16
V= 2.928 m³

Total volume= B1+B5+B7+B8+B9+CB2

Total volume = 39.872+3.1185+20.016+8.352+19.785+2.928

Total volume = 94.0715 m³

Cement Sand Gravel

=94.0715x9 =94.0715x0.5 =94.0715x1

=846.6435 =47.03575 m³ =94.0715 m³


Say 847bags

SUMMARY OF SUSPENDED BEAM

Cement Sand Gravel


=1059+1267+854+ =58.8+70.3721+47.43325+47.0 =117.60+140.7442+94.8665+94.
847 3575 0715
= 4027 bags = 223.6411 cu.m =447.2822 cu.m
STRAP BEAM
COLUMN VOLUME
(horizontal)

V= L x W x T
ACD 1 TO 2 V= 6.30x0.45x0.30x3
V= 2.5515 m³

ACD 2 to 3
ACD 3 to 4 V= L x W x T
ACD 4 to 5 V= 4.5x0.45x0.30x3
ACD 5 to 6 V= 1.8225 m³
ACD 6 to 7
ACD 7 to 8

V= L x W x T
ACD 8 to 9 V= 4.0x0.45x0.30x3
V= 1.62 m³

ACD 9 to 10
ACD 10 to 11 V= L x W x T
ACD 11 to 12 V= 4.5x0.45x0.30x3
ACD 12 to 13 V= 1.8225 m³
ACD 13 to 14

V= L x W x T
ACD 14 to 15 V= 5.18x0.45x0.30x3
V= 2.0979 m³

V= L x W x T
ACD 15 to 16 V= 4.90x0.45x0.30x3
V= 1.9845 m³

Note: if the column size is not included

COLUMN VOLUME
(vertical)

V= L x W x T
A to D V= 12.38x0.45x0.30x16
V= 26.7408 m³

Total volume= 2.5515+1.8825(6) +1.62+1.8825(5) +2.0979+1.9845+26.7408


Total volume= 55.0422

Cement Sand Gravel

=55.0422x9 =55.0422x0.5 =55.0422x1


=495.3798 =27.5211 m³ =55.0422 m³
Say 496 bags

Note: If column size is included

Horizontal
(6.3+4.5(11) +4.0+5.18+4.9-.45(16) = 62.68m
4.9-0.46(2) = 4m
(6.3+4.5(11) +4.0+5.18+4.9-.45(14) = 58.68m
(6.3+4.5(11) +4.0+5.18+4.9-.45(16) = 62.68m

Total measurement= 364.52 m


Total volume= 364.52x0.45x0.30= 49.21 m³

Cement Sand Gravel

=49.21x9 =49.21x0.5 =49.21x1


=442.89 =24.605 m³ =49.21 m³
Say 443 bags
TIE BEAM

L1 = (80.13 -17) x 0.45 = 72.48 m


L2 = 72.48 m
L3 = (64.97-13.5) x (0.45 - 0.25/2) = 58.77 m
L4 = (4.9 - 0.45) + (3.74-0.3) + (3.9- 0.25/2 – 0.45/2) x 2 = 14.99 m
L5 = ((12.38 - 2) x 0.45) x 14 + ((12.38 - 3) x 0.45) + (12.38 - 0.45) = 183.68 m
L6 = (11.36 – 0.45) x 2 = 21.82 m
L7 = 2 x (2 – 0.45) + 2 (2 + 0.75 – 0.15) + 4.775 – 0.25) = 12.825 m

Total Length = 72.48 + 72.48 + 58.77 + 14.99 + 183.68 + 21.82 + 12. 825
Total Length = 437.045 m

Total Volume = 0.25 x 0.4 x 437.045


Total Volume = 43. 7045 cu.m

Cement Sand Gravel


= 43.7045 x 9 = 43.7045 x 0.5 =43.7045 x 1
= 393.3405 =21.05225 cu.m =43.7045 cu.m
Say 394 bags
GROUND SLAB
12.38 x 59.8 x 0.15 = 111.05 cu.m
(12.38 x 5.17) -(4.45 x 2.59) = 52.48 x 0.15 = 7.87 cu.m
17.33 x 4.90 x 0.15 = 12.74 cu.m
12.38 x 10.26 x 0.15 = 19.05 cu.m
2.35 x 18 x 0.15 = 6.35 cu.m

TOTAL VOLUME
111.05+7.87+12.74+19.05+6.35= 157.06 cu.m
157.06 x 9 = 1413.54 say 1414 bags cement
157.06 x 0.5 = 78.53 cu.m.sand
157.06 x 1 = 1567.06 cu.m gravel
SUSPENDED SLAB
SECOND FLOOR
17.15 x 8.47 x 0.15 = 21.79 cu.m
16.85 x 53.5 x 0.15 = 135.22 cu.m
(16.85 x 5.17) -(4.45 x 2.59) = 75.59 x 0.15 = 11.34 cu.m
17.15 x 4.90 x 0.15 =12.61 cu.m
11.36 x 10.26 x 0.15 = 17.48 cu.m

TOTAL VOLUME
21.79+135.22+11.34+12.61+17.48 = 198.44 cu.m
198.44 x 9 =1785.96 say 1786 bags cement
198.44 x 0.5 = 99.22 cu.m sand
198.44 x 1 = 198.44 cu.m gravel

THIRD FLOOR
13.6 x 59.8 x 0.15 = 121.99 cu.m
(13.6 x 5.17) -(4.45 x 2.59) = 58.79 x 0.15 = 8.81 cu.m
15.98 x 4.90 x 0.15 = 11.75 cu.m

TOTAL VOLUME
121.99+8.81+11.75 = 142.55 cu.m
142.55 x 9 = 1282.95 say 1283 bags cement
142.55 x 0.5 = 71.28 cu.m sand
142.55 x 1 = 142.55 cu.m gravel

FOURTH FLOOR
13.6 x 59.8 x 0.15 = 121.99 cu.m
(13.6 x 5.17) -(4.45 x 2.59) = 58.79 x 0.15 = 8.81 cu.m
15.98 x 4.90 x 0.15 = 11.75 cu.m

TOTAL VOLUME
121.99+8.81+11.75 = 142.55 cu.m
142.55 x 9 = 1282.95 say 1283 bags cement
142.55 x 0.5 = 71.28 cu.m sand
142.55 x 1 = 142.55 cu.m gravel

FIFTH FLOOR
12.38 x 4 x 0.15 = 7.43 cu.m
7.43 x 9 = 66.87 say 67 bags cement
7.43 x 0.5 = 3.72 cu.m sand
7.43x 1 = 7.43 cu.m gravel
TOTAL VOLUME

198.44+142.55+142.55+7.43 = 490.97 cu.m

TOTAL BAGS OF CEMENT

1786+1283+1283+67 = 4419 bags

TOTAL SAND

99.22+71.28+71.28+3.72 = 245.5 cu.m

TOTAL GRAVEL

198.44+142.55+142.55+7.43 = 490.97 cu.m