Unit 4 Standard Costing
Unit 4 Standard Costing
:STANDARD COSTING:
Reporting of Yes No
Variances
COST VARIANCES
2
If actual price exceeds the standard price, variance will be
designated as adverse (A) and when actual price is less than the
standard price variance will be known as favorable (F)
3
:Example:
Ex:03. The following data are given for the production of 90 units
of output:
Standard cost Actual Cost
Material Quantity Price Amount Quantity Price Amount
Kgs. Rs. Rs. Kgs. Rs. Rs.
A 50 10 500 45 12 540
B 50 15 750 60 20 1200
Total 100 1250 105 1740
Findout:
1. Material cost Variance
2. Material Price Variance
3. Material Usage Variance
4. Material Mix Variance
5. Material Yield Variance
4
ii) Material Price Variance
iii) Material usage Variance
iv) Material Mix variance
v) Material yield variance
Ex:05. From the following data calculate:
(i) Material cost variance
(ii) Material price Variance
(iii) Material Mix Variance
(iv) Material yield Variance
Standard Actual
Quantity Rate Value Quantity Rate Rs. Value Rs.
Kgs. Rs. Rs. Kgs.
Material A 40 2 80 35 2.1 73.5
Material B 20 5 100 25 4.5 112.5
Total Mix 60 180 60 186
Loss 6 -- 9 --
Output 54 180 51 186
Standard Actual
Material Quantity Rate Per Kg. Quantity Rate Per Kg.
A 700 kgs. Rs.40 600 kgs. Rs.50
B 300 Rs.15 500 kgs. Rs.12
Output 960 kgs. 1,032 kgs.
5
40 of material B @ Rs.4 per kg. 160
25 of material C @ Rs. 6 per kg. 150
110
Standard Loss: 10 400
Actual production 2,000 kg. of Chemical No.456 and actual material
usage is as follows:-
Kg. Rs.
Material A 1,000 @ 1.90 Per Kg 1,900
Material B 850 @ 4.20 per kg. 3,570
Material C 450 @ 6.50 per kg. 2,925
2,300 8,395
6
:Labour Cost Variances:
7
between hours worked and paid by the standard labour rate. In
formula form, it may be written as follows:
Ex:01b. From the data given below, calculate labour variances for
the two departments:
Deptt. A Deptt. B
Actual Gross Wages (direct) Rs.2,000 Rs.1,800
Standard Hours Produced 8,000 6,000
Actual hours Worked 8,200 5,800
Ex:05. Trishul Industries turns out only one article, the prime
cost standards which have been established as follows:
Per Completed Piece
Materials 5 lbs. @ Rs.4.20 Rs.21
Labour 3 hours @ Rs.3 Rs. 9
The production schedule for the month of July, 1983 required
completion of 5,000 pieces. However, 5,120 pieces were actually
completed.
Purchases for the month July 1983 amounted to 30,000lbs. Of
material at the total invoice price of Rs.1,35,000.
9
Boys Re 0.40
In a normal working of 40 hours the gang is expected to produce
2,000 units of output.
During the week ended 31st December 1987, the gang consisted
of 40 Men, 10 Women and 5 Boys. The actual wages paid were @ re
0.70, re 0.65 and Re 0.30, respectively. 4 hours were lost due to
abnormal idle time and 1600 units were produced.
Calculate (i) Wage variance (ii) Wage rate variance (iii) Labour
efficiency variance (iv) Gang composition (v) labour idle tome
variance.
Standard Actual
Hours Rate P.H.(Rs) Hours Rate P.H.(Rs)
Skilled 90 20 44 25
Semi-skilled 60 10 66 5
10