Method Statement Pergolas & Shaded Structures

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
590 views7 pages

Method Statement Pergolas & Shaded Structures

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

REDCON INTERNATIONAL LIMITED.

WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023

TABLE OF CONTENTS:

1. SCOPE OF WORK

2. METHODOLOGY

3. PROJECT ORGANIZATION KEY PERSONNEL AND RESPONSIBILITIES

4. INTERFACE REQUIREMENTS

5. LIST OF SUB-CONTRACTORS

6. PERMIT AND LICENSING REQUIREMENTS

7. RESOURCES AND MATERIALS

8. EQUIPMENT AND TOOLS

9. TRAINING AND COMPETENCY REQUIREMENTS

10. ENVIRONMENTAL AND QUALITY REQUIREMENTS

11. FIRST AID AND EMERGENCY RESPONSE PROCEDURES

12. SUPERVISION AND MONITORING/INSPECTION ARRANGEMENTS

13. HEAT STRESS MANAGEMENT

14. ATTACHMENTS
Risk Assessment
REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023

1) SCOPE OF WORK

The procedure shall apply to all kinds of concrete, Timber, Metal works for installation of Pergolas & Shaded
Structures. RIL shall implement this procedure to ensure that activities done as per specs. The work covered
by this specification shall consist of furnishing all labor, materials, permits, and related work necessary to
complete the work.

2) METHODOLOGY

2.1 MATERIAL HANDALING, STORAGE AND PRESERVATION:

 Handling, storage, preservation and protection will be carried out as per project specification.
 All small components like bolts, nuts, washers, etc. will be stored in containers and in a dry
place.
 The threaded portion of anchor bolts will be kept clean and protected from damage.

2.2 Site Preparation:

2.2.1 Survey and Marking:

 Carry out a detailed site survey to mark the layout of the timber structure.
 Mark positions for footings or posts on the ground.
2.2.2 Site Clearing:

 Clear the site from any debris, plants, or obstacles.


 Level the ground for stable installation.

2.3 Foundation Installation (if applicable)

2.3.1 Excavation for Footings:

 Excavate to the required depth for concrete footings or posts.


 Ensure that all holes are level and at the same depth according to the plan.
2.3.2 Placing Concrete:

 Pour concrete into the footings as per the design.


 Allow sufficient time for the concrete to cure and set before proceeding with the installation of
timber posts.
REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023
2.3.3 Installation of Post Anchors:

 Mechanical Anchors:

1. Drill holes into concrete substrate perpendicular to the surface and at specified locations
and
spacing using carbide-tipped drill bits complying with ANSI 212.15 to depths appropriate
for
specified anchors.
2. Clear hole of dust and debris using oil-free compressed air.
3. Install anchors to specified embedment following recommendations provided by bolt
manufacturer including setting bolts with specified torque.
 Epoxy-Bonded Anchors:

1. Drill holes into concrete substrate perpendicular to the surface and at specified locations
and spacing using an electro-pneumatic hammer drill set in rotation-hammer mode and
carbide-tipped drill bits complying with ANSI B212.15 to depths appropriate for specified
anchors.
2. Clear holes of dust and debris using oil-free compressed air, brushing with a wire brush
two times and again blowing with compressed air. Holes must not contain any water at
the time of anchor installation.
3. Inject adhesive into holes using the manufacturer’s foil pack dispenser and injection
nozzle, filling the holes approximately two-thirds full with mixed adhesive after discarding
the first three or four “trigger-pulls” of adhesive from a new cartridge.
4. Install the anchors by twisting clockwise while inserting the anchor into the hole to the
required embedment depth.
5. Do not disturb anchor during the specified cure time.

2.4 Timber Structure Works:


REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023

2.4.1 Timber Cutting and Pre-Fabrication:

 Minor Cutting timber beams, rafters, and other parts to the adjust the required size as per the
design drawings.
 Pre-fabricate certain elements (if possible) off-site to minimize on-site work.

2.4.2 Erection of Timber Posts:

 Erect the vertical timber posts into the post anchors.


 Use temporary bracing to hold the posts in position.
 Check the alignment using spirit levels and adjust as necessary.

2.4.3 Installation of Horizontal Beams and Rafters:

 Install horizontal beams connecting the posts, ensuring they are securely fixed using bolts or
screws.
 Install roof rafters or shade slats at the required intervals. Maintain consistent spacing between
the rafters/slats for uniformity.

2.4.4 Structural Bracing:

 Apply paint, varnish, or stain to the structure as per the design specifications.
 Ensure even application and allow the finish to dry completely between coats.
REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023
2.5 Aluminum & Stain steel Structure Works:
2.5.1 Assembly of Structure:

 Installation of Columns/Posts:

 Fix the vertical aluminum or stain steel posts onto the concrete foundations using stainless
steel bolts and nuts.
 Ensure posts are plumb and aligned properly.
 Beam Installation:

 Install the horizontal aluminum or stain steel beams (main and cross beams) between the
posts. Attach them using brackets, bolts, or welding (depending on design).
 Verify the beams are level and correctly spaced.

 Cross Members/Rafters:

 Place the rafters or additional cross members on top of the beams, ensuring equal spacing.
Secure them with brackets and bolts.

2.5.2 Anchoring and Tightening:

 Tighten All Connections:

 Once all parts are in place, ensure that all nuts, bolts, and joints are tightened securely using
appropriate torque values.
 Conduct a final inspection to ensure the entire structure is stable and secure.

2.5.3 Sealing and Painting:

 Apply sealant to any exposed joints or welding points to prevent corrosion.


 Paint or coat the aluminum or stain steel as per the project specification for durability and
aesthetics (if applicable).

2.5.4 Cleaning:

 Clean the pergola and shade structure, removing any dust, dirt, or debris from the
installation.

2.6 FIELD QUALITY CONTROL:


REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023

A. Site Damage Repair / Replacement

 Any damage to stainless steel elements caused during handling and installation, or by
subsequent site operations, is to be rectified immediately. Obtain approval before commencing
extensive repairs or replacements.
 Replace components with damage considered unacceptable for repair.
B. Maintenance

 After removal of protective coverings, clean and maintain all stainless steel surfaces at regular
intervals until Practical Completion.
 All maintenance is to be in accordance with procedures detailed in the powder coating
manufacturer’s technical literature and the guarantee.
 At practical completion, maintenance details must be passed on to the Engineer to enable the
Employer to set up a maintenance contract.
 Maintenance records should be kept until the end of the guarantee period.

1. Materials:

• Aluminum profiles and beams (as per design)


• Stainless steel or galvanized fasteners
• Shade fabric
• Concrete mix
• Paints or protective coatings (if required)
• Timber profiles and beams (as per design)

2. Tools & Equipment

• Calibrated Batch Plant.


• Transit Mixers.
• Concrete Pumps.
• Concrete Buckets.
• Vibrators.
• Air Compressors.
• Cutting Machine.
• Hand Tools
• Scaffolding
 Welding machine (if on-site welding is required)
 Cutting machine or saw for aluminum
 Crane
 Man Lift
 Boom Truck
 Drill with appropriate bits
 Spirit level
REDCON INTERNATIONAL LIMITED.
WELLNESS PROJECT
Method Statement– Pergolas & Shaded Structures
Revision # C1 Date of issue Nov 09, 2023
 Measuring tape