0% found this document useful (0 votes)
21 views

Detail Estimate Tutorial

Uploaded by

Pratham Solanki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Detail Estimate Tutorial

Uploaded by

Pratham Solanki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Q 1)

Sr.No Particular No. Length Width Height Quantity Remark


1 UCR Masonry in CM (1:5)
L= (55.6-0.5*11*0.6)
Footing (F1) 1 52.3 0.6 0.5 15.69 m3 = 52.3
15.855 L= (55.6-0.5*11*0.5)
Footing (F2) 1 52.85 0.5 0.6 m3 = 52.85
14.952 L= (55.6-0.5*11*0.4)
Footing (F3) 1 53.4 0.4 0.7 m3 = 53.4
Total 46.497
Quantity m3
I st Class Brick Masonry in
CM (1:4) in Super 51.792
2 Structure. 1 53.95 0.3 3.2 m3
Deductions
Window(W1) 4 2 0.3 1.5 3.6 W1 = 2 x 1.5 m
Window(w2) 1 1.5 0.3 1.5 0.675 W2 = 1.5 x 1.5 m
Ventilation (v) 2 1 0.3 0.6 0.36 V = 1 X 0.6 m
Door (D) 2 1.2 0.3 2.1 1.512 D=1.2 x 2.1 m
Door (D1) 1 1 0.3 2.1 0.63 D1=1 x 2.1 m
Door (D2) 1 0.9 0.3 2.1 0.567 D2= 0.9 x 2.1m
Opening (o) 1 1.2 0.3 2.1 0.756 O=1.2 x 2.1 m
Total
Deduction 8.1 m3
Deductions for Lintel
L = 0.15+2+0.15
Window(W1) 4 2.3 0.3 0.3 0.828 =2.3
L = 0.15+1.5+0.15
Window(w2) 1 1.8 0.3 0.3 0.162 =1.8
L = 0.15+1+0.15
Ventilation (v) 2 1.3 0.3 0.3 0.234 =1.3
L = 0.15+1.2+0.15
Door (D) 2 1.5 0.3 0.3 0.27 =1.5
L = 0.15+1+0.15
Door (D1) 1 1.3 0.3 0.3 0.117 =1.3
L = 0.15+0.9+0.15
Door (D2) 1 1.2 0.3 0.3 0.108 =1.2
L = 0.15+1.2+0.15
Opening (o) 1 1.5 0.3 0.3 0.135 =1.5
Total
Deduction 1.854 m3
Total Quantity of I st
Class Brick Masonry in 41.838
CM (1:4) m3

16.185
3 2.5cm thick DPC (1:2:4) 1 53.95 0.3 - m2
Net quantity of 12 mm thick
4 internal plaster in CM (1:4)
Living Room 1 16.4 - 3.5 57.4
Kitchen 1 12.8 - 3.5 44.8
Bed Room 1 14.2 - 3.5 49.7
Bath room 1 7.4 - 3.5 25.9
W.C 1 5.8 - 3.5 20.3
Passage 1 11 - 3.5 38.5
Total
Quantity 236.6 m2
Deduction
Window(W1) 4 2 - 1.5 12
Window(w2) 1 1.5 - 1.5 2.25
Ventilation (v) 2 1 - 0.6 1.2
Door (D) 2 1.2 - 2.1 5.04
Door (D1) 1 1 - 2.1 2.1
Door (D2) 1 0.9 - 2.1 1.89
Opening (o) 1 1.2 - 2.1 2.52
Total
Deduction 27 m2

Net quantity of 12 mm
thick internal plaster in
CM (1:4) 209.6 m2
Q2)

Sr Description of length Height


No. width(W) Quantity Remark
No Particulate (L) (H)
Earthwork in L=52.8-(10*0.5*0.9)
1 1 48.3 0.9 1.4 60.858 m3
Excavation L=48.3 m
P.C.C (1:2:4) for L=52.8-(10*0.5*0.9)
2 1 48.3 0.9 0.2 8.694 m3
foundation bed L=48.3 m

D.P.C (2.5 cm thick) L=52.8-(10*0.5*0.3)


3 1 51.3 0.3 - 15.39 m2
in 1:3:6 L=51.3 m

I. Deduction
Doors (D) 1 1.2 0.3 - 0.36 D= 1.2x2.1
Doors (D1) 1 1 0.3 - 0.3 D1=1x2.1
Doors (D2) 1 0.9 0.3 - 0.27 D2=0.9x2.1 (assume)
Opening (O) 2 1.2 0.3 - 0.72 O=1.2x2.1
Final D.P.C
13.29 m2
Quantity

1st Class Brickwork


in superstructure 3m height of
4 1 51.3 0.3 3 46.17 m3
in cement mortar superstructure
(1:4)

I. Deduction for
openings
Doors (D) 1 1.2 0.3 2.1 0.756 D= 1.2x2.1
Doors (D1) 1 1 0.3 2.1 0.63 D1=1x2.1
Doors (D2) 1 0.9 0.3 2.1 0.567 D2=0.9x2.1 (assume)
Window (W1) 2 2 0.3 1.3 1.56 W1=2x1.3
Window (W2) 3 1.5 0.3 1.3 1.755 W2=1.5x1.3
Ventilation (V) 2 0.6 0.3 0.4 0.144 V=0.6x0.4
Opening (O) 2 1.2 0.3 2.1 1.512 O=1.2x2.1
Total Deduction for openings
6.924 m3

II. Deduction for Assuming Height


lintel of lintel as 0.3 M
Doors (D) 1 1.5 0.3 0.3 0.135 D= 1.5
Doors (D1) 1 1.3 0.3 0.3 0.117 D1=1.3
Doors (D2) 1 1.2 0.3 0.3 0.108 D2=1.2
Window (W1) 2 2.3 0.3 0.3 0.414 W1=2.3
Window (W2) 3 1.8 0.3 0.3 0.486 W2=1.8
Ventilation (V) 2 0.9 0.3 0.3 0.162 V=0.9
Opening (O) 2 1.5 0.3 0.3 0.27 O=1.5
Total Deduction for
1.692 m3
lintel
Final Quantity for
Brickwork in 37.554 m3
superstructure