ORDER SHEET Islamabad Highcourt
ORDER SHEET Islamabad Highcourt
2. The record shows that on 03.12.2009, NHA and CWE entered into
a contract for the construction of Four Lane Faisalabad – Khanewal
Project (M4), Package-1: Faisalabad – Gojra Section (58 KM) (“the
Contract”). The contract price was Rs.10,305,078,335.09, and the
contract period was 36 months from the commencement date i.e.
25.02.2010. The time for the completion of the works was extended on
three occasions and the works were completed on 29.01.2015 with the
defects liability period expiring on 29.01.2016. The Contract between
the parties was based on the Standard Bidding Document – Multilateral
Development Banks Version 2006 published by Fédération
Internationale Des Ingénieurs-Conseils (“FIDIC”) and commonly
referred to as the „Pink Book.‟ The contract documents included the
General Conditions of Contract (“GCC”) and Particular Conditions of
Contract (“PCC”).
3. The dispute resolution mechanism provided in the Contract
envisaged a process for disputes arising from and related to the
Contract to be amicably settled between the parties, failing which the
disputes could be referred to a Dispute Board. The party aggrieved by
the decision of the Dispute Board could give notice of dissatisfaction to
the other party and thereafter refer the matter to arbitration pursuant to
the Rules of Arbitration of the International Chamber of Commerce
(“ICC Rules”).
4. Clause 8.4 of the GCC entitled a contractor to an extension of the
time for completion (“EOT”) where the delay is on account of the causes
mentioned in the said clause. All these causes are such as are beyond
the control of the contractor. If the contractor considers himself entitled
to an EOT, he is required to give a notice to the Engineer, who is to
determine each EOT. Where the contractor considers himself to be
entitled to an EOT and/or any additional payment, clause 20.1 of the
GCC requires him to give notice to the Engineer describing the event or
circumstance giving rise to the claim. Such notice is to be given as soon
as practicable, and not later than 28 days after the contractor became
aware, or should have become aware, of the event or circumstance.
Within 42 days after the contractor becomes aware or should have
become aware of the event, or circumstance giving rise to the claim, he
3 Execution Application No.9/2019
continue until all payments of the unpaid sum have been paid. The rate
of interest was set at 6% per annum so as to encourage prompt
payment of the amounts due under the final award.
19. In short, the arbitration proceedings culminated in the award
dated 30.06.2019 declaring that NHA was responsible for the delays in
the execution of the Contract; CWE was entitled to delay costs claim in
respect of EOT-1 in the sum of Rs.522,285,555.50; EOT-2 in the sum of
Rs.1,183,068,265.32; and EOT-3 in the sum of Rs.1,428,122,066.43.; the
payment of Rs.338,000,000/- that had been made by NHA to CWE on
31.12.2014 was to be treated as the final and unconditional payment;
the Dispute Board‟s decisions requiring the Engineer to determine and
assess CWE‟s claim for costs associated with EOT-2 and EOT-3 by
adopting the same methodology as was used for determining and
assessing CWE‟s claim for costs associated with EOT-1 are final and
binding; and that the defects liability period expired on 29.01.2016. The
Arbitrator turned down CWE‟s claim for an amended bill of quantity rate
for Asphaltic Base Course Plant (ABCP).
20. As mentioned above, the award was rendered on 30.06.2019. Vide
letter dated 15.07.2019, CWE provided a copy of the said award to the
Chairman, NHA with the request to make payment in accordance with
the award and to return the bank guarantee. NHA neither made any
payment to CWE nor returned the bank guarantee. Instead, NHA filed
an appeal for the annulment of the award before the Cour‟ D Appel De
Paris (“Court of Appeal, Paris”). This appeal was dismissed on
14.09.2021. Perusal of the English translation of the judgment
dismissing NHA‟s challenge to the said award shows that NHA had
sought the annulment of the award on the ground that the Arbitral
Tribunal was irregularly constituted. NHA had alleged that the
Arbitrator had links with a company called Sinohydro which was an
undeclared sub-contractor of CWE. NHA questioned the independence
and impartiality of the Arbitrator on the ground of lack of disclosure as
to such link. It was also asserted by NHA that Mr. Chapman had been
appointed as a member of the Dispute Board on 04.04.2016 in a dispute
between Sinohydro and Water and Power Development Authority, and
that CWE would have had recourse to Sinohydro as its sub-contractor
in the dispute referred to Mr. Chapman as an Arbitrator. The Court of
9 Execution Application No.9/2019
Appeal, Paris held that the grounds taken by NHA in its appeal were
insufficient to demonstrate any bias on the part of the Arbitrator.
21. Further perusal of the judgment dated 14.09.2021 passed by the
Court of Appeal, Paris shows that under cover of the plea as to the lack
of impartiality of the Arbitrator, NHA in fact asked the said Court to
review the merits of the final award. NHA was not allowed to do so and
its appeal was dismissed with costs of Euros 100,000. There is nothing
on the record to show that the said judgment had been assailed any
further by NHA.
22. While the proceedings before the Court of Appeal, Paris were
pending, NHA filed an application under Sections 30 and 33 of the 1940
Act before the Court of Civil Judge, Islamabad praying for the award
dated 30.06.2019 to be set-aside. The primary ground agitated by the
NHA for setting aside the award was that the Arbitrator had committed
misconduct by not disclosing his association with Sinohydro which had
been one of CWE‟s sub-contractors. NHA alleged bias against the
Arbitrator and also took a spate of other grounds in an effort to avoid its
obligation to make payment in terms of the award to CWE. It is pertinent
to bear in mind that NHA, in its application, did not mention the fact as
to the filing of the appeal against the award before the Court of Appeal,
Paris.
23. Vide order dated 29.01.2021, the learned Civil Court returned the
said application so that it could be filed before the Court of competent
jurisdiction. As per the said order the High Court, in terms of the
provisions of the 2011 Act, had the exclusive jurisdiction to adjudicate
upon the application filed by NHA. Furthermore, it was held that the
application could not be entertained as it was beyond the pecuniary
jurisdiction of the Civil Court.
24. After the application was returned NHA, on 28.04.2021, filed the
very same application before the District Court, Islamabad. Vide order
dated 21.05.2021, the District Court, Islamabad dismissed the said
application with costs of Rs.1,000,000/-. The said Court also held that in
terms of Sections 2(d) and 3(1) of the 2011 Act, the High Court had the
exclusive jurisdiction to adjudicate upon NHA‟s application. The said
order dated 21.05.2021 has been assailed by NHA before this Court in
an appeal (FAO No.94/2021).
10 Execution Application No.9/2019
No.09/2019. This order was passed after the learned counsel for CWE
submitted that the said guarantee is valid till the end of this year.
29. Learned counsel for CWE, after narrating the relevant
background facts, submitted that a Court subordinate to the High Court
did not have the jurisdiction to set-aside a foreign arbitral award; that
by virtue of Section 3(1) of the 2011 Act, the High Court has the
exclusive jurisdiction to adjudicate and settle matters relating to or
arising from the said Act; that the Hon‟ble Lahore High Court in the case
of Orient Power Company (Private) Limited Vs. Sui Northern Gas
Pipeline Limited (PLD 2019 Lahore 607) held that the 2011 Act leaves no
room for interpretation on the issue of exclusivity of jurisdiction of the
High Court; that in the case of Taisei Corporation Vs. A.M. Corporation
Company (Private) Limited (2018 MLD 2058), the Hon‟ble High Court of
Sindh has held that after the enactment of the 2011 Act, all foreign
awards have to sail through the waters of the said Act; that the High
Court can refuse to recognize and enforce a foreign arbitral award only
if the grounds set out in Article V of the United Nations Convention on
the Recognition and Enforcement of Foreign Arbitral Awards, 1958
(“the NY Convention”) read with Section 7 of the 2011 Act are satisfied,
but does not have the jurisdiction to set-aside such an award; that in
terms of Article V(1)(e) of the NY Convention, an award can be set-aside
by the Courts of the country where the award was made or under the
specifically agreed procedural law of another country; that since the
seat of arbitration was Paris, it was the French law which is to be
treated as the procedural law governing the conduct of the arbitration
proceedings; that it is an admitted position that the contesting parties
had agreed for the laws of Pakistan to be the substantive law governing
the contract but had not agreed for the laws of Pakistan to be the
procedural law of the arbitration; that since the award dated 30.06.2019
was made at Paris under the ICC Rules, NHA had filed an appeal to set-
aside the said award before the Court of Appeal, Paris but the appeal
was rejected with costs of Euros 100,000, which have till date not been
paid by NHA; that the re-agitation by NHA of the grounds for setting
aside the award before Courts in Pakistan is barred under the principle
of res judicata; that the District Court, Islamabad had also dismissed
NHA‟s challenge to the said award with costs of Rs.1,000,000/- which
12 Execution Application No.9/2019
have also not been paid by NHA; and that for NHA to allege bias against
the Arbitrator after the award has been rendered is indicative of NHA‟s
lack of good faith.
30. Learned counsel for CWE further submitted that NHA has
embroiled CWE in wasteful litigation since the past eight years; that in
CWE‟s favour decisions have been made by the Engineer, Dispute
Board as well as the Arbitrator but NHA is refusing to honour any of the
said decisions; that the total amount payable under the award dated
30.06.2019 comes to Rs.3,435,255,571.32, US Dollars 10,703.88, and
GB Pounds 657,704.75 plus US Dollars 161,708.59 as costs of the
arbitration and Rs.2,160,000/- in respect of legal fees incurred in
Pakistan; that there is no reason for NHA to continue holding bank
guarantee dated 06.01.2015 for an amount of Rs.338,000,000/-; and that
with every passing day that NHA withholds the amounts due and
payable to CWE under the said award, the fiscal liability of NHA is
increasing. Learned counsel prayed for the award dated 30.06.2019 to
be recognized and enforced and for FAO No.94/2021 filed by NHA to be
dismissed.
31. On the other hand, learned counsel for NHA submitted that the
execution petition is not maintainable in its present form since no
executable decree has been issued; that CWE does not have the status
of a decree holder; that this Court ought to either dismiss the execution
petition or adjourn it sine die until a decree has been issued; that unless
a Court proceeds to pronounce judgment according to the award and
upon the judgment so pronounced a decree is issued, enforcement
proceedings cannot be initiated; that this procedure is to be followed
for domestic as well as foreign awards; that it is only when an award is
made a rule of Court that it becomes capable of execution; that Section
6(1) of the 2011 Act requires the Court to recognize and enforce an
award in the same manner as a judgment or an order of a Court in
Pakistan; that Section 3(3)(a) of the said Act requires the Court to follow
the provisions of the Code of Civil Procedure, 1908 (“C.P.C.”); that the
provisions of C.P.C. for enforcing a judgment would apply when a
decree is issued; that under Section 44(a) of C.P.C., a judgment of a
foreign Court based on an arbitration award cannot be enforced; and
13 Execution Application No.9/2019
that initially CWE had not even prayed for the award dated 30.06.2019
to be recognized.
32. Learned counsel for NHA further submitted that this Court, while
exercising jurisdiction under the 2011 Act, can either recognize and
enforce a foreign award or refuse to do so but cannot set-aside an
award; that the recognition and enforcement of an award can be
refused by a High Court without formally setting aside an award; that
this Court will refuse to recognize and enforce an award which has
been set-aside by a competent authority of the country or under the law
of which the award is made; that the NY Convention permits domestic
Courts to apply their own municipal laws when dealing with challenges
to foreign awards on the ground of illegalities or errors in the award;
that Courts in different jurisdictions have held that the NY Convention
does not apply to setting aside of arbitral awards; that admittedly the
governing law of the contract between NHA and CWE was the law of
Pakistan; that even though the seat of arbitration was Paris, France, the
law governing the contract between the parties was the law of Pakistan,
and therefore NHA could apply to Courts in Pakistan for the setting
aside of the award dated 30.06.2019 in accordance with the municipal
laws of Pakistan; that the said award is not enforceable under Section 7
of the 2011 Act read with Article V(1)(d) and (e) of the NY Convention for
the reason that the procedure adopted during the arbitration
proceedings was not in accordance with the laws of Pakistan which
governed the agreement between the parties; that NHA, in addition to
opposing CWE‟s petition seeking recognition and enforcement of the
award, can also seek the setting aside of the award in accordance with
the provisions of the 1940 Act; that for the setting aside of the award
under the provisions of the 1940 Act, NHA correctly invoked the
jurisdiction of the District Court, Islamabad by filing an application
under Sections 30 and 33 of the 1940 Act; that the District Court,
Islamabad ought to have given a finding on the merits of NHA‟s
objections and challenges to the award dated 30.06.2019; that this
Court ought to set-aside the order dated 21.05.2021 passed by the
District Court, Islamabad and remand the matter with the direction that
NHA‟s objections and challenges to the said award be decided on
merits; that until such a decision is made by the District Court,
14 Execution Application No.9/2019
Islamabad, this Court ought not to proceed with the execution petition
filed by CWE; and that alternatively, this Court ought to decide NHA‟s
objections since it has been vested with the powers of a Civil Court.
33. Learned counsel for NHA had submitted written arguments which
are in the nature of an appeal against the award in that NHA has
challenged the findings of the Arbitrator on the merits of CWE‟s
monetary claim. Learned counsel for NHA prayed for the execution
petition filed by CWE to be dismissed and for FAO No.94/2021 to be
allowed.
34. We have heard the contentions of the learned counsel for the
contesting parties. The facts leading to the filing of the instant petition
have been set out in sufficient detail in paragraphs 2 to 28 above and
need not be recapitulated.
38. The law governing the contract which creates the substantive
rights of the parties in respect of which the dispute has arisen is called
the proper law of the contract.
39. It is well settled that an arbitration agreement, which creates
rights and obligations of the parties to submit disputes to arbitration
and to abide by the award, is an agreement severable from the
substantive contract in which it is embedded. It is also capable of
surviving the termination, repudiation and frustration of the substantive
contract. Since an arbitration agreement is considered to have a
distinct life of its own, it can be governed by a proper law of its own
which need not be the same as the law governing the substantive
contract. Where there is no express choice of law governing the
arbitration agreement, the presumption would be that the parties
intended for the law chosen to govern the substantive contract to be the
law governing the arbitration agreement. The proper law of the
arbitration agreement governs the obligation of the parties to submit
the disputes to arbitration, and to honour an award. This must be
distinguished from the curial law of the arbitration, which governs the
conduct of the individual reference.
40. The procedural law of an arbitration which is also called „lex
arbitri‟ or „curial law‟ deals with a range of issues including the form
and validity of the arbitral award; and the finality of the award, including
any right to challenge the award in the Courts of the place of
arbitration. In order to determine the curial law in the absence of an
16 Execution Application No.9/2019
held that “in the absence of any contrary express agreement, the
proper law of arbitration agreement will be the same which is
applicable to the main agreement.” One of the principles summarized
by the Supreme Court of the United Kingdom in the case of Enka Insaat
Ve Sanayi AS Vs. OOO Insurance Company Chubb [2020] UKSC 38 was
that “where the law applicable to the arbitration agreement is not
specified, a choice of governing law for the contract will generally apply
to an arbitration agreement which forms part of the contract.”
43. As regards the curial law or the procedural law of the arbitration,
the parties are at liberty to choose the same. In the case at hand, since
the parties did not choose the curial law, the law of the seat of
arbitration would be the curial law. This makes it all the more necessary
to determine the seat of arbitration. According to Redfern and Hunter
on International Arbitration (Sixth Edition), the law of the seat of
arbitration is normally the law of the place of arbitration, and that in an
international arbitration, the parties usually have no connection with the
seat of arbitration. In the case of Naviera Amazonica Peruana S.A. v
Compania International de Seguros del Peru [1988] 1 Lloyd‟s Rep 116,
Kerr LJ regarded an agreement for arbitration in London as being a
colloquial choice of seat. The case of Enercon GmbH Vs. Enercon India
Ltd [2012] 1 Lloyds Rep 519 concerned an arbitration clause which
provided that the venue of the arbitration proceedings shall be London
and that the provisions of the Indian Arbitration and Conciliation Act,
1996 shall apply. Eder J. held the seat of arbitration to be London. In the
case of Shashoua Vs. Sharma [2009] EWHC 957, the England and Wales
High Court of Justice (Queen‟s Bench Division), it has been held inter
alia that where an arbitration clause provides for arbitration to be
conducted in accordance with Rules of the ICC, a provision that the
venue of arbitration shall be London, United Kingdom amounts to the
designation of a juridical seat. In paragraph 34 of the said report, it has
also been held as follows:-
“When therefore there is an express designation of the arbitration
venue as London and there is no designation of any alternative place as
the seat, combined with a supranational body of rules governing the
arbitration and no other significant contrary indicia, the inexorable
conclusion is, to my mind, that London is the juridical seat and English
law is the curial law”
18 Execution Application No.9/2019
44. Clause 20.6 of the GCC provides that disputes not amicably
settled and in respect of which the Dispute Board‟s decision, if any, has
not become final and binding shall be settled by arbitration. Clause 20.6
of the PCC provides that in case of a foreign contractor, arbitration
shall be carried out in accordance with the ICC Rules. For the purposes
of clarity, the said clause is reproduced herein below:-
“All disputes arising in connection with the Contract shall be finally
settled by arbitration. In case of foreign contractor, arbitration shall be
carried out in accordance with the Rules of Arbitration of the
International Chamber of Commerce, and in the case of domestic
contractor, arbitration shall be carried out in accordance with the rules
and provision of Arbitration Act, 1940 of Islamic Republic of Pakistan.”
45. As per clause 20.6(b) of the GCC, the place of arbitration shall be
the city where the headquarters of the appointed arbitral institution are
located. The headquarters of the Court of Arbitration of the ICC are
located in Paris, France, and that is indeed where the arbitration was
conducted. Article 18(1) of the ICC Rules provides that the place of the
arbitration shall be fixed by the Court of Arbitration of the ICC unless
agreed upon by the parties. The dispute resolution clauses in the
Contract do not contain a stipulation as to the seat of arbitration, but
since the venue of the arbitration was Paris, France that would also be
seat of arbitration.
46. Although NHA has been selective in placing the procedural orders
on the record, Procedural Order No.1 dated 18.10.2015 shows that
Paris, France was determined as the place of arbitration. Be that as it
may, since NHA, in its comments and written arguments, has stated
with clarity that Paris, France was the seat of arbitration, we shall
proceed further with the case treating Paris, France as the seat of
arbitration. We must however say that in the absence of an express
agreement regarding the seat of arbitration, the presumption is that the
parties intended the seat of arbitration to be the place where the
arbitration was conducted, i.e. Paris, France, and therefore, the curial
law or lex arbitri applicable to the arbitration proceedings would be
French Law. Paris, France has no connection either with CWE (which is
a company incorporated under the laws of the People‟s Republic of
China) or NHA (which is a statutory authority in Pakistan). This would
19 Execution Application No.9/2019
make Paris, France truly a neutral seat of arbitration for the said
parties.
47. The parties do not dispute that a party aggrieved by an award can
seek its setting aside in terms of Article V(1)(e) of the NY Convention
before the Courts of the country where the arbitration took place. And it
is for this very reason that NHA applied to the Court of Appeal, Paris for
the setting aside of the said award. Regardless of the fact that NHA‟s
appeal had been rejected by the Court of Appeal, Paris vide judgment
dated 14.09.2021 which has not been challenged any further, NHA
asserts that Courts in Pakistan have concurrent jurisdiction to entertain
a challenge to a foreign arbitral award. Learned counsel for NHA
asserted that since the parties had agreed for the Contract, in which
the arbitration clause was embedded, to be governed in accordance
with the Pakistan law, the Courts in Pakistan would be considered as
the “competent authority” having jurisdiction to set-aside the award
dated 30.06.2019. He takes the position that even though the seat of
arbitration was Paris, France, NHA could file an application under
Sections 30 and 33 of the 1940 Act before the Courts in Pakistan
seeking the setting aside of the award dated 30.06.2019 since under
Article V(1)(e), the Courts of the country “under the law of which” the
award was made had the jurisdiction to adjudicate upon the validity of
the award. He justifies filing the said application before the District
Court, Islamabad by asserting that there is no provision either in the
2011 Act or the NY Convention vesting jurisdiction in the High Court to
set-aside a foreign arbitral award.
48. We cannot bring ourselves to agree with the learned counsel for
NHA. Although the proper law of the Contract as well as the arbitration
agreement was Pakistan law, the conduct of the arbitration
proceedings was not to be governed by the proper law of the Contract
or the arbitration agreement but by the lex arbitri or the curial law
which in this case was French law. This is because the seat of the
arbitration between NHA and CWE was Paris, France and therefore a
challenge to the validity of the award dated 30.06.2019 lay before the
“competent authority” of the country under the law of which the award
was made. The word “law” employed in Article V(1)(e) of the NY
Convention refers to the lex arbitri or curial law i.e. the law of the seat of
20 Execution Application No.9/2019
arbitration and not the proper law governing the Contract or the
arbitration agreement. Since the seat of arbitration is admittedly Paris,
France, it is French law which is to be considered as the law under
which the award was made and not Pakistan law, which governs the
substantive contract between the parties as well as the arbitration
agreement embedded therein.
49. It is pertinent to quote the following extract from the Guide on the
Convention on the Recognition and Enforcement of the Foreign Arbitral
Awards (“UNCITRAL Guide”) published by the UNCITRAL Secretariat:-
“23. Although the Convention does not provide guidance as to the
meaning of the expression “under the law of which”, with very few
exceptions, courts have generally rejected arguments that these terms
referred to the law applicable to the merits. Courts have decided that it
referred instead to the procedural law governing the arbitration, in the
rare situation where the parties have selected a law to govern the
arbitration that is different from the law of the place of arbitration. In
Steel Corporation of the Philippines v. International Steel Services, a
United State District Court held that this expression “refers to the
theoretical case that on the basis of an agreement of the parties the
award is governed by an arbitration law which is different from the
arbitration law of the country in which the award was made”. In this
case the place of the arbitration was Singapore, but the arbitration
clause specified that “[t]he validity, performance and enforcement of
this contract shall be governed by Philippine law”. The respondent
contended that the award had been made under the law of the
Philippines and that, because it had filed a petition to vacate the award
in the Philippines courts, the award should not be recognized under
article V(1)(e). The court held that “while it would be rare for the parties
to choose a procedural law different from the arbitral situs, if they do,
the selection must be clear”, which it considered was not the case
here. In Karaha Bodas, the High Court of Hong Kong similarly stated
that the reference to the law under which the award was made
“undoubtedly refers to the law which governed the procedural law of
the arbitration, not the substantive law of the contract.”
51. In paragraph 157 of the said report, it was reiterated that the
expression “under the law” refers only to the procedural law / curial law
of the country in which the award was made and that it has no reference
to the substantive law of the contract between the parties. The said
conclusion was arrived at on the basis of the law laid down in the cases
of (i) Karaha Bodas Co. LLC Vs. Perusahaan Pertambangan Minyak Dan
Gas Bumi Negara (335 F 3d 357), (ii) Karaha Bodas Co. LLC (Cayman
Islands) Vs. Perusahaan Pertambangan Minyak Dan Gas Bumi Negara –
Pertamina (Indonesia) (Yearbook Comm. Arb‟n Vol.XXVIII (2003) Page
752), (iii) International Electric Corporation Vs. Bridas Sociedad
Anonima Petroleva, Industrial Y Commercial (745 F Supp, 178 SDNY
1990), and (iv) International Standard Electric Corp. (US) Vs. Bridas
Sociedad Anonima Petrolera (Argentina) ((1992) VII Ybk Comm Arb
639).
52. As mentioned above, the procedural law of the arbitration (as
distinguished from the proper law of the Contract or law applicable to
the arbitration agreement) is the law of the seat of arbitration unless the
parties explicitly agree otherwise. It is very rare for the parties to agree
to the curial / procedural law governing the arbitration proceedings to
be the law of a country other than the law of the country where the
arbitration is seated. But it is permissible for the parties to agree for the
curial / procedural law governing the arbitration proceedings to be
different from the law of the seat of arbitration. This is because Article
V(1)(e) gives a party aggrieved by an award to seek its setting aside
before “a competent authority of the country in which, or under the law
of which [the] award was made.” Only in those cases in which the
parties agree for the curial / procedural law governing the arbitration
proceedings to be different from the law of the seat of arbitration that
22 Execution Application No.9/2019
the courts of the country under the law of which the proceedings were
conducted will have the jurisdiction to suspend or set aside an award.
53. Had NHA and CWE agreed for the procedural law of the
arbitration to be Pakistan law and not the law of the seat of arbitration,
only then could it be argued that Courts in Pakistan, being the
“competent authority” of the country “under the law of which” the
award was made, have jurisdiction to set-aside or suspend the award.
Even in such a situation, a Court other than the High Court would not be
vested with the jurisdiction to adjudicate upon an application for the
setting aside or suspending of an award. This is because Section 3(1) of
the 2011 Act vests the High Court with exclusive jurisdiction to
adjudicate and settle matters relating to or arising from the said Act.
Since the 2011 Act accords statutory recognition to the provisions of
the NY Convention, and since Article V(1)(e) thereof read with Section 7
of the said Act prevents the High Court from recognizing or enforcing
an award which has been set-aside or suspended by a “competent
authority,” an application seeking the setting aside or suspension of an
award will a fortiori be a matter relating to or arising from the 2011 Act,
and therefore within the exclusive jurisdictional domain of the High
Court. Proceedings for the setting aside or suspension of a foreign
arbitral award before a Court in Pakistan other than the High Court
where the parties agree for the procedural law of arbitration to be
Pakistan law would be coram non judice and a decision to set-aside or
suspend such an award by a court other than the High Court would be a
nullity.
54. The learned counsel for NHA had requested for these
proceedings to be adjourned sine die until the decision of the District
Court, Islamabad on the application under Sections 30 and 33 of the
1940 Act. The grant of such request would ipso facto amount to
recognizing that the District Court, Islamabad had the jurisdiction to
adjudicate upon the application for the setting aside of the award dated
30.06.2019. We have already held that since the procedural law of the
arbitration between NHA and CWE was not Pakistan law, such an
application was not maintainable before the District Court, Islamabad.
In the case of Louis Dreyfus Commodities Suisse S.A. Vs. Acro Textile
Mills Ltd. (PLD 2018 Lahore 597), the Hon‟ble Lahore High Court held
23 Execution Application No.9/2019
that the 2011 Act and the NY Convention do not countenance a two-tier
adjudicative process, and that the policy and purpose of law will suffer
grievously if such an interpretation was allowed to be weighed with the
Courts. Additionally, in the case of Orient Power Co. (Private) Ltd. Vs.
Sui Northern Gas Pipelines Ltd. (supra), the Hon'ble Lahore High Court
held that it would be totally impractical to allow one party to seek
enforcement of a foreign arbitral award before a High Court and the
other party to file objections against the same award before a Civil
Court. Therefore, there is no reason for the proceedings before this
Court to be adjourned.
55. As NHA and CWE had admittedly not agreed for the procedural
law of the arbitration to be Pakistan law, Courts in Pakistan, including
the High Court, would not have jurisdiction to entertain or decide an
application seeking the setting aside or suspension of the award dated
30.06.2019. This does not mean that the party aggrieved by the said
award is left without a remedy. The procedural law of the arbitration
between NHA and CWE was the law of the seat of arbitration. The law of
the seat of arbitration is admittedly French law. Therefore, NHA could
only apply for setting aside or suspension of the said award before
French Courts, and cognizant of its entitlements under the law and the
NY Convention, it did challenge the said award before the Court of
Appeal, Paris albeit without success. Having failed before the Court of
Appeal, Paris, NHA wanted to take a second shot at challenging the
award dated 30.06.2019 before the District Court, Islamabad. Although
we agree with the decision of the learned District Judge to dismiss
NHA‟s application filed under Sections 30 and 33 of the 1940 Act on the
ground that the High Court had exclusive jurisdiction in the matter
pursuant to Section 3(1) of the 2011 Act, we feel the need to observe
that in this case where the procedural law of the arbitration between
NHA and CWE was to be the law of the seat of arbitration, it was neither
the District Court, Islamabad nor this Court which could entertain the
application for the setting aside of the said award.
award dated 30.06.2019 was that the said application could not have
been filed unless and until a decree had been issued by a Court of
competent jurisdiction in terms of the arbitration award. He submitted
that in Pakistan, it is only a decree that is executed and not an award
which has not been made a rule of court.
57. There is no requirement under the provisions of either the 2011
Act or the NY Convention for a decree to be issued in terms of the
award, either by a Court of the country in which the arbitration was
conducted and the award was rendered or the Courts of the country
where the award is sought to be enforced, before an application under
Section 6 of the 2011 Act is filed.
58. In the realm of arbitration laws in Pakistan, Section 17 of the 1940
Act requires a Court, as defined in Section 2(c) of the said Act, to
pronounce a judgment according to the award and upon judgment so
pronounced, a decree is to follow. The 2011 Act is a self-contained code
in which the provisions of the 1940 Act cannot be read into. The
operation of Section 6 of the 2011 Act is not preconditioned on the
issuance of a decree in terms of the foreign arbitral award. Although
Section 3(3)(a) of the 2011 Act provides that in exercise of its
jurisdiction, the Court shall follow the procedure as nearly as may be
provided for in the C.P.C., this provision cannot be interpreted such as
to thwart proceedings before this Court pursuant to Section 6 of the
2011 Act simply on the ground that a decree in terms of the foreign
arbitral award had not been issued. Be that as it may, the Hon'ble
Lahore High Court in the case of POSCO International Corporation Vs.
Rikans International (PLD 2023 Lahore 116), while recognizing a foreign
arbitral award, held that the award shall be executed as a decree of the
said Court and ordered for a decree sheet to be drawn accordingly.
Additionally, in the case of Louis Dreyfus Commodities Suisse S.A. Vs.
Acro Textiles Mills Ltd. (PLD 2018 Lahore 597), the Hon'ble Lahore High
Court, while recognizing a foreign arbitral award, granted a judgment in
favour of the award holder in the amount represented in the award
which was ordered to be executed as a decree of the said Court. We,
however, do not think that there is any need to issue an order for the
drawing up of a decree in terms of a foreign arbitral award since the
provisions of the 2011 Act contain no such requirement. Indeed, the
25 Execution Application No.9/2019
1
Oberlandesgeriht [OLG], Celle, Germany, 31 May 2007, 8 Sch 06/06
29 Execution Application No.9/2019
(to which the parties had agreed) or any provision of the French law
(being the curial law under which the award was made) which had been
violated by the Arbitrator while proceeding with the reference.
68. As per the UNCITRAL Guide, Article V(1)(d) expressly affirms the
supremacy of the parties‟ agreement concerning the composition of the
Tribunal and arbitral procedure, and that the law of the place of
arbitration should apply only failing such agreement; and the
application of the law by a Tribunal goes to the actual merits of the
dispute and therefore falls outside the scope of review at the
recognition and enforcement stage.
69. The NY Convention does not permit any review of the merits of the
award to which it applies. The grounds on which recognition and
enforcement of a foreign arbitral award can be refused are exhaustively
set out in Article V of the NY Convention. Even in cases where any of
these grounds are satisfied, the High Court may nevertheless proceed
to recognize and enforce the award. This is because the use of the word
“may” in Articles V(1) and (2) makes the refusal to recognize and
enforce an award permissive and not mandatory. It is by now well
settled that the grounds on which the recognition and enforcement of
an award can be refused under Article V of the NY Convention do not
include an erroneous decision in law or in fact by the Arbitral Tribunal.
This Court, while deciding an application under Section 6 of the 2011
Act, ought not to review the merits of the Arbitral Tribunal‟s decision.
Reference in this regard may be made to the following case law:-
(i) In the case of Jess Smith and Sons Cotton LCC Vs. DS
Industries (2019 CLD 23), the Hon‟ble Lahore High Court inter alia
held as follows:-
“The scope of inquiry before the Court before whom the
application for enforcement of the foreign award is pending is
circumscribed by the condition for refusal set out in clause (a) to
(e) of Article V. It is not open to a party seeking to resist a foreign
award to assail the award on merits or because a mistake of fact
or law has been committed by the Arbitral Tribunal.”
71. Even under the 2011 Act this Court, while deciding an application
under Section 6 of the said Act, does not sit as an appellate Court with
the power to re-examine and re-appraise evidence. A foreign award is
to be examined within the parameters set out in Article V of the NY
Convention read with Section 7 of the 2011 Act.
72. The Arbitrator turned down NHA‟s counterclaim made on the
ground that CWE had not completed the works on time. The Arbitrator
did so for the reason that CWE had completed the works within the
extended time for completion. It is not disputed that the Engineer had
been appointed by NHA and that the Dispute Board was appointed with
the consent of the parties. The Dispute Board had been appointed to
hear and decide the disputes between the parties. The Arbitrator did
not find NHA‟s effort to impugn the decisions taken by the Dispute
Board to be supported by any evidence. The Arbitrator treated NHA‟s
allegation that the Dispute Board incorrectly appraised the evidence or
had made a mistake at law to be bare statements aimed at persuading
the Arbitrator by words alone that the Dispute Board had acted
incorrectly or that its decisions should be set-aside.
73. The allegation of bias made by NHA against the Arbitrator has
already been spurned by the Court of Appeal, Paris. Since the judgment
dated 14.09.2021 passed by the Court of Appeal, Paris had attained
finality, NHA could not re-agitate the very same grounds that it had
taken in its appeal before the Court of Appeal, Paris in the objections to
CWE‟s application under Section 6 of the 2011 Act. Recently, the Privy
Council in the case of Gol Linhas Aereas SA v Matlin Patterson Global
Opportunities Partners (Cayman) II LP and others [2022] UKPC 21 held
that where an annulment action at the seat of arbitration involves an
independent or de novo determination of a question, the decision of a
court of competent jurisdiction at the seat of arbitration shall give rise
to an issue of estoppel on that question. Since before this Court NHA
raised the same question regarding the Arbitrator‟s bias which it had
raised before the Court of Appeal, Paris which had made a decision on
the merits after hearing the contesting parties, NHA is estopped from
raising the same question before this court in its effort to resist the
recognition and enforcement of the final award dated 30.06.2019.
32 Execution Application No.9/2019
74. As regards NHA‟s complaint that the Arbitrator had taken too long
to render the award, suffice it to say that in international arbitrations it
is commonplace for arbitral tribunals to render awards beyond the
period initially fixed for such purpose. In the instant case, the terms of
reference were originally framed by the Arbitrator on 06.09.2015, and
the final award was rendered on 30.06.2019. It may also be mentioned
that on 06.07.2016, the Arbitrator had rendered an interim award. The
closing submissions were submitted to the Arbitrator by the contesting
parties on 21.08.2018 and extensions in rendering the award had duly
been granted by the Court of Arbitration of ICC under Article 30 of the
ICC Rules. The period consumed in the arbitration proceedings, in our
view, was not unduly long and even otherwise furnishes no ground for
refusing to recognize or enforce the award under Article V(1)(d) of the
NY Convention.
75. NHA has also expressed its anguish over the pre-award interest
imposed on it. NHA has also complained about the accumulation of
interest that it has to pay under the award to CWE due to the delay
occasioned in the arbitration proceedings. It is not NHA‟s plea that it
was willing to make payment against CWE‟s claims regarding costs
associated with EOT-1 to EOT-3 on time or that it was due to the
arbitration proceedings or the proceedings before this Court that it was
unable to do so. Other than making a partial payment against CWE‟s
claim regarding costs associated with EOT-1, NHA has at all material
times resisted CWE‟s claims. Had NHA made payment to CWE when the
claims were made, it would have averted the burden of the interest
imposed on it. NHA knew or ought to have known that delay in making
payment against CWE‟s claims would entail simple interest at the rate of
6% per annum in terms of clause 14.8 of the PCC. In the case of
Shipowner Vs. Time Charterer, Oberlandesgericht (6 Sch 3/98, XXV Y.B.
COM. ARB. 641 (2000)), the Hamburg Court of Appeal rejected a
challenge to enforcement under article V(1)(c) made on the basis that
the arbitral tribunal had awarded more interest than had been claimed,
considering that an “arbitral tribunal can in its discretion and on its own
initiative award interest and compound interest for the time until the
rendition of the award and for the time after the rendition of the award.”
33 Execution Application No.9/2019
76. This Court has discerned from the record that NHA had resisted
making payment to CWE in terms of the concurrent decisions of the
Engineer, the Dispute Board and the Arbitrator regarding CWE‟s claim
for costs associated with EOT-1 and the decision of the Arbitrator
regarding CWE‟s claim for costs associated with EOT-2 and EOT-3. Had
these payments been made on time, NHA would not have found itself in
the unsavory situation of being burdened with interest at the rate of 6%
per annum on the sum that it was liable to pay to CWE. As regards
CWE‟s claims associated with EOT-2 and EOT-3, after the Dispute
Board decided that the Engineer ought to determine these claims in the
same manner as he had determined CWE‟s claims with respect to EOT-
1, NHA did not issue any notice of dissatisfaction regarding the Dispute
Board‟s said decision. At no material stage did the Engineer award any
amount in CWE‟s favour regarding its claims associated with EOT-2 and
EOT-3. This gave the Arbitrator the authority to determine these claims
on the same parameters as the Engineer had determined CWE‟s claims
associated with EOT-1. The record does not indicate NHA‟s inclination
to make payments to CWE in accordance with the award. It tried to
impeach the award before the Court of Appeal, Paris as well as the
District Court, Islamabad but was not successful before either forum.
We do recall that on one of the dates of the hearing, i.e., 16.12.2021,
learned counsel for the parties had sought an adjournment to explore
the avenue of an out of Court settlement but no settlement ever took
place. NHA ought to realize that its policy of challenging with impunity
before different fora every order for payment of money to contractors
causes an enhancement in its liability which is ultimately to be met by
the taxpayer. This case is one such unfortunate example.
77. Against CWE‟s claim for costs associated with EOT-1, the Dispute
Board had awarded Rs.744,068,695/-. In partial implementation of the
Dispute Board‟s said decision, NHA paid Rs.338,000,000/- to CWE.
NHA, in its letter dated 28.11.2014, had required CWE to furnish a bank
guarantee to secure the repayment of the said amount. CWE provided
bank guarantee No.IGT087400000315, dated 06.01.2015 furnished by
Habib Bank Limited for an amount of Rs.338,000,000/- in favour of NHA.
It is an admitted position that no agreement had been executed
between the parties to the effect that with the payment of
34 Execution Application No.9/2019
Whether the suit for declaration etc. instituted by CWE before the
District Court, Islamabad was maintainable:-
83. The final award was rendered on 30.06.2019 and CWE filed the
application under Section 6 of the 2011 Act before this Court on
21.12.2019. In the award dated 30.06.2019, the Arbitrator had ordered
inter alia that the bank guarantee be returned by NHA to CWE without
conditions and that CWE and the bank providing the guarantee are
released from all obligations thereunder.
84. On 18.12.2019, CWE filed a suit before the Court of the learned
Civil Judge, Islamabad and along with it filed an application seeking an
injunction to restrain NHA from encashing the bank guarantee. Vide
order dated 11.01.2021, the learned Civil Court returned the plaint on
the ground that the matter was beyond its pecuniary jurisdiction.
Thereafter, on 19.01.2021, CWE filed the same civil suit before the
District Court, Islamabad. CWE, in its suit, had prayed for a declaration
that NHA is not entitled to withhold or encash the bank guarantee. CWE
had also sought the return and cancellation of the said guarantee. In the
suit, CWE had also pleaded as to how the Arbitrator had dealt with the
issue of the guarantee.
85. The jurisdiction to grant such reliefs was exclusively with the High
Court and not the District Court, Islamabad. The recognition of the
award dated 30.06.2019 would have the effect of the order passed by
the Arbitrator with respect to the guarantee being made a rule of the
Court and enforceable against NHA. CWE could have, along with its
application under Section 6 of the 2011 Act, filed an application under
Order XXXIX, Rules 1 and 2 of C.P.C. and applied for the same very relief
that it had sought in its application for injunction filed along with its civil
suit. This is because Section 3(3)(a) of the 2011 Act provides that this
Court, in exercise of its jurisdiction, shall have the powers vested in the
Civil Court under the C.P.C., which includes the power to grant interim
injunctions. Since Section 3(1) of the 2011 Act provides that
notwithstanding anything contained in any other law for the time being
in force, the Court shall exercise exclusive jurisdiction to adjudicate
upon and settle matters related to or arising from the said Act, and
since “Court” has been defined in Section 2(d) as the High Court and
such other superior court in Pakistan as may be notified by the Federal
37 Execution Application No.9/2019
Government in the official Gazette, the District Court, Islamabad did not
commit any illegality by dismissing CWE‟s suit on the ground that the
matter lay within the jurisdiction of the High Court.
86. As mentioned above, not a single assertion made by NHA in its
written arguments for resisting the recognition and enforcement of the
award dated 30.06.2019 qualifies as a valid ground under Article V(1)(d)
of NY Convention to be termed as a transgression of the arbitral
procedure agreed between the parties or provided for in the law of the
seat of arbitration.
Relief:-
87. Since we do not find that any of the grounds envisaged by Article
V of the NY Convention for refusing to enforce a foreign arbitral award
to be satisfied in the instant case, the award dated 30.06.2019 is hereby
accorded recognition, and the same shall be executed by this Court as
though it is a decree. For the enforcement of the interim award dated
06.07.2016, which was recognized by this Court vide judgment dated
27.09.2023, separate execution proceedings are pending. In the event
payment is not made by NHA to CWE in accordance with the said
interim award read with the said judgment dated 27.09.2023 NHA, is
directed to pay Rs.3,435,255,571.32, US Dollars 10,703.88, and GB
Pounds 657,704.75 plus US Dollars 161,708.59 as costs of the
arbitration, and Rs.2,160,000/- in respect of legal fees incurred in
Pakistan along with interest at the rate of 6% per annum from the date
of the award till the date of payment. The said amount shall be paid by
the next date of hearing which is fixed for 30.10.2023.
88. Bank guarantee No.IGT087400000315, dated 06.01.2015
furnished by Habib Bank Limited at the instance of CWE for an amount
of Rs.338,000,000/- in favour of NHA is hereby cancelled and CWE is
discharged from all obligations under the said guarantee. The costs
associated with keeping the said guarantee valid after the award dated
30.06.2019 shall also be borne by NHA. The order regarding the
cancellation of the guarantee is being passed as a consequence of
recognition having been accorded to the award dated 30.06.2019.
89. For the reasons given in paragraphs 53 to 55 above, the Appeal
(FAO No.94/2021) filed by NHA is dismissed and so is the appeal
(Regular First Appeal No.881/2021) filed by CWE. NHA shall bear CWE‟s
38 Execution Application No.9/2019
(JUDGE) (JUDGE)