2 Text Book Project Risk Management Rev-1
2 Text Book Project Risk Management Rev-1
Risk
Management
Prepared by
Ajay Kumar Singhal
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 1 of 9
Dated 28-May-2009 Project Risk Management
Construction projects, from inception to closure, encounter unlimited risks. The risks
vary from project to project. Project risk management aims at planning and controlling of
risks, which might affect the performance of the project. It involves identifying,
analyzing, planning and controlling risks at project site.
Project Constraints :
Time
Quantity
Cost
What Is A Risk
The chance of an event occurring which would cause actual project circumstances to
differ from those assumed when forecasting project benefit and costs.
Unknown
Unexpected
Risk endeavor
action
Undesirable
Unpredictable
Risk Management
Risk is the degree of probability of an external event threatening the success of the
Project.
Risk Identification
Risk Monitoring
Controlled
Risk
Risk Analysis Risk
Analysis
Environment
Risk Response
Risk Planning
Risk Identification
1) Acts of God :
Flood,
Earthquake,
Landslide,
Wind damage,
Epidemic etc.
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 3 of 9
Dated 28-May-2009 Project Risk Management
4) Project Scope:
Ill-defined project scope,
Frequent change in work scope,
No extra work control.
5) Design :
Design responsibility,
No proper soil investigation,
Frequent changes in design during construction,
Unrealistic specifications / constructability of design,
Poor design and shop drawings.
6) Physical :
Inadequate or low quality procurement of resources,
Constraints on the availability of labour,
Non-availability of the material – quality as well as quantity,
Long hauling distance material problem,
Non-availability of special equipments, spares parts etc,
Non-availability of construction water, power, accommodations for labour and
staff,
Weather conditions; like high temperature / heavy rainfall,
Low load carrying capacity of existing culverts / bridges on the route,
Unsafe working conditions,
Fire, wastage and theft.
7) Contractual :
Insufficient time to prepare bid tenders,
Unrealistic time schedule,
Project schedules anticipate weather that may occur during the execution period,
Conflicting conditions of contract,
Delay in possession of site,
Differing site conditions,
Payment problems,
Extra works / variations,
Claims and disputes,
Inability to take timely corrective action.
8) Leadership :
No project vision, no team building,
Poor motivation,
Lack of senior management support,
Limited authority / control for Project In-charge,
Lack of co-ordination,
Insufficient liaison with public services,
Barriers in communication / poor communications.
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 4 of 9
Dated 28-May-2009 Project Risk Management
9) Organizational :
Lack of competent / experience persons in the project team,
Wrong selection of project team,
No project manual / documented procedures / processes,
Project being too complex for the available resources,
Inadequate communications infrastructure,
Poor quality control,
Unsatisfactory conduct of status review meetings,
Inability to take timely corrective action.
Risk Analysis
List-out all possible significant risks likely to be encountered in a Project.
Asses the probability and seriousness of each risk.
Asses the impact if it happens.
Risk Planning
Consider each risk and develop a strategy to manage that risk.
Avoidance strategies
o The probability that the risk will arise is reduced.
Minimization strategies
o The impact of the risk on the project or product will be reduced.
Contingency plans
o If the risk arises, contingency plans are planned to deal with that risk.
Risk Monitoring
Assess each identified risks regularly to decide whether or not it is becoming less
or more probable.
Also asses whether the effects of the risk have changed.
Each key risk should be discussed at management progress review meetings.
Deferred
o Activities can be moved to a later date in the Project when the adverse effects
of events may be minimized or reduced.
Retention
o Handling risks by the company who is undertaking the project.
o Two retention methods, active and passive.
- Active retention is a deliberate management strategy after a conscious
evaluation of the possible losses and costs of alternative ways of handling
risks.
- Passive retention occurs through negligence, ignorance or absence of
decision.
Reduction
o Continuous effort.
o Well-defined specifications.
o Detailed site survey.
o Detailed design.
o Completing design before execution.
o Early involvement of trained / expert project group.
o Related with improvements of a company’s physical, procedural, educational,
and training devices.
o Improving housekeeping, maintenance, first aid procedures and security.
o Education and training within every department.
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 6 of 9
Dated 28-May-2009 Project Risk Management
Risk Assessment Matrix
To build the risk matrix, you will divide likelihood and consequences into steps.
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 7 of 9
Dated 28-May-2009 Project Risk Management
Asses it : Risk Matrix = Impact x Likelihood
Risk Impact
Risk
Negligible Minor Moderate Major Catastrophic
Likelihood
1 2 3 4 5
1 2 3 4 5
Rare 1
Low Low Low Low Medium
2 4 6 8 10
Unlikely 2
Low Low Medium Medium Significant
3 6 9 12 15
Possible 3
Low Medium Significant Significant Major
4 8 12 16 20
Likely 4
Low Medium Significant Major Major
Almost 5 10 15 20 25
5
Certain Medium Significant Major Major Major
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 8 of 9
Dated 28-May-2009 Project Risk Management
Use Risk Matrix Data for Risk Management Strategy
______________________________________________________________________
AKS/TRG-NR/PRM/Rev-1 Prepared by : Ajay Kumar Singhal Page 9 of 9
Dated 28-May-2009 Project Risk Management