3 Final Text Book Construction Contract Management
3 Final Text Book Construction Contract Management
Contract Management
with particular
reference to
Construction Contracts Contract
By : Ajay Kumar Singhal
2
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
An agreement becomes a contract when : Documents generally forming part of the contract :
• Contract Agreement;
There is some consideration. • Letter of Acceptance (LOA) and Notice to Proceed (NTP);
• Contractors’ Bid / Tender Document;
The parties are competent to contract.
• Contract Data;
There is free consent of both parties.
• Conditions of Contract
Their object is lawful.
– Conditions of Particular Applications.
– General Conditions of Contract.
The term contract does not mean only the short
– Any other set of conditions namely: Project Specific
agreement to which the signatures of the parties are
Conditions, Special Conditions of Contract, Subsequent
affixed, but, includes all other documents and
Amendments incorporated etc.
correspondence which are mentioned to form
integral part of the agreement. That is why it is • Specifications;
customary to refer to them as Contract documents. • Drawings;
5 • Bill of Quantities. 6
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
1
By : Ajay Kumar Singhal
• In this form of contract, the Owner prepares schedule of items with • Cost plus percentage contract are generally adopted when
quantities, rates, unit and amount shown therein. conditions are such that the rates of labour, material etc. are liable
to fluctuate and there is an element of uncertainty in the scope of
• The Contractors are required to offer percentage above, below or the work.
at par with the rates given in the schedule.
• In this type of contracts there is an arrangement between the
• The percentage quoted by Contractor is applicable on the overall Owner and the Contractor by which the parties agree that the
schedule. work ordered would be completed and paid for on the basis of
actual cost incurred plus a fixed percentage as profit.
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
2
By : Ajay Kumar Singhal
• In a lump sum contract, the Owner has essentially assigned all the
risk to the Contractor, who in turn can be expected to ask for a
• This type of contract arrangement (also known as ‘package deal’
or EPC) places the duty to design, engineering, procurement,
higher mark-up in order to take care of unforeseen contingencies.
construction of the facility and thereafter preparation of start-up
• Beside the fixed lump sum price, other commitments are often procedures, to create operational manuals and training to people
made by the Contractor in the form of submittals such as a to operate the facility etc. on the Contractor.
specific schedule, the management reporting system or a quality
control program.
• The term ‘turnkey’ tends to mean the most extreme form of placing
design and construction responsibility on the Contractor, such that
• If the actual cost of the project is underestimated, the after completion the Employer only needs to turn the key to
underestimated cost will reduce the Contractor’s profit by that commence operation of the constructed facility.
amount.
• An overestimate has an opposite effect, but may reduce the
chance of being a low bidder for the project.
• The concept of Build, Operate and Transfer (BOT) project is the most • Federation Internationale Des Ingenieurs Conseil (i.e. International
viable way of building up the National network. NHAI brought this
Federation of Consulting Engineers) published standard forms of
concept into practice in the year 2000. Under the BOT scheme, the
construction contract for international use which are fairly balanced
projects are offered on concession for a specific time period and this
and equitable so far as the rights and obligations of both the parties
concession period involves both implementation, operation and
maintenance of the project
are concerned.
FIDIC Civil
Construction.
4 th
Engineering
Edition, 1987;
Reprinted in 1988 & 1992
Electrical and Mechanical
works.
3rd Edition; 1987 reprinted.
Design – Build and
Turnkey.
1st Edition; 1995.
Contract
with amendments.
This is recommended for This is recommended for the This is recommended
building or engineering provision of electrical and/or where Contractor takes
works designed by the mechanical plant, and for the total responsibility for the
Employer or by his design and execution of design and execution of
representative i.e. Engineer. building or engineering works. an engineering project.
The Contractor constructs The Contractor designs and The Contractor carries
the works in accordance provides, in accordance with out all the Engineering,
with a design provided by the Employer’s requirements, Procurement and
the Employer. plant and/or other works; Construction (EPC) :
which may include any providing a fully-
However, the works may
combination of civil, equipped facility, ready
include some elements of
mechanical, electrical and/or for operation (at the “turn
Contractor-designed civil,
construction works. of the key”).
mechanical, electrical and/or
construction works.
18
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
3
By : Ajay Kumar Singhal
The 1999 Suit of FIDIC Forms of Contract : The four books are - The 1999 Suit of FIDIC Forms of Contract : The four books are -
Red Book : Conditions of Contract for Yellow Book : Conditions of Contract Silver Book : Conditions of Contract for Green Book : Short Form of Contract.
Construction. for Plant and Design-Build Projects. EPC Turnkey Projects. 1st Edition; 1999
For Building & Engineering works, For Electrical & Mechanical Plant, and 1st Edition; 1999
Designed by the Employer. for Building & Engineering works,
(an update of old Red Book) Designed by the Contractor. The Silver Book is an entirely new The Green Book is an entirely new
1st Edition; 1999 (replaces both old Yellow & Orange FIDIC form for BOT and similar FIDIC form and adopts the overall risk
Book) 1st Edition; 1999 projects. It is intended to be used on philosophy of the Red and Yellow
fixed-price turn key projects. There is Books. It is intended for contracts of
The new Red Book is the traditional The new Yellow Book replaces the no Engineer, instead the Employer relatively small value, short
form for civil engineering construction existing Yellow and Orange Books. It deals directly with the Contractor. Risk construction time or involving simple
in which the Contractor constructs to is intended to be used for Design and is placed largely with the Contractor. or repetitive work. There is no
the Employer's design. There is Build contracts and for Plant Payment is on periods or installments Engineer and the payment
however provision for the Contractor to Contracts. The Engineer administers of the Lump Sum. mechanism is required to be specified
carry out design where specified. The the contract and payment is on in the Appendix to the Form of
form maintains the role of the Engineer periods or installments of the Lump Agreement, but payment is at monthly
and the payment mechanism is based Sum. intervals. It doe’s not matter who
on measure and value. The new Red provided the design. Also it doe’s not
Book revises the previous Red Book matter whether the project involves
version and incorporates current construction, electrical, mechanical,
thinking on the management of 19 or other engineering work. 20
contracts.
Conditions for applicable but there are some Clauses which must
necessarily vary to take into account of the circumstances
and locality of the Works. The Clauses of general application
Works of Civil have been grouped together and are referred as Part I –
General Conditions. The guidelines are given in FIDIC book
☻Concept of responsibility and liability based on sharing of ☻Employer should not restrict the powers of the Engineer other
risks. Risk sharing is balanced. Risk is allocated to the party than the situations where specific approval of the Employer is
that is best able to bear and control that risk. provided in the contract. He should not influence or interfere
with the functioning of the Engineer.
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
4
By : Ajay Kumar Singhal
Essential Features
and Concepts of FIDIC
☻Compensation and time extension allowed when
Various
Important
uncalculated hindrances occur.
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
5
By : Ajay Kumar Singhal
FIDIC Contracts
Notice of Claims (Sub-Clause 53.1 and 53.2 / 53.3 / 53.4 /
53.5) –
Events Entitling
A Contractor intending to make a claim for additional
payment must give notice that he will do so within 28 days of
the event. Thereafter he must keep records including any
Contractor,
Extension of
records required by the Engineer, who will be entitled to
inspect such records. If the Contractor fails to give notice,
keep records or provide details, his entitlement will be limited
by what can be proved from the records that do exist.
Entitling Extension of Time & Cost Entitling Extension of Time & Cost
6.3 / 6.4 6.3 / 6.4 - Disruption of Progress / Delays and Cost 6.3 / 6.4 20.4 - The Employer's Risks are :
a) war, hostilities (whether war be declared or not), invasion (attack), act
12.2 of Delay of Drawings : When planning or execution 12.2 of foreign enemies,
of the Contractor's works is likely to be hampered b) rebellion, revolution, insurrection, or military or usurped power, or civil
war,
20.4 / 65 because of late issue of drawings or instructions by 20.4 / 65 c) ionizing radiations, or contamination by radio-activity from any nuclear
the Engineer, it is important that the notice is given to fuel, or from any nuclear waste from the combustion of nuclear fuel,
27.1 Engineer informing that late issue will have certain 27.1 radio-active toxic explosive, or other hazardous properties of any
explosive nuclear assembly or nuclear component thereof,
29.1 cost and time effects. 29.1 d) pressure waves caused by aircraft or other aerial devices traveling at
sonic or supersonic speeds,
36.5 36.5 e) riot, commotion or disorder, unless solely restricted to employees of
the Contractor or of his Subcontractors and arising from the conduct of
40.1 12.2 - Not Foreseeable Physical Obstructions or 40.1 the Works,
Conditions : Inspite of the pre-tender investigations f) loss or damage due to the use or occupation by the Employer of any
Section or part of the Permanent Works, except as may be provided
42.1 / 42.2 of the Site by the parties, the Contractor may 42.1 / 42.2 for in the Contract,
encounter unforeseen physical obstructions or g) loss or damage to the extent that it is due to the design of the Works,
51 / 52 51 / 52
physical conditions, other than climatic conditions. other than any part of the design provided by the Contractor or for
which the Contractor is responsible,
69.4 The Contractor is required to give the earliest possible 69.4 h) any operation of the forces of nature against which an experienced
notice to the Engineer. 33
contractor could not reasonably have been expected to take
34
44.1 44.1 precautions.
Entitling Extension of Time & Cost Entitling Extension of Time & Cost
6.3 / 6.4 Clause 20.4 should be read in conjunction with 6.3 / 6.4 27.1 - Fossils : For the purpose of the Contract all
12.2 clause 65 (Special risks). Clause 65 makes it clear 12.2 articles of geological or archeological interest
that the Contractor is not liable for the consequences discovered on the Site are considered the property of
20.4 / 65 of Special Risks upon the works or other property nor 20.4 / 65 the Employer. Sometimes contractor suffers, delays
for injury or loss of life. and cost due to Engineer instruction relating to
27.1 27.1
discovery of fossils/antiquities etc.
29.1 Clause 65.3 also, entitles the Contractor to payment 29.1
for rectifying the damage "so far as may be required
36.5 by the Engineer or as may be necessary for the 36.5
29.1 - Interference with Traffic and Adjoining
40.1 completion of the Works“. 40.1 Properties : The Contractor should comply with all
local legislation and regulations and the rules of all
42.1 / 42.2 42.1 / 42.2
public bodies and companies affected by the works.
51 / 52 51 / 52 The Contractor will indemnify the Employer against
any breaches, but the Employer will be responsible for
69.4 69.4 and will indemnify the Contractor in respect of matters
44.1
35
44.1 such as planning permission. 36
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
6
By : Ajay Kumar Singhal
Entitling Extension of Time & Cost Entitling Extension of Time & Cost
6.3 / 6.4 36.5 - Engineer’s Determination where Tests not 6.3 / 6.4 42.1 / 42.2 - Possession of Site and access
Provided for : Where provision of Tests are not Thereto / Failure to Give Possession : If the
12.2 12.2
provided in Contract but tests conducted and it is found Employer fails to provide the Possession of Site (or
20.4 / 65 that materials, plant or workmanship are in accordance 20.4 / 65 portions thereof where appropriate) and Access
with the provisions of the Contract. Thereto in accordance with the requirements of the
27.1 27.1
40.1 - Engineer’s determination following contract / programme.
29.1 Suspension / Suspension lasting more than 84 days 29.1
: If the progress of the Works or any part thereof is 69.4 - Contractor’s Entitlement to Suspend Work :
36.5 36.5
suspended on the instructions of the Engineer and if Contractor’s entitlement to suspend work or reduce
40.1 permission to resume work is not given within a period of 40.1 the rate of work where the Employer fails to pay to the
84 days then, unless the Contractor is responsible for Contractor his due amount. (Here due payment
42.1 / 42.2 the suspension, the Contractor may, by notice to the 42.1 / 42.2
means - Employer fails to pay, the Contractor the
Engineer, require permission, within 28 days, to proceed. amount due under any certificate of the Engineer
51 / 52 51 / 52
If such permission is not granted, the Contractor may
within 28 days after the expiry of the time stated in
69.4 elect to treat the suspended work as omitted or, where 69.4 Sub-Clause 60.10 within which payment is to be
all work has been suspended, treat the Contract37 as
44.1 44.1 made). 38
repudiated (rejected).
Entitling Extension of Time & Cost Entitling Extension of Time & Cost
6.3 / 6.4 51/52 - Variations : Where the Contractor intends to 6.3 / 6.4 44.1- Extension of Time for Completion : In the
claim extra payment in respect of the varied work, i.e. event of delay on account of causes given in various
12.2 12.2 clauses the Contractor is entitled for extension of
20.4 / 65 a) increase or decrease of the quantity of any work 20.4 / 65 time.
included in the Contract,
¾Contractor is required to notify to Engineer with a
27.1 b) omission of any work (but not if the omitted work is to 27.1
copy to Employer, within 28 days after such event
29.1 be carried out by the Employer or by another 29.1 has first arisen.
contractor),
36.5 36.5 ¾Further, within 28 days after such notification,
c) change the character or quality or kind of any work,
Contractor to submit detailed particulars of any
40.1 d) change the levels, lines, position and dimensions on 40.1 extension of time to which he considers himself
any part of the works, entitled.
42.1 / 42.2 42.1 / 42.2
e) execute additional works of any kind necessary for the ¾However, where an event has a continuing effect,
51 / 52 completion of the works, or 51 / 52 Contractor has to submit interim particulars at
69.4 f) change any specified sequence or timing of 69.4 intervals of not more than 28 days and final
construction of any part of the works. particulars within 28 days of the end of the effects
39 40
44.1 44.1 resulting from event.
Events Entitling
dimensions or alignment of any part of the works).
20.3
Alone 58
38.2 - Uncovering and Making Openings : The
Engineer may require, as a consequence of later
discovery, that work already covered up be uncovered
and inspected and tested. Contractor incurs costs for
65.3 / 65.5 testing or uncovering works and such tests or
uncovering shows that the Contractor’s work were not
41
70.2 defective. 42
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
7
By : Ajay Kumar Singhal
FIDIC Contracts
Notices / Information's Required To Be Given by Contractor
Other Important FIDIC
Clause
Requirement for giving Notice / Information’s
FIDIC ……
b) the purchase of materials which are in accordance with
the standards specified in the Contract, or
c) the subcontracting of any part of the Works for which the
Subcontractor is named in the Contract.
45 46
47 48
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
8
By : Ajay Kumar Singhal
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
9
By : Ajay Kumar Singhal
FIDIC Contracts
Notices / Information's Required To Be Given by Contractor
FIDIC Requirement for giving Notice / Information’s
Clause
70.1 Increase or Decrease of Cost : The rise and fall in the cost
of labour, materials etc is to be taken into account in
accordance with a fluctuations clause as set out in Part II
(COPA). That is called Price Adjustment or Escalation and
the formula for calculating the amount is usually defined in
Part – II (COPA) Claim
55 56
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
10
By : Ajay Kumar Singhal
Tips
Tips
1) Be fully conversant with all the Clauses in the
Contract, Technical Specifications, Scope of works
etc.
2) Monitor the job on a day to day basis.
3) Whenever deviation arises in the form of Client’s
requirements through Drawings, Site Orders, Letters
etc. make note of the same and inform to Clients
immediately.
4) If it involves cost implications, same can be indicated
and approval sought.
5) In case of occurrence of delays due to various factors
intimate the same to Clients about it. The exact
duration may be notified later including cost
61 implications at an appropriate time. 62
Tips
6) Correspondence to Clients to be progressively built-
up. Never fail to reply any of Client’s letters.
7) Do not fail to apply for “Extension of Time” well
before the expiry of the contract period with
appropriate reasons.
8) Follow-up with Commercial Department for renewal
of Insurances, Bank Guarantee’s well in time.
9) Be on the look out to get information on certain
relevant details viz. increase in taxes, escalation,
force-majeure conditions etc. which have impact on
the job.
10) Read the contract between the lines and not the
lines alone for better interpretation of the same63to
our advantage.
Contract Management
AKS/TRG-NR/CCM/Rev-0, dated 18-Jan-2009
11