MITDP Closeout Guide v1.0
MITDP Closeout Guide v1.0
Prepared by:
Project Manager
Approved by:
Project Sponsor
Approved by:
Agency CIO
Approved by:
Executive Sponsor
Table of Contents
1 PROJECT INFORMATION 4
1.1 Project Information 4
2 PROJECT SUMMARY 4
2.1 Overall System Satisfaction 4
2.2 Current Cost-Benefit Justification 5
2.3 Needed Changes or Enhancements 5
3 OUTPUTS 5
3.1 Usefulness 6
4 SECURITY 6
4.1 Data Protection 6
4.2 Disaster Recovery 6
4.3 Audit Trails 7
4.4 Allowed Access 7
5 MAINTENANCE ACTIVITIES 7
5.1 Activity Summary 7
5.2 Maintenance Review 7
5.3 System Maintenance 8
Revision History
The MITDP Closeout template is used to assess the effectiveness of the system after it has been in
production for a period of at least six months and ensures all final project information is documented.
The objectives are to determine if the system does what it is designed to do:
● Has the project met all goals and objectives as defined by the project stakeholders?
● Does it support the end user as required in an effective and efficient manner?
● Is the system in a stable operations and maintenance environment?
The review should assess how successful the system is in terms of functionality, performance, and cost
versus benefit, as well as assess the effectiveness of the life-cycle development activities that produced
the system. The review results can be used to strengthen both the system and operations and
maintenance procedures. The report should be provided to both the DoIT EPMO and the agency
stakeholders, which will inform all parties of the system state.
A representative from the functional development group or other member of the major user organization
participates in the review. The system proponent ensures that all documentation and all personnel
needed to participate in the review are accessible. The reviewer and an assigned team collect the
information needed for the MITDP Closeout Review by interviewing end users and their managers,
system administrators and other project personnel.
1 PROJECT INFORMATION
Project Information
Project Sponsor
Project Manager
Project Name/Acronym
Agency
Project Objectives Met (Yes/No)
2 PROJECT SUMMARY
Provide a summary of the overall adequacy, acceptance, and completion of the project. Have all
established deliverables been made? Is there confirmation of project completion? Has a review of
all contracts and documents been done? Release/transfer of resources, lessons learned, and
archive of project documentation completed?
● The extent of the benefits and if they are reported to be less or greater than those
projected in the development analysis and functional requirements report.
● If any difference is permanent or will change over time.
● Is the system cost-justifiable, why, or why not?
● Did the system deliver the anticipated value and how or how not?
● How sustainable is this new system\application?
● Is there an anticipated application lifespan?
3 OUTPUTS
Please evaluate the adequacy and usefulness of the outputs from the new system. Care must be
taken to ensure that all reports are evaluated and that they cite the original intended output and
variances from the new system.
3.1 Usefulness
Provide information on how useful the new system and/or its output is to the end users. Provide
responses in the following areas:
3.2 Timeliness
Determine if output production performance meets user needs. Comments should address the
frequency with which output arrives on time, early, and late; and the amount of follow-up needed to
obtain the output. Previous results - if available - should substantiate new system improvements in
delivering output to meet user’s needs.
4 SECURITY
Please detail the adequacy of system security of data and programs and meet the standards in the DoIT
security policy. In addition to access security, procedures for backup, recovery, and restart should be
reviewed. Please also provide any information as it relates to security assessments performed.
5 MAINTENANCE ACTIVITIES
The purpose of this section is to ensure responsibility for maintenance is assigned and to evaluate
maintenance activity involving the system.
5.1 Activity Summary
Provide a summary of maintenance activity to date and planned cadence. Provide type, number of
actions, and scope changes required. Estimate a projected maintenance workload based on the
findings of the review. Discuss the adequacy of maintenance efforts or if major
enhancement/revision is required.