BhutanSep2024 HandoutDay2
BhutanSep2024 HandoutDay2
198
ICOLD Bulletins:
This is the heart of ICOLD activity. On a single precise
subject, our experts have met during 3 to 5 years and they
produced a « state of the art » with recommendations for
engineers from all over the world.
https://www.icold-cigb.org 199
IHA International Hydropower
Association
https://www.hydropower.org
200
Bank Guidelines
IFC PS
WB ESS
UN
ADB
201
Design Challenges 1
Hydrology
• large seasonal variation
• limited reservoir potential
Geology
• highly folded, faulted, sheared, fractured and
deeply weathered rock mass
• significant underground stability problems
• slope stability
• high overburden and expensive exploration
GLOF
• GLOF-proof design
Sediments
• sediment handling
• equipment erosion
• reservoir depletion
202
Design Challenges 2
Environmental and visual impact
Floods
203
Access Control
Fencing Security CCTV Authorised access
204
Workplace Standards
Emergency exits
minimum two exit possibilities
Lockout-Tagout
No permanent underground workplace
Windows in permanent workplaces
Illumination
Headroom
Stand-by equipment
batteries for emergency lighting
emergency diesel generator
205
Design Philosophy 2 BIM
Vamma:
Units 1-10: 1915-1944
Unit 11: 1971
(in BIM)
208
Turbine cellar (cl turbine)
209
Turbine floor
210
Generator floor
211
Machine hall floor
212
Powerhouse and
Transformer caverns
213
Technology Development
216
Components
Diversion Powerhouse main equipment Auxiliary electrical
weir/dam inlet valve switchgear
pond/reservoir turbine earthing
trash rack generator power and lighting
trash rack cleaner governor cables
intake gate transformer batteries
flood/flushing gates control & protection diesel generator
stoplogs Auxiliary mechanical Switchyard
desander dewatering Transmission lines
Waterways hoisting grid connection
canals cooling water intakes
culverts HVAC Workshop
pipes compressed air Storage for spares
tunnels water
penstock fire alarm
surge tank 217
DAM AND INTAKE
218
Glomfjord, 120MW, Norway
Main Dam Types
219
Intake Pond
220
Xeset, Lao PDR, 45 MW - Intake Weir
221
Xeset, Lao PDR, 45 MW - Intake Weir
222
Canutillar, Chile, 174 MW
223
St Laura, Brazil, 15 MW, RCC Dam – Overflow Spillway
Ecological flow
224
Braskereidfoss, Norway, 40 MW
225
Hunderfossen, Norway, 110 MW
226
Checras Dam, Cheves HPP, Peru
227
Checras Dam Founded on Alluvial Deposits
228
Checras Longitudinal Sections
ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙
𝑠𝑙𝑖𝑑𝑖𝑛𝑔
𝑣𝑒𝑡𝑖𝑐𝑎𝑙
𝑚 229
Ambuklao, Philippines, 3x35 MW
spillway
230
Kotmale, Sri Lanka, 180 MW
231
Altinkaya, Turkey, 700 MW – Rockfill Dam
232
Concrete Gravity Dam Sariyar, Turkey, 160 MW
233
RCC Gravity Dam
790 MW Yeywa HPP, Myanmar
137 m high with a RCC volume of 2.8 mill. m3
234
Arch Dam
Gökçekaya, Turkey, 278 MW
Spillway at saddle on right bank
235
Buttress Dam - Combinations
Buttress
Buttress / arch
237
Spillway Gates 1
238
Spillway Gates 2
239
Bottom Outlet and Flushing Gates
240
Reservoir Flushing
241
Stoplogs
242
Dam Design
Core drilling
Trial adits
Permeability test (Lugeon test)
Grout curtain
Foundation bearing capacity
Sliding - overturning
Spillway capacity
Gates, n-1 principle
243
Diversion Weir - Flood/Flushing Gate
Theun Hinboun, Laos, 210 MW
244
Diversion Weir – Power Intake
245
Intake Types
BIM of Intake (925 m2) – Vamma 12 - Norway Intake (925 m2) – Vamma 12 - Norway
247
Trash Rack
248
Intake Minihydro
Minihydros, Philippines Sediment problems
249
Khimti I, Nepal, 60 MW - Power Intake
250
Cahua, Peru, 46 MW - Desanders
251
Carhuaquero, Peru, 95 MW
Desanders
252
La Higuera, Chile, 155 MW - Pond
253
WATERWAYS
254
Cahua, 43MW, Peru
Esti, Panama, 120 MW - Headrace Canal
255
Itiquira, Brazil, 156 MW – Headrace Canal
256
Coya, Chile, 37 MW - Headrace Canal
257
Peuchén, Chile, 75 MW
258
Slope Stability 1
259
Slope Stability 2
260
Houay Ho, Lao PDR, 150 MW
261
Tunnel
262
Peuchén, Chile, 75 MW
Pangal, Chile, 37 MW
Janopol, Philippines, 5 MW - Surge Tank
264
Itiquira, Brazil, 156 MW
concrete culvert
steel pipe
concrete surge tower
265
Itiquira, Brazil, 156 MW
Surge Tower
266
Air Cushion Surge Chamber
267
Pumped Storage Heredecke, Germany, 153 MW
268
Penstock Configuration in Norway
269
Waterway Design
• Capacity
• Economic optimum size
• Spillways in canals
• Erosion protection in canal slopes
• Fencing of canals
• Excavation method
• Penstock orientation against
stratification
• Rock support in tunnels
• Transients
• Surge tank/shaft/tunnel
• Access for maintenance
270
POWERHOUSE
271
Laudal, 26MW, Norway
Pelton
Powerhouse
Illustration shows
earlier design. Transformer
Turbine
272
Francis Powerhouse
273
Kaplan Powerhouse
274
Turbine Range
• Pelton 300 -2,000 m
• Francis 40 - 700 m
• Kaplan, vertical 10 - 70 m
• Kaplan, horizontal 3 - 20 m
• Crossflow 5 - 40 m
• Turgo 50 – 250 m
275
Turbine Efficiencies
276
Generator
277
Rotor
278
Transformer Principle
279
Transformer
280
Control Room
282
Minihydro
283
Philippines 1MW Kvåle, Norway 5MW
Underground Powerhouse with Portal Building and
Switchyard
284
Powerhouse Layout
400 MW Francis
2 x 160 MW
1 x 80 MW
285
Penstock
286
Powerhouse Section
287
Powerhouse Construction 1
288
Powerhouse Construction 2
289
Access Tunnel and Tailrace
• Surface / underground
• Orientation depending on geological
conditions
• GLOF-proof
• Emergency exits
• Minimum 2 units
• Dimensions and weights of plant
transportable to site
• Accommodation for staff
• Fencing and CCTV
• Visitors allowed?
292
Switchyard
Ambuklao, Philippines, 230 kV
293
Transmission Line
Pylon Types
294