Types of Contracts
Types of Contracts
• Cost Reimbursable
– Cost plus percentage fee (CPPF)
– Cost plus fixed-fee (CPFF)
– Cost plus fluctuating fee (CPIF) (Also called as “Target Estimate”)
– Target Contract
– Guaranteed Maximum Terms (GMP)
1
11-09-2024
2
11-09-2024
3
11-09-2024
4
11-09-2024
5
11-09-2024
6
11-09-2024
7
11-09-2024
8
11-09-2024
Cost plus percentage fee (CPPF) Cost plus percentage fee (CPPF)
• The owner agrees to pay to the contractor the • Bid Documents
actual cost of the work plus an agreed – Notice Inviting Tender
percentage of the actual or allowable cost – Instruction to the Bidders
– Qualification Criteria
– General Conditions of Contract
– Special conditions of contract
– Project Details
– Details of Bid Bonds
Cost plus percentage fee (CPPF) Cost plus percentage fee (CPPF)
• Pros • Pros
– Early completion of the work : The work can be started
even before the drawings, designs, estimates and – Quality of Work : The contractor is assured of a
specifications are prepared; these being prepared as the reasonable amount of profit even though the
work progresses. The decisions can be taken speedily. prices of materials and the labour charges are
These factors lead to the rapid execution of the work.
subjected to fluctuations . Similarly , the use of
inferior type of materials than specified and
– Extra Works : No work or a portion thereof that the
contractor is directed to perform can be called an “extra hurried completion resulting in poor workmanship
work”. This flexibility allows the adoption of alternative do not increase the contractor’s profit. This
ways and methods of construction from which to choose induces him to perform the work in the best
the most economic one for the work as a whole. This may
reduce the cost of the work. Disputes arising due to extra interest of the owner. The final result is therefore
work are eliminated. a better quality work.
9
11-09-2024
Cost plus percentage fee (CPPF) Cost plus percentage fee (CPPF)
• Cons • Cons
– Lack of Incentive : Other than professional ethics – Unpredictability : The final cost is not known to
and goodwill, There is no incentive for the the owner. This may lead the owner to financial
contractor to complete the work speedily, and difficulties. Since profits of the contractor are
economically by proper planning and efficient linked with cost of materials, labour and
management . On the contrary any increase in equipment, a high cost gives the contractor a
the construction cost due to delay, wastage of higher amount of profits. This results in waste,
materials, changes in the drawings and designs inefficiency and extravagance by contractors
result in increase of his profit.
Cost plus percentage fee (CPPF) Cost plus percentage fee (CPPF)
• Suitability
• Cons – When there is an emergency or any other condition that
– Accounts Keeping : Both the parties have to do a requires constructing a facility in a hurry without time to
lot of accounts keeping regarding the materials develop plans for it, neither the employer nor the contractor is
sure about the cost of construction, a ‘cost plus percentage’
purchased and used, the labour and plant contract is generally used
employed and other miscellaneous expenses
incurred on the work. – Works ( in situations which are no emergencies )Where no one
can foretell with certainty just what troubles would be
encountered in the work, and correct decisions cannot be taken
– Illegal for Public Works : Where the owner except during the progress of the work
happens to be a public body or government
department this form of contract cannot be – Construction of expensive structures e.g. palaces, where the
adopted except during emergencies. cost of the work is of no consequences but the materials to be
used and the methods to be adopted are to suit the choice and
taste of the owner
10
11-09-2024
Cost plus percentage fee (CPPF) Cost plus fixed fee (CPFF)
• The owner should exercise great care in • The contractor is reimbursed the actual cost
incurred by him on materials and labour and is
selecting a contractor to carry out the work given a fixed amount of money as his fee.
for him. A person or firm of known integrity , • It has evolved because of the potential for abuse
who will not exploit the weakness of this type in CPPF format
of contract to his advantages, will be the best • The profit of the contractor is not linked with the
choice cost. The contractor receives only the stipulated
sum for his part in overseeing and doing the job,
no matter what the cost of the project may be
• The contractor will, therefore, try to complete the
job as fast as possible, to reduce his overheads
Cost plus fixed fee (CPFF) Cost plus fixed fee (CPFF)
• The agreement specifies the fixed lump sum to be • Mode of Payment, Documents, Suitability
paid to the contractor by the owner over and – Same as CPPF
above the actual cost of the work.
• The employer can select a reliable contractor to
execute the work. The parties can work in
harmony and accomplish amazingly fine results.
• However, there is no incentive for the contractor
to do the work economically
11
11-09-2024
made in this form of contract to overcome the main • The estimated cost ; fee ; contingencies are added to yield the
Guaranteed maximum price
drawback of the previous two types of cost-plus contracts.
• The GMP is the owner’s maximum financial exposure
• This is achieved by suitably changing the nature of the
• The owner agrees to reimburse the contractor for materials, labor
agreement in respect of the fee is determined by reference and the contractor's fee that covers profit.
to some form of sliding scale. Thus higher the actual cost, • The guaranteed maximum price is the highest amount owner would
lower will be the value of the fee that the contractor pay for the project, though if the final price is less than the
receives and vice versa. maximum, the client is not obliged to share those savings with the
contractor unless stipulated in the agreement
12