Sample Prob 1 2 Crashing
Sample Prob 1 2 Crashing
8
J = = S =
i
CRITICAL PATH =
A -
C -
E
(=
S = 1 5= 1
-
CRASH #
.)
a
Key PONTS IN CRASHING (CHOOSING WHAT TO CRASH AT MINIMA COST
·
3 = 5
13 DAYS DURATOT
STAYS
CRITICAL PATH
THE SAME
TOTAL COST-1200
CRASH C
PATH
iii
b) S = 1
New CRITICAL
B -
D -
#100 00
s
.
CRASH B
·
S = =
* -
4 -
#
S y
=
B -
D -
#
f =
Kost: Jo
CRASHD BY IDAY
COST : 900 .
28
-
CRASH A BY 1 DAY
i
10 DAYS DURATION
-
costo
C )
.
To get the minimum completion time, try crashing all activities to its maximum crash time. Then try
crashing activities only on the critical path ( first critical path). Compare the two. If the two
completion times differ, it indicates that the critical path has shifted as a result of crashing all
activities. This happens because crashing some non-critical activities may have created new paths
with durations as long as the original critical path, effectively changing which activities are critical.
In this case, the critical path is not consistent throughout the crashing.
ANSWER : 8 DAYS
CRASH, =
CC -
NC
CosyPeriod TuT-CT
S
-
S
2 3 .
& 20 000
,
35, 508 5888 .
88
3
4 40, 808 70 , 080 38 , 800 58
%
2
-
.
2 -
4 8 z z z
11, 088
i
i
4 S -
Sor 2888 85 .
4 -
6 588, 000 710 , 208 78 , 888 .
88
i
5-6 588 11 , 000 2888 . 88
6 7 -
158 000
, 220 , 000 78 888,
:
50
S= 8
·
S = 5
·
*
DURATION = 35 Weeks
3
CRITICAL PATH = (1 2)
- -
( 3)
-
-
13 -4) ,
(4 6)
-
=
(6 7)-
9) TO GET 30 Weeks TRY CRASHING THE PROJECT BY 6 Weeks
* THERE ARE ALSO X LOT OF COMBINATION OF ACTIVITIES THAT YOU CAN CRASH TO GET 38 WeeK]
a) If AT MINIMUM COST :
CRASH ACT . (12) By S weeks it will become 7 weeks
Eter
·
S =
=
&
J= 3
ANOTHER ONE:
·
S = 8 EXTRA COST
s(4000) + 70 ,
000
out
- 5= 4
-
d. -= 5
To get the minimum completion time, try crashing all activities to its maximum crash time. Then try
crashing activities only on the critical path ( first critical path). Compare the two. If the completion
time for crashing all activities matches the completion time for crashing only the critical activities, it
suggests that the critical path is consistent throughout the crashing process. This means that the
same set of activities continues to determine the project duration, even after crashing.
ANSWER : 24 WEEKS
#;
COST (KRASHING CRITICAL ACTIVITIES ONLY) = 5(4000) +
3(500) + 3(70 000)
,
+ 1175, 000)
= 315 800
, .
88