Check List 30 May
Check List 30 May
CONCRETING OPERATIONS
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
REINFORCEMENT WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
1 Is the bar bending schedule approved by the client?
Is the reinforcement steel stacked on a raised
2 platform minimum 300 mm above ground level?
Are the reinforcements free from dirt, grease, oil and
3 paint?
Are the reinforcements tested for rolling margin and
4
approved by clients and are the records
maintained?
Are the reinforcements tested from external agencies as
5
per contract agreement?
Are the rods cut & bent as per the approved BBS?
6
Before placing rods, is the centering leveled and mould
7 release oil applied?
Is placing of the rods (spacing, position of the bars, etc)
8 as specified in the structural drawings?
Are laps staggered and provided only at the approved
9 locations of the structure?
Are laps in column avoided at column beam junctions?
10
Are the lap lengths provided as per structural drawings?
11
Is the cover to main reinforcement provided as per
drawing?
Footing bars Bottom
Sides
12 Column bars Sides
Slab bars Bottom
Sides
Beam bars Bottom
Sides
13 Are sufficient No. of covers to reinforcements provided?
Are spacer bars provided in between layers of
14 reinforcements in beams?
Are the layers of steel in beams tied properly in position
15 as per drawing to avoid any dislocation while
concreting?
Are sufficient chairs provided to keep the layers of steel
16 in position at slab, raft, etc?
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Is the welding of reinforcement steel, mechanical splicing
17 (if any) done only with prior approval of structural
consultant?
Are any dowel bars to be provided?
18
Are reinforcing bars in slab, beam, footing etc, properly
19 tied?
20 Is proper binding wire used for tying bars?
Is the substitution of bars (if any) done only with prior
21 approval?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
SHUTTERING WORK FOR FOUNDATIONS
Project / Job No. Location:
Project Name Area/ Quantity
Drawing No. Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No Engineer
Check the marking done as per drawing
1 measurements
Check the inner measurements of foundation sides
2 shuttering
Check the supports / tie rods provided are sufficient
3 to take the concrete pressure.
Check whether form work is erected over the
4. marking and the column marking is exactly at the
centre.
whether gaps between shuttering boards are sealed
6 with masking tape?
7 Check for right angle of formwork.
8 Whether mould release oil is applied on the boards?
Whether proper cover is maintained to the
10 reinforcement bars?
12 Check for stability of scaffolding around column.
13 Check for vertical stability, plumb before concrete
14 Check for vertical stability, plumb after concrete
Is the working platform and safety arrangements
15 are adequate?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
SHUTTERING WORK FOR COLUMN AND WALL
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No Engineer
A COLUMN AND BEAM
1 Has the marking/starter been done as per drawings?
Have the inner measurements of column boxes /
2
wall shuttering been checked?
Are the No of veilors/tie rods provided sufficient to
3 take the concrete pressure? (Minimum spacing of
veilor 600 mm).
4. Is the form work erected exactly over the marking?
Are the No of supports provided enough to keep the
5
verticality of the column / wall?
Have the gaps between shuttering boards at corners
6
been checked?
7 Has right angle of formwork been checked?
Is mould release oil applied on column box / wall
8
panels?
Has thermo foam been provided around the bottom
9
surfaces?
Has the check for water tightness of form work
10
been carried out?
11 Has the verticality of form work been checked?
12 Has the stability of scaffolding been checked?
Have vertical stability & plumb been checked
13
before concreting?
Have vertical stability & plumb been checked after
14
concreting?
Are the working platform and other safety
15
arrangements adequate?
If Starters are not Cast
Has the alignment of the starter angle provided with
1
the marking been checked?
Has any anti corrosive paint applied on the face of
2
the angle?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
SCAFFOLDING WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Have the welded joints of all supporting members
1
been checked?
Is the scaffolding erected on well compacted level
2 ground / concreted surface?
3 Are the verticals in plumb?
Are the horizontals properly fixed in the cups and
4
the caps tightened properly?
Is the scaffolding properly anchored to the structure
5
at sufficient intervals?
Are the base plates used for verticals?
6
Is it ensured that the U heads and base plates are
7 not extended beyond 300 mm from the vertical?
Are proper connecting pins (square/round pipe with
8 bolt fixing) used for joining the verticals?
Are cross bracings provided if the height of
9 scaffolding is more than 4.00 mtrs?
Is it ensure that no eccentric load is placed on the U
10 head / base plate?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
EARTH WORK EXCAVATION
Project / Job No. Location:
Project Name Area/ Quantity
Drawing No. Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Checks Before Excavation
Whether drawings, specification details for
1 finalization of earth work checked?
2 Is the Excavation plan sanctioned?
Are the co-ordinates, bench mark, grids etc marked as
3 per plan at site?
4 Whether initial ground level taken?
5 Has the required depth of excavation been checked?
Whether any existing service lines to be protected? Or
6 re- located?
7 Is any statutory approval for excavation required?
8 Whether disposal area of the excavated earth is approved?
Is the required manpower, machinery etc arranged for
9 the work?
10 Is the arrangement for dewatering satisfactory?
After Excavation Checks
1 Whether shoring/nailing done as per requirement?
Whether re location of existing services done as
2 per requirements?
Whether final trimming is done as per the
3 required measurements?
Has the bottom of excavation checked? (Indicate RL
4 in remark column)
Whether sufficient working space is available on all sides?
5
Whether edges of excavation barricaded and proper
6 safety signage's provided?
Whether the edges of excavation clear and excavated
7 materials are kept away from the sides?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
EARTH FILLING
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No Engineer
Is filling material approved?
1
Are there any debris, brick bats and vegetation
2
mixed with filling material and have these been
removed?
Have all scaffolding materials and other
3
building materials been removed from the filling
area?
Are all service lines, manholes, benchmarks etc,
4 in the filling area protected?
Is the methodology of filling approved by client?
4
Is filling carried out in layers not exceeding 30cm /
5
as per specifications?
Has each layer of filling been compacted using
6
earth compactor or roller?
Is the filling soil containing optimum
7
moisture content?
Is the degree of compaction as per specifications?
8
Is the top surface trimmed and leveled as specified?
9
Has the top level of filling been checked?
10
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
ANTI-TERMITE TREATMENT
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No Engineer
Whether the earthwork for the area to be treated
1 is completed?
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PCC
Project / Job No. Location:
Project Name Area/ Quantity
Drawing No. Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No Engineer
Whether the soil surface is trimmed / compacted
1 properly to the specified level/slope?
Is the soil surface free from standing water, mud,
2 debris, soft or yielding soil?
Whether the soft or yielding soil pockets (if any) have
3 been removed and filled with approved soil/lean
concrete?
Has the bottom RL of excavation with respect
4
to bench mark been checked?
Whether button marks are kept as per thickness
5
and level specified?
Are the materials adequate for the work?
6
Is proper machinery for mixing available?
7
Have the mix proportions of concrete been checked?
8
Is the compaction sufficient?
9
Is the top surface finished to level / slope as
10
specified in the drawing?
Is curing sufficiently carried out?
11
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
BLOCK MASONRY
Project / Job No: Location:
Project Name: Area/ Quantity
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Before Masonry Works
1 Whether blocks are wetted prior to use?
2 Is the size and shape of Blocks are as per drawing?
3 Whether the blocks are tested for compressive strength?
Whether the concrete surface is hacked properly at the
3
junction of concrete and masonry?
4 Is the Cement-Mortar ratio as per specifications?
5 Whether the starter course that has been done is approved?
6 Have you checked the room dimension, diagonals etc?
7 Whether housekeeping is done satisfactorily?
Have you checked whether the openings of doors, cutouts
8
are as per drawing?
9 Are working platform & safety arrangements adequate?
After Masonry Works
Whether thickness of vertical / horizontal mortar joints is
1
maintained within 6 to 10 mm?
2 Are the horizontal courses in water level?
3 Are the joints properly packed and raking is done?
4 Have you checked the plumb of the masonry?
5 Whether vertical joints are staggered in each layer?
Whether reinforcement steel is provided at each 4th layer
6
of 100 thick block masonry?
7 Have you marked date of construction over masonry?
Whether the measurements of openings provided with
8 allowance for plastering?
Is it ensured that the gaps between top layer of block
9 work & beam/slab soffit are within 10 mm and
filled
properly?
If the of filling between top layer and beam / slab soffit is
10 more than 25 mm, has it been filled with screed
concrete?
11 Whether curing has been done for 7 days?
Whether thickness of vertical / horizontal mortar joints is
12 maintained within 6 to 10 mm?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
BRICK MASONRY
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Sl. Remarks
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Before Masonry Works
1 Whether the bricks are soaked in water prior to use?
2 Is the size and shape of bricks as specified?
3 Whether the bricks are tested for compressive strength?
Whether concrete surface at brick work junction is hacked
3
properly?
4 Is the Cement to Mortar ratio as per specifications?
5 Has the starter course that has been done, got approved?
6 Are room dimensions & diagonal measurements checked?
7 Whether housekeeping is done satisfactorily?
Have you checked whether the openings of doors, cutouts
8
are as per drawing?
9 Are working platform & safety arrangements adequate?
After Masonry Works
Whether thickness of vertical / horizontal mortar joints is
1
maintained within 6 to 10 mm?
2 Are the horizontal courses in water level?
3 Are the joints properly packed and has raking been done?
4 Have you checked the plumb of the masonry?
5 Whether vertical joints are staggered in each layer?
Whether reinforcement steel is provided at each 4th layer
6
of half brick thick masonry?
7 Have you marked date of construction over masonry?
Whether the measurements of openings provided with
8
allowance for plastering?
Have you ensured gaps between top layer of brick work
9 and beam/slab soffit are within 10 mm & filled
properly?
If the filling between top layer and beam / slab soffit is
10 more than 25mm, has it been filled with screed
concrete?
11 Whether curing is done for 7 days?
Whether thickness of vertical / horizontal mortar joints is
12
maintained within 6 to 10 mm?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
MEMBRANE WATER PROOFING
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Have the structural cracks (if any) been repaired
1 properly?
Has all loose concrete, loose particles, set mortar, etc been
2 removed and cleaning done properly?
Are there any protruding bars from the concrete surface to
3
be treated?
Has primer coat been applied on the entire surface
4
without leaving gaps? Coverage area of primer is
0.24 ltr/m2
6 Is the grade of bitumen as per specifications?
Has the bitumen been used at the rate of 1.5 kg/m2 for
7 every course treatment?
Has the procedure for laying bitumen felt been followed
8 as per Work Instruction?
Is correct method of laying of bitumen felt followed that
9 is from the lowest level to highest level?
Is pressing of the felt using wooden or similar flat against
10 hot bitumen for proper adherence, carried out?
Are the joints of the bitumen felts staggered while laying
11 succeeding layers?
Is the overlapping of the bitumen felt 75 mm at the ends
12
and 100 mm on the sides?
Is grit or gravel provided at the rate of 0.6 cum / 100 m2
13 for non accessible floors?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
CEMENT GROUTING WORK
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
1 Is the depth of drilled hole as specified?
Has dust from the drilled holes been removed using
2
air blower?
3 Is fixing of nozzles done using proper chemicals?
Are honeycombed areas covered using polymer
4
modified or similar mortar material?
5 Is the w/c ratio for grouting within 30 ltr per bag?
Is the specified non shrinking material used for
6
grouting purposes?
Is it ensured that grouting of nozzles is carried out in
7
a staggered manner?
Is the pressure gauge fitted to the grouting pump
8
working properly?
Is curing done for a minimum of 7 days for the
9
treated area?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PLASTERING WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Before Plastering
Is the type of finish specified in the drawing checked?
1
2 Has the masonry work been completed in all respects?
Are all door and window frames fixed truly in line and
3 level?
4 Is location of door/ window openings as per drawing?
Are all electrical and plumbing works
5
concealed
completed?
Are all the wall chasing grooves properly filled with
6 mortar and plaster mesh fixed over that?
7 Is the area of cladding identified?
Has hacking been done to the RCC surfaces where
8 plastering is to be provided?
9 Are masonry joints raked properly?
Has the fixing of wire mesh/ expanded metal lathe, corner
10 beads, etc completed as per specification at RCC/
masonry junctions?
Has the surface to be plastered, been cleaned of all dust,
11 loose mortar dropping etc and dampened prior to
plaster?
Is button marking done for plumb and is the thickness of
12 plastering as specified?
13 Is button marking checked for right angles?
14 Are the room dimensions ok after button marking?
15 Is the skirting level marked?
16 Are the ceiling button marks in water level?
Have the electrical switch boxes, fan boxes, etc, plumbing
17 points etc, been identified and protected properly?
Are proper scaffolding and working platform, etc
18 provided?
Is proper lighting arranged?
19
Are measurement boxes available for mortar mixing?
20
21 Does the sand for plaster conform to the requirements?
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
After Finishing
1 Is the proportion of the mortar used as per specification?
2 Are line, level, verticality of the surface checked?
3 Have all the button marks been removed?
4 Are the surface finish and evenness satisfactory?
5 Are all the corners at right angle?
Have you checked cleaning of mortar droppings on
6 nearby walls?
7 Is rough finishes done for cladding area?
8 Is the thickness of lime within limit for lime finish plaster?
Are the door, window jams- verticality and finishes done
9 properly?
Have the door/window frames, electrical boxes, plumbing
10 points etc been cleaned properly after plastering?
11 Have you checked the grooves for their line and finishes?
Has the cutting and removal of plaster at skirting level
12 been done properly?
Are close dents made on under layer plaster surface where
13 double coat plaster is to be done?
Is the under layer plaster allowed to set for minimum
14 three days before finishing coat?
15 Is the date of plastering marked on the wall?
16 Is curing done properly?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
TILE FLOORING & DADOING
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Has plastering been completed in all respects and
1
are verticality & right angle maintained?
2 Are room dimensions as specified?
Has the tile layout drawing been checked? Is it ensured
3 that cut tiles are located in the least prominent
places?
4 Are the tiles of approved make and quality?
Are the tiles checked for damages, shade variations, etc
5
and have defective tiles been segregated?
6 Are the ceramic tiles soaked in water prior to fixing?
Have all plumbing, electrical and other concealed service
7
lines been completed at the tiling area?
Have the finished levels, wall cladding lines etc been
8
marked with sufficient button marks?
Is the floor/wall surface cleaned properly and
9
wetted prior to tiling work?
Is specified bedding material (CM/tile-adhesive)
10
used?
Have the tiles been fixed firmly on the bedding
11
material and is the gap between tiles uniform?
12 Is the tiling pattern, border, colour etc as specified?
12 Is the height of skirting/dadoing as specified?
Have the corner beadings and tile spacers (If
12
specified) been provided?
Have the tile joints been grouted with approved
13
grouting material?
Has the excess grouting materials been wiped off
14
and is the tile surface cleaned properly?
15 Is finished surface checked for evenness / slope?
Is there any hollow sound on the finished tile
16
surface? If yes, the tiles must be replaced.
17 Is top of skirting and dadoing finished as specified?
18 Are the curing arrangements adequate?
Has the tile surface been protected with POP layer
19
or any other suitable material?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
MARBLE/GRANITE WORK
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Are the slabs of uniform colour & thickness
1
and are they free from cracks, stains, decay, etc?
Are the stones cut to proper sizes and are the edges
2
smooth and in right angle?
3 Has proper mirror polish been done to the surfaces?
Has the floor been cleaned properly and wetted prior to
4
laying of marble/granite?
Has preparation of the bedding mortar been checked and
5
are the proportion & thickness as specified?
Are the slabs laid properly and seated over the mortar by
6
gently tamping with wooden mallet?
Are the joints between slabs proper with less than 1 mm
7
thickness?
8 Is the top level of the slab as per specifications?
Are the joints cleaned of cement; and grouted with
9
suitable grouting material?
Has the grinding process of marble slabs (for un
10
finished slabs) been done as specified?
Has the polishing of the surface been done as
11
specified and is the surface smooth & even?
Is the nosing/chamfering of the edges and polishing
12
of counter slabs done properly?
13 Is the wall cladding/skirting level as specified?
Is the wall cladding/skirting fixed properly? Is there
14
any hollowness observed?
Has proper supporting structure (RCC slab / steel
15
frame) been provided for the counter slab?
16 Are the openings for sinks & basins as specified?
17 Are the edges of sinks/basins sealed with sealants?
18 Are proper curing arrangements made?
19 Is protection of granite slab done using POP?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
FIXING OF GRILLS AND HAND RAILS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Is the grill/hand rail sample approved?
1
Has the fabrication been done as per drawings?
1
Are the weights, sizes and measurements of the
2
elements used as specified?
Is the straightness, curves, pattern etc of the elements
3
as per drawing?
Are all joints of the grills/hand rails welded properly?
4
Has proper filling & grinding of welded joints been
5
done satisfactorily?
Have sufficient number of grip bars been provided on
6
all sides for fixing to the masonry?
Has one coat of red oxide / anti corrosive primer
8
been applied on handrails/grills before fixing?
Are the grills/handrails fixed with concrete blocks /
9
anchor bolts as specified?
Are the handrails/grills fixed in position, line, and
10
level as specified?
Are correct measurements, size diagonal of grills/
10
handrails ensured before fixing?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PLUMBING WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
1 Are the pipes & fittings conforming to specifications?
2 Are the fixtures as per the approved samples?
Have you checked whether the pipes, GI specials, CP
3
fittings, etc are without any visual cracks?
Is the plumbing layout marked as per the approved
4
drawings?
Is chasing done using proper tools and is the size of
5
the chasing as per requirement?
Are the finish floor level and the level of fixtures
6
marked as per approved drawings?
Has joining of the pipes been done as per the
7
approved methodology?
Are the pipes clamped properly to prevent any dis-
8
location while filling and tiling?
Are the branch connections of threaded pipe lines
9 provided with unions/flanges for easy
maintenance?
Are the concealed GI lines painted with bituminous
10
paints?
Are outlet connections of the water tanks provided
11
with isolation valves?
Are all vertical lines true in plumb and levels
12
maintained for horizontal lines?
Are all hot water lines wrapped with elastomeric
13
insulation?
Has pressure testing been done up to 7 kg/cm2 for a
14 min of 24 hrs & recorded in the presence of
clients?
Are all plumbing lines at least 30 mm inside from the
15
finished wall surface?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
SANITARY WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Are all sanitary pipes & fixtures conforming to the
1
type/quality as specified?
Have all the components been checked for any
2
visible damages.
Has proper pipe sizing of all services and pre-
3 installation details been carried out prior to
final fixing of the appliances?
Are vertical stack & horizontal runs adequately
4
supported?
Have access points been provided to the drainage
5
lines as specified?
Is the position of floor trap; Nahani trap, etc as per
6
drawings?
Has the joining of pipes and other components been
7 done as per specifications & are the joints
air/water tight?
Are the sanitary appliances installed as per the
8 specifications & are position and level
maintained?
9 Is the slope provided for the drainage lines adequate?
Are the sanitary appliances protected properly from
10
damages?
Are the contact edges of the sanitary appliances and
11
wall sealed with sealants?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PROJECT ELECTRICAL WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
First Fix Installation
1 Is the routing of conduits as per drawing?
2 Have adequate Nos. of conduits been laid?
3 Have the conduits been fixed in position securely?
4 Are pull boxes provided as per requirement?
5 Are junction boxes provided as per requirement?
Are junction boxes / pull boxes provided flush to the
6 finished surface?
Are the back boxes / templates fixed properly?
7
Are the conduits cleared after civil works & is GI wire
8 pulled?
Wire Pulling
Are the type and size of wires as per the approved
1 diagram?
Are required No of wires as per the diagrams pulled
2
through conduits?
Have different coloured wires as per the approved scheme
3 been used for phase and neutral?
Are the phase and neutral of particular circuits pulled
4 through same conduit?
Final Fix Installation
1 Are switch boxes along with required switches fixed?
2 Are the socket outlets installed as per drawing?
Are the location and type of light fittings installed as per
3 the drawings?
Are the ceiling fans and other fixtures as per
4 specification
?
Has termination of wires in switch boxes / socket outlets,
5 fittings been completed?
Are the type, model and rating of DBs as per
6 specification?
Is the fixing, leveling and alignment of the DBs checked?
7
8 Is earth resistance from DB to grid checked?
9 Is the outgoing feeder rating checked?
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Is the ELCB rating as per the single line diagram checked?
10
Testing
Is voltage at incoming terminals of DB checked?
1
Is earth resistance of DB to grid checked?
2
Is operation of MCBs / ELCBs checked?
3
Is availability of power at end terminals and sockets
4 checked?
Is operation and control sequence of switches checked?
5
Is operation of light fittings, ceiling fans and other
6 fixtures checked?
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PAINTING ON PLASTERED SURFACES
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Has plastering work been completed in all respects
1
and are the walls dried after the curing period?
Is the surface cleaned from dirt, dust, etc and has any
2
crack, damage etc. been rectified?
Is the type, shade, and make of the paint approved
3
and is the sample work also approved?
Are the surface of doors, windows, floors, and other
4 appliances protected from being splashed
upon?
Are the painting materials in good condition and
5
within the expiry date.
6 Is the priming coat applied to the wall as specified?
Is it checked that the application of the putty (if
7
specified) to get an even and smooth surface?
Is the mix proportion of the paint as per the
8
manufactures specification?
Is the application of the paint done as per the
9
specified method (by brush, roller or spray)?
Are there brush/roller marks visible after
10
any
painting?
Is it ensured that the final coat of paint is applied
11
after 6 – 8 hours of first coat?
Does the finished surface have evenly spread of paint
12
with smooth surface and uniform colour?
Have proper safety equipments and working
13
platforms been arranged for the work?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
INTERNAL ROAD WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
WATER BOUND MACADOM
Are the layout, gradient and camber of the road as
1
per the latest drawings?
Is the sub grade prepared as per the layout & gradient
2 and compacted to required degree of
compaction?
Is the course aggregate as per specification, free from
3
flat elongated and soft stones?
Is the binding material (murram / quarry dust) as per
4
specification?
Has the spreading of the aggregate and the binding
5
material been checked?
Has compaction been done with 8-10 T power/
6
vibratory roller up to the required No. of runs?
Is the sequence of rolling followed as per
7
specification
?
Has the application of screening material been
8
checked?
Has the application of roller after spreading of
9
screening material been checked?
Has the surface been applied with sufficient amount
10
of water and rolled to fill the voids?
Has binding material been applied to prevent
11
reveling of WBM?
12 Has the compacted thickness been checked?
Has the camber and gradient after finishing been
13
checked?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
INTERNAL ROAD WORKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
BITUMINIOUS CARPET
Is the aggregate as per specification, free from flat
1
elongated and soft stones?
Is the sand of approved quality?
2
Is the bitumen as per specification?
3
Has the mixing of premix carpet been checked?
4
Is the surface cleaned properly prior to application of
5
tack coat?
Is the tack coat applied as per the specification?
6
Is the application of the premix carpet checked?
7
Has rolling been done with 8-10 tonne power /
8
vibratory roller to the required amount?
Has the preparation of premix seal coat been
9 checked?
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
INTER LOCKING PAVER LAYING
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PREVENTION OF BULGING & UNDULATIONS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Are the column beam junctions supported
1
properly with tie-rods / C clamps
Are the beam sides in true line & level and properly
2 tightened with tie rod / C clamp to prevent any
bulging?
Whether the columns are concreted up to the beam
3
bottom to avoid ‘gabris’
Check whether the slab shuttering work is properly
4 leveled
Check whether all the floor form sheets/ slab
5
panels are in uniform level
Are the supporting members are rested on firm and
6
level surface to prevent sinking?
7 Are the supports provided truly in vertical?
Check whether the centering work is tighten properly
8
and gaps are sealed with masking tape?
Check whether trained workmen are used to
9
erect the shuttering work
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PREVENTION OF HONEY COMBING & SLURRY LEAKAGE
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
No DESCRIPTION YES NO N/A Initials of Site
Engineer
Are the shuttering boards/plates are tighten
1
properly to prevent grout loss?
Check whether proper water cement ratio is ensured
2
for workability and also to avoid segregation
Whether proper aggregates are used to get cohesive
3
concrete mix?
Are the joints of old & new concrete sealed with
4 form material to avoid slurry leakage?
Whether proper cover blocks are used to
5
prevent exposing of reinforcement?
Check whether extra care is taken at heavily
6 reinforced column beam junctions while
concreting.
Check whether properly trained workers are
7
operating the vibrators.
Whether the slurry leaked (if any) is cleaned
8
immediately after the concreting work
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date:
QUALITY INSPECTION REPORT
PREVENTION OF WASTAGE OF CONCRETE BLOCKS
Project / Job No: Location:
Project Name: Area/ Quantity:
Drawing No: Date:
Remarks
Sl.
DESCRIPTION YES NO N/A Initials of Site
No
Engineer
Are the concrete blocks are of good Quality
1
and well cured?
Whether the blocks are unloaded in level surface and
2
No. of layers are minimum
Whether he blocks are unloaded /shifted with care to
3
prevent damages?
Whether proper arrangements (hoist, wheel barrows,
4 tower crane buckets, etc.) are provided for
shifting blocks
Whether proper cutting tools are used for
5
cutting of blocks?
Whether readymade half blocks are used instead of
6
cutting full blocks?
Whether the No. of blocks required for the work only
7
is shifted to the work place to avoid wastage?
Comments if any: Comments if any:
Signature: Signature:
Name of Client: Name of Contractor:
Date: Date: