Feng Shun - Daily Report (28!05!2024)
Feng Shun - Daily Report (28!05!2024)
Trail trench No-20 backfilling and compaction works has done. Management Staff 4
Then start to excavate MH-21A-TT21,excavation reach to 700mm Project Director 1
from ground level,found singtel cable. Project manager 1
Phase 2 MH-E20A&21A
Project Engr 1
9th Cage ladder fabrication and welding works in progress WSH Coordinator 1
Site Staff 9
Site Supervisor 1
Asst Site Foreman - Trial Trench Excavation - MH-E20A -TT20
Machine Operator 1
Lifting Sup. 1 Picture
Rigger/signalman 2
Banksman 0
Land Surveyor -
welder 2
General Workers 2
C. Material Excavated
Hard soil Excavated 1.1 cum Dump near by site,backfill later
Cum