Shishinda-Teppi Direct Cost Analysis
Shishinda-Teppi Direct Cost Analysis
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Clearing &Grubbing)
1 Clearing & Grubbing Ha 1 Dozer 1 750 8 6,000.00 Doz. Operator 1 8 2.27 12.02 218.27 Fuel Lit 327.5 5.6718 1,857.51
S/ V 1 30 2.5 75.00 Grade Checker 1 8 2.27 3.25 59.02 Lub(10% fuel) 185.75
Equpiment Total 6,075.00 Manpower Total 363.43 Material Total 2,043.27 8,481.70 8,481.70
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Common Excavation To Waste)(Case I)
1 Excavation To Waste m3 648 Dozer 1 750 8 6,000.00 Dozer Operator 1 8 2.27 12.02 218.27 Fuel Lit 327.5 4.36 1,427.90
Small Vehicle 1 30 2.5 75.00 Grade Cheker 1 8 2.27 3.25 59.02 Lub(10% fuel) 142.79
Equpiment Total 6,075.00 Manpower Total 307.59 Material Total 1,570.69 7,953.28 12.27
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Common Excavation To Waste)(Case I)
Case 2:- Waste by Dump Trucks .
OUT PUT EQUIPMENT MANPOWER MATERIAL
Total Direct Total Cost
SN ACTIVITY Hourly
Total OP Index Hourly Total Cost per Unit
Unit Quantity Type No Rental OP Hr Trade No Type Unit Quantity Unit Price Total Amount
Rental cost Hr factor Wage Salery
Rate
1 Excavation To Stock m3 648 Dozer 1 750 8 6,000.00 Dozer Operator 1 8 2.27 12.02 218.27 Fuel Lit 327.5 5.6718 1,857.51
out put for Dozer =81m3/hr S/ V 1 30 2.5 75.00 Grade Checker 1 8 2.27 3.25 59.02 Lub(10% fuel) 185.75
Equpiment Total 6,075.00 Manpower Total 341.58 Material Total 2,043.27 8,459.85 13.06
Loader 1 180 3.51 631.80 Loader Operator 1 3.51 2.27 5.77 45.97 Lub(10% fuel) 89.44
(houling distance for dump truck =3
km round trip) S/ V 1 30 2.5 75.00 S/V Driver 1 2.5 2.27 2.84 16.10
Capacity 12m 3
Helper 1 8 1.42 1.13 12.78
303.157894736842 Equpiment Total 1,606.80 Manpower Total 215.06 Material Total 983.89 2,805.75 9.26
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Common Excavation To Embankement)(Case I)
1 Excavation To Stock m3 648 Dozer 1 750 8 6,000.00 Dozer Operator 1 8 2.27 12.02 218.27 Fuel Lit 327.5 4.36 1,427.90
S/V 1 30 2.5 75 Grade Checker 1 8 2.27 3.25 59.02 Lub(10% fuel) 142.79
Equpiment Total 6,075.00 Manpower Total 303.77 Material Total 1,570.69 7,949.46 12.27
2 Embankment Material Hauling m3 303.157895 D/T 1 112.5 8 900.00 Truck driver Driver 1 8 2.27 4.47 81.20 Fuel Lit 134.7 4.36 587.29
Loader 1 180 2.36 424.80 Loader Operator 1 2.36 2.27 5.77 30.91 Lub(10% fuel) 58.73
(houling distance for dump truck
=3km round trip) S/V 1 30 2.5 S/V Driver 1 2.5 2.27 2.84 16.10
Capacity 12m3 Equpiment Total 1,324.80 Manpower Total 153.29 Material Total 646.02 2,124.11 7.01
Water Truck 2 50 8 800.00 Roller Operator 1 8 2.27 2.88 52.38 Lub(10% fuel) 195.11
(houling distance for water truck
=13km for round trip) Roller 1 120 8 960.00 Forman 1 8 2.27 6.73 122.23
Equpiment Total 4,395.00 Manpower Total 683.75 Material Total 2,146.21 7,224.96 12.90
4 Sub Grade Finishing m2 2800 Grader 1 320 8 2,560.00 Grader Oprator 1 8 2.27 24.04 436.54 Fuel Lit 367.5 4.36 1,602.30
Water Truck 1 50 8 400.00 Roller Operator 1 0.25 2.27 2.88 1.64 Lub(10% fuel) 160.23
(houling distance for water
truck=13km round trip) Roller 1 120 8 960.00 Forman 1 8 2.27 6.73 122.23
Out Put for Grader 350m Daily Labourer 8 8 1.42 1.25 113.60
Equpiment Total 3,995.00 Manpower Total 746.60 Material Total 1,762.53 6,504.13 2.32
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Rock Excavation To Waste)(Case I)
Small Vehicle 1 30 2.5 75.00 Dozer Operator 1 2.4 2.27 4.33 23.57 Lub(10% fuel) 158.49
Out put for Excavator =15m 3/hr Dump Trucks 1 100 10 1,000.00 Dump Truck Driver 1 10 2.27 4.33 98.22 -
Out put for Dozer =50m 3/hr Dozer 1 450 2.4 1,080.00 Small Vehicle Driver 1 2.5 2.27 2.64 15.01
Round Trip=3Km Equpiment Total 5,755.00 Manpower Total 312.52 Material Total 1,743.35 7,810.87 65.09
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Borrow Excavation )
1 Borrow Production m 3
648 Dozer 1 450 8 3,600.00 Dozer Operator 1 8 2.27 9.62 174.62 Fuel Lit 327.5 4.36 1,427.90
S/ Vehicle 1 30 2.5 75.00 S/V Driver 1 8 2.27 2.64 48.02 Lub(10% fuel) 142.79
Equpiment Total 3,675.00 Manpower Total 236.83 Material Total 1,570.69 5,482.52 8.46
2 Borrow Material Hauling m3 144 D/T 1 100 8 800.00 Dump Truck driver 1 8 2.27 4.33 78.58 Fuel Lit 125.5 4.36 547.18
Loader 1 250 1.9 475.00 Loader Operator 1 1.9 2.27 6.73 29.03 Lub(10% fuel) 54.72
(houling distance for dump truck
=10km round trip) S/ Vehicle 1 30 2.5 75.00 Load Counter 1 8 1.42 1.88 21.30
Capacity 9m3 Equpiment Total 1,350.00 Manpower Total 147.29 Material Total 601.90 2,099.18 14.58
Water Truck 2 50 8 800.00 Roller Operator 1 8 2.27 2.88 52.38 Lub(10% fuel) 195.11
(houling distance for water truck
=13km for round trip) Roller 1 120 8 960.00 Forman 1 8 2.27 6.73 122.23
Equpiment Total 4,395.00 Manpower Total 665.45 Material Total 2,146.21 7,206.66 12.87
4 Sub Grade Finishing m2 2800 Grader 1 320 8 2560 Grader Oprator 1 8 2.27 24.04 436.54 Fuel Lit 367.5 4.36 1602.3
Water Truck 1 50 8 400 Roller Operator 1 0.25 2.27 2.88 1.64 Lub(10% fuel) 160.23
Equpiment Total 3,995.00 Manpower Total 806.88 Material Total 1,762.53 6,564.41 2.34
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Wearing coarse)
1 Wearing Coarse Finishing m2 4000 Grader 1 550 8 4,400.00 Grader Oprator 1 8 2.27 0.00 Fuel Lit 303.5 7.435 2,256.52
Water Truck 1 50 8 400.00 Roller Operator 1 8 2.27 0.00 Lub(10% fuel) 225.65
(houling distance for water
truck=13km round trip) Roller 1 260 8 2,080.00 Forman 1 8 2.27 0.00
Out Put for Grader 500m Daily Labourer 8 8 1.42 1.25 113.60
Equpiment Total 6,955.00 Manpower Total 138.18 Material Total 2,482.17 9,575.35 2.39
2 Wearing Coarse Material Hauling m3 680.0 D/T 10 100 8 8,000.00 Truck driver 10 8 2.27 4.33 785.77 Fuel Lit 967.5 4.36 4,218.30
(houling distance=26 km Round trip) Loader 1 200 8 1,600.00 Loader Operator 1 8 2.27 6.73 122.23 Lub(10% fuel) 421.83
106.43 Equpiment Total 9,675.00 Manpower Total 950.60 Material Total 4,640.13 15,265.73 22.45
3 Wearing Coarse Placing m3 680 Grader 1 550 8 4,400.00 Grader Operator 1 8 2.27 0.00 Fuel Lit 463.5 4.36 2,020.86
Roller 2 260 8 4,160.00 Roller Operator 1 8 2.27 3.37 61.12 Lub(10% fuel) 202.09
Equpiment Total 9,435.00 Manpower Total 214.00 Material Total 2,222.95 11,871.95 17.46
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (StucturalExcavation minor)
Hourly
Rental Total OP Index Hourly Total Total Direct Total Cost
SN ACTIVITY Unit Quantity Type No Rate OP Hr Rental cost Trade No Hr factor Wage Salery Type Unit Quantity Unit Price Total Amount Cost per Unit
1 Structural Excavation m3 200 Excavator 1 450 8 3,600.00 Excavator Operator 1 8 2.27 30.77 558.77 Fuel Lit 163 17.71 2,886.73
Equpiment Total 3,675.00 Manpower Total 936.86 Material Total 3,175.40 7,787.26 38.94
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Foundation fill)
Hourly
Rental Total OP Index Hourly Total Total Direct Total Cost
SN ACTIVITY Unit Quantity Type No Rate OP Hr Rental cost Trade No Hr factor Wage Salery Type Unit Quantity Unit Price Total Amount Cost per Unit
1 Foundation Material Production m3 480 Dozer 1 450 8 3,600.00 Dozer Operator 1 8 2.27 9.62 174.62 Fuel Lit 327.5 4.36 1,427.90
S/V 1 30 2.5 75 S/V Driver 1 1 2.27 2.64 6.00 Lub(10% fuel) 142.79
60
Equpiment Total 3,675.00 Manpower Total 194.82 Material Total 1,570.69 5,440.51 11.33
2 Material Hauling m3 144 D/T 1 100 8 800.00 Truck driver Driver 1 8 2.27 4.33 78.58 Fuel Lit 108.9 4.36 474.80
Loader 1 250 1.07 267.50 Loader Operator 1 1.07 2.27 6.73 16.35 Lub(10% fuel) 47.48
(houling distance for dump truck =10 km
round trip) S/V 1 30 2.5 75.00 S/V Driver 1 2.5 2.27 2.64 15.01
Capacity 12m3 Equpiment Total 1,142.50 Manpower Total 111.83 Material Total 522.28 1,776.61 12.34
Cargo Truck 1 50 2 100.00 Daily Loberer 10 8 1.42 1.00 113.60 Lub(10% fuel) 13.08
(houling distance for water truck =13km
for round trip) - -
Equpiment Total 150.00 Manpower Total 130.64 Material Total 143.88 424.52 26.53
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class B bedding)
1 Class "B" Bedding m3 20 Cargo Truck 1 50 2 100.00 Gang Chief 1 8 1.42 1.50 17.04 Fuel Lit 20 4.36 87.20
Equpiment Total 100.00 Manpower Total 130.64 Material Total 1,913.74 2,144.38 107.22
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class A concrete minor)
- -
Equpiment Total 19.20 Manpower Total 590.83 Material Total 1,492.13 2,102.16 109.49
Mixer 2 10 8 160.00 Str. Forman 1 8 2.27 6.73 122.23 Lub(10% fuel) 97.66
Vibreter 4 3 8 96.00 Mason 4 8 1.42 4.38 198.80 Cement Qt 95.76 99.59 9,536.74
Small Vehicle 1 30 8 240.00 Carpentor 1 8 1.42 4.38 49.70 Sand m3 12.60 112.94 1,423.02
Equpiment Total 1,096.00 Manpower Total 1,059.81 Material Total 22,926.77 25,082.58 1,045.11
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Reinforcement bar minor)
1 Bar cutting & bending kg 400 - Bar bender 1 8 1.42 3.50 39.76 Rebar kg 400 7.45 2,980.00
Equpiment Total - Manpower Total 62.48 Material Total 2,980.00 3,042.48 7.61
2 Re-Bar houling kg 20000 D/T 1 100 2 200.00 D/T driver 1 2 2.27 4.33 19.64 Fuel Lt 20 4.36 87.20
Equpiment Total 200.00 Manpower Total 42.36 Material Total 92.43 334.80 0.02
3 Bar Pacing kg 400 - Bar bender 1 8 1.42 3.50 39.76 Black wire kg 20 8.05 161.00
Equpiment Total - Manpower Total 73.84 Material Total 161.00 234.84 0.59
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class B massonary minor)
1 Masonry Stone Production m3 120 Excavator 1 200 8 1,600.00 Excavator Operator 1 8 2.27 7.69 139.69 Fuel Lt 167.5 4.36 730.30
excavator capa 15m^3/hr S/V 1 30 2.5 75.00 Helper 1 8 2.27 1.50 27.24 Lub(10% fuel) Lt 73.03
Equpiment Total 1,675.00 Manpower Total 6,127.48 Material Total 803.33 8,605.81 71.72
Excavator 1 200 0.5 100.00 Excavator Operator 1 0.5 2.27 7.69 8.73 Lub(10% fuel) 39.24
(houling distance for dump
truck =46 km round trip) S/V 1 30 2 60.00 S/V Driver 1 2 2.27 2.644231 12.00
Capacity12m 3 Equpiment Total 960.00 Manpower Total 100.20 Material Total 431.64 1,491.84 62.16
3 Class "B" Masonry m3 8 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 7.69 139.69 Cement Qt 15.12 99.72 1,507.77
Water Pump 1 5 1 5.00 Mason 4 8 1.42 4.38 198.80 Sand m3 2.64 112.94 298.16
S/V Bus 1 35 2 70.00 Quarry Man 1 8 1.42 3.5 39.76 Stone m3 11.2 133.88 1,499.40
Equpiment Total 125.00 Manpower Total 491.85 Material Total 3,391.65 4,008.50 501.06
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Reinforcement bar for pipe)
1 Bar cutting & bending(for pipe) kg 136 - Bar bender 1 8 1.42 3.50 39.76 Black wire kg 6.8 8.05 54.74
Equpiment Total - Manpower Total 73.84 Material Total 1,076.10 1,149.94 8.46
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (RC pipe D 30)
1 RC pipe production Pcs 9 Mixer 1 25 3 75.00 Pipe Forman 1 3 2.27 3.13 21.28 Cement Qt 7.353 139.00 1,022.07
Dia 30 Vibrator 1 3.5 3 10.50 Mixer Operator 1 3 2.27 1.68 11.46 C/Agg m3 1.368 106.27 145.38
pipe mould 9 0.25 8 18.00 Mason 1 3 1.42 4.38 18.64 Sand m3 0.684 112.94 77.25
Equpiment Total 103.50 Manpower Total 136.58 Material Total 2,310.08 2,550.16 283.35
2 RC pipe houling Pcs 10 D/T 1 100 4 400.00 Truck driver 1 4 2.27 4.33 39.29 Fuel Lit 40 4.36 174.40
Equpiment Total 400.00 Manpower Total 65.56 Material Total 191.84 657.40 65.74
3 RC pipe installation dia Pcs 10 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 6.73 122.23 Cement Qt 0.5 139.00 69.50
Water Pump 1 5 1 5.00 Mason 2 8 1.42 4.38 99.40 Sand m3 0.2 112.94 22.59
S/V Bus 1 35 2 70.00 Daily Lab 8 8 1.42 1.00 90.88 Fuel Lt 22 4.36 95.92
Equpiment Total 125.00 Manpower Total 312.51 Material Total 197.60 635.11 63.51
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (RC pipe D 36)
1 RC pipe production Pcs 6 Mixer 1 25 3 75.00 Pipe Forman 1 3 2.27 3.13 21.28 Cement Qt 6.45 139.00 896.55
Dia 36 Vibrator 1 3.5 3 10.50 Mixer Operator 1 3 2.27 1.44 9.82 C/Agg m3 1.2 106.27 127.53
pipe mould 6 0.25 8 2.00 Mason 1 3 1.42 3.75 15.98 Sand m3 0.6 112.94 67.76
Equpiment Total 87.50 Manpower Total 132.28 Material Total 2,664.55 2,884.33 480.72
2 RC pipe houling dia 36 Pcs 8 D/T 1 100 4 400.00 Truck driver 1 4 2.27 4.33 39.29 Fuel Lit 40 4.36 174.40
Equpiment Total 400.00 Manpower Total 65.56 Material Total 191.84 657.40 82.17
3 RC pipe installation Pcs 8 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 6.73 122.23 Cement Qt 0.5 139.00 69.50
dia 36 Water Pump 1 5 1 5.00 Mason 2 8 1.42 4.38 99.40 Sand m3 0.2 112.94 22.59
S/V Bus 1 35 2 70.00 Daily Lab 8 8 1.42 1.00 90.88 Fuel Lt 22 4.36 95.92
Equpiment Total 125.00 Manpower Total 312.51 Material Total 197.60 635.11 79.39
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (RC pipe D 42)
1 RC pipe production Dia 42 Pcs 5 Mixer 1 25 3 75.00 Pipe Forman 1 3 2.27 3.13 21.28 Cement Qt 7.095 139.00 986.21
Vibrator 1 3.5 3 10.50 Mixer Operator 1 3 2.27 1.68 11.46 C/Agg m3 1.32 106.27 140.28
pipe mould 5 0.25 8 2.00 Mason 1 3 1.42 3.75 15.98 Sand m3 0.66 112.94 74.54
Equpiment Total 87.50 Manpower Total 133.92 Material Total 2,892.11 3,113.53 622.71
2 RC pipe houling dia 42 Pcs 6 D/T 1 100 4 400.00 Truck driver 1 4 2.27 4.33 39.29 Fuel Lit 40 4.36 174.40
Equpiment Total 400.00 Manpower Total 65.56 Material Total 191.84 657.40 109.57
3 RC pipe installation dia 42 Pcs 6 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 6.73 122.23 Cement Qt 0.5 139.00 69.50
Water Pump 1 5 1 5.00 Mason 2 8 1.42 4.38 99.40 Sand m3 0.2 112.94 22.59
S/V Bus 1 35 2 70.00 Daily Lab 8 8 1.42 1.00 90.88 Fuel Lt 22 4.36 95.92
Equpiment Total 125.00 Manpower Total 312.51 Material Total 197.60 635.11 105.85
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (RC pipe D 48)
1 RC pipe production Dia 48 Pcs 4 Mixer 1 25 3 75.00 Pipe Forman 1 3 2.27 3.13 21.28 Cement Qt 7.224 139.00 1,004.14
Vibrator 1 3.5 3 10.50 Mixer Operator 1 3 2.27 1.44 9.82 C/Agg m3 1.344 106.27 142.83
pipe mould 4 0.25 8 2.00 Mason 1 3 1.42 3.75 15.98 Sand m3 0.672 112.94 75.89
Equpiment Total 87.50 Manpower Total 132.28 Material Total 2,981.59 3,201.37 800.34
2 RC pipe houling dia 48 Pcs 5 D/T 1 100 4 400.00 Truck driver 1 4 2.27 4.33 39.29 Fuel Lit 40 4.36 174.40
Equpiment Total 400.00 Manpower Total 65.56 Material Total 191.84 657.40 131.48
3 RC pipe installation dia 48 Pcs 5 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 6.73 122.23 Cement Qt 0.5 139.00 69.50
Water Pump 1 5 1 5.00 Mason 2 8 1.42 4.38 99.40 Sand m3 0.2 112.94 22.59
S/V Bus 1 35 2 70.00 Daily Lab 8 8 1.42 1.00 90.88 Fuel Lt 22 4.36 95.92
Equpiment Total 125.00 Manpower Total 312.51 Material Total 197.60 635.11 127.02
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (G.R paved water way)
1 Stone Production m3 120 Excavator 1 200 8 1,600.00 Excavator Operator 1 8 2.27 7.69 139.69 Fuel Lt 166 4.36 723.76
excavator capa 15m^3 S/V 1 30 2 60.00 S/V Driver 1 2 2.27 2.64 12.00 Lub(10% fuel) Lt 72.38
Equpiment Total 1,660.00 Manpower Total 6,124.48 Material Total 796.14 8,580.61 71.51
2 Stone Hauling m 3
24 D/T 1 100 8 800.00 Truck driver 1 8 2.27 4.33 78.58 Fuel Lit 90 4.36 392.40
(houling distance for Excavator 1 200 0.5 100.00 Excavator Operator 1 0.5 2.27 7.69 8.73 Lub(10% fuel) 39.24
dump truck =46 km
round trip) S/V 1 30 2 60.00 S/V Driver 1 2 2.27 2.644231 12.00
Capacity 12m 3 Equpiment Total 960.00 Manpower Total 100.20 Material Total 431.64 1,491.84 62.16
3 Paved Water Way m3 11 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 7.69 139.69 Cement Qt 3.96 94.20 373.03
Water Pump 1 5 1 5.00 Mason 2 8 1.42 4.38 99.40 Sand m3 0.73 112.94 81.99
S/V Bus 1 35 2 70.00 Daily Lab 6 8 1.42 1.25 85.20 Stone m3 3.08 133.67 411.69
Equpiment Total 125.00 Manpower Total 324.29 Material Total 972.23 1,421.52 129.23
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class C con. minor)
S/V 1 30 2 60.00 Carpentor 2 8 1.42 4.38 99.40 Black Wire Kg 5.26 8.05 42.38
Equpiment Total 68.00 Manpower Total 278.43 Material Total 416.68 763.11 95.39
Mixer 2 10 8 160.00 Str. Forman 1 2 2.27 6.73 30.56 Lub(10% fuel) 89.82
Vibreter 4 3 8 96.00 S/V Driver 1 8 2.27 2.64 48.02 Cement Qt 117.6 139.00 16,346.40
Small Vehicle 1 30 2 60.00 Mason 4 8 1.42 4.38 198.80 Sand m3 16.80 112.94 1,897.36
Equpiment Total 916.00 Manpower Total 1,016.15 Material Total 24,841.32 26,773.47 836.67
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Sheething material)
Excavator 1.00 200.00 2.00 400.00 Excavator Operator 1.00 2.00 2.27 6.73 30.56 Lubricant(10%Fuel) -
(houling distance for dump
truck =22 km round trip) S/V 1 30 2 60.00 S/V Driver 1.00 2.00 2.27 6.73 30.56 -
Capacity 7m 3
Equpiment Total 823.00 Manpower Total 100.32 Material Total 332.67 1,255.99 62.80
Sheating Material Crushing
2 and Hauling m 3
20 Crusher 1 35 8 280.00 Crusher Forman 1 8 2.27 2.50 45.40 Fuel Lt 39.4 4.36 171.78
Generator 1 16 8 128.00 Dump TruckDriver 1 1.94 2.27 4.33 19.05 Lubricant(10%Fuel) - - 17.18
(houling distance for dump
truck =25 km round trip) D/T 1 100 1.94 194.00 Daily Lab 10 8 1.42 1.00 113.60 -
Speed =20Km/hr
Capacity 10m3 Equpiment Total 602.00 Manpower Total 178.05 Material Total 188.96 969.02 48.45
- -
Equpiment Total 100.00 Manpower Total 159.00 Material Total 95.92 354.92 22.18
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Removal of rein. structure)
Equpiment Total 3,260.00 Manpower Total 394.15 Material Total 796.14 4,450.29 370.86
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Removal other structures)
1 Removal of Other Structure m3 80 Dozer 1 450 4 1,800.00 Dozer Operator 1 4 2.27 9.62 87.31 Fuel Lit 326 4.36 1,421.36
Excavator 1 200 8 1,600.00 Excavator Oper. 1 8 2.27 6.73 122.23 Lub(10% fuel) 142.14
Equpiment Total 3,460.00 Manpower Total 311.06 Material Total 1,563.50 5,334.55 66.68
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Structural Excavation )
Out put for Excavator =10m 3/hr Water Pump 1 2 8 16.00 S/V Driver 1 2 2.27 2.64 12.00 -
Equpiment Total 3,276.00 Manpower Total 210.70 Material Total 767.19 4,253.88 53.17
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Selected granular)
1 Selected Granular Material Production m3 486 Dozer 1 450 8 3,600.00 Dozer Operator 1 8 2.27 9.62 174.62 Fuel Lit 326 4.36 1,421.36
S/V 1 30 2 60.00 S/V Driver 1 2 2.27 2.64 12.00 Lub(10% fuel) 85.28
60.75
0.67 Equpiment Total 3,660.00 Manpower Total 200.82 Material Total 1,506.64 5,367.46 11.04
2 Material Hauling m3 144 D/T 1 100 8 800.00 Truck driver Driver 1 8 2.27 4.33 78.58 Fuel Lit 101.4 4.36 442.10
Loader 1 250 1.07 267.50 Loader Operator 1 1.07 2.27 6.73 16.35 Lub(10% fuel) 44.21
(houling distance for dump truck =10
km round trip) Helper 1 1.07 1.42 1.25 1.90
Speed =20Km/hr
Capacity 12m3 Equpiment Total 1,067.50 Manpower Total 96.82 Material Total 486.31 1,650.64 11.46
Excavator 1 200 8 1,600.00 Roller 1 8 2.27 2.88 52.38 Lub(10% fuel) 94.18
(houling distance for water truck =13km
for round trip) Roller 1 120 8 960.00 S/V Driver 1 2 2.27 2.64 12.00
Equpiment Total 2,670.00 Manpower Total 200.82 Material Total 1,035.94 3,906.76 32.56
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Hand laidRock Embankement)
exca capa 15m^3 Small Vehicle 1 30 2 60.00 S/V Driver 1 2 2.27 2.64 12.00 Lub(10% fuel) Lt 72.38
Equpiment Total 3,260.00 Manpower Total 6,124.48 Material Total 796.14 10,180.61 84.84
2 Stone Hauling m 3
38.9189189 D/T 1 100 8 800.00 Truck driver 1 8 2.27 4.33 78.58 Fuel Lit 90 4.36 392.40
Excavator 1 200 0.5 100.00 Excavator Operator 1 0.5 1.42 7.69 5.46 Lub(10% fuel) 39.24
(houling distance for dump
truck =46 km round trip) Helper 1 0.5 1.42 1.25 0.89
Speed =20Km/hr
Capacity12m3 Equpiment Total 900.00 Manpower Total 84.93 Material Total 431.64 1,416.57 36.40
3 m 3
40 S/V Bus 1 35 2 70.00 St Forman 1 2 2.27 7.69 34.92 Stone m3 40 121.24 4,849.45
Hand Laid Rock Embankment
Placing - Mason 1 8 1.42 4.38 49.70 Fuel Lit 10.00 4.36 43.60
Equpiment Total 70.00 Manpower Total 226.62 Material Total 4,897.41 5,194.04 129.85
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class A concrete)
- -
Equpiment Total 19.20 Manpower Total 590.83 Material Total 1,186.87 1,796.90 93.59
2 Class "A" Concrete m3 24 Water Truck 1 50 8 400.00 General Forman 1 8 2.27 7.69 139.69 Fuel Lit 224 4.36 976.64
Mixer 2 10 8 160.00 Str. Forman 1 8 2.27 6.73 122.23 Lub(10% fuel) 97.66
Vibreter 4 3 8 96.00 Mason 4 8 1.42 4.38 198.80 Cement Qt 95.76 99.52 9,530.04
Small Vehicle 1 30 8 240.00 Carpentor 1 8 1.42 4.38 49.70 Sand m3 12.60 112.94 1,423.02
Cargo Truck 1 50 4 200.00 Bar bender 1 8 1.42 3.75 42.60 Aggrigate m3 20.16 106.27 2,142.47
Mixer Operator 1 8 2.27 2.88 52.38 Form work m2 120 93.59 11,230.64
Equpiment Total 1,096.00 Manpower Total 1,059.81 Material Total 25,400.47 27,556.28 1,148.18
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class c concrete)
S/V 1 30 2 60.00 Carpentor 2 8 1.42 4.38 99.40 Black Wire Kg 5.26 8.05 42.38
Equpiment Total 68.00 Manpower Total 278.43 Material Total 416.68 763.11 95.39
Mixer 2 10 8 160.00 Str. Forman 1 8 2.27 6.73 122.23 Lub(10% fuel) 97.66
Vibreter 4 3 8 96.00 Mason 4 8 1.42 4.38 198.80 Cement Qt 117.6 139.00 16,346.40
Small Vehicle 1 30 8 240.00 Carpentor 1 8 1.42 4.38 49.70 Sand m3 16.80 112.94 1,897.36
Mixer Operator 1 8 2.27 2.88 52.38 Form Work m2 26.24 95.39 2,503.00
Equpiment Total 1,096.00 Manpower Total 1,059.81 Material Total 24,927.65 27,083.46 846.36
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Reinforcement bar)
1 Bar cutting & bending kg 400 - Bar bender 1 8 1.42 3.50 39.76 Rebar kg 400 7.45 2,980.00
Equpiment Total - Manpower Total 62.48 Material Total 2,980.00 3,042.48 7.61
2 Re-Bar houling kg 20000 D/T 1 100 2 200.00 D/T driver 1 2 2.27 4.33 19.64 Fuel Lt 20 4.36 87.20
Equpiment Total 200.00 Manpower Total 42.36 Material Total 92.43 334.80 0.02
3 Bar Pacing kg 320 - Bar bender 1 8 1.42 3.50 39.76 Black wire kg 16 8.05 128.80
Equpiment Total - Manpower Total 73.84 Material Total 128.80 202.64 0.63
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Class B massonary)
1 Masonry Stone Production m3 120 Excavator 1 200 8 1,600.00 Excavator Operator 1 8 2.27 7.69 139.69 Fuel Lt 166 4.36 723.76
Small Vehicle 1 30 2 60.00 S/V Driver 1 2 2.27 2.64 12.00 Lub(10% fuel) Lt 72.38
Equpiment Total 1,660.00 Manpower Total 6,124.48 Material Total 796.14 8,580.61 71.51
Excavator 1 200 0.5 100.00 Excavator Operator 1 0.5 2.27 7.69 8.73 Lub(10% fuel) 39.24
(houling distance for dump
truck =46 km round trip) S/V Vehicle 1 30 2 60.00 S/V Driver 1 2 2.27 2.644231 12.00
Capacity 7m 3 Equpiment Total 960.00 Manpower Total 100.20 Material Total 431.64 1,491.84 90.58
3 Class "B" Masonry m3 7.2 Water Truck 1 50 1 50.00 St Forman 1 8 2.27 7.69 139.69 Cement Qt 14.36 99.72 1,432.38
Water Pump 1 5 1 5.00 Mason 4 8 1.42 4.38 198.80 Sand m3 2.38 112.94 268.34
S/V Bus 1 35 2 70.00 Quarry Man 1 8 1.42 3.5 39.76 Stone m3 10.08 162.08 1,633.81
Equpiment Total 125.00 Manpower Total 491.85 Material Total 3,420.86 4,037.71 560.79
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (RC bridge railing)
Water Truck 1 50 0.5 25.00 Mason 2 8 1.42 4.38 99.40 Cement Qt 11.08 139.00 1,539.70
Water Pump 1 3 0.5 1.50 Bar bender 1 8 1.42 3.75 42.60 Sand m3 1.03 112.94 116.78
Dump Truck 1 100 1 100 S/V Driver 1 2.5 2.27 2.64 15.01 Form Work 5.148 95.39 491.06
Equpiment Total 361.50 Manpower Total 439.96 Material Total 5,122.92 5,924.38 370.27
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Concrete post)
Water Truck 1 50 0.25 12.50 Mason 1 2 1.42 4.38 12.42 Cement Qt 6.20 139.00 861.80
Water Pump 1 3 0.25 0.75 Bar bender 1 2 1.42 3.75 10.65 Sand m3 0.58 112.94 65.50
0 S/V Driver 1 2 2.27 2.64 12.00 Form Work 2.88 95.39 274.72
Equpiment Total 103.25 Manpower Total 116.06 Material Total 2,904.77 3,124.08 195.26
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Aggregate production)
Excavator 1.00 200.00 1.50 300.00 Excavator Operator 1.00 1.50 2.27 6.73 22.92 Lubricant(10%Fuel) 31.52
(houling distance for dump
truck =22 km round trip) S/V 1 30 2 60.00 S/V Driver 1.00 2.00 2.27 2.64 12.00
Capacity 7m3 Equpiment Total 723.00 Manpower Total 86.70 Material Total 346.75 1,156.45 57.82
Aggrigate Crushing and
2 Hauling m3 20 Crusher 1 35 8 280.00 Crusher Forman 1 8 2.27 2.50 45.40 Fuel Lt 39.4 4.36 171.78
Generator 1 16 8 128.00 Dump TruckDriver 1 1.94 2.27 4.33 19.05 Lubricant(10%Fuel) - - 17.18
(houling distance for dump
truck =25 km round trip) D/T 1 100 1.94 194.00 Daily Lab 10 8 1.42 1.00 113.60 -
Speed =20Km/hr
Capacity 10m3 Equpiment Total 602.00 Manpower Total 178.05 Material Total 188.96 969.02 48.45
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Sand production &hauling)
1 Sand Production and Hauling m3 10 D/T 1.00 100.00 5.00 500.00 D/T Driver 1.00 5 2.27 4.33 49.11 Sand m3 1 120 120.00
Speed =15Km/hr - - - - - -
Capacity 10m 3 Equpiment Total 500.00 0 49.11 Material Total 359.80 908.91 90.89
2 Sand Washing m3 10 Water Truck 1 50 1 50.00 Gang Chief 1 8 1.42 1.50 17.04 Fuel Lt 12 4.36 52.32
Water Pump 1 5 1 5.00 Daily Lab 8 8 1.42 1.00 90.88 Lubricant(10%Fuel) 5.23
0.00 -
Equpiment Total 55.00 Manpower Total 107.92 Material Total 57.55 220.47 22.05
Add 20%
Total Direct Adjusted
SN ACTIVITY Unit EQUIPMENT LABOUR MATERIAL project Remark
Cost Per Unit unit price
overhead
1 Clearing & Grubbing #REF! 6,075.00 363.43 2,043.27 8,481.70 1,696.34 10,178.04
6 Borrow Excavation Case (II) m3 24.32 2.86 11.07 38.25 7.65 45.90
14 30" Dia. Class 3 R.C. Pipe Pcs 64.00 52.98 295.62 412.60 82.52 495.12
15 36"Dia. Class 3 R.C. Pipe Pcs 80.21 69.31 492.77 642.29 128.46 770.74
16 42"Dia. Class 3 R.C. Pipe Pcs 105.00 89.79 643.33 838.12 167.62 1,005.75
17 48"Dia. Class 3 R.C. Pipe Pcs 126.88 108.68 1,003.90 1,239.46 247.89 1,487.35
18 G.R. Paved Water Way m2 11.36 29.48 88.38 129.23 25.85 155.07
23 Excavation for Structures (Rock) m3 40.95 2.63 9.59 53.17 10.63 63.81
25 Hand laid Rock Embankment m3 1.75 5.67 122.44 129.85 25.97 155.82
29 Class 'B' Stone Masonry m3 17.36 68.31 475.12 560.79 112.16 672.95
1 Form works m2 11.33 - Carp Forman 1 8 1.6 3.37 43.08 Euc Pole Pcs 20 5 100.00
Equpiment Total - Manpower Total 727.08 Material Total 406.60 1,133.68 100.06
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (C25 Concrete)
1 C25 concrete m3 12.65 Mixer 1 25 8 200.00 Mason Forman 1 8 2.27 3.37 61.12 Cement Qt 71.5 60 4,290.00
Vibrator 1 3.5 8 28.00 Mason 7 8 1.42 3.75 298.20 C/Agg m3 12 #VALUE! #VALUE!
Equpiment Total 228.00 Manpower Total 847.80 Material Total #VALUE! #VALUE! #VALUE!
NORI-LA
SHISHINDA-MIZAN ROAD PROJECT
Direct Cost Breakdown (Eucalyptus tree)
F/Agg m3 9.15 -
2 D/T 1 100 - Truck driver 1 1.6 4.33 0.00 Fuel Lit 0 4.36 -